Escolar Documentos
Profissional Documentos
Cultura Documentos
4 X 30 MW CPP
Revision No : 00
TURBINE SOP
CONTENTS
INTRODUCTION
TECHNICAL SPECIFICATION
SAFETY CHECKLIST
COOLING WATER AND AUX COOLING WATER
CHARGING
OIL SYSTEM START UP
BARRING GEAR START UP
TURBINE AUXILLIARY EQUIPMENT START UP
STEAM LINE CHARGING AND VACCUM BUILD UP
DEFINITION OF HOT, COLD STARTUP
TURBINE COLD STARTUP AND SYNCHRONIZATION
TURBINE RE START FROM WORK CONDITION
TURBINE PROTECTION AND INTERLOCKS
Prepared By
Checked By
PAGE
2
3-9
10
11-12
12-14
14-15
15-16
16-18
18-20
21-25
26
27-28
Approved By
Commissioning Team
GENERAL MANAGER
1
TURBINE SOP
1. INTRODUCTION
The purpose of the Turbine system is to convert the heat energy in the steam
from generator into kinetic energy & to drive the TG train.
The SST300 C160 Turbine is a single flow turbine with 15 stage & downward
exhaust. When admission steam reaches the turbine, it first passes through an
emergency shut off valve (ESV) with steam strainer & then continues to a
control valve. A hydraulic servomotor controls the steam valve.
G.A. DAIGRAM
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
2
TURBINE SOP
2 TECHNICAL SPECIFICATION
Design Data
Make
Type of Turbine
Model
:
No. of stage
:
Rotor blade type
Rotor weight
:
Distance between brg centers
Journal dia. (NDE bearing) :
Journal dia. (DE bearing) :
Turbine Output
Rated
Speed
Rated (Turbine)
Rated (Generator)
Emergency Trip (Turbine)
First Critical Speed
Siemens Limited
:
Single cylinder, single flow exhaust,
Non-reheat, condensing
SST300 C-160
15
:
Impulse/reaction
4750 Kg
:
2798 mm
179.63 mm
199.67 mm
32.450 MW
:
:
:
:
1500
7765
3460
Direction of Rotation
Seen Turbine Generator :
Live Steam
Pressure Rated
Temperature Rated
Flow
:
:
:
63 Ata
460C
124.49 TPH
:
:
:
0.100Ata
45.5C
112.46 TPH
Exhaust To Condenser
Pressure
Temperature
Flow
Bleed 1
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
3
TURBINE SOP
Pressure
Temperature
Flow
:
:
:
3.71 Ata
140.5C
12.03 TPH
Siemens Limited
Single Pressure, Two Pass, Under Slung,
3290 m2
85%
2
:
5%
:
2.07 m/s
<6 mmWC
:
:
:
:
112.53 TPH
0.100 Ata
45.50C
546.98 Kcal/kg
0.299 TPH
113.04 TPH
45.50C
3C
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
4
TURBINE SOP
Flow Maximum
:
:
:
6400 m3/h
33.76 TPH
1.8 Ata
150C
:
:
:
:
:
:
:
:
:
:
:
Checked By
4860
23 mm
0.7 mm
Roller Expanded
Approved By
Commissioning Team
GENERAL MANAGER
5
TURBINE SOP
Hotwell
Hotwell retention Time
Hotwell Volume
Weight
Empty
Operating
Flooded
:
:
:
180 sec.
~5.71 m3
69580 kg (Apr.)
:
99000 kg (Apr.)
129000 kg (Apr.)
Make
Flender Graffenstaden
Type
TX90 / 4C
:
:
:
:
:
33651 KW
AGMA 6011-103
7046 RPM
1500 RPM
4.7
GEAR BOX:
Gear data
Gear rated
Service Factor
Rated Input speed
Rated Output Speed
Speed Ratio
Lubrication
Lube Oil Designation
Filtering
Inlet Pressure
:
Normal Oil Inlet Temp.
:
Maximum Oil Inlet Temp. :
Oil Flow
:
Calories to evacuation
Construction Features
Centerlines Distance
Total Weight
:
Upper Casing Weight
Lower Casing empty Weight
High Speed Shaft Weight :
Low Speed Shaft Weight :
Prepared By
:
ISO VG46
:
25 Micron
15 Bar(g)
50C
60C
579 l/mn
:
406677 kcal/h
:
890 mm
14800 kg
:
1900 kg
:
6002 kg
569.2 kg
6642.2 kg
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
6
TURBINE SOP
Oil Type
Empty Weight
:
Working Weight
Working Volume
Working Temperature
Design Temperature
:
Working
:
Design
:
Tank Dia./ height / thickness
:
ISO VG46
900 Kg
:
8550 Kg
:
6000 Liters
:
45C
80C
Atmospheric
Full of water
:
2250 / 1800 / 3 (mm)
:
17.25 Bar(g)
15 Bar(g)
:
7.5 Bar(g)
Oil Data
Oil Type
:
Lube Oil outlet flow
:
Lube Oil outlet pressure
Control Oil outlet flow
Control oil outlet pressure :
ISO VG46
974 LPM
:
3.5 Bar (g)
:
30 LPM
9.5 Bar (g)
Lube
:
:
:
1200 LPM
25 Microns
SS 304
60 LPM
:
10 Microns
Paper
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
7
TURBINE SOP
Revision No : 00
:
:
1200 LPM
6080502 kcal/Hr
67.4C
:
48C
2500 LPM
:
33C
42C
AD Brass
Pump Data
Quantity
Type
Flow
Speed
Pressure
:
:
:
:
:
Motor Data
Supply System
Make
KW
Speed
Supply
Supply
:
:
:
:
:
:
AC & DC
Siemens Ltd.
3.7
1450 RPM
415V , 50Hz (AC Motor)
110V (DC Motor)
Oil Flow
Head Load
Oil Temp. Inlet
Oil Temp. Outlet
Cooling Water Flow
C.W. Temp. Inlet
C.W. Temp. Outlet
Tube Material
:
:
:
:
5 Bar(g)
:
300 Bar(g)
Make
Type
Flow
Pressure
AOP
Tuschaco
Screw
1200 LPM
12 Bar(g)
EOP
Rotodel
Gear
400 LPM
1.5 Bar(g)
Motor Data
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
8
TURBINE SOP
Item
Make
KW
Supply
AOP
EOP
Siemens
CGL
45
5.5
415V/AC
220V/DC
Vent Fan
Siemens
1.5
415V/AC
Empty Weight
Working Weight
12000kg
:
27000kg
:
:
:
:
:
:
:
KSB
Vertical pump
:
120 m3/hr
65 m
:
46C
1.85 m
:
72.6 %
86 m (5%)
:
36 m3/Hr
:
170 liters
EBIPL
BSTFN
Observation
(Yes / No)
DESCRIPTION
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
9
Remarks
TURBINE SOP
14
16
17
18
19
20
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
10
TURBINE SOP
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
11
TURBINE SOP
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
12
TURBINE SOP
21.
Start auxiliary oil pump and switch over the emergency oil pump to
AUTO.
22.
Start the oil pump well in advance of turbine start because for
starting up the turbine
mentioned hours and also inlet oil temperature should be at least 40C. To
increase the oil temperature use the oil heaters in oil tank (simultaneously
with the auxiliary oil pump operation).
23.
Oil pumps are not allowed to be started with the oil temperatures
under20C
Control and lube oil pressures and oil temperature after cooler.
Control and lube oil filter-fouling degree on p indicator.
Oil level in the main oil tank.
Any leakages in joints/flanges, coolers, filters etc.
Check whether all instruments are working.
Check for operation of all valves.
Check AOP discharge Pressure -12 kg/cm.sq
Ensure discharge Header pressure 3 kg/cm.sq
1- Contentious rotation of the shaft with the barring gear prevent the
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
13
TURBINE SOP
By turning the shaft you can avoid the shaft deformation (deflection)
caused by accidental
standstill.
Before startup the turbine must be on turning gear for the following
minimum periods of time.
Shaft stand Still
2 Hours
Upto7 days
6 Hours
7to 30 days
12 Hours
24 Hours
If the above time requirements cant meet, the vibration level must be
observed thoroughly.
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
14
TURBINE SOP
Condenser Extraction pump is provided to pump the condenser hot well to the
Deaerator or condensate storage tank through ejector. The pump is operated by
varying the discharge flow so as to maintain the hot well level constant in normal
operation. There are 2 nos C.E.P provided where one is running condition and
another is stand by.
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
15
TURBINE SOP
REQUIRED PARAMETERS:
a) Main steam temperature > 350 C
b) Main steam pressure 10 bar
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
16
TURBINE SOP
Ejector steam isolation valve at Deaerator floor should be opened slowly for
line charging.
Water must be observed at ejector drain and must be waited still steam
appears.
Hogger Ejector steam inlet isolation valve should be opened slowly for line
charging.
After observing steam in silencer drain, Hogger Ejector air isolation valve
must be opened.
Thus startup of Hogger Ejector is done.
Vaccum is created in Condenser by Hogger Ejector. After synchronization, Main
Ejector is taken into line and Hogger Ejector is closed for preventing the waste
of steam.
2) TO TAKE MAIN EJECTOR IN SERVICE
Deaerator Charging
Pre Checks
1. Ensure all permits are cleared.
2. Ensure that the de aeration tank manual vents are in full open condition.
3. Ensure that the de aerator overflow v/v is in closed condition.
4. Ensure that the drain v/v is in closed condition.
5. De aerator floor should be cleared from foreign materials.
Operation
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
17
TURBINE SOP
1. Wear PPE. Hand gloves, ear plugs, helmet, safety shoes for de aerator
charging.
2. Start D.M transfer pump and fill de aerator up to 80%.
3. Ensure that PRDS outlet temperature below 250C and pressure is below 5
kg/cm2.
4. Ensure drain valve after initial heating valve is in open condition.
5. Slowly open (crack) the initial heating line valve and observe the de aerator
pressure.
6. Stop the opening of initial heating valve, if de aerator pressure reaches to
0.1kg/cm2.
7. The water temperature in the de aerator storage tank starts increasing.
8. Observe the any abnormalities and leakages during Deaerator charging.
9. Continuously monitor the Deaerator temperature and pressure.
10.
Keep the initial heating valve in open condition until unless water
temperature reaches 100C and there is a no continuous water flow to the
Deaerator.
11.
If water temperature rises to 100C. and there is a continuous water
flow to the
Deaerator, and then charge the pegging line.
12.
Keep the Deaerator PCV outlet isolation valve full open and open the
inlet isolation is 5%, and then controls the Deaerator pressure with PCV.
13.
Maintain the de aerator pressure at around 0.3-0.4 kgcm2
14.
Then slowly close the initial heating valve.
15.
Chemical preparation in L.P dosing tank (Maintain 50% tank level, add
4 liters of hydrazine or 10 liters of hydrazine. Run both dosing pumps @80 %
stroke until turbine rolling. After rolling monitor the feed water DO and adjust
the dosing.)
16.
Measure for DO in continuous running.
De aerator charging from turbine extraction:
1. Ensure that steam flow through extraction line.
2. Ensure that Deaerator pressure and extraction pressure is same.
3. Open the turbine Extraction drain.
4. Then open the QC NRV.
5. Then slowly open the Extraction isolation valve. If the condensate is
completely removed from drain, open the isolation valve fully.
6. Then slowly open the Extraction isolation valve.
7. Once Deaerator pressure stabilizes, then slowly isolate the pegging line.
Isolation of Deaerator:
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
18
TURBINE SOP
1.
2.
3.
4.
Cut off the steam supply to the Deaerator from turbine extraction/ PRDS.
Cut off the water supply to Deaerator.
Ensure L.P dosing stopped condition.
Observe the de aerator storage tank pressure and temperature.
(Shutdown
The turbine is warm, i.e. the determined flange temperature is less than or
equal 280C
A warm start occurs for some minor repair
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
19
TURBINE SOP
Revision No : 00
works.
Hot
time<2Hours)
Start
(Shutdown
The turbine is hot, i.e. the determined flange temperature is less than or
equal to 360C
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
20
TURBINE SOP
a) Pressure
:
40 - 50kg/cm2
b) Temperature :
400 420 Deg.C.
6. Vacuum pulling and Gland steam Charging should start by the following
parameters of Boiler.
a) Pressure
:
40 - 45kg/cm2
b) Temperature :
420 430 Deg.C.
7. TG Rolling should start by the following parameters of steam.
a) Pressure
:
40 - 45kg/cm2
b) Temperature :
430 450 Deg.Cent.
10
4 Ensure all Governing Valves, MSSV, Bypass of MSSV, all QCNRVs and manual
isolation valves of Extraction lines are closed.
5 All Main Steam Line drains, ESV and Casing drains, extraction line drain,
ejector drain, Gland steam header drain, PRDS I/L & O/L drain, De-aerator
initial heating line drain, De-aerator PCV bypass line drain and air evacuation
lines from heaters to condenser are in open condition.
6 Start the cooling water pump and deaerate the condenser water box and
cooling water O/L lines and make the system through.
7 Start ACWP, de-aerate oil cooler water side (TUBE) and make the system
through.
8 Maintain hot well level around 40% through hotwell make up line. Start CEP
and de-aerate water side of ejector (both inter and after condenser water
side), and Gland Steam Condenser waterside.
9 MOT level should be normal i.e. before starting AOP/AOP-2.
10 Start the AOP/AOP-2 and de-aerate both the oil coolers (shell side oil), lube oil
filters and control oil filters.
11 Oil temperature at outlet of cooler to be maintained between 32 to 35 Deg. C.
12 Observe oil flow through the bearing drain sight glasses of lube oil system.
13 Observe lube oil header pressure and control oil pressure, oil pressure at inlet
of individual bearings.
14 Start the turning gear motor from control room and keep its control in manual
mode. Turning gear should be started before 4 hours of turbine rolling.
15 Check for any kind of abnormality during turning gear operation. If anything
found abnormal check and inform to the concerned.
16 Start heating of Main Steam Line by opening one pulse of the bypass of MSSV
.While heating the steam lines; observe the rise of steam temperature. It
should not exceed more than 5 Deg/Min, observe drains of MSL. Open the
valve fully. Keep open the ACW valve to flash tank, which is at TG Building
G.floor.
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
21
TURBINE SOP
17 Observe condensate coming from drains, in any case the increase rate of
steam temperature must not be more than 5 Deg./minute.
18 Open the MSSV one pulse upto 100% so as to bring the temperature of
turbine inlet header upto 430 Deg. C and pressure 40-45 Kg/cm2.
19 Along with Main steam line also charge the ejector steam line, PRDS line by
slowly opening the respective isolation valves from De- aerator floor, check
that air side isolation valves to LP Heaters which are connected to condenser
are open, PRDS drain and ejector drains should be open.
20 PRDS inlet isolation valve to be opened slowly by observing condensate
draining of PRDS line.
21 Ensure GS header outlet valve at 4.5 m floor is closed. Header drain should
be open.
22 When superheated steam starts coming from the PRDS line drain, slowly open
the Gland Steam supply isolation valve from De-aerator floor.
23 Heat the ejector line fully observing the drains; open the ejector isolation
valve from De-aerator.
24 Open the Hogger ejector steam side isolation valve when line pressure gauge
shows 17 kg/cm2 slowly @ 6m, also the drain valve of the silencer should be
kept open.
25 Slowly slowly open the hogger ejector steam valve fully @ 4.5 m, and also
valve from De-aerator floor. Now open airside valve of ejector side. While
starting, always open the steam side valve first and then open the airside
valve and while closing vice-versa.
26 Before opening the G S Supply isolation Valve ensure that the vent valve of
gland steam supply which is at turbine floor is kept in open condition so that
condensate forming during heating comes out.
27 Now by opening the PCV of PRDS increase the pressure and temperature of
PRDS and Gland steam supply line. Temperature rate of increase should not
be more than 5 Deg/min. Since the vent valve of Gland Steam supply line is
open the Gland steam header pressure will come around 0.06 kg/cm2.
28 After 15 minutes of taking hogger ejector in line vacuum will come around
0.60 kg/cm2
29 Close the Gland Steam supply line vent valve, which is at Turbine floor. The
Gland steam header pressure increase upto 0.155 kg/cm2 and vacuum
improves to 0.85 kg/
Turbine is ready for rolling; reset the trip command from control room,
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
22
TURBINE SOP
30 At turbine inlet header pressure 63 kg/cm^2 and temperature 460 Deg.C the
machine is ready for rolling. Slowly open the ESV and observe turning gear
disengages at >240 rpm automatically.
31 Increase turbine speed up to 500 rpm, hold 15 minutes. Observe all bearing
vibrations, drain oil temperatures, any abnormal noise, axial shift, casing
expansion, differential expansion, casing temperatures, exhaust hood
temperature, hotwell level, drain oil coming out thru sight glass, Steam inlet
temperature and Pressure, Condenser Vacuum, Exhaust Hood Temperature,
Lube oil cooler DP, Control oil DP, Seal steam Pressure, Generator Stator
Temperatures, Compare if earlier readings are available at same RPM.
32 Increase the rpm slowly upto 1000 rpm and hold for 20 minutes. Observe all
bearing vibrations, drain oil temperatures, any abnormal noise, axial shift,
casing expansion, differential expansion, casing temperatures, exhaust hood
temperature, hotwell level, drain oil coming out thru sight glass. Compare if
earlier readings are available at same RPM.
33 With the increase in RPM primary oil pressure starts building up. Increase the
RPM upto 3700 beyond the critical speed. Dont hold the turbine rpm near the
critical speed 3460 rpm.
34 Slowly to 7059 RPM. Check the function of governing valves must go down,
Slowly full open the other ESV.
35 Open the manual isolation valve of Exhaust Hood Spray @ 4.5m when
exhaust hood temperature starts increasing i.e. > 45 Deg. C.
36 Observe all bearing vibrations, drain oil temperatures, any abnormal noise,
axial shift, casing expansion, differential expansion, casing temperatures,
exhaust hood temperature, hotwell level, drain oil flow thru sight glass.
Compare if earlier readings are available at same RPM.
SYNCHRONIZING
Synchronizing can be carried out manually or
automatically.
For synchronizing follow special instructions.
a) Before synchronizing: Check the over speed trip test of TG SET. In this
test both electrical and mechanical trips to be carried out at least twice
at the time if initial commissioning. Speed details are given in turbine
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
23
TURBINE SOP
technical data.
b) Manual synchronizing: The speed is adjusted by pushing the
corresponding WOODWARD keys until the turbine speed is synchronized
with network frequency. The generator circuit breaker can be then
closed, if the frequency, voltage, relationship and sequence of phases
and rotating field direction of generator and of the mains are equal.
c) Auto synchronizing: The speed of the turbo set is now maintained by
the frequency of the external grid.
For automatic synchronization see special instructions given in Woodward
manual.
LOADING
Aft e r synchronizing increase the load to app.2% of its rated load in
order to avoid the activation of reverse power relay.
C o n t i n u e increasing the load according to the start-up graphs by
pushing the corresponding keys on the WOODWARD GOVERNOR.
D u r i n g loading check all parameters and check also the control
stage pressure.
C l o s e all manually controlled drains and vents.
C h e c k the cooling air temperature of generator and open cooling
water to the air cooler according to special instructions.
C h e c k the seal-steam pressure and temperature.
37 If all the functions are normal, the turbo set is ready for Synchronizing.
38 After Synchronization take load upto 3 MW.
39 Depending upon the generator winding temperatures take Generator air
coolers inline.
40 At this load (3 MW), heat the turbine for 40 minutes. Observe all bearing
vibrations, drain oil temperatures, any abnormal noise, axial shift, casing
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
24
TURBINE SOP
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
25
TURBINE SOP
Prepared By
Checked By
Approved By
Commissioning Team
GENERAL MANAGER
26
TURBINE SOP
Revision No : 00
12
Turbine Trip
The Turbine will trip due to any of following fault condition as listed below
S.N
o.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Normal
status
Logic out
1
Logic out
1
Description
Set point
31kg/cm2
68kg/cm2
Logic out
1
350C
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
474C
Active
out
out
out
=110%20rpm
1234mmW
out
out
out
out
out
out
out
out
out
Prepared By
Checked By
Remarks
MS temp. to
be
implemented
=120C
=105C
For 1 hr
Active
Active
<=1.8kg/c
m2
<=7.5kg/c
m2
=110%
Approved By
Commissioning Team
GENERAL MANAGER
27
TURBINE SOP
Revision No : 00
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
out
out
out
out
out
out
out
out
out
out
out
out
out
out
out
out
out
out
out
Prepared By
Checked By
C
Active
=82 micron
=82 micron
HMI
=107 micron
=107 micron
=232 micron
=232 micron
=232 micron
=232 micron
=0.6mm
=100C
=105C
=105C
=120C
=120C
=110C
=110C
=110C
Approved By
Commissioning Team
GENERAL MANAGER
28
TURBINE SOP
Revision No : 00
1
Logic
1
Logic
1
Logic
1
Logic
1
Logic
1
35
36
37
38
39
out
out
out
out
out
high high
Gearbox LS DE bearing temp
high high
Generator front bearing temp
high high
Generator rear bearing temp
high high
Governor emergency shutdown
Main steam temp gradient high
high
=110C
=90C
=90C
Active
5C/min
Generator trip:The Generator will trip due to any of following fault condition as listed below
S.N
o
Normal
status
Logic out 0
Logic out 0
Logic out 0
Logic out 0
Logic out 0
Logic out 0
7
8
9
Logic out 0
Logic out 0
Logic out 0
10
Logic out 0
Prepared By
Description
Generator
1
Generator
2
Generator
3
Generator
4
Generator
5
Generator
6
Generator
Generator
Generator
Generator
Checked By
Set points
130C
130C
130C
130C
130C
130C
130C
130C
130C
Active
Approved By
Commissioning Team
GENERAL MANAGER
29
Remarks
Hardwire
d