Executive Summary
Executive Summary
90
80
70
60
Actual
50
40
30
20
10
High Growth Scenario based on average growth in peak hour train loading 2008 - 2014
Low Growth Scenario based on annual average weekday boardings 2000 - 2014
Clark Junction is the largest constraint in the RPM corridor, limiting capacity on all three lines that pass
through this area. General rail transit design guidance recommends junctions be grade separated when
trains operate as frequently as they do through Clark Junction. The number of trains CTA needs to
operate to meet crowding standards in the peak hour is already within the range of maximum capacity at
Clark Junction, and demand has been growing.
Red-Purple Bypass Project Environmental Assessment
Executive Summary
NEPA Scoping
Process
Alternatives
Re nement
Research and
Concept Design
Process
Executive Summary
six year s of p
over 20 alt ernat ives,
Executive Summary
Alternatives Considered
This EA compares the No Build Alternative and Build Alternative for the Red-Purple Bypass Project.
The No Build Alternative is required as part of
the NEPA environmental analysis and is used for
comparison to assess the relative bene ts and
impacts of the Build Alternative. It represents the
future situation that would likely exist if the RedPurple Bypass Project were not implemented.
Includes typical ongoing maintenance and repairs,
including funding for emergency repairs at
historical levels
Does not expand capacity
Does not modernize infrastructure to improve
service quality or travel times
Limited bene ts that only provide a short-term
extension of structure life
The Red-Purple Bypass Project Build Alternative
consists of constructing a fth track bypass for
the northbound Brown Line and reconstruction of
approximately 0.3 mile of the mainline Red and
Purple line tracks from Belmont station on the south
to the segment of track between Newport and
Cornelia Avenues on the north. The project area is in
the Lakeview community area.
Executive Summary
fro
mK
imba
ll
ne to
Kimb
all
Br
Bro
wn
Li
To Loop
ow
nL
ine
The Build Alternative would provide a gradeseparated junction allowing northbound Brown Line
trains to cross unimpeded over the other tracks on a
new aerial structure, resulting in increased capacity
for all three lines while also improving travel time
Belmont Southbound
Platform
Track 1
Track 2
Track 3
Belmont Northbound
Platform
Track 4
From Loop
SHEFFIELD AVENUE
CL
EE
CORNELIA AVENUE
Tight curves
to be
straightened
NORTH
NEWPORT AVENUE
ROSCOE STREET
SCHOOL STREET
BELMONT AVENUE
WILTON AVENUE
AR
R
ST
Not to Scale
Executive Summary
Executive Summary
Existing Conditions
Executive Summary
Existing Conditions
10
Executive Summary
Existing Conditions
11
Executive Summary
CTA developed a conceptual staging plan for construction with the goal of limiting impacts on passengers
during peak periods.
Three conceptual stages for construction are
proposed: early work, construction of the new
bypass, and construction of the mainline tracks.
Early work would include demolition of
buildings and utility relocation in preparation
for construction, among other tasks. This stage
would not affect train operations in the project
area.
Construction of the new bypass and mainline
track structure would result in some temporary
operational changes, and service disruptions
would be scheduled to occur during weekends
and off-peak periods when possible to limit
impacts on riders.
Construction would take place within existing
CTA right-of-way and on the properties that
Preliminary construction costs for Red-Purple Bypass Project were estimated based on conceptual
engineering. These estimates will be re ned through ongoing preliminary engineering.
Anticipated capital costs for the Red-Purple
Bypass Project are approximately $570 million
in year-of-expenditure dollars, inclusive of repair
work on the Brown Line tracks east of Seminary
Avenue.
CTA is intending to seek Capital Investment Grant
(CIG) program funding from FTA for the Red-Purple
Bypass Project. The CIG program, more commonly
known as the New Starts, Small Starts, and Core
Capacity Program, involves a multiyear, multistep
process that project sponsors must complete
before a project is eligible for funding. The steps
in the process and the basic requirements of the
12
Executive Summary
NEPA Analysis
Potential adverse environmental impacts are detailed in Chapter 3 of the EA and summarized below.
The Build Alternative would result in positive bene ts
to transportation, increasing both train capacity and
speeds for Red, Purple, and Brown lines. Temporary
impacts on transportation would be related to
construction:
Temporary service disruptions to the Red, Purple
and Brown lines would be scheduled to occur
during weekends and off-peak periods when
possible to limit impacts on passengers.
Bus bridges (shuttles) would be used for Brown
Line riders between Belmont and Southport
stations during a limited number of weekends
while the new bypass is tied into the Brown Line
tracks. A Red Line bus bridge between Belmont
and Addison stations would be used during a
limited number of weekends while tying in tracks
or installing special trackwork.
Temporary short-term street closures/detours
or lane restrictions would occur along roadways
and alleys beneath the existing and proposed
structure.
On-street parking would be subject to temporary
impacts due to road closures, detours, or lane
restrictions.
Temporary sidewalk and bicycle lane closures
would occur, to maintain a safe work zone.
NEPA
Section 4(f )
Section 6(f )
RCRA/CERCLA
Endangered Species Act
Farmland Protection Policy Act
Executive Summary
Executive Summary
Public Involvement
Multiyear public involvement has been crucial in
the development of this project. From the initiation
of the 9.6-mile RPM corridor vision study in 2009
through the development of the Build Alternative
evaluated in this EA in 2014, CTA has continued to
solicit feedback from the public. This feedback has
shaped development of the phased approach for
implementing the RPM corridor vision and de nition
of the Build Alternative.
Full details on the extensive public outreach efforts
undertaken on this project may be found within the
EA document.
The FTA has issued a Notice of Availability for this
EA to provide the public an opportunity to review
and comment on the EA. A 30-day comment period
has been established to take formal comments.
All comments received during the 30-day public
15
Executive Summary
Commitments
CTA is committed to a number of activities to minimize impacts. Additional details on mitigation measures
are provided within each resource area of the EA. The nal NEPA decision document will contain a detailed
listing of all project commitments.
Efforts to reduce the potential impacts of the project due to property displacements will include the
following:
Prior to
construction, CTA will work with the City, Ward 44
aldermans of ce, chambers of commerce, and
the surrounding community to develop a plan for
redevelopment following construction. This plan
will identify development opportunities for parcels
remaining after construction that will t within
16
Executive Summary
Detailed
Maintenance of Traf c and Access plans will be
developed to ensure safety during construction,
continued emergency access, and to coordinate
alternative access, garbage and delivery services.
Temporary
service disruptions to the Red, Purple and Brown
lines will be scheduled to occur during weekends
Next Steps
The following are major next steps in the process during 2015:
CTA will respond to public comments on the EA
and submit it to FTA.
FTA will issue a NEPA Decision Document
summarizing results of the EA including all
comments and responses.
CTA will complete preliminary engineering in fall
2015.
17