Jamaica Energy Partners

Doctor Bird Power Plant


Engineering Report.

Report No. 20140228-DG2_FR

DG #11 Failure

September 2013

Prepared By: Carlos Mohan

Executive Summary

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Prior to the failure on Saturday September 08, 2013 at 0111hrs, DG#11 was taken
offline to investigate and correct high cylinder liner temperatures on cylinders A2
and A3. The cylinder liner, piston and cylinder head were all replaced.
On the morning of the failure, (September 08, 2013) unit was started at 0151hrs
and began its running program. During the running-in program, at 20% loading,
the unit experienced a catastrophic failure where cylinder A2 and B2 connecting
rod and counterweight became separated from their respective cranks and exited
through both sides side of the engine block.
The failure resulted in extensive damages to the engine block in the cylinder liner,
crankcase, tappets and camshaft areas, and a fire that caused severe damages to
engine instrumentation system and control wiring for both DG#11 and DG #10, the
engine room fire detection system, instrument and power cables for common
engine support systems, and the two engine hall gantry cranes.
The inspection and assessment of the failed components and a review of the
operating data, trends and statements and interviews with personnel who were
directly involved in the maintenance and operations work were carried out.
This revealed that the root cause of this failure came from a combination of human
and latent causes.

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

In order to reduce the likelihood of future failures, the following were


recommended:
1. Address the latent root cause of this accident by implementing and enforcing
a handing over procedure for all shift personnel.
2. Work orders should have clear close out comments at the end of a shift, and
that personnel continuing with the same job along with the shift supervisor
review these comments before continuing.
3. Adherence to maintenance procedure MMP-11(Quality Assurance/Quality
Control Section 3-A-1 QC/QA procedures) should be enforced.

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Introduction
On Sunday September 08, 2013 at 0149hrs DG#11was started and shutdown due to
low HT water pressure, the unit was restarted at 0151hrs and synchronized at
0155hrs. The unit was at twenty percent of its running-in program at 0217hrs
(3.415MW) when a loud grinding sound was heard followed by a loud explosion
and a huge fire from the engine, the unit was immediately emergency stopped by
the control room operator, DG#9 was also emergency stopped ( DG#10 was offline
for maintenance work).
The engine experienced catastrophic damages in the area of the A2 and B2 drive
train and engine block area. The connecting rod and counterweight for both
cylinders became detached from their respective crank and exited the side of the
engine block, the resulting fire from the accident resulted in severe damages to the
instrumentation and control system wiring for both DG#11 and DG#10 A-bank
along with the plants fire detection system and the two engine room gantry cranes.
Investigative Actions
The objectives of this investigation were to identify the cause of the failure of the
connecting rod and counterweight fastening mechanism for cylinder A2 and B2,
and to provide recommendations to prevent a recurrence of this kind of failure.
The investigation examined the three main possible areas of the failure roots
namely, Physical, Human and Latent roots, the investigative actions taken were:
1. Analysis of the DG Set operating trends to identify if there were any
abnormal operating conditions that could have contributed to the failure.

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

2. Thorough review of written statements of submitted by Operations and


Maintenance personnel who were directly involved with the unit during the
period of maintenance custody and the period of startup by the Operations
personnel prior to the failure.
3. Examination of the failed components, particularly the fracture faces of
these components, with the aim of identifying the nature of the forces
involved. Determining if there were possibly defects in material that
precipitated the failure. In the absence of laboratory type equipment to
perform full metallurgical analysis a fair degree of accurate determination
was able to be arrived at.
4. Analysis of the DG Set operating trends to identify if there were any
abnormal operating conditions that could have contributed to the failure.

Findings
The following were the findings from the different aspects of the investigation:
1. The written statements submitted by plant operations and maintenance
personnel revealed that there is no standard procedure driven protocol that
exist that governs the way jobs are handed over from on shift to another.
Interviews carried out further revealed that the techniques employed for the
handing over of jobs vary across shifts.

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

2. There were no consistency in updating the comments in the work orders by


shift personnel at the end of their shift, and there were no enforcement on the
path of the shift supervisors to ensure that this is done.
3. Examination of the trends for the different engine operating parameters did
not reveal any abnormalities; they were consistent with normal operation of
a unit leading up to the twenty percent point in a running-in program.
4. The practice of not running a nut onto a stud to its full threaded run without
carrying out any immediate plan to carry out tensioning of that stud was not
done. This was left for relieving shift to be done for cylinder A2
5. Shift supervisor for the afternoon shift to which the day shift handed over to
failed to ascertain and communicate the total status of the work being done
on the DG set, this led to his Mechanical Technicians taking over the job
making their own assessment and assumptions of what was completed and
what was outstanding.
6. Physical examination of the failed connecting rod studs fractures revealed
with a fair degree of accuracy that the four studs from the A2 cylinder failed
from fatigue, which could most likely be due to under tensioning, the studs
from the cylinder B2 displayed signs of plastic deformation at point of
fracture. Only three of the total of four counterweight studs from
the two cylinders, A2 and B2, were found and the examination of these
indicates that they possibly failed as a result of mechanical impact to the
counterweight.

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Analysis
The deformation of the studs for the connecting rods and counterweight were
carefully analysed with a view to determine the cause of failure, connecting rod
studs for cylinder A2 showed signs of failure consistent with fatigue, those
however from cylinder B2 showed signs of failure from impact.
The counterweight studs failure faces were all consistent with that caused by
external mechanical impacting forces.
The displacement of the cam section for cylinder A2 occurred as a result of one of
the counterweight exiting the engine coming in contact with it.
The A2 connecting rod studs may not have been tensioned as per specification, and
thus initiated the failure, the result of this been a detached A2 connecting rod from
the crank that gave way quickly and coming in contact with connecting rod and
counterweight for cylinder B2. The forces involved in this collision coupled with
the level of unbalance on the crank may have caused further failure of the A2
counterweight.

Conclusion
Having analysed all available data and information pertinent to the failure of
Diesel Engine #11 drive train A2 and B2 against the three main possible areas of
failure roots a number of anomalies were identified, the possible physical root
contribution when analysed revealed that the actual failure mechanisms for

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

cylinder B2 and A2 counterweight were all externally drive, while that of cylinder
A2 connecting rod studs were human induced and did not point to any defect in the
material.
For the human root, the investigation concluded that there were inappropriate
human actions that contributed to the failure.
The failure investigation as far as the Latent root revealed that anomaly as far as
non-adherence to procedure and the lack of other relevant procedures to guide and
control the flow of effective communication existed.
This investigation concludes that the root cause of this failure was a combination
of human and latent causes.

Appendix

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Historical Trends

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

th

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Failed Components

Failed counterweight studs

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Remainder of stud in main bearing housing

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Statements

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

INCIDENT REPORT
NAME: Gregory Bartley
DATE: September 07, 2013
TOPIC: DG #11 A2/A3 Drive Gear Failure

When I took up shift at 1600hrs from Newton Burke, I was made aware of the
status of the plant inclusive of the work been carried out on DG #11, the list
included

Investigate reported high liner temperatures on A2, A3


Change A-Bank charge air compensator (bellow) before turbo
compressor
Repair oil leak at A2 crankcase door relief valve
Change O-ring on the rocker box covers and hand wheels
Investigate and correct cause of B-bank turbine wash failure
Lubricate fuel pump racks; grease control arms and linkages
Replace B6 straight pipe
Replace A8 vertical exhaust gas bellows
Inspect and service instrumentation motors and controls on
lube oil separator unit

I was then told of the work that was conducted, which was that both A2 and
A3 liners were replaced, A2 piston replaced and torqued, A8 vertical bellows
was removed but not replaced, was then told that none of the other works
scheduled for the morning shift was attempted, then I called Phillip Martin
informing him of the work to be done just in case he saw Troy Simms before I
did.
I then read the shift summary and proceeded to the change room where I
saw mechanics Ricardo Newsome and Garron Palmer getting ready to leave I
told them they should not leave as the scope of work left to be completed on
DG #11 is a lot, for it to be returned by midnight, they insisted they had to
leave.

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Mechanic Michael Morris was the only one I saw at the time for the present
shift so I told him to proceed to DB2 DG#11 where there is an A8 vertical
bellows to be installed, he then left. I then went in search of Stefan pitters
whom I was told was working on ALOF #1, I found him and told him that he
should proceed to DG #11 to render assistance I also made my way there, on
the way I met Troy Simms where I informed him of the work to be done
including replacing A3 piston and cylinder heads for both cylinders along
with pressure testing of the injectors, I also told him that I would be seeking
assistance for the completion of the job, Craig Bernard the fourth of the
mechanics was present from the earlier shift working along with R. Newsome
and G. Palmer and continued through to the present shift.
I then got back to the office and made a call to the maintenance supervisor
Giovanni Valentine informing him of the situation he then told me he would
call out Martel Lynch and Miguel Gordon he later called back to say he got
them and they will be coming in, M. Gordon arrived and called I then made
my way to the stores to facilitate the location of the parts needed for the job,
I then made my way to DB2 where I did a sump clearance on DG #11 after
the cleaning of the sump was done on this shift no foreign particles found I
then instructed the control room operator Phillip Martin that when the HT
pipe work was completed then water should be added a liner underside
inspection done and then lube oil can be added
At 2200hrs I handed over the shift to Dawin Brown with most of the work
from prior list completed save for the completion of the A-Bank charge air
compensator (bellow) which was far advanced.

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Jamaica Energy Partners


Doctor Bird Power Plant
Engineering Report.

Report No. 20140228-DG2_FR

Você também pode gostar