Você está na página 1de 119

HOIS Good Practice Guide on In-Service Inspection of

Offshore Composite Components


HOIS GP1 Issue 2
A Report prepared for HOIS
M Wall, RJ Lee, ESR Technology
martin.wall@esrtechnology.com
May 2012

HOIS GP1 Issue 2

Authorisation Sheet
Report Title:

HOIS good practice guide on in-service inspection of


offshore composite components

Customer Reference:

HOIS

Project Reference:

UC000138-01-01-12

Report Number:

HOIS GP1

Issue:

Issue 2

Distribution List:

Open Publication

Updated

Author:

Dr Martin Wall

16/4/2012

Reviewed:

Richard Lee

16/4/2012

Authorised:

Dr Stephen Burch

2 May 2012

COPYRIGHT ESR Technology Ltd


This report is the Copyright of ESR Technology Ltd and has been prepared by ESR Technology Ltd under
contract to HOIS. Subject to the terms of the contract the contents of this report may not be reproduced in whole
or in part, nor passed to any organisation or person without the specific prior written permission of the
Commercial Manager, ESR Technology Ltd. ESR Technology Ltd accepts no liability whatsoever to any third
party for any loss or damage arising from any interpretation or use of the information contained in this report, or
reliance on any views expressed therein.

Cover photo: UT inspection of offshore GRP joint, courtesy Petrobras

ii

HOIS GP1 Issue 2

Executive Summary
This updated good practice guide covers the inspection and non-destructive evaluation
(NDE) of offshore composite components in-service and includes lessons learnt from several
inspection trials on HOIS FRP samples including the glass reinforced flow loop pipe sample
supplied by Petrobras. Specifically this guide excludes manufacturing quality control, quality
assurance or inspection, for which the reader is referred to ISO 14692.
All components that form part of a GRP piping system (e.g. pipe, branches, bends, tees,
tapers, flanges, fittings and joints) are covered. This includes piping, from 50 mm (2) to over
1 m (40) diameter, and fittings. Specific guidance is provided on composite connections
including adhesively bonded joints, laminated joints and flanged connections. Fittings include
T-joints, bends, branches and flanged connections and may typically be manually overwound
or laminated giving a wide range of wall thickness, 2 mm to 50 mm.
The guide encompasses the recommendations regarding NDE of composites in available
standards including ISO 14692, NORSOK M-622, preceding NORSOK and UKOOA studies,
and relevant API and ASTM standards. Good practice has been included from individual oil
companies design and engineering specifications, HOIS members inputs, and ESR
experience in composite inspection. Relevant published studies and initiatives in the UK
funded by the Department for Business, Innovation & Skills (formerly the Department of
Trade & Industry) and the Technology Strategy Board, TSB have been cited. In addition, a
watching brief of technologies employed in the USA on inspection and monitoring of
composites have also been assessed.
We have restricted consideration to defect types that may occur in-service or be present after
installation. It is assumed that an appropriate inspection and quality control plan has been in
place during manufacture including monitoring the state of cure in line with that in ISO 14692.
Composite vessels and tanks are not specifically included as there is limited use of these
offshore. The recommendations regarding process pipework inspection will however
generally be applicable to vessels and accessibility is often better.
Secondary structures such as ladders, walkways, gratings, and equipment housings are not
included. The major issue here is removal of the protective gel coat in marine environments,
exposing fibres. Visual inspection and painting or refurbishment of the gel coat is usually
adequate here. The inspection methods considered for pipework applications may also be
relevant to these applications if the application is safety critical.
Although this guide refers to offshore components, it is equally relevant to onshore
applications and in several cases the techniques used would be similar.
Inspection of GRP piping is generally more difficult to carry out compared to metal pipes for a
number of reasons. This includes general unfamiliarity by inspectors of inspecting
composites and the anisotropic and heterogeneous nature of these materials causing signal
noise and attenuation. Porosity and the laminated nature of the microstructure account for
some of these effects.
This guide has been updated to take account of lessons learnt from a series of inspection
trials conducted under the auspices of the FPSO and Flexible Risers Working Group on a 6
GRE spool piece (flow loop) prepared by Petrobras. The flow loop contained a number of
intentional bondline defects including paper inserts, incorrect application of adhesive and
incorrect surface preparation. The 3 metre flow loop contains two 90-degree elbows and a

iii

HOIS GP1 Issue 2


centre bell and spigot bonded joint with five separate adhesive joints. Some of these joints
had manufacturing or adhesion defects introduced in the assembly process. Differences in
joint fabrication practice have also been used in the joints.
Data obtained using manual ultrasonics were somewhat variable but were generally able to
detect the back wall echo but not necessarily the deliberately introduced defects. Automated
ultrasonics using either twin probes or phased arrays produced reasonable B-scan images
showing the layered nature of the material and in some cases reflections from the introduced
defects. Interpretation of reflected signal waveforms was more complex than would be
expected for steel components as the GRP structure is elastically anisotropic and
heterogeneous with signal attenuation due to voids/porosity and the scattering nature of the
laminated structure. It was sometimes difficult to get a consistent back wall echo with some
variability in response between joints. The inspection operators will need to familiarise
themselves with particular glass reinforced epoxy components and choose optimum probe
type. Ultrasonic B-scan images are the preferred acquisition mode as they can give a clearer
delineation of bond line defects and back wall echo. Generally the lower frequency probes
( MHz - 2 MHz) gave better sample penetration than 5 MHz probes but with reduced
resolution. Phased array wheel probes were relatively quick to scan the pipe surfaces but
had some positional difficulties around elbows and fittings due to roller sliding.
Of the various non contact inspection methods trialled, i.e. laser shearography, microwave
inspection and radiography, the latter technique produced the best images using the XRS-3
portable pulsed X-ray source used in conjunction with a GEIT DXR250P digital detector
array. In this case some details of the joints were revealed including bondline defects such
as porosity (however there was no evidence of the paper inserts) and good images of the
pipe wall and fittings.
After the inspection trials were completed the flow loop was cut open and macrophotographs were taken of joint sections to reveal the location and extent of the defects. In
many cases the joint defects were lack of adhesive and porosity. The quality of the elbow
end fittings was also assessed and showed evidence of poorly wetted out fibres which was
detected during several ultrasonic trials. A section of the centre bell and spigot joint was
prised open, as recommended by a consultant from the pipe manufacturer, to reveal the
quality of the bond.
In summary, each of the inspection trials had practical challenges and most techniques were
able to detect some of the defects. Ultrasonic inspection was able to detect loss of back wall
echo, bondline features and end fitting irregularities. Radiographic examination using digital
detectors together with image enhancement filters was able to reveal pipe wall and end fitting
details, bondline porosity and quality of adhesive fillet but not gaps in the adhesive bond.

iv

HOIS GP1 Issue 2

Contents
1.0

SCOPE ........................................................................................................... 1

2.0

REASONS FOR INSPECTION ....................................................................... 3

3.0

BACKGROUND.............................................................................................. 4

4.0

3.1

Introduction .................................................................................................4

3.2

Requirements for Non-Destructive Evaluation (NDE) .................................. 4

3.3

Factors affecting inspection.........................................................................5

3.4

Materials .....................................................................................................6

3.5

Applications.................................................................................................6

3.6

Fabrication methods....................................................................................7

3.7

Issues during installation .............................................................................7

3.8

Issues in-service .........................................................................................7

3.9

Life prediction..............................................................................................9

3.10

Painting .......................................................................................................9

3.11

Lined vessels and pipework ........................................................................9

REFERENCES ............................................................................................... 9
4.1

GRP Design, Qualification and Integrity Standards ..................................... 9

4.2

NDE Codes and Standards ....................................................................... 10

4.3

NDT Procedures .......................................................................................10

4.4

HSE good practice guides ......................................................................... 11

5.0

DEFINITIONS ............................................................................................... 11

6.0

PERSONNEL QUALIFICATIONS ................................................................ 13


6.1

Installer requirements................................................................................ 13

6.2

NDT personnel ..........................................................................................13

7.0

EQUIPMENT ................................................................................................ 13

8.0

HEALTH AND SAFETY ............................................................................... 13

9.0

8.1

Inspection .................................................................................................14

8.2

Dust hazards .............................................................................................14

DAMAGE MECHANISMS ............................................................................ 14


9.1

Overview ...................................................................................................14

HOIS GP1 Issue 2

10.0

11.0

12.0

13.0

9.2

Manufacturing defects ............................................................................... 15

9.3

Defects following handling and installation ................................................ 15

9.4

In-service defects ......................................................................................15

INSPECTION STRATEGY ........................................................................... 16


10.1

Manufacturing inspection .......................................................................... 17

10.2

Documentation required ............................................................................ 17

10.3

Handling and delivery................................................................................ 18

10.4

Inspection after installation ........................................................................ 18

10.5

In-service inspection ................................................................................. 21

10.6

HSE good practice guides ......................................................................... 22

10.7

DNV guidance for operation and in-service inspections ............................ 23

10.8

Inspection strategy for life extension and ageing ....................................... 23

10.9

When to Inspect ........................................................................................26

SELECTION OF NDE METHODS ................................................................ 26


11.1

Manufacturing inspection .......................................................................... 33

11.2

After installation ........................................................................................33

11.3

In-service ..................................................................................................33

INSPECTION PRACTICE BY COMPONENT............................................... 33


12.1

Pipework ...................................................................................................36

12.2

Fittings ......................................................................................................38

12.3

Supports ...................................................................................................38

12.4

Joints ........................................................................................................39

12.5

Adhesively bonded joints........................................................................... 40

12.6

Laminated joints ........................................................................................42

12.7

Flange connections (fixed and loose ring designs) .................................... 44

12.8

Repairs .....................................................................................................45

INSPECTION GUIDANCE BY DEFECT TYPE ............................................ 45


13.1

Delaminations ...........................................................................................45

13.2

Erosion or loss of wall thickness................................................................ 47

13.3

Impact damage .........................................................................................48

13.4

Matrix cracking ..........................................................................................49

13.5

Significant cracks ......................................................................................51

13.6

Materials degradation................................................................................ 52

13.7

Environmental ingress and weepage (matrix cracking and delamination) .. 53

vi

HOIS GP1 Issue 2

14.0

NDE METHODS ........................................................................................... 53


14.1

Validation and calibration samples ............................................................ 53

14.2

Visual inspection .......................................................................................55

14.3

Pressure testing ........................................................................................56

14.4

Ultrasonics ................................................................................................57

14.5

Radiography..............................................................................................62

14.6

Tap testing ................................................................................................65

14.7

Thermography...........................................................................................67

14.8

Shearography ...........................................................................................69

14.9

Acoustic emission .....................................................................................71

14.10

Acousto-Ultrasonics ..................................................................................72

14.11

Microwave inspection ................................................................................ 73

14.12

Differential Scanning Calorimetry (DSC) and hardness tests (e.g. Barcol or


Shore) .......................................................................................................76

15.0

MONITORING METHODS ............................................................................ 76

16.0

DEVELOPING NDE METHODS ................................................................... 77

17.0

EVALUATION AND ASSESSMENT ............................................................ 78

18.0

FAILURE PREVENTION .............................................................................. 80

19.0

ACKNOWLEDGEMENTS ............................................................................ 80

Appendices
APPENDIX A GRP CODES AND STANDARDS................................................ A-82
APPENDIX B INSPECTION GUIDANCE FROM ISO 14692 .............................. B-85
APPENDIX C DAMAGE MECHANISMS IN COMPOSITES .............................. C-97
APPENDIX D EXAMPLES OF IN-SERVICE DEGRADATION OF COMPOSITE
COMPONENTS ......................................................................... D-110

vii

HOIS GP1 Issue 2

1.0 Scope
This good practice guide covers the inspection of offshore composite components in-service
and after installation. The focus is on inspection of low to medium pressure process
pipework (~10-50 bar), the primary application of composites offshore. This good practice
guide specifies additional and optional requirements to ISO 14692 (all parts). All components
that form part of a GRP piping system (e.g. pipe, branches, bends, tees, flanges, and joints)
are covered. The good practice is directed towards piping systems in GRP materials used on
offshore production platforms, but may also be used for similar onshore systems dependent
on the location and fabrication method.
Composite materials in the context of this good practice guide are defined as, and limited to,
fibre reinforced thermosetting matrix (or resin) systems. These have several features that
make them attractive for use in the Oil and Gas industry, namely ease of installation, light
weight and good corrosion resistance. Glass fibres are the most common reinforcement and
epoxy resins are primarily used as the matrix material. Other types of resins can be used
depending on the application and in many cases corrosion resistant liners are used which
may affect the inspection results obtained.
Conventional inspection strategy and practice is described. In addition, this document
provides guidance on selection and how to apply non-destructive examination (NDE) and
testing (NDT) methods; an area where very limited guidance is available in existing
standards such as ISO 14692. Newer NDE methods such as microwave inspection, acoustoultrasonics, tap-testing, ultrasonic B-Scan and laser shearography are also included in
addition to those found in the main industry standards ISO 14692, NORSOK M622 and the
ASME Boiler and Pressure Vessel Code Section V. Such methods are widely used
elsewhere for inspection of composites and are starting to find application in the Oil and Gas
sector.
All components that form part of a GRP piping system (e.g. pipe, branches, bends, tees,
tapers, flanges, fittings and joints) are covered. This includes piping, from 50mm (2) to over
1m (40) diameter, and fittings. Specific guidance is provided on composite connections
including adhesively bonded joints, laminated joints and flanged connections. The guidance
is applicable both to high quality filament wound pipework, and to piping systems that have
been manufactured by manual overwinding or hand laminated giving variability in thickness
and surface quality. Wall thicknesses ranging from 2mm to 50mm are considered. Higher
wall thicknesses are generally associated with fittings or connections.
Inspection of GRP piping is generally more difficult to carry out compared to metal pipes for a
number of reasons. This includes general unfamiliarity by inspectors of inspecting
composites and the anisotropic and heterogeneous nature of these materials causing signal
noise and attenuation. Porosity and the laminated nature of the microstructure account for
some of these effects.
This document is directed towards GRP piping and components used topside on offshore
production platforms, but may also be used for similar onshore systems. The same
technologies have applicability to subsea, downhole and pipeline applications of composites,
though there will be issues in terms of access and marinisation if carried out in-situ.
The following generic component types have been considered in the development of the
NDE recommended practice:

HOIS GP1 Issue 2


Process pipework and fittings

Filament wound piping 2 to 40 diameter, 2mm to 50mm wall thickness;


Tapered, laminated or moulded fittings, t-joints (5mm to 50 mm wall thickness).

Connections

Adhesively bonded joints;


Laminated joints;
Flange connections (fixed and loose ring designs).

These encompass most currently relevant topside components offshore.


This good practice guide does not specifically cover composite vessels and tanks as there is
limited use of these offshore. The recommendations regarding process pipework inspection
will however, generally be applicable to vessels and accessibility is often better. Established
practice has developed for inspection of lined and unlined GRP vessels and tanks in
refineries using ultrasonic B-scanning and TOFD in addition to visual inspection.
The guide encompasses the recommendations regarding NDE of composites in available
standards including ISO14692, NORSOK M-622, preceding NORSOK and UKOOA studies
and relevant US standards such as API, ASME and ASTM. Elements of good practice have
also been included from individual oil companies design and engineering specifications
together with inputs from various HOIS members and ESR general experience in composite
inspection. Relevant published studies and initiatives in the UK funded by the UK
Government such as the former DTI and the Technology Strategy Board; in the USA on
inspection and monitoring of composites; and aerospace, defence, military and space
standards have also been assessed.
We have restricted consideration to defect types that may occur on installation or in-service.
It is assumed that an appropriate inspection and quality control plan has been in place during
manufacture including monitoring the state of cure in line with that in ISO 14692.
The NDE technology discussed could also be applied to structural beams, pultruded sections
and secondary structures such as ladders, walkways, gratings, and equipment housings.
The major issue here is removal of the protective gelcoat in marine environments, exposing
fibres. Visual inspection and painting or refurbishment of the gelcoat is usually adequate
here. The inspection methods considered for pipework applications may also be relevant to
these applications if the application is safety critical.
For structural components such as beams an appropriate life management strategy should
be put in place in line with ISO 14692 and relevant ASTM standards.
Thermoplastic polymers and reinforced thermoplastics (RTPs) are outside the scope of this
guide, although the same NDE methods are likely to be applicable. Resins commonly used in
RTP include polyethylene (PE), polypropylene (PP), and polyamide (PA-Rilsan) and
polyvinyldifluoride (PVDF).
In many cases visual inspection is the only method used for composite components after
they enter service and provided the system design accounts for all anticipated loadings
(including thermal and axial loads, pressure and surge forces, etc.) and they are installed
correctly can provide many years of service often in severe corrosive environments.

HOIS GP1 Issue 2

2.0 Reasons for inspection


Integrity management of composite materials is less developed than for metallic materials.
This tends to be application specific and relies on engineering judgement. Problems are most
likely to be encountered during or after installation. If properly installed, composite
components are normally very tolerant of service conditions and few problems are likely to
occur during the design life (typically 20-25 years). Hence, it is usual to apply just visual
inspection and routine pressure testing after installation. Non destructive evaluation (NDE)
methods may be applied in the following circumstances:

For safety critical components;

For quality assurance reasons;

Following installation;

Where problems have been encountered in service;

For re-qualification following any repairs;

To assess quality of adhesive joints;

To establish current condition of the component and ageing encountered;

To assess in-service damage;

To assist in assessment of remnant life;

For plant life extension;

If required for health and safety reasons or to satisfy legal or regulatory


requirements;

To establish condition of the lining in lined vessels;

To determine condition relevant parameters such as glass transition


temperature tg, Barcol hardness or coupon testing;

To verify that the component is performing in accordance with its design


intent;

As part of an integrity management strategy;

Identify deviations from specifications or functional requirements as early as


possible and form a basis for corrective action.

The role of inspection is to assure technical integrity during operations and form a basis for
maintenance evaluation/planning. It may also serve to provide a fitness-for-purpose
evaluation and contribute to the improvement of current and future designs and inspection
strategy. Composites are becoming used in an increasing range of structural and process
applications, and at higher pressures and more severe environments. For this reason NDE
in-service is becoming more common.

HOIS GP1 Issue 2

3.0 Background
3.1

Introduction

Fibre reinforced plastic (FRP) composite materials are seeing increased use in the Oil and
Gas industry. Composite materials have been used in chemical, processing and refinery
applications for over 40 years primarily in containment applications. The first application in
the North Sea was in the early 1980s 1. Corrosion resistance, light weight and in some cases
design flexibility and continuous manufacture are the primary business drivers, which when
used to advantage in design, can lead to either reduced life-cycle costs or improved safety.
There are also advantages in ease of fabrication, mechanical and chemical properties and
cost.
Composites are fundamentally different to metallic materials, and provided the correct resin
and fibre types have been selected and the components are properly installed and qualified,
few issues are normally encountered in service. Particular problems may be encountered
with adhesive joints especially those made in the field. Material selection in corrosive
environments is a specialist area and end users are reliant on service experience and advice
and ratings supplied by the main composite suppliers.

3.2

Requirements for Non-Destructive Evaluation (NDE)

The application of non-destructive evaluation (NDE) methods on composites is primarily


undertaken on manufacture. Currently, very little in-service NDE inspection is performed on
composites on offshore installations.
Composites are traditionally conservatively designed to allow for in-service damage and
based on previous experience. Reliance is placed on proof testing following installation with
visual inspection and dimensional checks. Whether this is the best approach in the longer
term remains to be established. NDE in-service is often more difficult and less widely done.
Installation of composite components is not always straightforward and service difficulties
can often be traced back to incorrect installation. There is also an increased use of
composites in more structural applications and in more severe environments. For these
reasons, it is becoming more important to understand the degradation that may occur in
material properties in service and to confirm that installation has been effective.
Composites offer particular advantages in weight and corrosion resistance for floating
installations such as floating production storage and offloading vessels (FPSOs). Minimising
topside weight is a key issue for floating installations. Applications of composites in FPSOs
include water treatment, firewater mains and secondary structures.
FPSOs can also offer a more challenging environment due to hull motion and movement of
the vessel under wave loading. This can lead to a specific requirement for in-service NDE of
composites due to issues that have arisen in offshore service. This includes the fatigue of
longer pipe sections under wave loading of the vessel in FPSOs, cracking of pipe flanges
following installation, and failure of adhesively bonded connections.
The lack of detailed procedures and qualification of NDE methods for offshore may limit the
uptake of composites in more challenging process applications offshore.

HSE research Report RR039 Cost Effective use of composites offshore; Part B: Summary of the Joint industry industry programme on the cost effective use of fibre reinforced composites offshore. UK Health & Safety
Executive HSE; HSE Reports, 2003 http://www.hse.gov.uk/RESEARCH/rrhtm/rr039.htm

HOIS GP1 Issue 2

3.3

Factors affecting inspection

The main factors affecting inspection of composites offshore are access, surface finish,
material quality, complex geometry and thickness. These and other factors such as
unfamiliarity with composites may limit the applicability of traditional NDE methods such as
ultrasonics and favour composite or polymer specific methods such as microwave inspection,
thermography, acoustoultrasonics or radiography for complex geometries and thick
sections. An advantage is the fact that composites generally have good defect tolerance and
fatigue properties.
The way in which NDE methods are applied is similar to metallic materials though the types
of defects that may be present are different. Delamination and disbonding are the most
important defects compared to cracking in metallic materials. Composites are damage
tolerant and can support a significant amount of damage compared to steel where an
individual fatigue crack can become critical and lead to failure.
Composite materials by their construction and diverse methods of fabrication pose some
physical challenges and benefits to inspection as some are transparent or translucent. Their
mechanical properties are generally anisotropic (in many cases they are orthogonally
anisotropic, i.e. orthotropic) due to the methods of lay-up and the different properties of
polymer and reinforcement. Surface roughness is generally higher than would be expected
for a metallic pipe and hence there may be difficulties in probe coupling. Composite materials
are usually more highly attenuating than steel and lower frequencies are used when
inspecting using ultrasonics.
There are differences associated with individual NDE methods. Visual inspection can show
up a wider range of defects in composites. With suitable illumination it is possible to look
through some composite components to see internal defects. Ultrasound is more highly
attenuated by composites due to the many internal interfaces and porosity so it is normally
necessary to use lower frequencies. The surface finish can also pose difficulties in coupling.
Common electromagnetic methods such as eddy current and magnetic particle inspection,
MPI, are not applicable to glass-fibre reinforced epoxy (GRE) composites as the materials
are non-conducting. Composites are less absorbing of X- or gamma- rays so it is necessary
to use lower energy sources or less penetrating isotopes. Thermal diffusion is slower than in
metals which simplify thermography inspection. Long wavelength methods such as
microwaves which would cause reflection on metal surfaces are well suited to polymers and
composites because of their dielectric properties and better match of wavelengths to
microstructural differences. Similarly surface strain measurements such as laser
shearography are easier because of the lower stiffness and the ease of distortion of
composites compared to metals.
Composite components are often painted for cosmetic or protective reasons. This may be
for pipe identification and also provide some additional protection against ultra-violet rays
(UV) or from the external environment. A consequence is that it is no longer possible to
inspect the component visually using internal illumination, a standard method. In this case
detection and monitoring of service damage may be more difficult.
On FPSOs process equipment can be more closely packed than on conventional platforms
making access for NDE difficult.

HOIS GP1 Issue 2

3.4

Materials

The composite materials used in the offshore industry are primarily glass fibre reinforced
plastic (GRP) which can be used in tanks, vessels or piping systems. A variety of glass fibre
types and resins may be used dependent on environment and conditions.
The primary fibre used is glass, although carbon and aramid are used in limited applications.
The primary resin system (thermosetting) used is epoxy or polyester, although vinyl esters,
polyurethanes and furanes are also used to a limited extent. The method of manufacture is
predominantly filament winding implying continuous fibre composites, although some
components are pultruded, resin transfer moulded or made by hand lay-up.

3.5

Applications

Composites are used in an increasing range of applications, Figure 1. Off-shore applications


are diverse and include pipework, e.g. fire water mains systems, water injection systems,
and access structures. Generally speaking, the major use of composite components offshore
is in pipework and containment applications.
The most commonly used composite structure is filament wound glass fibre reinforced
thermosetting plastic matrix (GRP) pipe, often epoxy, polyester or vinyl ester. Typically, these
GRE pipes range in diameter from 50 to 4000 mm. Pressure ratings range from 5 to 120 bar,
the higher pressure ratings only applicable to smaller pipe diameters.
The primary applications of composites within the Oil and Gas industry include:

piping systems;
process equipment;
access equipment (stairs, gratings);
beams;
modules and secondary structures;
tubing and casings;
tanks and vessels;
lifeboats;
risers;
pipelines;
mudmats;
protective covers.

HOIS GP1 Issue 2

Figure 1 Example of GRP pipework offshore. Left, water treatment and firewater mains
GRP components, Petrobras P50 FPSO (Courtesy Petrobras); right, GRP firewater mains.

3.6

Fabrication methods

Commercial grade composites in these industries are normally produced by filament winding,
with increased use of moulding processes such as resin transfer moulding (RTM). Manual
overlay, lamination or moulding is used on filament wound pipe in the tapered regions
associated with nozzles, flanges, manifolds and attachments.

3.7

Issues during installation

Correct handling and installation is important for composite components. There is a risk of
surface or impact damage. Adequate supports are required for pipework, in accordance with
the guidance in ISO 14692. Care is needed in preparation of adhesive and laminated joints
to ensure good alignment, clean surfaces and adequate distribution and curing of adhesive.
A common issue for flanged joints is over-tightening leading to overstressing of joints and
flange cracking. The integrity and leak tightness of piping systems is usually verified by
pressure testing. Composite pipework is normally subjected to thorough inspection and
acceptance criteria at the manufacturing stage in accordance with ISO 14692. There is the
likelihood that some manufacturing flaws, usually benign, may carry through to service in the
nature of the fabrication methods used.

3.8

Issues in-service

Composites do not corrode in the conventional sense but can be subject to a number of
degradation mechanisms in-service, including: physical ageing, mechanical ageing and
chemical ageing. The consequence of these can be a reduction of 20 - 40% or greater in the
strength characteristics of the polymer during the lifetime of the component and introduction
of damage including matrix cracking and delaminations. This is handled in design codes by
use of regression curves based on short term and longer term (typically 1,000h and 10,000h)
tests to determine the qualification pressure for the component and the allowed operating
pressure over the design life.
There is concern about whether such methods of life assessment are sufficiently robust,
given the increasing diversity of applications in which composites are applied. In contrast to
steel vessels or pipework, where non-destructive methods such as ultrasonics,
electromagnetics and radiography are widely applied, very little inspection other than visual

HOIS GP1 Issue 2


inspection or pressure testing is currently undertaken on composite components in the
offshore, chemical, process and petrochemical industries.
Limited guidance on in-service NDE methods for composites is included in offshore GRP
standards notably ISO 14692 (currently under revision) and NORSOK M-622. These provide
general guidance on NDE methods that may be applicable but limited information on the
practical application of the methods. Moreover there has been significant development of
newer NDE methods in other industries, such as aerospace and marine, which do not feature
in these current standards. There is a need to assess the potential benefits of these methods
in offshore applications and to provide a more rigorous recommended practice to guide their
application.
There are limitations in the testing methods used in ISO 14692 and ASTM standards to
estimate the regression curve or degradation that may occur with ageing in service. Most
studies are in water rather than organic solvents or the other fluids that are seen in service.
Tests are also expensive to run (ASTM D2992 asks for data up to 2 years) thus the lack of
widespread usage of these tests in environments aside from water. Recent developments
have been to use 1,000h tests as a shorter term alternative to confirm long term properties.
Immersion testing rather than single-sided exposure mechanisms may cause mass gain as
well as loss; so single-point data is of limited use in prediction of longer term degradation.
Service components suffer environmental degradation from the surfaces; hence the
degradation seen in immersion tests may be worse than seen in practice 2. Most ageing
studies accelerate ageing by testing for a shorter time (~1,000h) at a more elevated
temperature. Small temperature increases above the service temperature but below the resin
glass transition temperature (Tg) can offer useful indications of long term behaviour 3.
However, if the mechanisms encountered over the longer term differ to those in the
accelerated tests the degradation curves and predictions of remnant life obtained may be
unrepresentative.
A diversity of environments can be encountered in the oil, gas and process industries. These
can cause damage to both matrix and the fibres. It is important that the resin and fibre types
are correctly selected for the application to maximize the resistance in service. In Oil industry
applications a corrosion resistant layer (or veil) containing more resistant fibres and gel coat
is commonly applied to the surface. Similar practice may be used in chemical applications.
Such layers are effective at preventing environmental damage but are relatively thin
(~200um). It is important to confirm on visual inspections that excessive grazing of the gel
coat has not occurred and that damage has not occurred to these protective layers.
Areas of pipe bends, variations in wall thickness, support or change in geometry are
particularly susceptible to damage or degradation in composite systems. These may
encounter local stress concentrations and care is needed in design to ensure these can
adequately support the operating pressures of the piping or vessel and that the allowance
made in regression curves for ageing is sufficient.
Composites are more susceptible to impact damage than conventional materials, but also
exhibit a good tolerance. In most cases this is benign and repairable, though may affect
residual life. Significant impact damage can produce immediate weepage and partial loss of
containment. It is important that impact damage is identified and repaired if necessary.
For all these reasons, more application of NDE methods in-service would be beneficial.
2

Ageing of composites in oil and gas applications, S Frost; Ageing of Composites, Ed. Rod Martin, Chapter 14 p
375-395, Woodhead publishing, ISBN 978-1-84569-352-7, 2008
3
ISO/TS 24817 Petroleum, petrochemical and natural gas industries- Composite Repairs for pipeworkQualification and design, installation, testing and inspection; 2006

HOIS GP1 Issue 2

3.9

Life prediction

In the onshore and offshore Oil and Gas industries a more robust approach is developing2 to
life prediction and extension, based on materials characterisation and non destructive
evaluation of the actual damage in service components. This offers to improve the accuracy
of life prediction and reduce the risk of premature failure. There would be benefits in
extending such good practice more widely in the offshore and onshore industries.

3.10

Painting

External painting is not required since GRP is not subject to atmospheric corrosion. If
painting is necessary for other reasons, the surface should be lightly blast-cleaned before the
paint system is applied and painting should be carried out after inspection and test of the
component. Painting is detrimental to inspection as it impedes visual inspection methods
particularly where internal illumination is used.

3.11

Lined vessels and pipework

In chemical and onshore processing applications, pressure vessels and piping are often lined
with polyethylene or other resistant polymers. Most GRP pipework offshore is unlined. There
are particular issues for lined or painted GRE vessels or pipework. If a lining is used then a
compromise may be made on the resin and fibres used in the GRE vessel. These may not
be as resistant as would be used if the GRE was exposed to the environment. It is important
in this case to monitor the lining condition since lining failure could lead to degradation and
failure of the GRE vessel in a shorter timescale than might typically occur for an unlined
vessel exposed to the same environment.

4.0 References
The following codes and standards have been considered and have been referred to in this
good practice guide. The latest issue of the references shall be used unless otherwise
agreed. Other recognized standards may be used provided it can be shown that they meet or
exceed the requirements of the standards referenced below.

4.1

GRP Design, Qualification and Integrity Standards

ISO 14692-1, Petroleum and natural gas industries Glass-reinforced


plastics (GRP) piping BS EN ISO Part 1: Vocabulary, symbols, applications
and materials.

ISO 14692-2, Petroleum and natural gas industries Glass-reinforced


plastics (GRP) piping BS EN ISO Part 2: Qualification and manufacture.

ISO 14692-3, Petroleum and natural gas industries Glass-reinforced


plastics (GRP) piping BS EN ISO Part 3: System design.

ISO 14692-4, Petroleum and natural gas industries Glass-reinforced


plastics (GRP) piping BS EN ISO Part 4: Fabrication, installation and
operation.

Det Norske Veritas Offshore


components, January 2003.

Standard;

DNV-OS-C501,

Composite

HOIS GP1 Issue 2

4.2

4.3

NORSOK STANDARD M-622 Fabrication and installation of GRP piping


systems Rev. 1, April 2005 (Replaces M-621 and M-622 (1999), based upon
ISO 14692 (all parts), but extended with sections on quality control and
NDT).

ASME BPVC Section X Fibre-reinforced plastic pressure vessels, The


American Society of Mechanical Engineers.

NDE Codes and Standards

ASTM D2563 Standard Practice for Classifying Visual Defects in GlassReinforced Plastic Laminate Parts.

EN 473 Non-destructive testing Qualification and certification of NDT


personnel General principles.

ASTM E1067 Standard Practice for Acoustic Emission Examination of


Fiberglass Reinforced Plastic Resin (FRP) Tanks/Vessels.

ASTM E1495 02 Standard Guide for Acousto-Ultrasonic Assessment of


Composites, Laminates, and Bonded Joints.

ASTM E2191 - 08 Standard Practice for Examination of Gas-Filled FilamentWound Composite Pressure Vessels Using Acoustic Emission.

ASTM E2832 Standard Practice for Active Thermography of Composite


Panels in Aerospace Applications.

ASTM E2582 - 07 Standard Practice for Infrared Flash Thermography of


Composite Panels and Repair Patches Used in Aerospace Applications.

ASTM D 2563 Standard Practice for Classifying Visual Defects in GlassReinforced Plastic Laminate Parts.

ASTM WK 12737 Standard Practice for Shearography of Flat Panel


Sandwich Core Materials Used in Aerospace Applications.

NDT Procedures

The following procedures have also been developed but have not reached full standards
recognition:

DRA/NPL Working Draft Standard v05, Fibre Reinforced Plastics


Ultrasonic C-scan inspection of composite structures: Parts 1-6, National
Physical Laboratory & QinetiQ Ltd.

Aker Recommended Practice on radiography of GRP offshore.

Offshore generic ultrasonic procedure (ESR, DTI CPD4D).

Ultrasonic A-scan and B-scan procedures (ESR, DTI CPD4D).

Ultrasonic C-scan procedure (ESR, DTI CPD4D).

Active thermography procedure (ESR, DTI CPD4D).

Laser shearography procedure (ESR, DTI CPD4D).

Ultrasonic TOFD practice GRP vessels (ESR, Sonomatic).

10

HOIS GP1 Issue 2

4.4

Escape craft NDT procedures (Amerada Hess and others).

HSE good practice guides

Concise good practice guides have recently been produced by HSE on FRP pipe and
composite overwrap repairs. Designed for HSE inspectors, these provide simple summaries
on what can go wrong, damage mechanisms and normal inspection practice (based on ISO
14692). Photographs are included showing damage mechanisms. The latter included advice
from members of the Association of Composite Repair Suppliers AcoRes originally formed
by ESR Technology.

HSE GRP pipe fact sheet, Health and Safety Laboratories HSL; Final draft
Revision 1, 2009.

FRP composite repair fact sheet, Health and Safety Laboratories HSL; Draft
Final, 2009.

5.0 Definitions
For the purposes of this practice document, the following terms, definitions and abbreviations
apply in addition to those in ISO 14692 Part 1.
E-glass

Glass fibre normally used to reinforce GRP pipes, consisting


mainly of SiO2, Al2O3 and MgO.

ECR or C-glass

Glass fibre or synthetic veil having a better chemical resistance


against acids than E-glass, used primarily as reinforcement for
the resin-rich internal liner.

Fittings

Pressure-tight fluid containing components with geometry


different from straight pipe (e.g. flanges, tees, elbows, reducers
etc.).

Hand lay-up

A process for fabricating a composite structure in which


discontinuous reinforcements (woven mats, chopped strand
mats) are impregnated with a matrix material and are manually
applied on a mandrel.

In-field hydrostatic test Short term hydrotest after installation, used as a leak test.
Defined as 1.5 times the system design pressure.
Mill hydrostatic test

Short term hydrotest at the mill (or factory), used as a quality


control check. Defined as 1.5 times the nominal pressure
rating.

Phenolic

A class of polymer resins made from phenol and formaldehyde,


and cured by air drying or heat baking. Chemical resistance
can be further increased via heat and catalyst treatment.

Pipeline system

Pipe with components subject to the same design conditions


and typically used to transport fluids between wells and field
facilities, field facilities and processing plants, processing plants
and storage facilities.

Piping components

Mechanical elements suitable for joining or assembly into


pressure-tight fluid containing pipeline or piping systems.
Components include bends, reducers, tees, flanges, gaskets,
bolting, valves, and devices such as expansion joints, flexible

11

HOIS GP1 Issue 2


joints, pressure hoses, liquid traps, strainers and in-line
separators.
Piping system

Pipe with components subject to the same design conditions


and typically used within a processing facility. The piping
system also includes pipe supports, but does not include
support structures.

Regression curve

Decay curve based on short and long term testing at the design
stage to show the predicted degradation in materials properties
and safe operating pressure during the design life of the GRP
component (See ISO 14692 for use and derivation).

R-Glass

Glass fibre having a better chemical stability than E-glass in


high pH environments.

S-Glass

Glass fibre having a higher strength than E-glass and


considerably more expensive than E-glass.

The following abbreviations are used:


DN

Nominal diameter

DSC

Differential scanning calorimetry

DWSI

Double wall single image

ECR

Glass fibre grade with good chemical resistance in acidic environment

EX

Classification of explosion hazards

FRP

Fibre reinforced plastic

GRE

Glass-fibre reinforced epoxy

GRP

Glass-fibre reinforced polyester

GRVE

Glass-fibre reinforced vinylester

HSE

Health and Safety Executive (U.K.)

MAWP

Maximum Allowable Working Pressure

MW

Microwave

NDE

Non-destructive evaluation

NDT

Non-destructive testing

NPD

Norwegian Petroleum Directorate

PE

Pulse echo

PED

Pressure Equipment Directive

RT

Radiographic testing

UT

Ultrasonic testing

TT

Transient thermography

12

HOIS GP1 Issue 2

6.0 Personnel qualifications


6.1

Installer requirements

All pipe, fittings and related items shall be installed by qualified GRP pipe fitters and
thereafter approved by a qualified GRP piping inspector. GRP pipe fitters and GRP piping
inspectors shall be qualified according to the minimum requirements detailed in Annex D of
ISO 14692 Pt 4.
As an alternative, the pipe fitters, supervisors and inspectors maybe qualified in accordance
with another internationally recognised certification scheme based on acceptance by the
company.

6.2

NDT personnel

NDT Personnel should be qualified in accordance with a recognised international code and
standard such as EN 473.
It is recommended that all personnel carrying out visual or NDE inspection of GRP
components have appropriate certification (ASTM, CSWIP etc) for the NDE method and
specific experience in the inspection of GRP components.
Routine inspections may be carried out by a Level I inspector with Level II supervision. More
sophisticated NDE methods such as transient thermography or shearography should be
undertaken by a specialist practitioner in the NDE method, preferably with at least Level II
certification.
NORSOK M622 recommends that ultrasonic inspectors shall be qualified according to EN
473, Level 2 or equivalent. Additionally, they shall also have had specific training for GRP
pipe joints in the ultrasonic test method to be used.
Within Europe, NDT inspectors of joints in piping systems falling into category III and IV
(equipment/vessels) according to PED, shall be approved by a 3rd party organisation
recognised by an European Union (EU) member state.

7.0 Equipment
The NDE equipment to be used for the inspection shall be portable and rugged enough for
the intended service. Equipment intended for laboratory use will normally not be suitable for
field use. In particular moisture is detrimental. If outdoor testing is performed, the necessary
precautions shall be taken to protect the equipment from rain, wind etc.
Most offshore platforms have EX 1 zones in which no electric equipment that can produce
sparks is allowed. The operator of the NDE equipment shall ensure that the equipment to be
used fulfils the EX requirements, or obtain special permission from the safety department on
board to execute the inspection in special zones, in shutdown periods, etc.

8.0 Health and Safety


In general, all safety precautions set forth by the manufacturer of pipes and fittings,
chemicals, etc., shall be adopted. Materials safety data sheets should always be read before

13

HOIS GP1 Issue 2


commencing work. The installer shall follow the health and safety guidance given in Annex F
of ISO 14692 Part 4.

8.1

Inspection

In general, all safety precautions relevant to the NDE method being deployed should be
followed as in the test procedure. Individual NDE methods such as radiography,
shearography, thermography or microwave inspection will have their own specific safety
requirements.

8.2

Dust hazards

During machining of GRP, a dust mask and adequate work clothing should be worn in order
to prevent inhalation of, or skin irritation by, the glass-fibre dust produced. Machining should
be done in a well-ventilated room or in the open air in order to minimize contact with dust. In
the workshop a portable dust extraction unit should be used with the point of extraction as
close as possible to the work.

9.0 Damage mechanisms


9.1

Overview

Composite components are subject to ageing by a number of processes which can reduce
the strength and properties of the pipework. This includes physical ageing, mechanical
ageing and chemical ageing. These are normally allowed for in design through regression
curves, encompassed in relevant design standards such as ISO 14692. A detailed overview
of damage mechanisms in composites can be found in Appendix C.
Physical ageing processes include moisture ingress, swelling and plasticization common with
other polymeric components. These processes are referred to as static fatigue. Mechanical
ageing refers to the development of defects during service including matrix cracking,
delaminations and impact damage. Chemical ageing refers to environmental processes that
change the chemical structure or bonding within the component and therefore degrade its
physical properties; this includes hydrolysis, and modification of bonding or cross linking.
These ageing processes apply equally to adhesive as well as the composite resin and result
in a change in the glass transition temperature tg and properties.
In its broadest definition ageing can be defined as the reduction in performance of a
component as a function of the applied conditions. The three primary causes of ageing for
composite components in the Oil and Gas industry are through chemical species ingress,
elevated operating temperature and length of time of load application.
Service experience in the Oil and Gas sector is that damage to the composites from ingress
of the environment (internal or external) is minimal and does not significantly affect materials
properties. Progressive damage may occur under service loadings by matrix cracking, the
normal response of composite materials to loading.
For process pipework the main service risk is weepage of the process fluid eventually
leading to failure of component. The other failure mode of concern is fibre failure. Generally,
this occurs at the ultimate load-bearing capacity of the composite component and results in
gross failure. The ageing process accelerates the failure process, be it increasing the density
of micro-cracks, affecting the glass transition temperature Tg, changing the physical
properties of the matrix, or reducing the strength of fibres.

14

HOIS GP1 Issue 2


Offshore GRP components in-service are designed so that the loading is insufficient to cause
fatigue or stress corrosion cracking. Fatigue can be relevant in aged components or in new
designs due to inadequacies in the design or variations in loading beyond that allowed for.
There is experience of fatigue cracking of GRP piping in FPSOs where longer pipe lengths
have been used than normal.
Defects can occur in either the GRP material or in the mechanical and/or adhesive-bonded
joints that make up the piping system. Joint defects, including defects in prefabricated pipe
spools, are more likely to occur than defects in the GRP material, provided QA procedures
are followed during manufacture, handling and delivery. Care is needed in the preparation
and assembly of adhesive joints as well as recognition of the degradation and ageing of the
adhesive bond that will occur in service. Other relevant mechanisms include impact damage,
disbonding, flange cracking, erosion, cavitation and environmental ingress.

9.2

Manufacturing defects

The possible causes of manufacturing flaws, and an overview of NDE techniques suitable for
detecting these defects, are summarized in the Tables in ISO 14692 and NORSOK M-622
together with acceptance criteria. These tables are included in Appendix B.
Manufacturing and handling defects are outside the scope of this guide except insofar as
they carry over into the service component and affect service life or the properties in service.

9.3

Defects following handling and installation

Defects that can potentially occur during handling and installation are summarised in ISO
14692 Pt. 4, Table 4, (see Appendix B). The main issues of concern to operators are impact
damage and problems with adhesive joints.
Defect types include the following:

9.4

Impact wear or abrasive damage;

Barely visible impact damage (BVID);

Incorrect curing of adhesively bonded or laminated joint;

Misaligned joints;

Defects in adhesive bond (disbond, kissing bonds, lack of adhesive, excess


adhesive);

Flange cracks and leaks;

Residual manufacturing flaws.

In-service defects

The relevant in-service defects for which NDE inspection is considered in offshore vessels,
tanks, process pipework and fittings are as follows:

Ageing, materials degradation;

Matrix cracking;

Delamination;

15

HOIS GP1 Issue 2

10.0

Disbonding;

Weepage (matrix cracking and delamination);

Impact damage;

Fatigue;

Fibre failure;

Erosion or wall loss;

Cavitation;

Significant cracks;

In lined pipework or vessels the possibility of liner damage or disbonding


should also be considered.

Inspection Strategy

The operator shall define an inspection strategy for the GRP systems and components to
identify system criticality and the requirements for inspection. This shall cover:

manufacturing control and following installation;

detection of in-service damage;

detection of damage due to accidental loads or overloads at all stages;

detection of damage due to unexpected high degradation of long term


properties.

Inspection shall be linked to possible failure modes and mechanisms identified in the design
or experienced on installation or in-service. The strategy shall at least contain:

the items to be inspected, arranged according to their order of importance;

the parameters to look for and or measure, e.g. cracks, delaminations,


impact damages, overheating (or damages from local burning), visible
overloading (bending, unintended use), discoloration;

methods of inspection to be applied for each item;

inspection frequency;

acceptance criteria;

reporting routines.

Guidance on the development of an inspection strategy for GRP components can be found in
ISO 14692 Part 2 Annex H, which groups components for inspection in terms of criticality,
probability of failure and consequences. This is referred to below and the relevant Tables
are reproduced in Appendix B. NORSOK M-622 includes additional and optional
requirements beyond that provided in ISO 14692 as well as a specific and different grouping
for pre-fabricated pipe spools and adhesive joints. The Operator should specify which
grouping method is being followed.
Specific guidance on inspection for other reasons, such as life extension, defect detection or
due to service reasons is provided later in this Section.

16

HOIS GP1 Issue 2


In projects where more than one set of Regulatory Authorities' rules apply or several
contractors are involved, only one inspection strategy and one common inspection
programme shall apply for the GRP piping system.

10.1

Manufacturing inspection

The possible causes of manufacturing flaws, and an overview of NDE techniques suitable for
detecting these defects, are summarized in the Tables in ISO 14692 and NORSOK M-622
together with acceptance criteria (See Appendix B).
Manufacturing processes used to produce fittings are typically more complicated and less
automated than those used to manufacture pipes. The manufacturing problems which may
occur tend, therefore, to be more prevalent in the fittings, and NDE of fittings should be
prioritised.
Manufacturing and handling defects are outside the scope of this guide except insofar as
they carry over into the service component and affect service life or the properties in service.

10.2

Documentation required

All relevant as-built drawings and records shall be available and maintained. It is
recommended that as a minimum these include the following details:

pipe nominal diameters and pipe wall thicknesses;


key layout dimensions;
location of supports/restraints;
fire classification and location of fire-rated pipe, if applicable;
conductivity classification, location of conductive pipe, location of earth-grounding
points, earth continuity requirements, frequency and method of inspection.

The supplier shall provide the installer with the following information, which shall include but
not be limited to:
a) Operating and Design parameters:

design pressure;
design temperature;
Tg of the resin used in component manufacture;
Tg of the adhesive used in component manufacture (if appropriate);
qualified pressure of each component and minimum qualified pressure in each
piping system;
mean and maximum velocity conditions in each piping system;
chemical resistance limitations, if applicable;
procedures to eliminate or control water hammer and cavitation, if applicable;
fire classification and location of fire-rated pipe, if applicable;
conductivity classification, location of conductive pipe, earth linkage/grounding
requirements and location of earthing points;
criticality.

b) System drawings and support requirements for heavy equipment;


c) Preferred locations for connection of final joint in pipe loops, if appropriate;
d) System criticality and minimum requirements for inspection during installation.

17

HOIS GP1 Issue 2


The dimensions of the components and spools shall be available for the installer and
operator. The quantity, qualified pressure, nominal dimensions, and relevant special
requirements of all piping components and prefabricated spools shall be verified for
compliance with the purchase order. Shipments of piping components not complying with the
purchase order shall be reported to responsible personnel and to the pipe producer for
corrective actions.

10.3

Handling and delivery

The installation of composite structures shall be carefully planned. It shall be part of the
design analysis. Handling composite structures like metal structures may introduce severe
damage. Any aspects of handling that deviates from typically practice with metal structures
should be identified. Procedures should be in place to describe special handling
requirements for composites.
Handling of composite structures requires special care. Handling instructions should follow
each component. Point loads should be avoided. Scraping, wear and tear should be avoided.
Bending the structure into place should be avoided. Lifting shall only be done at specially
indicated spots that were designed to take such loads.
Inspection requirements after installation are covered in Sections 5.1 and 5.2 of ISO 14692.
This part of ISO 14692 assumes that the fittings and pipes have been correctly manufactured
and inspected according to the criteria given in ISO 14692-2. The handling of the GRP
components shall follow the guidelines given in Annex B of ISO 14692 Part 4 and the
requirements of the pipe manufacturer. All piping components shall be visually inspected in
accordance with Table A.1 of ISO 14692 Pt. 4 for damage that may have occurred during
storage and shipment. Rejected components shall be replaced. If doubts concerning the
extent of defects occur during inspection, a specialist approved by the operator shall perform
a second inspection of the delivered items.
Upon arrival at site the packaging shall be checked visually for possible transport damage.
Vessels should be handled and stored in the original packing for as long as possible to avoid
possible damage. The vessel shall be inspected after unpacking.
External surface cracks (e.g. caused by the hydrostatic pressure test, transport or storage)
shall not exceed Level III of ASTM D2563.
All piping components shall as far as possible be installed so that they are stress-free.
Therefore:
bending of pipes to achieve changes in direction, or forcing misaligned
flanges together by over-torquing bolts is not permitted;
the manufacturers recommendations for bolt-torquing sequence, torque
increments and maximum bolt torque shall be followed.
All installation activities shall be verified independently for high safety class components.
Whether the verification shall be done by the manufacturer himself, by the customer, or by a
third party should be decided by the project.

10.4

Inspection after installation

Traditionally, most GRP piping applications have been inspected visually and the quality
assessed by pressure testing prior to commissioning. Once commissioned no further
inspection has been performed.

18

HOIS GP1 Issue 2


This approach has generally functioned well and it is anticipated it will remain. Some
difficulties with this approach have been noted when GRP has been applied offshore.
Current limitations associated with inspection of GRP pipe and piping systems include:

over-reliance on system pressure testing, occasionally contributing to inadequate


quality control of the system during various stages of manufacture, material receipt on
site and installation;
visual inspection criteria being overly subjective (i.e. photographic standards for
piping applications have not been readily available);
pressure testing occurring at a late stage in construction which may limit access and
make any necessary repairs difficult and costly.

The following routine quality assurance/control measures are intended to help in ensuring
that GRP piping systems are installed without problems. A suggested inspection strategy for
GRP piping systems after installation, which considers system criticality and availability/
accessibility, is illustrated in Figure 2 taken from NORSOK M-622 (1999). This should be
used as the basis for developing an appropriate specific strategy for a particular installation.
The limitations noted above are addressed by:

Highlighting key quality control activities;

Emphasising visual inspection in accordance with NORSOK M-622 Annex A;

Identifying the (limited) circumstances when system design pressure testing


may be replaced with various combinations of additional NDT and functional
testing at operating pressure.

19

HOIS GP1 Issue 2

Piping or Tank
system to be
inspected

QC to Standard by
Supplier (1), PreFabricator (2),
Installer (2)

Is system
critical?
(3)

Are
QC findings
acceptable
(9)?

No

Yes
No
No

Yes

Is system
available/
testable?
(4)

Visual Inspection
(5)

Visual Inspection
(5)

Yes
Additional NDT
(7)
Visual Inspection
(5)
Yes

Inspection
Findings
Acceptable?
(10)

Pressure test per


Standard
(6)

No

Fail

Functional Test
(8)

Pass
Functional Test
(8)

Pass
Pass

Fail

Fail, Replace,
Redesign

Fail
System
Acceptance

Fail, Replace,
Redesign

Figure 2 Inspection Strategy for manufacture and installation of GRP piping and tank
systems based on flowchart in NORSOK M622

20

HOIS GP1 Issue 2


Notes to Figure 2
1. Includes 100% hydrostatic pressure testing at a frequency to be defined. 100% visual
inspection should be performed.
2. Certified personnel shall be appointed for fabrication and installation. 100% visual inspection
recommended.
3. System is critical if failure can result in: Injury to personnel; operational shutdown with
unacceptable economic consequences (Examples: fire water delivery system, some cooling
water systems). System is non-critical if System is non-critical if: acceptable functionality is
maintained even if most likely failure modes occur; operating pressure is much lower than
system design pressure (examples: open drains, some cooling water systems).
4. System is ready available for testing if it is: physically accessible; not prohibitively expensive
to prepare for pressure testing (i.e. blinding off joints, blocking deluge nozzles, etc.)
5. Visual inspection shall be done on 100% of system in accordance with Annex A.
6. Full system hydrotest in accordance with ISO 14692.
7. Other NDT methods applied as appropriate (see ISO 14692 Pt. 4 or Appendix B). NDT to be
performed on at least: 10% of joints 250 mm diameter, 25% of joints > = 250 mm diameter;
and all field joints.
8. Pressure testing per ISO 14692 to be replaced by a leak test at operating pressure.
9. Supplier and prefabrication testing frequencies may be reduced for non-critical systems,
however at least 10% of all testable components shall be tested. QC findings are acceptable if
there is no risk that system safety or function will be compromised.
10. Inspection QC findings are acceptable if there is no risk that system safety or function will be
compromised.

10.5

In-service inspection

The objective of this section is to provide guidance on development of an inspection strategy


and the requirements for operation and in-service inspections.
In case of findings at the inspections, a plan should be worked out listing suggested actions
to be taken, depending on the type of findings. The plan may be included in the inspection
strategy.
GRP piping systems shall be inspected at regular intervals, in accordance with the inspection
strategy, to ensure that the piping system is in a satisfactory state consistent with its
continued operation. This strategy shall be documented and communicated to the qualified
inspectors and NDT personnel responsible for the equipment and system.
The selection of an inspection programme should be based on a thorough evaluation of the
consequences of failure. Assessment of the likelihood and severity of failure should be based
on parameters such as previous experience, material properties, design of process units,
operating process conditions, etc.
Guidance on the development of an in-service inspection strategy is given in the flow charts
in Figure 3 and Figure 4. Figure 3 shows the development of an inspection strategy in
accordance with Annex H of ISO 14692 Pt. 4. Figure 4 gives guidance on development of an
inspection strategy where inspection is carried out for other reasons; for example where
damage has occurred in service, for defect detection, or for life extension.

21

HOIS GP1 Issue 2


A system is non-critical if:

Failure will not result in injury to personnel;


Failure will not result in unacceptable economic consequences;
Acceptable functionality is maintained even if the most likely failure modes
occur;
The operating pressure is significantly less than nominal design pressure,
e.g. the system includes open drains, cooling-water systems.

A system is considered ready and available for pressure testing if it is: physically
accessible; and not prohibitively expensive to prepare for pressure testing (i.e. blinding off
joints, blocking deluge nozzles, etc.).
In projects where more than one set of Regulatory Authorities' rules apply or several
contractors are involved, only one inspection strategy and one common inspection
programme shall apply for the GRP piping system.
Unless there are other specific reasons for carrying out NDE inspection, it is recommended
the in-service inspection strategy for the GRP components shall be developed in accordance
with the guidance given in ISO 14692 Pt. 3 Annex H and Tables H.1. and H.2. (see Appendix
C). Table H.1 gives suggested inspection programmes based on the likelihood of defects or
degradation occurring and the criticality of the system. The interactions between materials
and process conditions should be considered when selecting condition-monitoring methods.
This entails a comprehensive materials engineering evaluation that considers the most
probable failure/degradation mechanisms and defects.
Equipment shall be classified into Inspection Groups (A-D) given in Annex H of ISO 14692
Pt. 3 based on equipment classification (or criticality), probability of failure, and severity
(consequence) of failure. The selection of NDT methods and inspection intervals shall take
account of the recommendations for the Inspection Group given in Table H.2. Suggested
inspection intervals are given in Table H.2.
It is recommended that an initial selection of NDE methods for use in detecting defects which
are most likely to occur during operation of GRP piping systems is made using the Tables in
ISO 14692 Pt.4 Table 4 along with the recommended acceptance criteria. Possible causes
and recommended corrective actions are also included.
Relevant non-destructive testing (NDT) methods should be selected if possible, bearing in
mind the possibilities and limitations of each method. A combination of several methods may
be required in order to achieve safe and cost-effective utilization of the equipment/ system.
Since ISO 14692 was issued a number of new NDE methods have become established.
More detailed guidance on Selection of NDE methods encompassing these new methods is
given below in Section 11.0.

10.6

HSE good practice guides

Concise good practice guides 4,5 on inspection of GRP pipe and FRP composite overwrap
repairs have been produced by HSE. The latter includes advice from members of the
Association of Composite Repair Suppliers AcoRes, originally formed by ESR
Technology.

4
5

HSE GRP pipe fact sheet, Health and Safety Laboratories HSL; Final draft Revision 1, 2009
FRP composite repair fact sheet, Health and Safety Laboratories HSL; Draft Final, 2009

22

HOIS GP1 Issue 2


In each case, the fact sheet provides guidance to inspectors on what can go wrong, the
types of damage to look for in offshore pipework and the inspection methods that are
recommended in ISO 14692. This includes a useful 1 page Summary of issues at the end
for inspectors conducting site inspections, with photographs of relevant damage
mechanisms. Relevant advice is also given on joints and fittings. Photographs are included
showing damage mechanisms.

10.7

DNV guidance for operation and in-service inspections

DNV Standard DNV-OS-C501 provides general guidance on structural integrity assessment


of composite components to demonstrate fitness for purpose in cases where deviations from
the originally intended design appear during operations. In Section 12 of DNV-OS-C501 an
inspection philosophy for integrity assessment of composite components is developed which
defines the requirements for operation and in-service inspections.
It is noted that, once the component is commissioned, an inspection philosophy for the
component should be established and the philosophy shall at least contain:

Items to be inspected, arranged according to their order of importance (criticality


rating);
Parameters to look for and or measure, e.g. cracks, delamination, impact damage,
overheating (or damage from local burning), visible overloading (bending, unintended
use), discoloration, etc.;
Methods of inspection to be applied for each item;
Inspection frequency;
Acceptance criteria;
Reporting routines.

It is also noted that in the case of inspection indications, which may be false calls or genuine
defects, a plan should be executed listing suggested actions to be taken depending on the
type of findings. The plan may be included in the inspection philosophy. Inspection
procedures shall be defined for:

Manufacturing control;
Detection of damage due to accidental loads or overloads;
Detection of damage due to unexpected high degradation of long term properties.

Inspection shall be linked to possible failure modes and mechanisms identified in the design.

10.8

Inspection strategy for life extension and ageing

The inspection programmes in Table H.2 of ISO 14692 Pt 3 include the use of destructive
testing of material samples to characterize long-term material degradation under the most
aggressive operating conditions, and as a justified means to extend GRP equipment past its
rated life. Such material samples should be representative of the equipment in-service, i.e.
by testing a pipe sample removed from service, or by testing coupons which have been
exposed to the same media and stress levels that are seen in service. If the initial materials
engineering evaluation indicates that destructive tests are required, the same test methods
as those used to pre-qualify the material should be used. More guidance on the assessment
of ageing is given in Section 13.6 below.
The Tables from ISO 14692 referred to above are reproduced in Appendix B.

23

HOIS GP1 Issue 2

Piping System, Vessel or


Tank system to be
inspected

Follow Flow Chart


in Table for non
ISO 14692
Inspections

Reason for
inspection?

Other

To satisfy ISO 14692


Classify System by Criticality, Probability
of Failure and Severity according to Table
H.1 of ISO 14692 Pt/ 3

Inspection
Group in ISO
14692 Table
H.1.?

D
Inspect as Group D
in Table H.2 of ISO
14692 Pt/ 33

A-C
Inspect according to the
relevant Group A, B or C
in Table H.2 of ISO 14692
Pt/ 3

Visual Inspection
internal/ external at
intervals of 0.3 x
service life. First
inspection after 1-2
years

Visual inspection
internal/ external
Define next
inspection interval

Identify
degradation
mechanisms and
suitable NDE

Service life
beyond
original
estimated
service life?

NDE Inspection
No

Modify or change
inspection group.
See ISO 14692
pt. 3 Table H2?
Yes
Assess defects.
Replace, Repair

Defects
Found?

Yes
Destructive testing of
relevant components
or NDE to assess
current condition and
potential for life
extension

No

System assumed OK
for continued service

Define new
operating life and /or
safe operating
pressure

Figure 3 Inspection Strategy for in-service inspection of GRP piping and tank systems
taking account of guidance in Annex H and Tables H.1. and H.2. of ISO 14692 Pt 3.

24

HOIS GP1 Issue 2

Piping System, Vessel


or Tank system to be
inspected

Life
Extension

To satisfy
ISO 14692

Reason for
inspection?

Follow Flow Chart in


Table for ISO 14692
Inspections

Defect detection,
Other

Remove selected
components for
destructive testing
or carry out NDE

Identify relevant damage


mechanisms

Estimate actual
regression in
condition

Define next
inspection interval

Accessible for
inspection?
Yes
No

Compare with
initial regression
curve (ISO 14692)

Select suitable NDE


methods

Visual inspection
internal/ external

Assess and define


new operating life
and /or safe
operating pressure
(ISO 14692)

Modify or change
inspection group.
See ISO 14692 pt.
3 Table H2?

NDE Inspection

Yes
Defects
Found?

Assess defects.
Replace, Repair

No
System assumed OK
for continued service

Figure 4 Inspection Strategy for in-service inspection of GRP piping and tank systems for
life extension, damage detection or other reasons (Non ISO 14692 Pt. 3 inspections).

25

HOIS GP1 Issue 2

10.9

When to Inspect

GRP piping systems are often used in systems that are not safety-critical and which may be
classified as ANSI/ASME B 31.3 Category D systems requiring no inspection. However,
these systems can be crucial in maintaining uninterrupted production. Therefore, the choice
of when to inspect is largely an economic question.
Unless there are specific reasons to inspect more frequently, it is recommended that the
guidance in ISO 14692 Pt 3, Annex H referred to above is used to define inspection
frequency. This will be dependent on the group (A-D) defined in Annex H for the component.
The probability and consequences of system failure must warrant the added cost of
inspection. For prefabricated pipe spools or adhesive joints the guidance on inspection timing
and grouping of components according to criticality in Table 3 of NORSOK M622 (2005) may
be followed as an alternative.
The specific guidance in NORSOK M622 (2005) is as follows:
The GRP piping systems shall be inspected within the first year (group 2 and group 3
systems) and within the second year (group 1) after start of service. The inspection interval
thereafter shall be 1 year to 2 years for group 2 systems and group 3 system and 3 years for
group 1 systems. The inspection intervals shall be adjusted, i.e. reduced or increased
depending on observed severe degradation or gained confidence in materials and
construction. An increase of inspection intervals can be considered after 5 years of service.
Destructive testing is required if the service life is extended beyond the originally estimated
service life.
Economic and risk considerations will not only determine whether a GRP system is inspected
at all, but also whether it should be periodically inspected while in service. A suggested,
reasonable balance between costs and benefits of inspections is that both non-critical and
critical piping systems should at least be visually inspected within 1-2 years after start of
service. Following this the frequency of inspection should be according to the developed
strategy.
To ensure satisfactory operation of GRP pipework and vessels over a period of years,
periodic inspections shall be performed to check that the GRP material is sound. This
inspection shall include connections and branches to the wall, bottom corner, supports and
the inner liner, if present. Although visual inspection is the most common method of
inspection, other non-destructive techniques such as ultrasonics and radiography are being
developed with increasingly reliable results.
During inspection, damage to surfaces should be avoided by suitably covering footwear and
ladders. Cleaning processes shall be checked to ensure that the internal or external
protective surfaces will not be damaged or destroyed by incorrect application.

11.0

Selection of NDE methods

The choice of NDE method which is practically applicable to a given component will depend
on a number of factors including the access, wall thickness and surface conditions. Available
inspection methods may not detect all critical failure mechanisms. However, the methods
may detect preceding failure mechanisms. A link between detectable failure mechanisms
and critical failure mechanisms shall be established. The reliability and functionality of all
inspection methods should be documented.

26

HOIS GP1 Issue 2


In many cases a complete inspection programme cannot be developed due to the limited
capabilities of available NDE equipment. In that case the following alternatives taken from
the DNV OS 501 guidance may be used:

Inspection of components during or right after manufacturing may be


replaced by well documented production control.

Inspection to detect damage due to accidental loads or overloads may be


compensated for by monitoring the loads and comparing them to the design
loads.

Effect of higher degradation than expected can be compensated for by using


the failure type brittle in the long term analysis. If this method is used the
component must be replaced or re-evaluated after all overloads or other
events exceeding the design requirements. This approach shall be agreed in
advance.

If the failure mechanisms are not fully understood, or competing failure


mechanisms are present and one is uncertain about their sequence,
inspection is required.

Since ISO 14692 was issued in 2002 a number of new NDE methods have become
established for inspection of composites such as microwaves, shearography and acoustoultrasonics. The guidance in Tables 4 and 5 of ISO 14692 Pt. 4 forms a basis for the initial
selection of NDE methods. However, the recommendations on NDE are general, do not
define the specific NDE method to be used (for example stating ultrasonics), and do not
encompass more recent developments.
For this reason it is recommended that Table 1 and Table 2 below are used for selection of
suitable NDE methods. In these Tables the advice in ISO 14692 Pt 4 has been updated to
take account of other potential NDE methods that are now available. For specific defect
types Table 12 of ISO 14692 Pt. 2 should also be considered (see Appendix C). This Table
refers to manufacturing inspection, but the recommendations are still relevant in-service and
following installation provided access is sufficient. More detailed guidance on the selection
of NDE methods and NDE practice for specific components and defect types is given in
Sections 12.0 and 13.0 below.
Section 14.0 gives advice on how to practically apply individual NDE methods as well as the
current status in regard to application offshore.
Relevant non-destructive testing (NDT) methods should be selected if possible, bearing in
mind the possibilities and limitations of each method. A combination of several methods may
be required in order to achieve safe and cost-effective utilisation of the equipment/ system.

27

HOIS GP1 Issue 2

Table 1

NDE selection and acceptance criteria for defects potentially occurring during fabrication, handling and installation
(Update of Table 4 from ISO 14692 Pt. 4, additions shaded).

Possible defects

Cause(s)

Consequence(s)

Recommended
NDT method(s)
ISO 14692

Other potential NDE methods

Criteria

Corrective action

Comments

Incorrect
dimensions

Incorrect
prefabrication.

Joint cannot be
sealed, leakage
GRP can be
overstressed if joint
pulled up

Measurement to
verify
documented
dimensions

Ultrasonic wall thickness.


Radiography.

In accordance with
6.8.5 of ISO
14692-2:2002

Replace (major defect).


Compensate elsewhere in
piping system (e.g. use field
joints, hook-up adjustments etc.)

NDE unlikely to be applicable in


most cases. Arguably not ISI.

Weepage or pipe
failure

Visual inspection,
with light source
inside pipe

Transient thermography,
ultrasonics, microwave,
shearography, or acoustoultrasonics to detect
delamination damage
associated with impact.

In accordance with
Table A.1

Replace (major defect) Repair


(minor defect)

Visual inspection would be


normal practice.

Remake joint (major defect)


Post-cure joint (minor defect)

Thermography can have a good


sensitivity to the characteristic
features of impact damage
(conical damage area, multilayer
delamination). Heating methods
difficult to apply offshore.
DSC and leak testing are well
established in this application.

Joint not shaved


correctly.
Impact, wear or
abrasive damage

Incorrect transport.
Incorrect handling

Acoustic emission to monitor.


Incorrect curing of adhesive laminated joint

Outside temperature
and humidity
specifications.

Weakened joint or
leakage

In accordance
with 8.3.3 of ISO
14692-2:2002

Improper mixing.
Heating pad overlap
or controller
problems.

Differential Scanning
Calorimetry (DSC) to determine
Tg for adhesive and extent of
cure. See NORSOK M622
Table 3. DSC will require a
small off cut of material to be
removed and heated.

In accordance with
8.3.3 of ISO
14692-2:2002

Radiography for intact joints

Alignment to
project
specifications

Unlikely in a correctly
commissioned system. Should be
ironed out in system qualification.

Cooling effect of air


in pipe.
Out-of-date or
incorrect materials
Misaligned joints

Movement during
curing.

Air sucked in,


resulting in voids

Bending

Residual stress,
resulting in less
than rated
performance

Incorrect dimensions

Visual inspection.
Ultrasonics

Replace components (major


defect).

Ultrasonics to detect voids or


disbonding.

Remake joint (minor defect)

Radiography is normal method to


detect lack of adhesive.

28

HOIS GP1 Issue 2


Possible defects

Cause(s)

Consequence(s)

Recommended
NDT method(s)
ISO 14692

Other potential NDE methods

Criteria

Corrective action

Comments

Defects in adhesive
bond

Too little adhesive or


not applied uniformly

Weakened joint or
leakage

Ultrasonics, or
radiography

Microwave inspection,
shearography, acoustoultrasonics or tap testing

Debond area
greater than 30 %
of total bond area.

Remake joint

Ultrasonics to detect voids or


disbonding.

Movement during
curing

Radiography is normal method to


detect lack of adhesive; though
may not be effective unless a
radiation absorbant filler is used
in the adhesive.

Axial length of
debond area
greater than 20 %
of total axial bond
length.

Applicability of other methods will


depend on surface finish and
thickness.

Improper treatment
of joint surfaces

Contaminated
surface after grinding

Weakened joint or
leakage

Visual inspection

Microwave inspection,
shearography, acoustoultrasonics or tap testing

In accordance with
adhesive supplier's
requirements

Remake joint

Excess adhesive

Too much adhesive


applied

Restriction in pipe
to flow

Radiography

Internal visual inspection with


endoscope

No flow
obstruction. 5 % of
inner diameter or
10 mm, whichever
is less

If access: remove by careful


grinding. If no access:
reject/major repair.

Visual inspection

Radiography, Leak testing

In accordance with
Table A.1

Replace thread in accordance


with supplier's guideline

Increased risk of
erosion damage of
pipe
Damaged threads

Teeth chipped
Damaged end faces

Joint cannot be
sealed, leakage

NDE methods to detect


disbonding of the joint surfaces.
Tap testing only likely to work
through thin sections.

Threaded GRP joints not used


offshore. Normal practice would
be to dismantle and check if
leakage occurred.

29

HOIS GP1 Issue 2

Table 2 NDE selection and acceptance criteria for defects that could potentially occur during operation
(Update of Table 5 from ISO 14692 Pt. 4, additions shaded).
Operational defects

Cause(s)

Consequence(s)

Recommended NDE
method(s) ISO 14692

Other potential NDE


methods

Criteria

Corrective action

Comments

Flange cracks, leaks

Bolts over- or undertorqued. GRP against


raised-face flanges.

Joint not sealed,


leakage. Reduced life

Visual inspection

Ultrasonics.

No leakage permitted

Replace flange (major


defect). Grind and fill
minor cracks with resin.

Radiography unlikely to be
successful unless well
aligned.

System failure

Visual inspection

Monitoring by acoustic
emission or leak detection
methods

No failure permitted

Replace pipe or system

NDE not likely to be


applicable

Weepage

Ultrasonics

Ultrasonics, microwave,
shearography, acoustoultrasonics or transient
thermography to detect
delamination damage
associated with ageing or
impact.

More than 20 %
reduction in original
axial modulus

Accept, but monitoring


required

Delamination may occur in


the latter stages of ageing
leading to weepage. Main
initial damage mechanism
is matrix cracking. Linear
scanning UT methods (Bscan, C-scan) more likely to
pick up delaminations.

Radiography

Wrong GRP flange


design selected.
System failure, e.g.
burst pipe

Design conditions,
loads, temperatures
exceeded.
Operational procedures
inadequate (e.g. water
hammer due to valve
opening).

Ageing

Long-term materials
degradation

Phased array or rapid


scanning wheel probes may
be considered, given
greater speed and quality of
visual indication, if GRP
quality and surface finish
sufficient to allow higher
frequencies (1-2.5 MHz)

30

HOIS GP1 Issue 2


Operational defects

Cause(s)

Consequence(s)

Recommended NDE
method(s) ISO 14692

Ageing
(Continued)

Impact damage

Other potential NDE


methods

Criteria

Corrective action

Destructive testing and


characterisation of
condition or NDE using
Ultrasonic velocity to
measure matrix cracking
non -destructively.

Impact e.g. from


dropped scaffolding,
tools

Weepage

Ultrasonics.
inspection

Visual

Transient thermography,
ultrasonics, microwave,
shearography or acousto
ultrasonics to detect
delamination damage
associated with impact.

Comments

Normal practice for life


extension is destructive
testing using representative
samples to compare actual
condition with regression
curve assumed in design
(ISO 14692).

In accordance with
Table A.1 Visual
inspection

Replace (major defect).


Temporary repair (minor
defect)

NDE methods now


developed to measure
matrix crack spacing from
ultrasonic velocity
measurements.
Visual inspection would be
normal practice.
Thermography can have a
good sensitivity to the
characteristic features of
impact damage (conical
damage area, multilayer
delamination).
Ultrasonic A-scan or
phased array can detect
damage dependent on
surface finish and
thickness.

Earthing cable
damage

Some cables
susceptible to corrosion
in marine atmosphere

Earthing reduced or
eliminated

Visual inspection

Scale deposits (salt


water systems only)

Operating conditions
resulting in e.g. barium
sulphate deposits

Reduced flowrate

Visual (reduced flow).


Radiography

None

None permitted

Replace cables

Radiography.

Reduction in internal
diameter of more than
10 mm or 5%

Clean using e.g. water


jetting

Mega-ohm meter

Ultrasonics

Shearography potentially
good but expensive.
NDE unlikely to be
applicable
Applicability of NDE
methods will depend on the
nature of the scale
deposition and the
interface. Linear scan (BScan) preferable to point
measurements for
ultrasonics.

31

HOIS GP1 Issue 2


Operational defects

Cause(s)

Consequence(s)

Recommended NDE
method(s) ISO 14692

Other potential NDE


methods

Criteria

Corrective action

Comments

Erosion

Particulates in flow

Reduction in wall
thickness leading to
pipe weepage

Ultrasonics

Ultrasonic B-Scan.

Reduction in original
wall thickness of less
than 20 %.

Accept, but monitoring


required. A long-term
solution may be required
for erosion and scaling.

Applicability of ultrasonics
will depend on thickness
and surface quality. Linear
scanning methods (B-Scan,
TOF) preferred to point
measurement for erosion
damage.

Reduction in original
wall thickness of more
than 20%.

Reject

Radiography may have


application for complex
geometries.

Depth limited to
surface resin layer

Accept

NDE unlikely to be
necessary

Ultrasonic Time of flight


(TOF).
Radiography.
Acousto-ultrasonics.

Chalking

Exposure to UV
radiation

Minor breakdown of
outer surface

Visual inspection

None

32

HOIS GP1 Issue 2

11.1

Manufacturing inspection

Manufacturing NDE is outside the scope of this document except insofar as manufacturing
defects persist into the final system or component. Defects can occur in either the GRP
material or in the mechanical and/or adhesive-bonded joints that make up the piping
system. Joint defects, including defects in prefabricated pipe spools, are more likely to
occur than defects in the GRP material, provided QA procedures are followed during
manufacture, handling and delivery.
Manufacturing processes for fittings are typically more complicated and less automated
than those used to produce pipes. Therefore, manufacturing related defects tend to be
more prevalent in fittings.
NDE methods recommended for use in detecting those defects most likely to occur during
specific stages in the manufacture and operation of GRP piping, together with acceptance
criteria and recommended corrective actions are listed in Table A.1 of ISO 14692-4:2002.
(reproduced in Appendix C).
Similar NDE methods may be applicable in-service, subject to the more limited access
restrictions. The Operator shall be notified of all repairs. On agreement between the
Operator and the manufacturer, a mill hydrostatic test on all minor repaired items shall be
performed.

11.2

After installation

Inspection requirements after installation are covered in Sections 5.4 to 5.9 of ISO 14692
Part 4. It is recommended that the Operator carry out hydrotesting of representative sitefabricated joints and fittings soon after the start of installation to verify the standard of
workmanship. This is particularly important for pipe diameters above about 200 mm
(ISO14692 Part 4, Section 5.5.8). This is due to correct on-site installation, workmanship,
alignment and achieving required dimensional tolerances being more difficult for larger
diameter pipes.

11.3

In-service

Inspection requirements in-service are covered in Section 6 of ISO 14692 Part 4 and
guidance on NDE methods provided in Annex E. Recommendations on NDE methods for
the defects that may occur during operation and relevant inspection methods are given in
Table 5 of ISO 14692 Part 4 (see Appendix C). Since ISO 14692 was released in 2002 a
number of new NDE methods have become available. These have been identified in Table
1 and Table 2 above and are identified by component and defect type in Sections 12 and 13
below. It is recommended that these updated recommendations regarding NDE techniques
are followed.

12.0

Inspection practice by component

This Section provides guidance on the selection of NDE methods for specific GRP piping
system components. In each case the recommendations in ISO 14692 have been updated
to take account of newer alternative NDE methods that have become available since the
last revision of ISO 14692 in 2002. The guidance from ISO 14692, encompassed in the
HSE Good Practice Guide is summarised below in Table 3 together with the potential
alternative NDE methods identified earlier in this document in Table 2.

33

HOIS GP1 Issue 2


Table 3 Optimum Methods of inspection for the in service inspection of GRP pipework.
Damage type
Installation
Incorrect dimensions

Impact, wear or abrasive


damage

ISO 14692 Recommendation

Alternative NDE methods


(from Table 2)

Measurement to verify
documented
dimensions.
Visual inspection

Ultrasonic wall thickness.


Radiography. Laser profiling.

Incorrect curing of
adhesive/laminated joint

Establish degree of cure

Misaligned joints
Defects in adhesive bond

Visual inspection/ultrasonics
Ultrasonics/Radiography

Improper treatment of joint


adherents

Visual inspection

Excess adhesive

Radiography

Damaged Threads

Visual inspection

Ultrasonics, microwave,
shearography, acoustoultrasonics or transient
thermography to detect
delamination damage
associated with impact.
Acoustic emission to monitor.
Differential Scanning
Calorimetry (DSC) to
determine Tg for adhesive
and extent of cure. See
NORSOK M622 Table 3.
Radiography for intact joints
Microwave inspection,
shearography, acoustoultrasonics or tap testing
Microwave inspection,
shearography, acoustoultrasonics or tap testing to
detect disbonding
Internal visual inspection with
endoscope, Radiography.
Radiography, Leak testing

34

HOIS GP1 Issue 2


Operation
Flange cracks, leaks

Visual Inspection

Pipe cracks, leaks

Visual Inspection

System Failure, e.g. Burst pipe

Visual Inspection

Ageing

Ultrasonics

Impact Damage

Visual Inspection/Ultrasonics

Wear and Abrasion Damage


Earthing Cable Damage
Scale Deposits (Salt Water
Systems Only)

Visual Inspection
Visual
Inspection/Megohmmerter
Visual (reduced flow),
Radiography

Erosion

Ultrasonics

Chalking

Visual Inspection

Ultrasonics.
Radiography
Monitoring by acoustic
emission or leak detection
methods. Shearography,
ultrasonic angled shear wave
inspection, TOFD,
radiography or possibly
microwaves for cracks.
Monitoring by acoustic
emission or leak detection
methods
Destructive testing and
characterisation of condition
or NDE using Ultrasonic
velocity to measure matrix
cracking non-destructively.
Ultrasonics, microwave,
shearography, acoustoultrasonics or transient
thermography to detect
delamination damage
associated with ageing.
Transient thermography,
ultrasonics, microwave,
shearography or acoustoultrasonics to detect
delamination damage
associated with impact.
Acoustic emission to monitor.
As impact damage
None
Radiography.
Ultrasonics
Ultrasonic B-Scan.
Ultrasonic Time of flight
(TOFD).
Radiography.
Acousto-ultrasonics.
None

35

HOIS GP1 Issue 2

12.1

Pipework

ISO 14692 recommends the following inspection methods for GRP pipework in-service as
detailed in Table 3 above:

Visual inspection.

Ultrasonics.

Radiography.

The applicability of ultrasonics and other NDE methods will depend on the thickness, quality
and surface condition of the GRP pipework, defect type, location and the purpose of the
inspection (defect detection or assessment of ageing).
Inspection trials, conducted under the auspices of the HOIS FPSO and Flexible Risers
Working Group, confirmed the above recommendations. Data obtained using manual
ultrasonics were somewhat variable but were generally able to detect the pipe back wall
echo but not necessarily the deliberately introduced bondline defects. Automated
ultrasonics using either twin probe TOFD or phased arrays produced reasonable B-scan
images showing the layered nature of the material and in some cases reflections from the
introduced defects. Interpretation of reflected signal waveforms was more complex than
would be expected for steel components as the GRP structure is elastically anisotropic and
heterogeneous with signal attenuation due to voids/porosity and scattering nature of
laminated structure. It was sometimes difficult to get a consistent back wall echo with some
variability in response between joints. Inspection operators need to familiarise themselves
with particular glass reinforced epoxy components and choose optimum probe types.
Ultrasonic B-scan images are the preferred acquisition mode as they can give a clearer
delineation of bond line defects and back wall echo. Generally the lower frequency probes
( MHz - 2 MHz) gave better sample penetration than 5 MHz probes but with reduced
resolution. Phased array wheel probes were relatively quick to scan the pipe surfaces but
had some positional difficulties around elbows and fittings due to roller sliding.
Of the various non contact inspection methods trialled, i.e. laser shearography, microwave
inspection and radiography, the latter technique produced the best images using the
portable pulsed X-ray source used in conjunction with digital detector arrays. In this case
some details of the joints were revealed including bondline defects such as porosity
(however there was no evidence of the paper inserts) and good images of the pipe wall and
fittings.
After the inspection trials were completed the flow loop was cut open and macrophotographs were taken of joint sections to reveal the location and extent of the defects. In
many cases the joint defects were lack of adhesive and porosity. The quality of the elbow
end fittings was also assessed and showed evidence of poorly wetted out fibres which was
detected during several ultrasonic trials. A section of the centre bell and spigot joint was
prised open, as recommended by a consultant from the pipe manufacturer, to reveal the
quality of the bond.
In summary, each of the inspection trials had practical challenges and most were able to
detect some of the defects. Ultrasonic inspection was able to detect loss of back wall echo,
bondline features and end fitting irregularities. Radiographic examination using digital
detectors together with image enhancement filters was able to reveal pipe wall and end
fitting details, bondline porosity and quality of adhesive fillet but not gaps in the adhesive
bond.

36

HOIS GP1 Issue 2


GRP pipes are generally maintenance-free, but the following points identified in Section
6.2.1 of ISO 14692 Part 4 should be given attention during inspection.

Care shall be taken in the use of conventional methods for removal of scale and
other blockages (e.g. high-pressure water lances, mechanical and chemical
cleaning methods). The manufacturers recommendations shall be followed in all
cases.

Earthed GRP piping systems shall be periodically checked to ensure that all
earthing leads are functional and that the requirements for continuity of electrical
path and the resistance to earth are not greater than the specification given in the
operator's documentation. The testing of resistance to earth shall be in accordance
with 5.5.4.4 of ISO 14692 Part 4.

Taking account of the above information and our experience in inspection of GRP, it is
recommended that the advice in ISO 14692 and NORSOK M622 and the HSE good
practice guide 4,5 is followed for GRP pipework after installation and in service, but subject to
a number of additional considerations:

A suitable asset integrity management strategy shall be in place including periodic


inspections and condition monitoring (photographs recommended).

It is good practice to provide suitable training and education for inspectors on


damage detection in GRP pipe (what to look for) and inspection procedures should
be composite specific.

For damage mitigation pipes should not used as a step up, not be exposed to
deleterious foreign fluids and not be exposed to heat sources. Earthing cables (if
required) shall be present and in good condition.

For commercial grade GRP pipework visual inspection for impact damage and
possible signs of delaminations is recommended as the primary inspection method,
supplemented by periodic NDE inspection. The guidance on when to apply NDE
methods in Section 10.9 and ISO 14692 Pt. 4 should be followed.

The general appearance of pipework should be uniform with smooth surfaces and
none of the following, or within prescriptive limits, given in associated standard/
manufacturers guidance: cracks (including adhesive fillets between repair laminate
and substrate), delamination, wear, chips/gouges, resin loss, exposed fibres/cut
edges, leaks/weepage, dry spots, variation in resin colour, contamination/foreign
matter, heat damage, softening/ bulging/ discolouration/ burn, blisters/ pin holes/
pores, chemical attack, erosion .

For ultrasonic inspection of commercial grade filament wound pipework it is normally


possible to use relatively high frequencies (2 MHz or above) to optimise resolution.
For thicker section or hand laminated quality GRP pipework, ultrasonics will be
difficult and require low frequencies (0.5 to 1 MHz) to minimise attenuation. Smaller
probe sizes are beneficial if coupling is difficult or surface condition poor.

The use of suitable alternative NDE methods to ultrasonics identified in Table 2 and
Table 3 such as microwave inspection, tap-testing, radiography or shearography is
acceptable provided these are qualified on the component or suitable reference
samples.

The guidance in Section 14 shall be followed in regard to the application of specific


NDE methods to GRP pipework, joints, and fittings.

37

HOIS GP1 Issue 2

The guidance in Section 17 should be followed in terms of evaluating any damage


and defects found, any repair or remediation required and the acceptability of the
GRP pipework, fittings or joints for continued service. A simple assessment in terms
of priority levels is provided in the HSE good practice guide4.

For more critical systems monitoring using acoustic emission or graded optical fibres
should be considered.

Guidance on NDE and destructive testing methods for the assessment of ageing is given in
Section 13.6. Ultrasonic velocity measurement to determine the matrix cracking density,
following methods developed by ESR Technology9, offers an alternative to destructive
testing.

12.2

Fittings

Manufacturing processes for fittings are typically more complicated and less automated
than those used to produce pipes. Therefore, manufacturing related defects tend to be
more prevalent in fittings. It is possible that such defects could extend in service. Providing
the fittings have been adequately designed and qualified then the main concern is likely to
be matrix cracking leading to weepage later in the life of the component.
Fittings pose specific difficulties for inspection due to the geometry, thicker section and
quality of the GRP arising from the methods of construction. Filament wound fittings will
generally be easer to inspect than fittings that are manually overlaid. Fittings are usually
tapered to accommodate the higher loading in these regions, which makes inspection more
difficult than for parallel surface pipework. The interface should be considered for fittings
that have been manually overlaid or laminated to the pipework.
It is recommended that fittings are subject to periodic visual inspection to check for impact
damage or signs of ageing. If NDE is required then the recommendations given above for
thicker section or hand laminated quality GRP pipework should be considered. Ultrasonics
will be difficult and require low frequencies (0.5 to 1 MHz). For more complex or less
accessible geometries, radiography may be the only feasible inspection option.
NDE methods applicable to flanged connections are discussed below (Section 12.7).

12.3

Supports

GRP piping systems may be supported using the same principles as those for metallic
piping systems. However, due to the proprietary nature of piping systems, standard-size
supports will not necessarily match the pipe outside diameters. The use of saddles and
elastomer pads may allow the use of standard-size supports. Guidance on support methods
is provided in Section 5.5.3 of ISO 14692 Part 4.
It is recommended that the areas around pipe supports are subject to more detailed visual
inspection as such areas can experience higher or more variable loading than the normal
pipework. Enhanced visual inspection using dye-penetrant or application of NDE methods
should be considered if defects have been encountered in service or inadequacies are
suspected in support design.
It should be established from visual inspection after installation that the guidance on pipe
supports in ISO 14692 has been followed:

38

HOIS GP1 Issue 2

Supports in all cases should have sufficient width to support the piping without
causing damage and should be lined with an elastomer or other suitable soft
material.

Clamping forces, if applied, should be such that crushing of the pipe does not occur.
Local crushing can result from a poor fit and all-round crushing can result from overtightening.

In all cases, support design should be in accordance with the manufacturers


guidelines.

Supports should preferably be located on plain pipe sections rather than at fittings or
joints.

Supports shall be spaced to avoid sag (excessive displacement over time) and/or
excessive vibration for the design life of the piping system. Guidance on support
spacing is given in ISO 14692 and in the AWWA M45 Manual Chapter 8.

Valves or other heavy attached equipment shall be independently supported.

GRP pipe shall not be used to support other piping, unless agreed with the principal.

Consideration shall be given to the support conditions of fire-protected GRP piping.


Supports placed on the outside of fire protection can result in loads irregularly
transmitted through the coating, which can result in shear/crushing damage and
consequent loss of support integrity.

GRP piping should be adequately supported to ensure that the attachment of hoses
at locations such as utility or loading stations does not result in the pipe being pulled
in a manner that could overstress the material.

The anchor support shall be capable of transferring the required axial loads to the
supporting structure without causing overstress of the GRP pipe material.

Anchor clamps are recommended to be placed between two double 180 saddles,
adhesive-bonded to the outer surface of the pipe. The manufacturers standard saddles are
recommended and shall be bonded using standard procedures.
Urgent action is required if pipes are found to be inadequately supported; or pipe supports
missing, extensively damaged or corroded. Such damage is considered to be unsafe (HSE
priority level P1 urgent). Risk assessment shall be performed as a matter of urgency and
suitable mitigation strategies implemented.
Minor damage or corrosion that leaves the supports still structurally sound is acceptable but
requires caution (HSE priority level P2). In this case, a risk assessment shall be performed
as soon as reasonably practicable to identify a suitable course of action.

12.4

Joints

The joints are one of the main areas of concern for composite pipework, but generally
function reliably in-service if they are properly designed, qualified and installed. The most
likely form of failure in GRP piping systems is a leaking joint.
Visual inspection and pressure testing after installation are the primary methods of
ensuring joint integrity. Barcol Hardness may be used to establish adequate curing of
adhesive joints. Guidance on testing and inspection of joints can be found Section 5.5.6 and
Annex C of ISO 14692 Pt. 4 including the percentage of joints to be tested.

39

HOIS GP1 Issue 2


Joint designs for GRP pipe are covered in Part 3 of ISO 14692, Section 5.6. These joint
designs are proprietary but can be categorised into the following types:

adhesive-bonded joints;

laminated joints;

elastomer bell-and-spigot sealed joints (with/without locks);

flanged joints;

threaded joints.

Potential defect types in joints include: de-bonds (lack of adhesive), fibre breakage,
damaged or cracked threads, cracked flanges, environmental access and degradation.
Threaded connections between composite materials are not often used offshore. Metal end
connectors may be threaded.
A detailed assessment of integrity issues including NDE methods for joints has been made
in the ACLAIM programme (www.ndt.esrtechnology.com/aclaim) and followed by the UK
TSB funded Imajine programme (www.imajine.co.uk). In ACLAIM, a range of NDE methods
were assessed including tap-testing, ultrasonics, microwaves and shearography.
The ACLAIM project (Advanced Composite Life Assurance and Integrity Management), is
one of several that DTI has funded through its Technology Programme. This was aimed at
developing an integrated structural health management framework to assess the integrity of
Composite Structures. The primary objective was to provide an integrated approach that
includes detection techniques (embedded), assessment procedures and guidance
documentation to:

Increase confidence in the use of composite materials in safety critical


components and structures through improved inspection schemes;

Minimise in-service structural or component failures through improved


understanding of the influence of defects and damage on residual life;

Lower maintenance costs through remote monitoring and analysis based on


cost effective and novel multi-functional sensors.

Specific guidance for adhesive and laminated joints is given in the following Sections. It is
recommended to visit the ACLAIM and Imajine websites if a more comprehensive
consideration of joint issues is required, including assessment of NDE methods.

12.5

Adhesively bonded joints

Access for inspection and NDT of adhesively bonded connections is not straightforward.
Therefore, careful preparation and procedure during the adhesive bonding process and
component alignment are crucial to obtain a joint of good integrity. There is currently no
good NDE solution, particularly in the case of end connectors.
Relevant defect types include disbonding, lack of adhesive, kissing bonds, and voids and
other defects within the adhesive layer. ISO 14692 specifies rejection if the area of debond
is more than 30% of the total bond area bonds; or the axial length of any debond area is
greater than 20 % of total axial bond length.

40

HOIS GP1 Issue 2


It is recommended that the practice in Annex C of ISO 14692 is followed in terms of visual
inspection, pressure testing and NDE inspection following installation.
For critical systems or where defects have been encountered, it is recommended that other
NDE methods (e.g. random verification of joint quality using ultrasonics) are used in
addition to visual inspection and pressure testing to determine the presence of excessive
debond or void areas that may have a detrimental effect on service life.
Joint inspection methods summarised in ISO 14692 after installation include: visual
inspection; pressure testing; ultrasonics; and radiography. Radiography is recommended to
inspect for defects in adhesive bonds assuming no adhesive is present (i.e. a gap).
Ultrasonics is recommended for misaligned joints, and defects in adhesive bonds. Specific
procedures for all these methods are given in Annex E of ISO 14692 Part 4 with more
detailed procedures for ultrasonics and radiography in NORSOK M-622.
A pressure test at 1.5 times the design pressure reveals leaks and such major defects as
severe impact damage (e.g. from improper transport), improperly designed or fabricated
systems (lacking adequate strength), or poor adhesive bonding. However, adhesive-bonded
joints are designed with a large margin of safety and bonded joints having as much as 80 %
unbonded area can pass a pressure test. Thus the pressure test is a major element in
ensuring that the GRP pipe system is structurally and functionally adequate, but cannot be
viewed as an absolute guarantee of performance. A pressure test provides an integrity
indictor at the time of test, but does not provide any long-term assurance. This is
particularly important for loss of mechanical properties due to ageing.
The presence of a uniform fillet of adhesive is an indicator that an adhesive joint has been
assembled correctly. Internal visual inspection can be used to check that the joint, when
made up, does not protrude significantly into the bore of the pipe. Such a protrusion can
create a substantial blockage factor as well as a source for erosion and cavitation damage.
Operator experience is that the NORSOK and ISO 14692 procedures for ultrasonics and
radiography of adhesive joints are not always effective for a number of reasons. The
surface finish of commercial joints can make coupling for ultrasonic inspection difficult. In
most offshore joints the adhesive does not contain the radiation absorbing fillers, e.g. ZnI2,
BaSO4, PbO or W (at 5 weight percent) noted in Appendix B.1. of NORSOK M-622.
Without these fillers it can be extremely difficult to show up lack of adhesive by radiography.
The procedures in ISO 14692 Pt. 4 and NORSOK M-622 are designed for inspection after
installation and not specifically in-service.
For these reasons, it is recommended that the guidance in ISO 14692 Part 4 and NORSOK
622 is followed after installation and in-service, but subject to a number of additional
considerations:

Proper calibration standards should be produced using the same adhesive, jointing
method and GRP material and geometry as the pipework to be inspected.

It is recommended that at the design stage a good quality surface finish (Peel-ply or
gel coat) is procured on the joint surfaces to facilitate ultrasonic inspection.

For ultrasonic inspection, common scanning methods such as linear scanning (Bscan) or area scanning (C-scanning) are preferred over point measurements.

Rapid scanning methods (using wheel probe or phased arrays) should be


considered to increase the speed of inspection. However the capability to detect
disbonds or lack of adhesive should first be established using standard probes.

41

HOIS GP1 Issue 2

For radiography a low photon energy isotope source (<100keV) is likely to be


required to optimise contrast, particularly for smaller diameter pipework (<6) and
thinner components. Source activities in the range ~10Ci to ~25Ci are said to be
beneficial. The advice on radiography of joints in NORSOK M622 and Section 14.5
shall be followed.

For practical reasons, X-radiography is unlikely to be used for GRP inspection in


offshore applications. [In the aerospace industry X-radiography is undertaken rather
than use of gamma sources because this gives better contrast and resolution.]

Where difficulties are encountered using ultrasonics or radiography, or there are


issues with material thickness, surface quality, safety or access, other NDE methods
should be considered.

The alternative NDE methods assessed by ESR Technology as having the greatest
promise in this application are microwaves, shearography and acousto-ultrasonics.
Trials using simple tap-testing in the ACLAIM programme encountered difficulties. It
is not believed transient thermography would be particularly effective because of the
curvature and thickness. Procedures for application of these new techniques on
GRP pipe-joints have yet to be established. These latter methods need to be
investigated further to establish their limitations and potential applicability.

Tap and bond-testing methods are limited in applicability to offshore joints by the
thickness and quality of the GRP the tap and acoustic response needs to transmit
through to access the bond.

The possibility of installing graded optical fibres within the adhesive layer could be
considered to monitor the degradation and any defect growth in service. Such
technology is currently available and is being assessed in the Imajine programme.
For critical components, the use of acoustic emission should also be considered.

Detection of kissing bonds is particularly difficult and there is no good NDE solution.
Several methods have a potential capability, but the difficulty of this defect type is
well recognised by NDE providers. Laser shearography has the potential to detect
lack of adhesion and the strength or weakness of the bond, an advantage over
ultrasonics in this application and relevant to kissing bonds. However, the section
thickness in commercial joints is likely to limit the sensitivity of resolution for
shearography. Kissing bonds are a difficult defect for thermography. Ultrasonic
guided and surface waves have been evaluated for adhesive disbonds in
connectors with limited success. Shockwave methods (such as Remote acoustic
impact Doppler (RAID) developed in the aerospace industry for kissing bonds 6 may
have applicability in connectors but have so far not been applied to offshore grade
GRP or thicker section composites.

12.6

Laminated joints

For laminated joints the same NDT methods could be considered as given above for
adhesive joints, although as there is no adhesive radiography is unlikely to be so applicable.
The recommendations for delaminations In ISO 14692 Pt. 4 could be considered relevant.
The main issue is delamination or disbonding of the joint, and any degradation in joint
integrity that may occur in service. It would be normal to visually assess and proof test the
joint following installation. The following recommendations are given in the standards:

New Technologies to Improve the Quality, Speed and Safety of Production; Production; Dr. Peter H. Wu, Vice
President & Chief Scientist, Spirit Aerosystems. Manufacturers Summit 2006, Low Mass Transport Systems
Symposium 2006, Manchester 2 November 2006

42

HOIS GP1 Issue 2

NORSOK M-622 recommends Visual inspection (incorrect dimensions, missing


plies, etc.), radiography, pressure testing, ultrasonics, and acoustic emission for
incorrect lamination in laminated joints to detect incorrect lay up, or if the lay up
is not structurally adequate. No recommendations are made in relation to inservice inspection.

ISO 14692 gives limited advice on inspection of laminated joints. Tap-testing is


suggested for general assessment of laminated joints for delamination and
acoustic emission for wrong lay-up on laminated joints.

For incorrect lamination in composites, ISO 14692 Pt. 2 recommends visual


inspection with a light source inside the pipe, if appropriate, followed by
radiography.

Ultrasonics or thermography is recommended in ISO 14692 pt. 4 for detailed


assessment of delaminations in thin components; with radiography for thick
components.

A recent HSL report 7 on composite overwrap repairs, a similar manual laminating


procedure, recommends the following:

Substrate (e.g. Pipe): composite - none available; metallic - radiography or


electromagnetic techniques such as low frequency or pulsed eddy current.
Interface (between repair and substrate): microwaves or laser
shearography show most promise currently (both at research stage) in this
application.
Laminated composite repair: visual.

Microwaves and shearography were also found to be the most promising methods for
disbonding in NDE tests undertaken by the offshore composite repair workgroup.
Ultrasonics was variable with some difficulty in achieving back-wall echoes. Tap-testing
performed less well than had been suspected. Taking these recommendations into account,
we would recommend visual inspection of the joints with occasional leak testing as the main
approach for assessing integrity of laminated joints. Acoustic emission monitoring could
also be considered. If NDE is required or considered to look for incorrect lamination or
degradation in-service of the joint, then the following methods that are sensitive to
delaminations or disbonds are recommended:

Ultrasonics (can be problematic);

Microwave inspection (developmental);

Laser shearography (developmental);

Note that the latter two methods are still at the development stage for offshore application.
The following alternative NDE methods are potential alternatives if first qualified on similar
joints:

Acousto-ultrasonics;

Tap testing;

Radiography.

HSE/HSL FRP composite repair fact sheet; Draft: Final, March 2009

43

HOIS GP1 Issue 2


However, radiography is not well suited for the detection delaminations or disbonds in
laminated joints. NORSOK M-622 notes in relation to voids in adhesive joints, that if the air
gap between the bonded faces is less than 0.5 mm, voids will be very difficult to detect by
radiography. Disbonds or delaminations in laminated joints are likely to be tighter than this
as no adhesive is used. There is no general procedure for defect assessment in laminated
joints; this will depend on the location and cause of damage.

12.7

Flange connections (fixed and loose ring designs)

Flange connections may be fixed or loose flange designs, with composite to metal or
composite to composite connections. Manufacture is by filament over-winding or manual
lay-up with moulding. Relevant defect types include flange cracking or delamination of the
flange itself or adjacent laminated material. Over-tightening, poor design or residual
stresses introduced during curing are the main causes of flange cracking.
Recommended NDT methods for flange cracking in ISO 14692 Pt. 4 include:

Visual inspection;

Tap testing (general assessment of flange surround);

Thermography;

Manual UT;

Radiography.

ISO 14692 and NORSOK M-622 recommend visual inspection for flange cracking with tap
testing for general assessment of the GRP material in the taper and around the joint. For
thin components, thermography or ultrasonics are recommended; with X-radiography for
thicker components.
It is recommended that the ISO 14692 and NORSOK M622 guidance on NDE techniques is
followed in the first instance. In all cases the NDE method should be qualified on a suitable
reference sample or on the component.
If the above methods prove ineffective then the following are potential alternative methods:

Dye-Penetrant

Microwave inspection;

Laser shearography;

Acousto-ultrasonics.

These methods do not have an established record in this application and should be first
qualified on a suitable reference sample or representative component. There are a number
of NDE issues and limitations. The surface finish of the flange surround is generally less
good than pipework, particularly if laminated. Wall thickness is variable around the taper
and access may be limited.

44

HOIS GP1 Issue 2

Figure 5 Cracking on the flange faces in an offshore flange connection

12.8

Repairs

A repair is basically a joint introduced into the structure. In DNV-OS-501 it is recommended


that repair procedures shall be given for each component. A repair shall restore the same
level of safety and functionality as the original structure, unless changes are accepted by all
parties in the project. If local damage may happen to the structure detailed procedures to
repair such anticipated damage shall be given.
It may also be acceptable to keep a component in service with a certain amount of damage
without repairing it dependent on criticality. The size and kind of acceptable damage shall
be defined and it must be possible to inspect the damage. The possible damage shall be
considered in the design of the structure.
It is recommended that the inspection and assessment guidance in the HSE FRP
composite repair fact sheet 5 shall be followed in the first instance.
If this proves inadequate it is recommended that the repairs shall be qualified and inspected
in the same way as given above for an adhesive or laminated joint. The geometry of the
repair should be considered in planning inspection.

13.0
13.1

Inspection guidance by defect type


Delaminations

Inspection for delaminations is one of the most common uses of NDE in composites.
Delaminations can directly affect the integrity of a composite component and of adhesive
bonds. There are a variety of NDT methods that potentially can detect delaminations. The
most appropriate method will depend on thickness, surface finish and ease of coupling,
material quality, geometry of the component and access limitations.
Installation and in-service inspections are covered in ISO 14692 Part 4 as well as a
summary of defect types and NDE methods. NDE methods identified for delaminations are
visual inspection with internal illumination if appropriate, ultrasonics and radiography.
Several non contact inspection methods are available including laser shearography, pulsed
video thermography, microwave inspection as well as conventional, computed or digital

45

HOIS GP1 Issue 2


radiography techniques. NDE methods identified for delaminations in the NORSOK
guidelines are visual inspection with internal illumination if appropriate, ultrasonics,
thermography, radiography and acoustic emission. Which is appropriate will depend on the
geometry, surface finish, material quality and thickness of the component. Procedures for
these methods are included in the Annexes to the NORSOK guidelines. The methods
should be validated on calibration samples. Ultrasonics and tap testing methods become
less favourable for detection of delaminations in thick components; if geometry is complex;
or if the material quality or surface finish is poor. In these circumstances radiography is
often used, although it is not particularly well suited for laminar defects.

Figure 6 Delamination in GRP linked to


through thickness crack

Figure 7 Bondline defect between GRP pipe and elbow fitting


caused by incorrect adhesive application.
Manual ultrasonics or visual inspections are common inspection techniques to apply for
delaminations in GRP components. Laser shearography is relatively costly but simple to
apply. Laser shearography has become the accepted method for detection of delaminations
and other defects in lifeboat hulls replacing ultrasonics. Radiography is not intrinsically
suited to laminar defects but is favoured increasingly in thicker sections. Acoustoultrasonics is well suited to thicker composites and relatively fast but, in common with other
newer methods, published information on field trials is limited. Transient thermography has
advantages as a fast global method, but can be difficult to apply to thick sections and on
curved geometries. There is more limited experience of thermography on GRP than CFRP
components. Tap testing is simple to apply but becomes less sensitive as thickness
increases or if with lower quality hand laid material. Microwaves have been trialled in
laboratory conditions and potentially are very promising. In common with most methods not
currently included in standards more experience is needed in the use of microwaves in field
conditions and in the interpretation of data.

46

HOIS GP1 Issue 2


In summary, the following NDE methods have promise for detection of delaminations:

Visual - if unpainted and internal illumination is possible;

Manual ultrasonics (hand-held probe and flaw detector);

Automated ultrasonics using scanning methods(B-scan, TOFD) providing adequate


coupling can be achieved;

Rapid ultrasonic inspection (B-scan, C-scan) using wheel probe or phased array;

Tap testing;

Microwaves (e.g. Evisive or similar system);

Laser shearography;

Transient thermography modern integrated system with image processing.

For thicker sections > 25mm, more complex geometries or where surface finish or porosity
makes ultrasonic inspection difficult the following methods should be considered and can
also be applied to thin sections:

Microwaves;
Radiography (using appropriate radioactive source);
Acousto-ultrasonics (e.g. T-Scout or similar system) ;
Vibro-thermography (developmental -effective for delaminations and cracks).

Microwave inspection, acousto-ultrasonics and laser shearography offer alternatives to


radiography in thicker sections. Microwaves and acousto-ultrasonics are particularly suited
to thicker section GRP, Figure 7.

13.2

Erosion or loss of wall thickness

Loss of wall thickness can occur by erosion or chemical attack. In lined piping there may
also be a need to assess the integrity of internal liners, since loss of the liner protection may
lead to a rapid loss of properties. Criteria and corrective action for loss of wall thickness
(LOWT) are defined in Table 5 of ISO 14692 Part 4. For erosion a reduction in original wall
thickness less than 20% is acceptable with monitoring required; reductions greater than
20% are to be rejected.
Chemical attack (liner or resin rich layer removal) is covered in Table A.1 of the above
standard. If the resin surface is absence rejection is recommended at manufacture, delivery
or installation. In operation the corrective action recommended is rejection/ major repair.
There is no acceptable wall loss if the protective resin layer or liner has been removed. Any
chemically damaged layer should be treated as having no residual strength and replaced.
Monitoring of wall thickness, liner condition and the depth of any chemical damage may
provide a short term solution based on engineering judgement, if it does not exceed
corrosion allowables, but is not recommended by ISO-14692.
ISO 14692 specifies ultrasonic thickness measurement with an averaging 1-D assessment
and a conservative minimum wall thickness approach.
The NORSOK guidelines recommend visual inspection (internal), ultrasonics, thermography
or radiography. Procedures are included in Annexes A, C, D and E. of the NORSOK
guidelines.

47

HOIS GP1 Issue 2


Spot thickness measurements using ultrasonic wall thickness meters as used in metallic
pipe are not well suited as the high ultrasonic noise levels and scatter in GRP make
accurate location of the back wall by spot measurements difficult. Methods involving a linear
scan (ultrasonic B-Scan, TOFD) or C-scan are preferable. A different approach may be
necessary for generalised wall loss compared to localised damage.
For the reasons outlined ultrasonic B-scanning at low frequency is the recommended
procedure for wall thickness measurement in GRP pipework. The following other methods
may also be worth consideration:

Ultrasonic TOFD linear scan;

Acousto-ultrasonics (T-Scout);

Ultrasonics phased array (e.g. Rapid-Scan);

Gamma-radiography (difficult geometries);

Microwave (thicker or variable components);

Thermography for localised wall thickness loss;

Tap testing for localised wall loss in thinner GRP components;

Laser shearography.

The choice of technique will be determined by the same factors outlined above for
delaminations, namely: surface finish; thickness; material quality; and the complexity of the
component. NDT is difficult where material has been manually overlaid; with coupling
difficulties and significant attenuation for manual UT even at low frequency (< 2MHz).
Recent trials by HOIS in Houston suggest that tap and bond-testing methods also can
become difficult when applied to thicker section or hand laminated quality material
compared to commercial filament wound piping.
Procedures are available for ultrasonic A-scan wall thickness measurement, ultrasonic Bscan and C-Scan, shearography and thermography from the UK DTI funded CPD4D
programme8 and can be accessed from the MMS15 IKB website www.mms15.com .

13.3

Impact damage

Impact damage can occur to composite components during manufacture, transport or inservice. This is usually characterised by a conical region of damage, which may include
delaminations, matrix cracking and fibre cracking, emanating below the surface of the
component from the point of impact. Where the damage is only faintly visible to the naked
eye this is known as barely visible impact damage (BVID). The extent of damage will
depend on the force of impact.
ISO 14692 refers to use of visual inspection to detect impact damage. A maximum
diameter of 5mm is given as acceptable for impact damage. No specific NDT techniques
are recommended for impact damage.
The NORSOK guidelines do not include impact damage specifically in the summary table
on NDE methods. Methods that are given in the NORSOK and ISO tables for the

CPD4D Procedures for ultrasonics, thermography and shearography of FRP composites, ESR Technology,
DTI CPD4D Programme Final Report, 2002 (available at www.mms15.com )

48

HOIS GP1 Issue 2


constituent damage mechanisms arising from impact damage (delaminations, matrix
cracking and fibre-cracking) are likely to be relevant.
For impact damage visual inspection is likely to be the first port of call. NDT methods that
could be applied for barely visible impact damage include the following:

Visual inspection;

Thermography;

Shearography;

Ultrasonic A-scan;

Ultrasonic image processing (B-scan, C-scan).

Trials at the NNDTC have shown thermography to be particularly suitable for impact
damage; picking up the conical region of damage, particularly if modern image processing
methods are used to give images at different depths. Simple ultrasonic pulse-echo has
potential if delaminations have occurred. More sophisticated ultrasonic imaging methods
(C-scan, B-scan, 3D dataset) can show up regions of impact damage visually. This is likely
to be too detailed for offshore application. Shearography has potential as a fast global
method and should give good sensitivity to surface strains and sub-surface damage arising
from the impact damage. Further trials are needed on offshore pipework to establish the
best methods for applying the load change required (vacuum, thermal or internal pressure)
and the thickness limitations.
Additional methods that could have potential include:

Microwaves;

Acousto-ultrasonics.

We are not aware that either has been specifically trialled on impact damage.

13.4

Matrix cracking

Matrix cracking is a progressive damage mechanism, in which transverse cracks are


initiated within the plies. The amount or density of cracks increases as either the load is
increased or the length of time the load is applied. In combination with delaminations
between plies this can lead to weepage and eventually loss of containment. There is
interest in developing an NDT procedure for matrix cracking as this could provide a basis
for life extension of aged GRP.
This is the main progressive materials degradation mechanism in offshore composites and
design life is based on a regression curve approach. NDT methods offer the potential to
measure the actual spacing of matrix cracks in GRP components. This enables a life
assessment based on actual condition.
The NORSOK M-622 guidelines recommend visual inspection (e.g. dye penetrant/ felt tip
pen) and acoustic emission for propagating cracks. Procedures are included in Annexes A
and E respectively of the standard.
A damage mechanics approach has been suggested 9 as a way to estimate the density and
consequence of matrix cracking. This is based on the ASTM D2992 regression curve
9

Frost S R and Lee R J; Integrity assessment procedures for GRP pipes, Technical Exchange Meeting, Saudi
Aramco, Dhahran, 27th May 2008

49

HOIS GP1 Issue 2


approach. Acoustic emission is recommended for general assessment with ultrasonic
velocity measurement for quantification.
There are no established NDT procedures for characterisation of matrix cracking in GRP
composites. Methods that have been applied include:

Visual inspection (unpainted and with internal illumination);

Axial velocity measurement of ultrasound;

Acoustic emission;

Gamma-radiography.

Additional methods that could have potential include:

Ultrasonic C-scan with image processing;

Angled or phased array ultrasonics.

If the GRP component is left unpainted and thin, i.e. transparent, then visual inspection with
internal illumination is a simple and effective approach. Digital X-radiography is the
accepted method in the aerospace industry but has not been applied in-field in an oil and
gas environment. Angled ultrasonic and C-scan methods have been developed in the
aerospace industry specifically for detection of matrix cracking, but again they have not
been applied to GRP components used in oil and gas applications.
Velocity measurements using ultrasonic waves for monitoring the change in axial modulus
due to matrix cracking has been trialled in the laboratory and shows potential, linking the
reduction in velocity to the increase in micro-crack density. This technique has not been
applied in the field. The axial ultrasonic velocity method is used to determine the modulus
and relate this to crack spacing. The number or density of cracks within each ply increases
as the level of load or over-stressing is increased. Modelling of the process of matrix
cracking within the wall of GRP pipes9 showed that:

Crack spacing is the parameter which can be used to characterise the amount of
damage;

Short term stress-strain response of the pipe can be predicted;

The parameter which is the strongest function of crack spacing is the axial modulus;

The regression gradient relating to the long term performance of the pipe can be
estimated from short term and long term stress, strain measurements.

The most sensitive parameter to infer crack spacing is pipe axial modulus. As the crack
spacing increases the axial modulus will decrease. Hence from velocity measurements, the
remaining life of the pipe can be estimated from the inferred regression gradient and the
current level of damage (or crack spacing) within the pipe wall. The assumption here is that
the axial modulus will degrade at the same rate as the tensile properties required for
pressure containment2.
In the previous DTI DCC3 10 programme on composite materials an assessment approach
was developed and a number of NDE methods were evaluated for assessing the crack
10

Final Report from DTI/DCC3 Programme on design guidelines for Brittle-Matrix composite components, Subprogramme: Evaluation of NDT methods for transverse cracking, Eckold G C, Wall M et al, April 1997.

50

HOIS GP1 Issue 2


separation. These included ultrasonic velocity, X-radiography, visual and attenuation
measurement. Some success was obtained with an axial attenuation method in which
ultrasound was input at a critical angle (similar to CHIME) and propagated along internal
plies. Separate probes were used for transmission and receiving the ultrasound.

13.5

Significant cracks

This refers to the situation where cracking has extended over a number of plies through the
section and in many cases through to the component surface. This will normally include
both matrix cracking and fibre breakage and frequently link to delaminations.
The same NDE methods are applicable as for matrix cracking. Significant cracks are likely
to be revealed by visual inspection enhanced by penetrant or internal illumination.
ISO 14692 makes no specific recommendations on detection of discrete cracks but
recommends acoustic emission for general assessment, ultrasonic velocity measurement
for quantification, with a damage mechanics approach to estimate density and
consequences. The NORSOK M622 guidelines recommend visual inspection (e.g. dye
penetrant), acoustic emission (propagating cracks), ultrasonics or radiography. Procedures
are included in Annexes A, E, C and D respectively of the guidelines.
Through-thickness cracking or fatigue cracking is unlikely to be detected using conventional
0 ultrasonic probes, though associated delaminations may be detectable.
Methods focussed on detection of delaminations such as ultrasonic C-scanning or
thermography, and attenuation methods like radiography, may not reveal tight throughthickness cracks. However, the nature of crack propagation in composites is that cracks are
likely to be a mix of matrix cracking, fibre breakage and delaminations and a crack of this
type is potentially detectable by a range of NDT methods. It is recommended that the NDE
methods included in NORSOK M-622 are used in the first instance for crack detection in
GRP pipework and joints:

Visual (with illumination or dye penetrant);


Acoustic emission;
Ultrasonics;
Radiography.

Ultrasonic velocity methods can be used to indirectly assess cracking based on the effect
on measured modulus.
In most cases visual inspection is likely to be adequate.
If the above NDE methods prove inadequate in the application then one of the following
techniques shall be used, subject to qualification on the component or a suitable reference
sample.

Laser shearography;
Ultrasonic pulse-echo (B-scan, angle probe);
Thermography;
Ultrasonic TOFD;
Ultrasonic phased array (conventional or roller probes);
Vibro-thermography (developmental);
Acousto-ultrasonics.

51

HOIS GP1 Issue 2


Reliability trials by the University of Bath 11have shown vibro-thermography (otherwise
known as thermosonics) is particularly suited to crack detection as this method generates
acoustic responses directly from crack tips. This is not yet sufficiently developed as a field
method.

13.6

Materials degradation

Materials degradation is handled in ISO 14692 by use of regression curves, after testing at
the design and qualification stage. The normal approach recommended to assess the
actual condition of aged composites, in relation to life extension, is destructive testing as
detailed in ISO 14692 Pt. 4.
For destructive testing a two stage combination of measurements is recommended. The
first stage involves a simple assessment as to whether the component has suffered
degradation or not. This stage involves the following tests:

Microstructural analysis of the pipe wall;


Measurement of the glass transition temperature;
Short term pressure test to failure.

These tests can be completed on the GRE component relatively quickly; which implies that
an answer to the question has the component suffered any degradation? can be
answered in a short timeframe.
If the first stage assessment demonstrates that the component has suffered degradation
then the second stage involves further testing to establish the amount of or quantification of
degradation. This stage might typically involve the following tests:

Further microstructural analysis;


Further glass transition temperature measurements;
Chemical analysis and weight gain/loss measurements;
Low speed loading rate pressure tests over a 1000 hour time period.

From the results of these further tests and application of the damage mechanics model an
assessment of the remaining lifetime or remaining strength of the GRE component can be
made following the guidance in ISO 14692.The one drawback of this assessment procedure
is that GRE samples are required from the field to enable the destructive tests to be
performed.
Ultrasonic velocity measurement of modulus in combination with laminate9 potentially offers
an NDE alternative to assess the level of matrix cracking (the dominant ageing mechanism
in oil industry applications) and is recommended where removal of components for
destructive testing is difficult or not preferred.
In oil and gas industry applications the main degradation mechanism is matrix cracking and
the methods described above for matrix cracking would be applicable. In the latter stages
these lead to delaminations or larger transverse cracks arising from linkage of the matrix
cracks, which are precursors to weepage. Such severe ageing damage may be detectable
visually or with the NDE methods identified above for delaminations and cracks (See
Section 13.7 below specifically for weepage).

11

D P Almond, R J Ball, A Dillenz, G Busse, J C Krapez, F Galmicher and X Maldague:.Round robin


comparison II of the capabilities of various thermographic techniques in the detection of defects in carbon fibre
composites. Eurotherm Seminar 64. QIRT 2000, eds. D.Balageas, J L Beaudoin, G Busse and G M
Carlomagno, pp224 9.

52

HOIS GP1 Issue 2


Time dependent environmental damage to composites can be assessed using dielectric
methods for which equipment is routinely available.
Thermography is used to detect water ingress to the core in aerospace and sandwich
structures and marine hulls. In offshore applications monolayer composites are used rather
than sandwich structures, so application of thermography for water ingress is likely to be
limited to lifeboats and marine structures.

13.7

Environmental ingress and weepage (matrix cracking and


delamination)

Environment ingress is not significant in oil industry composites except where damage has
progressed sufficiently to the surfaces to permit ingress or allow weepage through the
composites. Water or environment ingress will soften and weaken the composite.
Weepage is a more severe combination of matrix cracking and delaminations where the
cracking has extended to the surface and allows liquid to seep through the composite. This
is effectively the failure mechanism for GRP pipe as the pipe is no longer fit for purpose. If
damage has progressed this far it is likely to be evident on visual inspection and use of
NDE methods is unlikely to be applicable.
Weepage is a failure condition and it would be anticipated that damage should be detected
at an earlier stage by NDE methods that can detect delaminations. In most Oil industry
applications environment damage has been found to be cosmetic and evident on visual
inspection. The precursor damage is likely to be revealed by the NDT methods identified
above for delamination and matrix cracking.

14.0

NDE Methods

This section provides guidance on the application of NDE methods available for inspection
of GRP. Visual inspection remains the most important technique if the resin is transparent,
as large areas can be inspected quickly within the laminate. However, some of the most
important defects, such as poor bonding, may require more sophisticated NDE methods
and a high degree of operator skill. Specific guidance on the application procedures for
primary NDE methods is given in Annex E of ISO 14692 Pt. 4 with more detailed
procedures for ultrasonics and radiography in NORSOK M622. More detail on individual
NDE methods and data examples can be found in the HOIS review on NDE of
composites 12. Relevant NDE codes and standards are given in Section 4.2.

14.1

Validation and calibration samples

To validate an inspection method and to set the sensitivity for the inspection, appropriate
calibration samples should be used. An example of a calibration sample is shown in Figure
8. It is recommended these should be of similar thickness, material type, ply structure,
surface finish and geometry as the actual component and contain real or simulated defects.
The method used for insertion of defects should be representative of the defect and suitable
for the NDE method (or methods) being evaluated.

12

HOIS Review on NDE of composites, 2008

53

HOIS GP1 Issue 2


Common practice for parent material and joints includes the following:

Insertion of PTFE film (50 m) to simulate inclusions;

To simulate delaminations a double PTFE layer (50m) with the edges sealed by
heat resistant tape to leave an air gap;

For adhesive joints areas free of adhesive or use of double PTFE layers to simulate
disbonding;

Flat bottomed holes milled on the far surface to simulate erosion damage or voids;

Insertion of simulated inclusions (PTFE, peel-ply etc.) or voids in an intermediate


layer between two plates;

Methods now exist which involve the insertion of individual air pockets (similar
principle to bubble wrap). These provide a better simulation of a delamination than
a PTFE film defect.

A difficulty with simulated defects is that some NDE methods may be good with simulated
PTFE flaws, but not with artificial flaws or vice versa. Ideally a range of defect sizes and
depths should be included to assess the technique sensitivity.
Examples of calibration samples are shown in the ultrasonic and radiographic procedures
included in the Annexes to NORSOK M-622, including a stepped adhesive bond sample
relevant to different thicknesses of composite joint (Figure 9).

Figure 8 Example of a GRP inspection calibration sample with delaminations of different


size and depth.

54

HOIS GP1 Issue 2

Figure 9 Examples of calibration samples for ultrasonics in NORSOK M-622: left, Sketch
of calibration standard for voids and delaminations, defects achieved by machining holes
with diameter and depth selected to match defects to be detected; right, Sketch of
calibration standard for bonded pipe joints.

14.2

Visual inspection

Visual inspection is the primary inspection method used on composites at manufacture and
in-service. The advantage is the speed and simplicity and the range of surface visible
defects that can be detected. If the composite is uncoated then due to the transparency of
the material internal defects may also be visible on back illumination.
It is recommended that visual inspection is carried out in accordance with the guidance in
Section 5.7 of ISO 14692 Pt. 4, with defects classified in accordance with ASTM D 2563 13.
The main visually detectable defects are:

deformations and dimensional deviations;


surface cracks and microcracks;
near-surface delaminations, inclusions and air entrapments;
impact damage;
blisters;
internal excess of adhesive (internal inspection);
chemical degradation or ageing;
erosion (internal inspection).

It is important that inspectors are familiar with inspection of GRP and the defect types that
may occur from manufacture and in-service. Suitable aids such as an illumination source,
mirrors, boroscope, and if appropriate penetrant, to maximize the extent and accuracy of
the visual inspection.
Possible defects along with acceptance criteria and corrective actions are listed in Table 4
of ISO 14692 Part 4 with further information concerning defects arising during fabrication
and installation, and corrective action, given in Table A.1. The presence of a uniform fillet of
adhesive is often an indicator that an adhesive joint has been assembled correctly.
Visual inspection, both internally (as far as physical access allows) and externally, should
be carried out of all joints and all surfaces.

13

ASTM D 2563. Standard Practice for Classifying Visual Defects in Glass-Reinforced Plastic Laminate Parts

55

HOIS GP1 Issue 2

14.3

Pressure testing

The hydrotest is considered by many to provide the best assurance of a GRP pipe systems
or vessels integrity, and to be more reliable than NDE techniques for assessing that the
system has been properly fabricated and installed. It is recommended that the guidance in
ISO 14692 Part 4 and NORSOK M-622 Section 5.5.4.6 is followed. It is normal to follow the
pressure test (1.5x maximum operating pressure) with a separate leak test at 1.1 times
maximum operating pressure. The hydrotest may be done in conjunction with Acoustic
Emission monitoring to detect early onset of damage and identification of damage locations.
Pressure testing in service may also be considered, particularly if defects are suspected in
adhesive joints or after long term ageing. A disadvantage is that the cost of blinding off
systems can be significant.
The main defects detectable by pressure testing are:
a) adhesive-bonded joints lacking adhesive or improperly prepared and assembled,;
inadequately cured adhesive in the bonded joints;
b) manufacturing defects in GRP materials;
c) leaking joints.
A pressure test at 1.5 times the design pressure reveals leaks and such major defects as
severe impact damage (e.g. from improper transport), improperly designed or fabricated
systems (lacking adequate strength or pressure retention), or very poor adhesive bonding.
However, adhesive-bonded joints are designed with a large margin of safety and bonded
joints having as much as 80 % unbonded area can pass a pressure test. Thus the pressure
test is a major element in ensuring that the GRP pipe system is structurally and functionally
adequate, but cannot be viewed as an absolute guarantee of performance.
For critical systems, other NDE methods (e.g. random verification of joint quality using
ultrasonics) can be used along with pressure testing and AE monitoring to determine the
presence of excessive debond or void areas that may have a detrimental effect on service
life.
The test pressure shall be raised over a period of 30 min or longer to 1.5 times the design
pressure or 0.89 times the qualified pressure, whichever is lower. The pressure-decay test
shall be conducted for a minimum of 1 hour.
Following successful conclusion of the strength test, a further leak test, at 1.1 times the
design pressure, should also be carried out for a minimum of 24 hours.
The following additional points are worth consideration:

All necessary measures shall be taken to remove air from the pipe spool or
vessel during filling;

If possible, the system should be filled from the lower end;

Venting shall be carried out repeatedly at points in the test section where
air might accumulate, e.g. at ancillary piping;

After filling, a minimum period of between 6 and 48 hours shall be allowed


for temperature stabilisation before commencing pressurisation;

56

HOIS GP1 Issue 2

During the test, the pressure shall be recorded continuously and


deadweight tester readings shall be recorded every 30 minutes.

The following factors influence the choice of test duration:

Joint expansion and material creep, particularly when long runs of pipe are
being tested;
Water uptake properties of the GRP material, e.g. phenolic materials;
Temperature; which is more noticeable when testing is being carried out in
a hot or cold climate and if relatively large changes in temperature may
occur during the course of the test.

Additional checks shall be carried out after this time has elapsed, by visual inspection of the
complete piping system. Any leaking or weeping shall constitute a defect, and the test shall
be terminated and a repair effected.
The system shall be considered to have passed the hydrotest if there is no leaking or
weeping of water from the piping and there is no significant pressure loss that cannot be
accounted for by usual engineering considerations, e.g. thermal expansion of pipe, or other
factors previously agreed with the principal.

14.4

Ultrasonics

Ultrasonic pulse echo (PE) (where one transducer functions as both transmitter and
receiver) is the most commonly used ultrasonic test method for GRP in Oil industry
applications. In particular situations, through-transmission (using two transducers) may be
used.
The main defects detectable with ultrasonic testing are

areas in bonded pipe joints lacking adhesive;


delaminations;
disbonds;
voids;
deviations in wall thickness.

A specific HOIS procedure on ultrasonic testing is being developed for GRP. In the interim
it is recommended that the Guidance in Annex E.4 of ISO 14692 Pt. 4 is followed together
with the procedure in Annex A of NORSOK Standard M-622.
If a more detailed or specific inspection procedure is required for ultrasonic B-scan or Cscan inspection then the following procedures may be considered:

DTI CPD4D offshore generic ultrasonic procedure and ultrasonic A-scan, B-scan
and C-scan procedure developed by ESR Technology (downloadable from
www.mms15.com )
DRA/NPL Working Draft Standard v 05, Fibre Reinforced plastics Ultrasonic Cscan inspection of composite structures: Parts 1-6, NPL, QinetiQ.

According to ISO 14692 Pt. 4, voids and areas lacking adhesive can be detected using
available ultrasonic methods to resolutions of approximately 10 mm and to depths of 100
mm; areas of poor adhesion, i.e. little or no adhesion but with joint faces in contact (also
known as kissing bonds) are not reliably detected by this method; variations in wall

57

HOIS GP1 Issue 2


thickness of approximately 20% can also be detected and delaminations can be detected
with resolution similar to that for voids.
The following additional points should be considered:

A compromise is required in probe selection between resolution (typically higher at


higher frequencies), depth of penetration, initial reverberation and probe diameter.

The selection will depend on the quality of the composite and surface finish.

For filament wound offshore grade GRP piping a frequency of 2.25MHz or greater
may be used giving good resolution and better defined echoes from defects. Higher
frequencies (>5MHz) may not be beneficial because interpretation is confused by
natural signals from the ply structure.

For fittings, manually overwrapped or lower quality GRP it will generally be


necessary to use a frequency in the range 0.25 to 1MHz because of the high signal
attenuation.

It is beneficial to use a probe that is acoustically matched to GRP to minimise signal


loss.

The use of a delay-line probe is beneficial to reduce the initial reverberation in the
signal, and hence the depth near the surface that is not generally inspectable. The
depth affected is frequency and probe dependent.

A standard glycerine or gel couplant with low viscosity is preferred as this gives
better wetting of the surface. Coupling is improved if time is allowed for the couplant
to wet and seep into the surface.

It is beneficial to procure GRP joints with a good surface finish on surfaces from
which ultrasonic inspection may be conducted, to facilitate good coupling. The
increased inspectability after installation and in-service is likely to outweigh the
additional cost.

Coupling with larger diameter probes (>20mm) is unlikely to be successful if the


surface is rough or undulating. In these situations smaller diameter probes (~10mm)
give much better coupling and signal response.

The clearest indication of laminar defects is the loss of back-wall echo, in addition to
any reflected signal that may occur.

The use of time-dependent gain can be beneficial if looking for back-wall echoes, for
example in thickness measurement.

Phased array or wheel probes may allow a more rapid inspection and provide more
visible defect indications. However, it is important to establish first that the probe
selection and UT conditions are correct using a conventional probe and A-scan.

Linear scanning methods (B-scan, TOFD) or mapping methods (C-scan) and


multiple point measurements are more effective at measuring wall loss and defect
detection in GRP than simple point measurements. The scatter and attenuation in
GRP and uncertainties associated with coupling, surface finish and materials
fabrication makes delineation of back wall echo position on point scans difficult.

Use of back-wall echoes is recommended for inspecting adhesively bonded joints,


since missing adhesive causes the back-wall signal to disappear.

Rapid scanning systems with wheel probes or phased arrays and good time
resolution can be used to collect 3D datasets, which can be used to reveal depth
dependent detail such as ply layers, porosity or wrinkling.

58

HOIS GP1 Issue 2

Time of flight diffraction (TOFD) with twin probes has been successfully used on
lined GRP vessels in South Africa.

Reflected pulses in GRP have more complex waveforms and less time separation
between the reflected pulses than is the case for steel. Therefore multiple echoes
cannot reliably be used in signal interpretation.

Two methods for increasing the time between reflected signals are: transmission
through flooded GRP pipes with the signal returning from the opposite pipe wall; and
use of a suitable (e.g. polymethyl methacrylate) stand-off.

Ultrasonic signals obtained from GRP can be of variable quality and possibly less
than would be expected for equivalent steel components as the FRP structure is
highly attenuating due to voids/porosity and signal scattering from the nature of the
laminated structure.

It was sometimes difficult to get a consistent back wall echo with some variability in
response between joints.

The inspection operator will need to familiarise themselves with particular


components and choose an optimum probe type.

Ultrasonic B-scan is the preferred acquisition mode as B-scan images can give a
more clear delineation of bond line defects and back wall echo.

Generally 1 MHz probes gave a better image than 5 MHz but with reduced
resolution. 2 MHz appeared to be the optimum frequency for a filament wound
GRE pipe spool.

Some probe types produce a full width of joints on the screen whereas others were
much smaller and required multiple passes to achieve the same result.

The mixed woven Fiberbond spool was much more attenuating of ultrasound and
required a probe frequency of 1 MHz or below to get any reasonable response.

Most defects were evident by reflection within the bondline and/or loss of back wall
echo. In some cases it was difficult to hold large probes sufficiently perpendicular to
the surface and it might require a jig to be used to ensure correct alignment. A probe
manipulator or holder might be useful.

Some joints exhibited high signal attenuation with high levels of noise and coupled
with pipe elbow curvature it was sometimes difficult to get a good back-wall echo. It
was possible to obtain C-scan images by manual scanning, with appropriate gates
set for back wall and bondline but setting gates can be problematic.

Use of soft (gel) faced probes appeared to be acceptable but could be improved if
pipe surface had a smooth gel coat (e.g. apply smooth polymer peel-ply sheet to gel
coat in manufacture). There was some variability in acoustic response between
joints as some were more difficult to achieve a suitable back wall echo.

There may be some benefit in using water column probes for samples with rough
surfaces.

59

HOIS GP1 Issue 2

Figure 10 Typical A-scan display showing debond and back wall echo in the centre joint at
the 12 oclock position.

Figure 11 Sonomatic twin probe TOFD arrangement

Figure 12 Sonomatic B-scan examples using 5 MHz and 2 MHz probes

60

HOIS GP1 Issue 2

Figure 13 Advanced NDT Instruments - indications observed for loss of back wall echo
and interface signal changes

Figure 14 Sonatest Rapidscan2 5 MHz pipe scanner

Figure 15 Sonatest Rapidscan2 data presentation including A, B and C-scans

61

HOIS GP1 Issue 2

Figure 16 GE Inspection 1 MHz phased array probe

Figure 17 Scanning on bonded joint using 5 MHz GE Inspection phased array probe

14.5

Radiography

Radiography is used with variable success on offshore GRP components for detection of
volumetric defects and lack of adhesive in bonded joints. Of the various non contact
inspection methods trialled, i.e. laser shearography, microwave inspection and radiography,
the latter technique produced the best images. A portable pulsed X-ray system was used
with a digital detector array. In this case certain details of the joints were revealed including
bondline defects and clear images of the pipe wall section.
A specific radiography procedure for GRP is being developed within the HOIS programme.
In the interim it is recommended that the guidance in Annex E.5 of ISO 14692 Pt. 4 and the
radiography procedure in NORSOK M-622 Annex B are followed. As an alternative, inhouse or company specific procedures may be followed. Radiographic techniques are
described in the ASME Boiler and Pressure Vessel Code, Section V, Article 2.
Radiographic testing is generally not sensitive to surface roughness, but it is sensitive to the
orientation of the defect. It is relatively easy to perform onshore, while it is somewhat more

62

HOIS GP1 Issue 2


complicated on offshore installations because of the need to close off areas while tests are
being conducted.
It is recommended that isotope sources (Ir 192, Se 75 etc.) are used as recommended in
NORSOK M-622. Isotope sources are routinely used offshore (Iridium and less commonly
Selenium). X-ray sources are too fragile and not intrinsically safe and hence are rarely if
ever used. [Note: X-ray inspection of composites is generally preferred for composites in
other industries over use of isotope sources because it has been found to give better
contrast.]
There are radiation safety hazards in the use of radiography both onshore and offshore. It is
recommended that a collimated isotope source projector is used if the controlled area
needs to be minimised.
The main defects detectable by radiography include:

incorrect wall thickness (up to 20% deviation), or fit between male and female
adherends;
some voids, delaminations and lack of adhesive (up to 5 % deviation);
axial misalignment;
excess adhesive on inner wall of pipe at joint;
scale build-up on inside of pipe;
incorrect insertion of pipes in adhesive sockets.

The following additional points should be noted:

Areas of poor adhesion, i.e. little or no adhesion but with joint faces in contact, are
not reliably detected by this method.

Radiographic test (RT) parameters, i.e. source energy and exposure time, should be
selected to allow for the low density of polymers and composites.

Radiography of composites is not straightforward and it is recommended that


calibration samples are used that are as representative of the component, material
and relevant defect types as possible. This will help optimise the selection of source,
film and inspection conditions.

It is highly beneficial that operators have experience with interpretation of


radiographs taken of similar GRP joints or components.

The technique (setup) recommended for bonded joints in NORSOK M-622 is double
wall single image (DWSI), as described in ASME B&PV Code Section V Art.2

The following film and sources are recommended by NORSOK M-622 for inspection
of GRP joints: Ir 192 with focus 2 x 2mm with activity less than 25Ci (or Se 75 in lieu
of or as a supplement to Ir 192), Agfa Gevaert D3, D4, D5 (bonded joints) and D7
for mechanical couplings.

It is recommended that as low an energy (keV) source as possible should be


selected (e.g. Se-75 in preference to Ir-192). Non standard low energy sources such
as Yb-169 are worth evaluation. A lower activity (10Ci or below) may also be
beneficial.

For smaller diameter pipework (<6) and thinner components Ir-192 is likely to have
too high an energy to give good contrast.

63

HOIS GP1 Issue 2

For X-ray inspection (may not be applicable offshore) low to medium tube voltages,
typically in the range of 10 keV to 100 keV, are likely to be required. The voltage
required will depend critically on wall thickness. Heavier duty oil and gas composites
may require a higher voltage.

As no image quality indicators (IQIs) are currently available to verify the sensitivity
on GRE bonded joints, it is very important that a fine grain film and a source with
lowest energy as practical are used. The use of 1-2mm thick GRP step wedges is
suggested as an aid to optimise contrast and sensitivity (see Figure 9).

From radiographic test results it is possible to determine wall and laminate (i.e.
repair) thicknesses, particularly if tangential radiography is used. In some cases it
has also been possible to determine the winding angle, voids or lack of adhesive by
contrast/change of density (particularly where these become filled with e.g. water).

Detection of cracks or laminar defects is difficult in adhesive joints unless there is a


significant air gap. Experience is that if the air gap is less than 0.5mm, voids and
lack of adhesive will be very difficult to detect.

In general, it can be difficult to detect lack of adhesive without modifying the


adhesive by adding heavy elements which act as contrast enhancers (such as ZnI2,
BaSO4, PbO and W at 5 % mass fraction) as recommended by NORSOK M-622
Annex B.1. Such contrast enhancers are not normally used in practice.

Digital radiography could offer advantages in adjusting the contrast after the
inspection has been concluded. This needs to be established.

Contrast enhancing penetrants (usually iodine based) as used in Military and


Defence applications to improve the sensitivity of radiography to impact damage and
other defects are not considered to be a practical option or needed in Oil industry
applications.

Figure 18 Photo and schematic diagram of 1mm and 2mm thick GRP step wedges to aid
contrast and sensitivity setting for radiography of composite pipework. Holes are same
diameter as step height.

64

HOIS GP1 Issue 2

Figure 19 GE Inspection Rhythm 3.0 - Digital X-radiograph (weld flash filter) pipe centre
joint with bondline defects. Stepped GRP wedge and EN10-16 IQI wires were used.
20 mm diameter steel ball used for dimensional reference.

14.6

Tap testing

Tap testing is long established as an inspection method for aerospace composites to detect
disbonds and delaminations. This can vary from a simple coin tap or small hammer to
automated tap testers, or bond testers, that may offer a number of techniques (e.g.
mechanical impedance analysis (MIA), acoustic resonance and pulse-echo). The technique
is also referred to as acoustic impact (AI). The virtue of the technique is its simplicity.
Application to thicker section GRP and in Oil industry applications is less established.
Application to hand laminated quality GRP and thicker sections is more difficult than
commercial filament wound pipework.
Equipment for manual tap testing can vary from a simple coin to the Airbus hammer, which
facilitates a more controlled impact. Suitable commercial automated equipment includes the
Olympus Bondmaster, Fokker Bondester, V-95 Bond Tester, and Woodpecker.
It is recommended that an automated tap-tester is used, preferably a system that allows a
combination of techniques to be assessed. This allows the optimum technique to be found
for a particular GRP type, quality and location. The method should be qualified in each new
application using suitable reference panels or calibration samples.
It is permissible to use manual tap testing methods if the method can be qualified on
suitable reference samples. These allow a simpler but more subjective inspection. In this
case it is recommended that a record of the area scanned is kept on a transparent sheet as
detailed below, to allow future repeat inspection.
Guidance is given in aerospace standards including DOT/FAA/AR-02/121 14 Guidelines for
Analysis, Testing, and Non-destructive Inspection of Impact-Damaged Composite Sandwich
14

DOT/FAA/AR-02/121 Office of Aviation Research Washington, D.C. 20591: Guidelines for Analysis, Testing,
and Non-destructive Inspection of Impact-Damaged Composite Sandwich Structures; U.S. Department of
Transportation, Federal Aviation Administration; Final Report, March 2003, Section 4.

65

HOIS GP1 Issue 2


Structures. There are no relevant oil industry standards on tap testing. No procedure for
tap-testing is included in ISO 14692 or NORSOK M-622.
Aerospace standards SAE ARP5605 Solid Composite Laminate NDI Reference Standards
and SAE ARP5606 Composite Honeycomb NDI Reference Standards refer to the
manufacture of a single, generic set of composite reference standards that would
accommodate tap testing inspections on the majority of composite structures found on
aircraft. Development of similar standards is recommended for the oil industry.
Automated tap-testers allow data to be recorded, are less subjective and have less risk of
causing damage to the component.
For manual tap testing the following points should be noted:

This method is portable, but no data is recorded. The accuracy of this test depends
on the inspectors subjective interpretation of the test response; therefore, only
qualified personnel should perform this test.

A record may be obtained by mapping the damaged area on a transparent sheet on


the sample with location marks. This enables the same area to be inspected at a
later date to measure any crack growth.

Care should be taken to avoid causing impact damage to the GRP component.

Tap testing is widely used for a quick evaluation of any accessible composite
surface to detect the presence of delamination or debonding.

The basic tap testing procedure consists of lightly tapping the surface of the part
with a coin or light special hammer with a maximum of 2 ounces or any other
suitable object.

The acoustic response is compared with that of a known good area.

A flat or dead response is considered unacceptable. The acoustic response of a


good part can vary dramatically with changes in geometry, in which case a standard
of some sort is required.

The entire area of interest must be tapped.

The surface should be dry and free of oil, grease, and dirt.

The method should be qualified for the thickness of GRP to be investigated.


Tap testing is generally used to find relatively shallow defects in skins with a
thickness less than 2mm. In a honeycomb structure, for example, the far side
bondline cannot be evaluated, requiring two-side access for a complete inspection.

For automated tap-testing the following points should be noted:

A suitable calibration sample should be available similar in material and quality to


the actual component and containing representative defects.

It is recommended that a system is chosen that allows a combination of different


probes and acoustic impact methods to be used.

A simpler system is acceptable if it can be shown to detect relevant defects on a


reference or calibration sample.

66

HOIS GP1 Issue 2

Data should be recorded if possible to allow later examination. For disbonding and
delaminations, it has been found that the signature, fingerprint or shape of the
response and decay curve varies, particularly in thicker section components.

Such variations in the signal response can provide a better delineation of defects
than the amplitude response.

Validation trials are recommended to establish the optimum method, or combination


of methods for a particular geometry or application.

There are advantages in using a system with encoder or probe location method that
allows the data to be presented as a C-scan type map.

Mechanical impedance methods have been found in some trials to provide an


improved response in thicker section components, compared to resonance methods
(see MMS15 Interactive Knowledge Base www.mms15.com) .

Higher loading mechanical tapping systems developed by HOIS and others for
inspection of passive fire protection may have application in thicker section GRP
and fittings.

14.7

Thermography

Thermography is a commonly used NDE technique on composites and one of the methods
recommended for Oil industry application in ISO 14692. Thermography techniques use
infra-red sensitive camera detectors and film or video display and recording methods, to
monitor the apparent surface temperature of an area of component. The thermal response
from a component is altered in the presence of a defect.
Defects detectable by thermography include: delaminations, disbonds, voids, inclusions and
impact damage. The main defects identified for thermography in ISO 14692 are: scale
build-up, major deviations in wall thickness, and areas in the joint lacking adhesive.
ISO 14692 identifies thermography as an NDE method under development that may be
applied for inspection of GRP if reliable calibration standards are established and agreed in
advance of the inspection. It is assumed that this refers to transient thermography. To see
defects at a reasonable resolution it is necessary to provide a pulse of heat into the
component and use a high quality thermal imaging camera. This is the basis of transient
thermography, the most common thermography method applied to composite materials,
also known as pulse-video thermography or active thermography. Fully integrated systems
including flash tube, thermal camera and data processing hardware are now routinely
available. Sensitivity can be markedly improved by using synthetic processing methods.
There are a number of ways to provide heat including, flash lamps, induction heaters (not
for GRP) and hot-air guns. Simple monitoring of temperature with a thermal camera is
known as passive thermography. This is only really suitable for identifying global
differences, acting as a form of enhanced visual inspection. Passive thermography is
sometimes used to detect impact damage on GRP using natural thermal transients. Passive
thermography can in some circumstances reveal damage in GRP vessels and pipework,
particularly if the process fluids are at a higher temperature. A procedure for thermography
was included in the 1999 Version of NORSOK M-622, but guidance in ISO 14692 Pt. 4. is
limited. There is no current Oil industry standard on thermography.
If no suitable in-house procedure is available it is recommended either that the procedure in
the 1999 Version of NORSOK M-622 , the advice or procedures from the equipment
supplier, or the active thermography procedure developed by ESR technology in the DTI
CPD4D programme is used.

67

HOIS GP1 Issue 2


Guidance on application of the technique in the following procedures may also be
considered:

ASTM E2832 Standard Practice for Active Thermography of Composite Panels in


Aerospace Applications.

ASTM E2582 Standard Practice for Infrared Flash Thermography of Composite


Panels and Repair Patches Used in Aerospace Applications.

For application of thermography on Oil industry GRP components and joints the following
additional points are worth considerations:

There is very little practical experience of application of active thermography


offshore, more on refinery plant and pipelines.

Where thermography is being used for the purpose of defect detection in


composites, it is recommended that transient thermography is used.

If possible a modern integrated thermography system with data processing software


is used which allows images to be captured at a range of times (or depths) in the
component.

A high speed, high sensitivity good resolution thermal imaging camera should be
used.

The camera should be capable of uninterrupted monitoring of the sample surface for
the entire duration of the acquisition. Cameras with automatic internal shuttering
mechanisms should allow the shuttering to be disabled during the data acquisition
period.

The camera should provide real-time digital output of the acquired signal (typically 8
bits at 60Hz). The camera output signal should be approximately linear over the
(post-flash) temperature range of the sample. The camera wavelength should be in
either the 2-5 micron range or the 8-14 micron range, selected such that the test
material is not IR translucent in the spectral range of the camera. A medium wave 25 micron wavelength is typical for GRP.

The optics and focal plane should be sufficient so that the projection of nine
contiguous pixels onto the sample plane is less than or equal to the minimum flaw
area that is to be detected.

If a modern thermal imaging camera is used it is recommended that video


information is captured as defects are most clearly evident when viewing the
transition in heat. A series of static images may also be acceptable.

For Oil industry applications flash lamp or air heater (hairdryer) are the most
practical heat sources. For GRP coatings on steel components or repairs an
induction heater could also be considered.

A suitable calibration sample should be available representative of the component,


material and defect type being examined.

It is beneficial if the calibration sample contains defects of a range of sizes and


depths so the sensitivity and detectability of defects may be established. For
adhesive joints a suitable calibration sample containing lack of adhesive or
simulated disbonds (double PTFE) should be available.

Delaminations, inclusions, voids and loss of wall thickness can be simulated in


calibration samples by flat bottomed holes or PTFE film inserts.

68

HOIS GP1 Issue 2

As a general rule the minimum size of delamination or disbond detectable is


proportional to the depth below the inspection surface.

Care should be taken to avoid reflections on pipework or curved components that


may confuse the images.

The environmental conditions should be noted. Stable conditions as free of wind or


temperature variation as is practically feasible are preferred.

14.8

Shearography

Laser shearography is not included as an NDE method in the current version of ISO 14692
or NORSOK but accepted as a common inspection method for composites in other
industries. The method measures and images the surface strain field at high resolution
which is altered in the presence of internal and near surface defects. The method is the
preferred method for inspection for delaminations, disbonding and core damage of GRP
sandwich structures in lifeboats and marine hulls. Commercial integrated systems are
available.
The basis of all shearography techniques is that the video system captures a sheared
image of the laser speckle pattern formed of the surface at one stress state and stores this
as a reference image. While the stress state is modified, new images of the surface are
compared against the stored reference by image subtraction correlation; only the difference
is presented on the screen in real time. This process is carried out, and the screen updated
at the rate of 30 times a second until the predetermined second stress state is reached.
There is very little experience of use of shearography in Oil industry applications although it
is routinely used in the Marine industry and on GRP lifeboats. The method has been trialled
on offshore adhesive joints and overwrap repairs. Vacuum loading systems used on boat
hulls are robust. There is some concern about more delicate laser systems being
sufficiently robust to use offshore. The technique is fast and global covering several square
metres in a few hours but relatively costly.
In the absence of an offshore specific standard, it is recommended that in-house
procedures, advice or procedures from the equipment suppliers, or the guidance in the
following procedures and practice documents are followed:

ASTM WK 12737 Standard Practice for Shearography of Polymer Matrix


Composites, Sandwich Core Materials, and Filament Wound Pressure Vessels
Used in Aerospace Applications

Laser shearography procedure developed by NNDTC on the


Programme (www.mms15.com)

DTI CPD4D

The following additional points should be noted in relation to oil industry application:

The technique relies on the images being captured in two different stress states.

A suitable calibration sample should be used in set-up representative of the


component, material and relevant defect types.

A commercial shearography system should be used where the shear is applied


predominately out-of-plane; it is therefore sensitive to the weakest direction of the
bonded laminate. There are advantages if the system can also apply in-plane shear
variations.

69

HOIS GP1 Issue 2

For large diameter pipework, tanks or vessels, use of a standard vacuum loading
shearography system (vacuum hood) is recommended as used in global inspection
of lifeboat hulls.

For smaller diameter pipework the stress difference required may be achieved by
change in internal pressure or heating with an air heater (or hairdryer).

Shearography is a highly specialised technique and should be carried out by NDE


technicians fully familiar with the method, analysis of results and its application on
GRP components.

Suitable and specific image processing software is required for calculation and
display of the shearography images, phase stepping comparison etc.

Phase processing of the data can give clearer images of defects than standard
fringe pattern analysis.

The fringes in the shearography data can be used to give an indication of the
relative bond conditions (lack of, or increased adhesion).

Modern laser shearography equipment comprises integrated systems incorporating


laser, image receiver and data processing. Other systems such as the Strain
Mapper system from Laser Optical Engineering Limited and the LTI digital
shearography system direct the laser beam remotely at the equipment, but also
include image receiving, electronics and data processing equipment. Integrated
systems with vacuum hoods are simple and fast to apply for inspection of large
areas such as marine hulls or airframes and require no scanning frame or coupling.
It is possible to quickly inspect large areas globally using a direct imaging system or
sequentially using a vacuum hood.

Figure 20 LOE Strain Mapper

70

HOIS GP1 Issue 2

Figure 21 Interference fringes were densely spaced near known bondline defects

14.9

Acoustic emission

Acoustic emission is a well established NDE monitoring method for composites and
guidance on application is provided in ISO 14692 Pt. 4 Annex E.6.
Standard procedures for performing acoustic emission inspection on GRP materials exist
e.g. ASTM E2191 and ASME V Article 11, and should be available from acoustic emission
equipment suppliers.
It is recommended that supplier guidance or in-house procedures where applicable are
followed. In addition the following standards should be consulted:

ASTM E1067 - 07 Standard Practice for Acoustic Emission Examination of


Fiberglass Reinforced Plastic Resin (FRP) Tanks/Vessels

ASTM E2191 - 08 Standard Practice for Examination of Gas-Filled Filament-Wound


Composite Pressure Vessels

ASME Boiler and Pressure Vessel Code, Section 5, Article 11

It can be possible to establish fingerprinting or characteristic acoustic signatures for


specific defect types. Use of several sensors (typically three) allows the signal location to be
estimated using triangulation. The applicability of these location and characterisation
methods to offshore grade GRP piping needs to be established. There could be issues with
anisotropy and attenuation.
ISO 14692 notes the main defects detectable by acoustic emission testing as:

inadequate structural integrity (can be caused by weaknesses in design, production,


material degradation, etc.);

71

HOIS GP1 Issue 2

wrong lay-up on laminated joints;

under designed laminates in areas with multi-axial stresses;

growth of delamination cracks;

crack growth in matrix material;

fibre fracture and pull-out;

inadequate curing, leading to excessive strains;

leakages.

Acoustic emission requires that the component be under load, up to a maximum of the
design load. Only growing or propagating defects are detected.

14.10 Acousto-Ultrasonics
Acousto-Ultrasonics (AU), or the Stress Wave Factor (SWF) technique, is a variant on
acoustic emission recently developed in the aerospace and defence industries for
inspection of thick section GRP and also applied in Oil industry applications. Commercial
equipment for AU is available but not always available for trials. An ultrasonic wave is
generated in the component and acoustic sensors used to monitor the emissions from the
component. These can be analysed to build up image maps of the component resembling
ultrasonic C-scans. Pulses of ultrasound are injected into the component and are detected
some distance away on the same side of the component.
The method seeks to characterise a component by investigating the way in which it
modifies an ultrasonic pulse that travels through it non-destructively.
Standard procedures are available from the AU supplier. The following procedure should
also be consulted:

ASTM E1495 - 02(2007) Standard Guide for Acousto Ultrasonic Assessment of


Composites, Laminates, and Bonded Joints

Commercial AU systems are capable of generating C-scan images of amplitude and Time
of Flight (TOF), as well as A-scans of different areas of the composite structure using a
high-precision computer controlled scanning bridge. This has been used in onshore and
refinery applications but has yet to be established offshore.
The method is relatively new commercially but was evaluated as far back as 1988 as a
remote method for adhesive bond inspection. The name Acousto-Ultrasonics (AU) is
derived from a combination of Acoustic-emission monitoring and Ultrasonic characterization
originally developed by NASA 15.
The following points should be noted:

AU has been used in investigations of the following: porosity content, fibre


alignment, condition of resin, impact damage, fatigue damage, thermal shock, and
adhesive bonds.

15

NASA/CR-2002-211881 Acousto-ultrasonics to assess material and structural properties, Harold E. Kautz,


Cleveland State University, October 2002

72

HOIS GP1 Issue 2

The method is well suited to thick section components and complex sandwich
structures.

As a remote, non-contact and high speed method it offers the potential to screen
large areas of pipes or vessels that would be impracticable and slow by
conventional ultrasonic methods.

Acousto-Ultrasonics uses air-coupled probes offering some simplification over


conventional ultrasonic methods.

The advantages are the speed of inspection, that it is non contact and the particular
suitability to thick section GRP components.

Acousto-Ultrasonics is an advanced technique using digital signal processing and


pattern recognition algorithms. Specialist inspectors are required.

The disadvantage is the novelty of the method and the quality and resolution of the
data, which is less good than more conventional NDE methods such as ultrasonics
or shearography.

The method is worthy of consideration as a screening method for applications of


GRP.

Acousto-Ultrasonics considers the entire ultrasonic response, in time as well as in


frequency, of the entirely isonified material.

14.11 Microwave inspection


Microwave inspection is increasingly considered for inspection of GRP composite and non
metallic components. The method does not have the coupling restrictions, sensitivity to
surface condition or attenuation in GRP found with ultrasonics. For these reasons the
method appears well suited to the thicker section and variable quality GRP found in
offshore GRP pipework and fittings. Oil industry trials and application to date has been
almost exclusively on onshore applications.
The method works by scanning the material under inspection with microwave energy of an
essentially constant frequency. This energy is reflected from each interface of differing
dielectric constants within the specimen allowing detection of defects or other material
discontinuities. The reflected energy creates a resulting signal measured in volts, which is
sampled at discreet locations across the sample to create a C-scan type image. A
frequency of 10-50GHz is typically used with a 7.5 to 30mm wavelength. Different dielectric
constants reflect the microwave energy. The signal voltage is sampled across the test piece
to create an image. Specific features and limitations of the method include reflection at
metals and absorption in water (frequency dependent). Microwave signals easily penetrate
non-conducting materials and may therefore be employed for defect detection within these
materials. Defects potentially detectable in composites using microwaves include the
following:
Delaminations;
Disbonds;
Foreign Material Inclusions;
Voids;
Changes in thickness;
Moisture or liquid contamination;
Mechanical damage;
Physical changes.

73

HOIS GP1 Issue 2


There are no current industry standards or procedures for microwave inspection. NASA has
used this method for inspection of foam insulation on flight hardware. It is recommended
that advice and procedures from the equipment manufacturer or inspection service provider
are used or alternatively in-house company procedures where available.
The following points should be noted in relation to application of microwaves:

It is recommended that inspection is undertaken using a commercial near-field


microwave inspection system (such as those produced by Evisive).

The microwave power associated with near-field systems is low (in the milliwatt
range) and therefore poses no Health and Safety concerns.

For laboratory near field examinations simpler equipment comprising: source,


waveguide, diode detector may be considered.

A suitable scanning system with encoders is required to scan the probe.

Sufficient access is required for the probe and scanning system. The data
acquisition system (PC-based) may be sited remotely.

A suitable known calibration sample is required which should be similar in material,


geometry and surface condition to the component being inspected and contain
known and representative defects.

Inspectors should be familiar with microwave inspection and interpretation of the


data acquired.

Interpretation of the data and images arising is still quite subjective and there is
limited experience in interpreting microwave data for GRP pipework and joints.

The probe may be used in contact or non-contact.

No couplant is required.

For NDE purposes the two main operating parameters to be considered are
operating frequency and stand-off distance (the distance between the inspection
surface and the waveguide aperture).

The scanning system should be set up on the pipework or component with the probe
in contact or at a fixed stand-off (few mm) from the component surface. The region
to be scanned should be defined in the data acquisition software relative to a known
position on the specimen. The probe should be scanned along and circumferentially
on the specimen to cover the area of interest. A 3D data set through the sample is
generated.

Inspection may be undertaken using system default settings. It is preferred that


settings are optimised on a known calibration sample to improve the resolution of
defect indications.

Inspection should normally be undertaken from one side only or from both sides
looking for reflections. Through-transmission inspection may also be undertaken.

Suitable open-ended waveguide probes are generally available. Near-field the size
of the source is significant.

Signals may be detected using a simple, inexpensive diode detector at a strategic


location within the waveguide source.

Indications that are detected may be interpreted based on a comparison to known


calibration standards.

74

HOIS GP1 Issue 2

Appropriate software is required for analysis and presentation of the data.

Interpretation of microwave data should be undertaken by the NDE service provider


or engineers familiar with interpretation of microwave data. This is best done by
comparison with data from known calibration samples.

Microwaves can detect irregularities which because of poor surface condition,


thickness or quality of the GRP are not easily detectable by other NDE techniques.

Inspection speed is comparable with Ultrasonic methods.

Near-field microwave methods that transmit the wave into a dielectric structure
located in the near-field of a sensor offer significant advantages: inspection systems
are compact in size and can be battery operated; spatial resolution is primarily
influenced by the dimensions of the probe rather than the operating wavelength;
spatial resolution is better compared to that achieved with plane or spherical waves
(far-field, radar); contact as well as non-contact measurements are possible;
mapping the magnitude or phase of the reflected wave can be used to create two- or
three-dimensional images of the structure under investigation; unwanted reflections
from changes in geometry associated with far-field methods are minimised.

Figure 22 Evisive microwave probe mounted on Olympus HSP XY pipe scanner

Figure 23 Microwave data example for adhesive joint section

75

HOIS GP1 Issue 2

14.12 Differential Scanning Calorimetry (DSC) and hardness tests (e.g.


Barcol or Shore)
These are not NDT tests but are standard methods of assessing cure condition. Differential
scanning calorimetry (DSC) and hardness testing are established methods for establishing
cure condition in composite materials and adhesive joints. Guidance on the use and
application of these methods is included in ISO 14692 Pt 4 Annex E7.
The main defects detectable by DSC and Barcol or Shore hardness testing are:

improperly mixed or cured adhesive in bonded joints (DSC);


improperly mixed or cured laminate in laminates or laminated joints (Hardness).

Barcol or Shore hardness is an indirect method of measuring the degree of cure in vinyl
ester and polyester laminates and laminated joints.
DSC is a quantitative, accurate and relatively fast semi-non-destructive technique which is
based on the measurements of thermal changes related to phase transitions and chemical
reactions, such as the curing of thermoset resins. Small samples can be cut from the
external adhesive seams of the joints for measuring the glass transition temperature, Tg, by
DSC analysis.
It is recommended that the two methods are applied as identified in ISO 14692 Pt 4 and no
additional guidance is offered.

15.0

Monitoring methods

The use of structural health monitoring (SHM) methods such as acoustic emission,
conventional strain gauging or optical fibre technology on composite components is well
established.
Guidance on monitoring methods for composite joints has recently been produced in the UK
TSB sponsored ACLAIM project 16. ACLAIM formed part of the Advanced Composite Life
Assessment and Integrity Management (ACLAIM) Technology Programme project, funded
by the Technology Strategy Board (TSB) of the UK Department for Business, Enterprise
and Regulatory Reform (BERR).This is recommended as the main reference if application
of monitoring methods is considered.
Relevant outputs from the SiMoNet network 17 should also be considered well as the
relevant standards noted earlier for Acoustic Emission. SiMoNet is focussed on industrial
application of monitoring and sensor technology.
Monitoring methods for GRP joints are also being considered in the current TSB funded
Imajine project, the successor to ACLAIM. This includes the use of embedded optical fibres
within the adhesive in bonded joints to monitor service degradation and properties. Similar
work on optical fibres is being undertaken by Smart Fibres Limited and at Surrey University.
By use of specially graded fibres it is possible to measure parameters including

16

ACLAIM Current practice guide: A Guide to Current Structural Health Monitoring (SHM)
Practice for Advanced Composite Applications, S Frost et al, ISBN: 978-0-946754-52-6, ESR Technology,
National Physical Laboratory (NPL), 2008.
17
SiMoNet Structural Integrity Monitoriing Network www.simonet.org.uk

76

HOIS GP1 Issue 2


temperature, stress and strain over a 100mm length within the joint and monitor the
degradation and change in properties in service.
It is recommended that the use of such technology be considered in new installations. The
earlier guidance on acoustic emission should be considered if use of AE is considered.

16.0

Developing NDE methods

There is a number of developing NDE methods that show promise for application offshore
but are not currently included in industry or composite standards or guidance. These
include:

Rapid scanning methods for ultrasonic C-scan and B-scan inspection of pipes and
vessels to detect delaminations, disbonds and wall thickness loss ( e.g. wheel
probes or other phased array methods);

Increased use of linear scanning (B-scan) methods including TOFD for inspection of
composite pipes and vessels in place of point measurements (A-scan or thickness).
This significantly improves the reliability of detection of erosion, wall thickness loss,
liner degradation or environmental ingress;

Computed Radiography (CR) trials on composites using isotope sources relevant to


ISI offshore;

Application of the microwave method on thicker section (>10mm) components;

Commercial acousto-ultrasonics systems such as T-SCOUT for inspection of thick


section composites for delaminations and disbonds;

For matrix cracking further development of the axial ultrasonic velocity measurement
is recommended as a function of matrix cracking;

Trial of shockwave methods, such as Remote Acoustic Impact Doppler (RAID),


being developed in aerospace for kissing bond detection and assessment of
condition of adhesive bonds;

Use of laser shearography for fast detection of delaminations and de-bonds;

Utilisation of new integrated thermography systems such as Thermoscope in place


of conventional ultrasonic C-scanning;

Development and application of simple mechanical tap-testing systems for global


screening of composite components;

For delaminations and lack of adhesive in adhesive bonds, recommended


inspection techniques worthy of further investigation include mechanical tap testing,
microwaves, digital radiography, or acousto-ultrasonics.

Laser bond inspection is a relatively new technology for non-destructive evaluation


of bonds in a broad range of materials. It is designed to complement existing bond
inspection techniques such as UT and CT scanning. It is currently capable of
detecting sub-standard bonds in structures up to 25 mm thick and possibly thicker in
the near future. It works by analysing multiple locations across a substrate and a
high energy pulsed laser beam generates a shock wave which subjects the bond to
a controlled dynamic stress. Bonds meeting the design strength specification are
unaffected whereas sub-standard bonds are fractured enabling subsequent
detection.

77

HOIS GP1 Issue 2


POD simulation models that are available from ESR Technology could be valuable to
optimise the inspection reliability and to improve more quantitative life assessment.
More information on these and other developmental methods for NDE of composites can be
found in the HOIS NDE of Composites review12 and also in the MMS15 interactive
knowledge base (IKB) on composites www.mms15.com .

17.0

Evaluation and assessment

The evaluation and assessment of damage in composites is outside the scope of this
document. Limited information and guidance is provided below.
For GRP pipes and fittings it is not possible to develop a single all encompassing
assessment procedure. For each identified defect or damage mechanism within a
component a separate assessment procedure is required.
As an initial assessment, acceptance criteria for common defect types and locations are
given in the Tables in ISO 14692 Parts 2 and 4 reproduced in Appendix C and included
earlier in this document. This advice primarily relates to manufacture and qualification but
is worth consideration where defects are encountered.
Defect assessment for composites is normally experienced based. Information is fed back
to the original designer and a decision is made on whether to repair, replace or leave as is.
The questions an integrity assessment procedure should answer are:

What is the relevant damage mechanism?


How can these damage mechanisms be inspected?
How to interpret the measured damage in terms of fitness for purpose and, or future
life?

The HSE Good Practice Guide4 on GRP pipework defines two priority levels in terms of
criticality. For priority level 1 (P1Urgent) a risk assessment shall be performed as a matter
of urgency and suitable mitigation strategies implemented. For priority level 2 (P2- Caution)
items, a risk assessment should be performed as soon as reasonably practicable to identify
a suitable course of action.

For damage mitigation pipes should not used as a step up, not be exposed to
deleterious foreign fluids and not be exposed to heat sources. Earthing cables (if
required) shall be present and in good condition.

The general appearance of pipework should be uniform with smooth surfaces and
none of the following or within prescriptive limits given in associated standard/
manufacturers guidance: cracks (including adhesive fillets between repair laminate
and substrate), delamination, wear, chips/gouges, resin loss, exposed fibres/cut
edges, leaks/weepage, dry spots, variation in resin colour, contamination/foreign
matter, heat damage, softening/ bulging/ discolouration/ burn, blisters/ pin holes/
pores, chemical attack, erosion .

The following damage types are considered to be unsafe (P1) for pipes and joints if
they extend deeper than the surface resin rich layer (gel coat) and risk assessment
shall be performed as a matter of urgency and suitable mitigation strategies
implemented: weepage, leak, fracture or cracking, delamination, cracking in a
flange, exposed fibres post-impact, heat damage- softening/ bulging/ discolouration/

78

HOIS GP1 Issue 2


burn, dry fibres, exposed fibres/ cut edges, gouge, delamination, blisters, pin holes,
pores, contamination/ foreign matter, chemical attack, erosion (internal);

The following items are also classified as unsafe (P1-Urgent): supports which
provide inadequate support or are missing, extensively damaged or corroded; or
joints which leak, are misaligned or deformed or exhibit the damage types identified
above extending below the resin rich layer.

Photographs are included in the good practice guide of typical defects.

The following damage types are defined as priority 2 (P2- Caution) for pipe and
joints provided they do not extend deeper than the surface resin rich layer: loss of
resin rich surface layer; blisters/pin holes/pores/chips/wear; heat damage discolouration, burn, foreign matter/contamination; and minor damage/corrosion of
the supports, provided they remain still structurally sound.

Techniques for integrity assessment of metallic materials are well established such as API
579. No such equivalent yet exists for composite materials. For composite materials
guidance exists in standards such as ISO 14692 but assessment methods are still under
development. Generic assessment procedures consist of the following:

Definition of the defect or damage mechanism;


Inspection procedure;
Interpretation of the inspection data;
Assessment as to the criticality of the defect or damage.

Guidance on assessment of ageing in composites in offshore applications and life


prediction or extension can be found in a recent reference book 18. Treatment of matrix
cracking in ASTM standards is based on a regression curve. This assumes a time
dependent degradation in properties due to stressing and the consequent increase in
density of matrix cracking. Further information on ageing mechanisms in composites and
damage types is included in Appendix A.
Destructive testing or additional NDE will normally be required to characterise the damage
and assess the repairs that may be necessary. This needs to be considered against the
alternative of replacement. Composites offer an advantage that they are easily repairable
and repair methods are encompassed in ISO 14692.
The DTI funded MMS13 programme 19 completed in 2004 developed a staged approach to
defect assessment similar to that used on steel piping components. This had three levels of
assessment in increasing detail. This varied from a simple initial assessment (Level 1) to
detailed finite element (FE) analysis (Level 3).
ESR has developed more quantitative approach to piping integrity assessment based on
characterisation of the extent of matrix cracking from NDT using ultrasonic velocity
measurements. Guidance on integrity management of composite joints can be found in the
outputs from the ACLAIM programme. An improved integrity assessment approach is being
developed for composite joints and composite overwrap repairs in the TSB funded Imajine
Programme.

18

Ageing of composites in oil and gas applications, Ed. Rod Martin, Woodhead publishing, ISBN 978-1-84569352-7, 2008
19
Measurement Good Practice Guide No. 78 Assessment and Criticality of Defects and Damage in Material
Systems;,NPL/ ESR Technology; DTI MMS13 Programme 2002-2005; National Physical Laboratory Report
ISSN 1368-6550, June 2005.

79

HOIS GP1 Issue 2

18.0

Failure prevention

To minimise the occurrence of failures of GRP pipe it is good practice to:

Limit the operating temperature so that the effects of chemical attack are minimised.
If possible limit the concentration of aggressive fluids in the flow;

Limit axial and pressure loads to no greater than the long term allowable loads;

Ensure that pipe joints are installed correctly; by trained installers and that the joints
are not over-loaded.

To minimise the occurrence of failures of composite repairs it is good practice to:

Ensure repair is correctly applied by trained installers;

Limit the operating temperature so that the effects of chemical attack are minimised;

If possible limit the concentration of aggressive fluids in the flow.

In summary composite materials are used in many safety critical applications, the most
obvious examples are in aerospace structures (e.g. Airbus 350 and Boeing 787
Dreamliner).
Large structures pose particular difficulties for inspection. Examples include oil & gas (FRP
pipes and composite repairs) and Civil Infrastructure applications including new build and
bridge strengthening. Inspection tools are now available but the nature of composites still
present unique challenges compared to metals. Recent developments have included large
area, non contact inspection techniques such as microwaves, shearography and
thermography for use in inspection of large wind turbine blades used in the growing
offshore wind energy sector. Potential strategies include fast screening, global methods,
monitoring or application of risk-based inspection methods depending on how much is
known on type and location of damage and integrity requirements. Ultrasonic inspection
using phased arrays mounted inside roller probes are being used effectively for in service
inspection particularly in marine and aircraft inspection.

19.0

Acknowledgements

The inputs from several HOIS members are gratefully acknowledged, especially those who
conducted inspection trials at the ESR Technology NICE facility. The continued support of
the HOIS Project Champion Francisco Marques of Petrobras and his colleagues in Rio de
Janeiro are also acknowledged. HOIS is an established Joint Industry Programme aimed at
quantifying and improving the performance of NDT technology in the oil and gas industry.

80

HOIS GP1 Issue 2

Appendices
APPENDIX A

GRP CODES AND STANDARDS .............................. A-82

APPENDIX B

INSPECTION GUIDANCE FROM ISO 14692 ............ B-85

APPENDIX C

DAMAGE MECHANISMS IN COMPOSITES ............. C-97

APPENDIX D

EXAMPLES OF IN-SERVICE DEGRADATION OF


COMPOSITE COMPONENTS .................................. D-110

81

HOIS GP1 Issue 2

Appendix A

GRP Codes and Standards

In addition to the NDE related codes and standards noted in the practice document, there
are a diversity of codes and standards relevant to design, testing and qualification of GRP
components. These include the following:

A.1 Integrity standards

API 579 Fitness for Service


ASME RTP-1 and B&P Vessel Code X
Erosive wear in piping systems DNV RP OS501

A.2 Prior GRP Standards (Discontinued)

NORSOK M-622 NDE of GRP piping systems, tanks and vessels; the
Norwegian Oil industry Association (OLF); February 1999

NORSOK Standard M-621 GRP Piping Systems; the Norwegian Oil


industry Association (OLF) 1999

UKOOA Guidelines OPS04 1994 Fibre Reinforced Plastics (FRP) for use
Offshore

Specification and recommended practice for the use of GRP piping


offshore, UKOOA, first edition, March 1994

NORSOK Standard M-630 Material Data Sheets for Piping

A.3 General GRP standards

Shell DEP 30.10.02.13


ASME RTP-1, Reinforced Thermoset Plastic Corrosion Resistant
Equipment, American Society of Mechanical Engineers
ISO TS 24817 (draft) Composite repairs
prEN 13121 GRP vessels
BS EN 13280 GRP water tanks
prEN 14122 Access engineering
ISO 11119 Wrapped gas cylinders
FRP-ICE Design Guideline Rehabilitation of metallic structures using FRP
DNV OSC 501 Offshore Standard for composite components January 2003

82

HOIS GP1 Issue 2

BS 7159:1989 British Standard - Code of practice for design and


construction of glass reinforced plastics (GRP) piping systems for individual
plants or sites
ASME X 2007 ASME Boiler And Pressure Vessel Code, Part X, FiberReinforced Plastic Pressure Vessels
ASTM D1599-99e1, Standard Test Method for Resistance to Short-Time
Hydraulic Failure Pressure of Plastic Pipe, Tubing, and Fittings
API Specification 12P Reinforced Plastic Tanks 2nd edition, January, 1995
API Specification 15HR Specification for high pressure fibreglass line pipe,
Third Edition August 2001, Addendum Nov 2004
API 15TL4 Recommended practice for care and use of fiberglass tubulars
2nd Edition, March 1999
API 15LR Specification For Low Pressure Fiberglass Line Pipe and Fittings
7th Edition, August 2001 Effective Date: February 1,2002
ASTM D 2563-70, "Standard Practice for Classifying Visual Defects in
Glass-Reinforced Plastic Laminate Parts", Reapproved 1987.
ASME RTP-1-1995 Edition: "Reinforced Thermoset Plastic Corrosion
Resistant Equipment
DNV-RP-F202 Recommended Practice Composite Risers; Det Norske
Veritas May 2003
DNV-OS-C501 Det Norske Veritas Offshore Standard, GRP pipes tanks
and vessels January 2003
BS 4994 Design and construction of vessels and tanks in reinforced
plastics
Fibre-reinforced plastic pressure vessels ASME Section X
ASTM D1599-99e1, Standard Test Method for Resistance to Short-Time
Hydraulic Failure Pressure of Plastic Pipe, Tubing, and Fittings
DIN 16965-2, Wound glass fibre reinforced polyester resin (UP-GF); pipes,
Type B pipes, dimensions

DIN 16966-1, Glass fibre reinforced polyester resin (UP-GF) pipe fittings
and joint assemblies; fittings; general quality requirements and testing

DIN 16966-2, Glass fibre reinforced polyester resin (UP-GF) pipe fittings
and joints; Elbows, Dimensions

DIN 16966-4, Glass fibre reinforced polyester resin (UP-GF) pipe fittings
and joints; Tees, Nozzles, Dimensions

DIN 16966-5, Glass fibre reinforced polyester resin (UP-GF) pipe fittings
and joints; Reducers, Dimensions

DIN 16966-6, Glass fibre reinforced polyester resin (UP-GF) pipe fittings
and joint assemblies; collars, flanges, joint rings, dimensions

DIN 16966-7, Pipe joints and their elements of glass fibre reinforced
polyester resins Part 7: Bushings, flanges, flanged and butt joints; general
quality requirements and test methods

DIN 16966-8, Glass fibre reinforced polyester resin (UP-GF) pipe fittings
and joints; Laminated joints; Dimensions

NTS-GRP-FJS/01, Certification of personnel for installation of composite


pipes

83

HOIS GP1 Issue 2

NTS-GRP-Insp/01, Certification of inspectors for installation of composite


pipes

KRV A 984/82-2, Kunststoffrohrverband (KRV); GFK-Industrierohre.

A.4 HSE Guidance


Relatively few research studies and guidance documents have been produced by HSE in
relation to composites and GRE, particularly in regard to ageing. These include:

HSE/ HSL GRP Pipe Fact sheet, Draft: Final Revision1, March 2009.

HSE/ HSL Composite Repair Fact sheet, Draft: Final, March 2009.

HSE RR131 Long-term testing of composite through-thickness properties, 2004

HSE RR115, Erosion in elbows in hydrocarbon production systems: Review


document, 2003

HSE RR285 Protection of piping systems subject to fires and explosions

HSE RR039 Cost Effective use of composites offshore; Part B: Summary of the
Joint industry - industry programme on the cost effective use of fibre reinforced
composites offshore. UK Health & safety Executive HSE; HSE Research Report,
2003 http://www.hse.gov.uk/RESEARCH/rrhtm/rr039.htm

HSE-AL-FWI
Specification for full-wrapped Composite aluminium alloy gas
cylinders, Issue 1 - January 1991

HSE OTO01038 Temporary/permanent pipe repair Guidelines; HSE Offshore


Technology Report 2001/038

HSE RR198, TEMPSC Structural Design Basis Determination; Part 1 Input Data
Capture and Review, research report 198, 2004

Feasibility study to compare steel and adhesive/composite-based emergency repair


methods for damaged hulls, HSE Research Report 293,2004

HSE RR059 An assessment of skin sensitisation by the use of epoxy resin in the
construction industry, HSE research report 198, 2003

A.5 Other references

The European Pressure Equipment Directive (PED)

84

HOIS GP1 Issue 2

Appendix B

Inspection guidance from ISO 14692

Guidance tables are provided in ISO 14692 for visual inspection, inspection of process
pipework as well as recommendations on NDE techniques for specific defect types. These
are reproduced here for completeness.

B.1 ISO14692 Part 2

85

HOIS GP1 Issue 2

B.2 ISO 14692 Part 3

86

HOIS GP1 Issue 2

87

HOIS GP1 Issue 2

B.3 ISO 14692 Part 4


Table 4 Inspection guidance for fabrication, handling and installation defects in ISO14692
Part 4 (Table 4)

88

HOIS GP1 Issue 2


Table 5 Inspection guidance for operational defects in ISO14692 Part 4 (Table 5)

89

HOIS GP1 Issue 2

Table 6 Defect types, acceptance criteria and recommended corrective action (Table A-1)

90

HOIS GP1 Issue 2

91

HOIS GP1 Issue 2

92

HOIS GP1 Issue 2

93

HOIS GP1 Issue 2

94

HOIS GP1 Issue 2

95

HOIS GP1 Issue 2

Table 7 Summary of recommendations for NDE method and defect type in ISO 14692 Part
4 Annex E. (Compiled by ESR from Annex E of ISO 14692 Part 4.)
NDE Method

Details

ISO 14692
Pt. 4
Annex E.
Section

Visual inspection

Deformations and dimensional deviations


Surface cracks and microcracks
Near-surface delaminations, inclusions and air
entrapments
Impact damage
Blisters
Internal excess of adhesive (internal inspection)
Corrosion and erosion (internal inspection)
Adhesive-bonded joints lacking adhesive or improperly
prepared and assembled
Inadequately cured adhesive in the bonded joints
Manufacturing defects in GRP materials
Leaking joints
Areas in bonded pipe joints lacking adhesive
Delaminations, voids
Deviations in wall thickness (20 %)
Incorrect wall thickness (up to 20 % deviation), or fit
between male and female adherends
Some voids, delaminations and lack of adhesive (up to 5
% deviation)
Axial misalignment
Excess adhesive on inner wall of pipe at joint
Scale build-up on inside of pipe
Incorrect insertion of pipes in adhesive sockets
Inadequate structural integrity (can be caused by
weaknesses in design, production, material,
degradation, etc.)
Wrong lay-up on laminated joints
Underdesigned laminates in areas with multiaxial
stresses
Growth of delamination cracks,
Crack growth in matrix material,
Fibre fracture and pull-out,
Inadequate curing, leading to excessive strains,
Leakages
Improperly mixed or cured adhesive in bonded joints
(DSC),

E.2
E.2
E.2

Pressure testing

Ultrasonic testing

Radiographic testing

Acoustic emission
testing

Differential scanning
calorimetry (DSC) and
Barcol hardness
testing

Thermographic testing

E.2
E.2
E.2
E.2
E.3
E.3
E.3
E.3
E.4
E.4
E.4
E.5
E.5
E.5
E.5
E.5
E.5
E.6

E.6
E.6
E.6
E.6
E.6
E.6
E.6
E.7

Improperly mixed or cured laminate in laminates or


laminated joints (Barcol).

E.7

Scale build-up
Major deviations in wall thickness,
Areas in the joint lacking adhesive.

E.8
E.8
E.8

96

HOIS GP1 Issue 2

Appendix C

Damage mechanisms in composites

C.1 Issues in service


Composites do not corrode per se but can be subject to a number of degradation
mechanisms in-service including physical ageing, mechanical ageing and chemical ageing.
The consequence of these can be a reduction of 20 - 40% or greater in the strength
characteristics of the polymer during the lifetime of the component and introduction of
damage including matrix cracking and delaminations. This is handled in design codes such
as ISO 14692 by use of regression curves based on short term and longer term (typically
1000h) tests to determine the qualification pressure for the component and the allowed
operating pressure over the design life.
There is concern about whether such methods of life assessment are sufficiently robust,
given the increasing diversity of applications in which composites are applied. In contrast to
steel vessels or pipework where non-destructive methods such as ultrasonics,
electromagnetics and radiography are widely applied, very little inspection other than visual
inspection or pressure testing is currently undertaken on composite components in the
chemical, process and petrochemical industries.
There are limitations in the testing methods used to estimate the regression curve or
degradation that may occur with ageing in service. Most studies are in water rather than
organic solvents or the other fluids that are seen in service. Immersion testing rather than
single-sided exposure mechanisms may cause mass gain as well as loss; so single-point
data is of limited use in prediction of longer term degradation. Service components suffer
environmental degradation from the surfaces; hence the degradation seen in immersion
tests may be worse than seen in practice.
Most ageing studies accelerate ageing by testing for a shorter time (~1000h) at a more
elevated temperature. Small temperature increases above the service temperature but
below the resin's glass transition temperature can offer useful indications of long term
behavior. However, if the mechanisms encountered over the longer term differ to those in
the accelerated tests the degradation curves and predictions of remnant life obtained may
be unrepresentative.
A diversity of environments can be encountered in the chemical and process industries.
These can cause damage to both matrix and the fibres. It is important that the resin and
fibre types are correctly selected for the application to maximize the resistance in service. In
Oil industry applications a corrosion resistant layer (or veil) containing more resistant fibres
and gelcoat is commonly applied to the surface. Similar practice may be used in chemical
applications. Such layers are effective at preventing environmental damage but are
relatively thin (~200um). It is important to confirm on visual inspections that excessive
grazing of the gel coat has not occurred and that damage has not occurred to these
protective layers
Areas of bend, variations in thickness, support or change in geometry are particularly
susceptible to damage or degradation in composite systems. These may encounter local

97

HOIS GP1 Issue 2


stress concentrations and care is needed in design to ensure these can adequately support
the operating pressures of the piping or vessel and that the allowance made in regression
curves for ageing is sufficient.
There are particular issues for lined or painted GRE vessels or pipework. If a lining is used
then a compromise may be made on the resin and fibres used in the GRE vessel. These
may not be as resistant as would be used if the GRE was exposed to the environment. It is
important in this case to monitor the lining condition since lining failure could lead to
degradation and failure of the GRE vessel in a shorter timescale than might typically occur
for an unlined vessel exposed to the same environment. Composite components are often
painted for cosmetic reasons. This may provide some additional protection to the external
environment. A consequence is that it is no longer possible to inspect the component
visually using internal illumination, a standard method. In this case detection and
monitoring of service damage may be more difficult.
In the onshore and offshore oil and gas industries a more robust approach is developing 20
based on materials characterization and non-destructive evaluation of the actual damage in
service components. This offers to improve the accuracy of life prediction and reduce the
risk of premature failure. There would be benefits in extending such good practice more
widely in the chemical and process industries.

C.2 Overview
Composite components are subject to ageing by a number of processes which can reduce
the strength and properties of the pipework. This includes physical ageing, mechanical
ageing and chemical ageing. These are normally allowed for in design through regression
curves; encompassed in relevant design standards such as ISO 14692.
Physical ageing processes include moisture ingress, swelling and plasticization common
with other polymeric components. These processes are referred to as static fatigue.
Mechanical ageing refers to the development of defects during service including matrix
cracking, delaminations and impact damage. Chemical ageing refers to environmental
processes that change the chemical structure or bonding within the component and
therefore degrade its physical properties; this includes hydrolysis, and modification of
bonding or cross linking. These ageing processes apply equally to adhesive as well as the
composite resin and result in a change in the glass transition temperature tg and properties.
In its broadest definition ageing can be defined as the reduction in performance of a
component as a function of the applied conditions. The three primary causes of ageing for
composite components in the Oil and Gas industry are through chemical species ingress,
elevated operating temperature and length of time of load application.
Service experience in the Oil and Gas sector is that damage to the composites from ingress
of the environment (internal or external) is minimal and does not significantly affect
materials properties. Progressive damage may occur under service loadings by matrix
cracking, the normal response of composite materials to loading.
For process pipework the main service risk is weepage of the process fluid eventually
leading to failure of component. The other failure mode of concern is fibre failure. Generally,
this occurs at the ultimate load-bearing capacity of the composite component and results in
20

Ageing of composites in oil and gas applications, S Frost; Ageing of Composites, Ed. Rod Martin, Chapter 14
p 375-395, Woodhead publishing, ISBN 978-1-84569-352-7, 2008

98

HOIS GP1 Issue 2


gross failure. The ageing process accelerates the failure process, be it increasing the
density of micro-cracks, affecting the glass transition temperature tg, changing the physical
properties of the matrix, or reducing the strength of fibres.
Offshore GRP components in-service are designed so that the loading is insufficient to
cause fatigue or stress corrosion cracking. Fatigue can be relevant in aged components or
in new designs due to inadequacies in the design or variations in loading beyond that
allowed for. There is experience of fatigue cracking of GRP piping in FPSOs where longer
pipe lengths have been used than normal.
Defects can occur in either the GRP material or in the mechanical and/or adhesive-bonded
joints that make up the piping system. Joint defects, including defects in prefabricated pipe
spools, are more likely to occur than defects in the GRP material, provided QA procedures
are followed during manufacture, handling and delivery. Care is needed in the preparation
and assembly of adhesive joints as well as a recognition of the degradation and ageing of
the adhesive bond that will occur in service.
Other relevant mechanisms include impact damage, disbonding, flange cracking, erosion,
cavitation and environmental ingress.

C.3 Manufacturing defects


The possible causes of manufacturing flaws, and an overview of NDE techniques suitable
for detecting these defects, are summarized in the Tables in ISO 14692 and NORSOK
M622 together with acceptance criteria.
Manufacturing processes used to produce fittings are typically more complicated and less
automated than those used to manufacture pipes. The manufacturing problems which may
occur tend, therefore, to be more prevalent in the fittings, and NDE of fittings should be
prioritized.
Manufacturing and handling defects are outside the scope of this document except insofar
as they carry over into the service component and affect service life or the properties in
service.

C.4 Failure mechanisms


The failure mechanisms in composite components in the Oil, Gas, Chemical and Process
industries are well understood. There have been numerous studies looking at the sequence
of damage events leading to failure and the relevant fracture mechanisms. 21 22 23 24 25 . As
a significant number of applications of composite components are pressure containment
and given the fact that internal polymeric liners are not commonly used, then the principal
21

Hogg, PJ and D Hull, "Micro mechanisms of Crack Growth in Composite Materials under Corrosive
Environments," Metal Science, pp. 441-449, August-September 1980.
22
Ageing of composites in oil and gas applications, S Frost; Ageing of Composites, Ed. Rod Martin, Chapter 14
p 375-395, Woodhead publishing, ISBN 978-1-84569-352-7, 2008
23
Ageing of composites in the chemical process industry,R Martin; Ageing of Composites, Ed. Rod Martin,
Chapter 17 p 375-395, Woodhead publishing, ISBN 978-1-84569-352-7, 2008
24
AG Gibson, The cost effective use of fibre reinforced composites offshore. University of Newcastle Upon
Tyne, HSE Research Report 039, 2003
25
C.M. Renaud and M.E. Greenwood, Effect of Glass Fibres and Environments on Long-Term Durability of
GFRP Composites.

99

HOIS GP1 Issue 2


failure mode of GRE pipes in oil and gas applications is a loss of containment known as
weepage; a gradual seepage of internal contents uniformly over the pipe length20,21. The
failure is caused by internal pressure (plus also axial loads).
The failure is resin dominated; and damage accumulation is by resin cracking with no fibre
breakage. As the load is increased or as time progresses, matrix cracks form in the central
plies. The number or density of these matrix cracks increases until they join together in a
convoluted arrangement, creating a fluid path through the composite. The fluid path
through the pipe wall is the combination of mostly through-thickness matrix cracks running
parallel to fibres with some delaminations. Eventually this can lead to formation of fluid
paths through the material to the outside surface.
This microstructure of the failure through the pipe wall consists of delaminations between
plies with ply through thickness matrix cracks20. Both short term and long term failures from
a mechanism perspective are similar in appearance. Microstructure of the pipe wall consists
of all plies with ply through thickness matrix cracks. Both short term and long term failures
from a mechanism perspective are similar in appearance, i.e. weepage. Microstructure of
the pipe wall at failure involves both matrix cracks and delaminations. The presence of
delaminations provides more paths for the fluid to flow implying fewer through-thickness
matrix cracks are required to complete the fluid path through the pipe wall.

Figure 24 Weepage failure of a GRP pipe

100

HOIS GP1 Issue 2

Ply

Delaminations

Figure 25 Microstructure of GRP pipe weepage failure

C.5 Matrix cracking


The main mechanical degradation in composites is matrix cracking20, see Figure 12 where
lots of transverse microcracks form in the central ply in response to strain or loading,
analogous to formation of dislocations in metallic alloys. Delaminations and throughthickness matrix cracks result from the coalescence of matrix micro-cracks and interfacial
debonding. The creation of these micro-cracks and interfacial de-bonds are accelerated due
to the combined effects of the ageing process and applied loads when compared to short
term failures through the sole application of pressure. However, the failure mode remains
unchanged.

101

HOIS GP1 Issue 2

Figure 26 Microstructure of GRP pipe showing matrix cracking due to the application of
continuous load.

C.6 Environmental damage


Service experience in the Oil and Gas sector is that damage to the composites from ingress
of the environment (internal or external) is minimal and does not significantly affect
materials properties. For oil and gas applications the chemicals that are present generally
will not cause fibre degradation.
In Oil industry applications a corrosion resistant layer (or veil) containing more resistant
fibres and gel coat is commonly applied to the surface. The resins and fibres currently used
offshore also give good resistance to ultraviolet light. Such layers are effective at preventing
environmental damage but are relatively thin (~200 um). It is important to confirm on visual
inspections that excessive crazing of the gel coat has not occurred and that damage has
not occurred to these protective layers
Chemical attack is a long term degradation process as it takes time for the chemical
species to absorb into and diffuse through the GRP. In oil and gas applications this primarily
involves reduction in matrix properties due to absorption of fluid into the surface layers. This
causes a reduction in strength and stiffness of the resin or localised swelling resulting in
weepage at lower pressures. Chemical ingress also lowers the glass transition temperature
of the resin. This is allowed for in design (e.g. ISO 14692) by an allowance in thickness over
and above that required structurally, similar to a corrosion allowance in metallic materials.

102

HOIS GP1 Issue 2


Stress cracking only occurs in glass fibres in low or high pH service fluids. For medium pH
service fluids the strain to cause stress cracking of glass fibres is about 0.7%, significantly
greater than normal design strains, of the order of 0.25%. In most Oil and Gas applications
the strains are too low and the environments insufficiently aggressive to cause SCC.

Figure 27 Examples of chemical attack. Left, Breakdown of inner liner due to chemical
attack; right, SEM electron image of glass fibres from a filament wound pressure vessel,
following sulphuric acid attack. The micrograph shows considerable fibre cracking due to
stress corrosion cracking

C.7 Cosmetic damage


After a number of years, surface degradation of GRUP (and, to a lesser extent, GRE) by
ultraviolet light can be expected and, although this will hardly affect the strength of the
material, it may be considered necessary to paint the vessel to protect personnel from
splinters, in which case the paint system should be one generally used for outdoor service.
The surface preparation should consist of cleaning with a detergent solution (e.g. Teepol),
followed if necessary by a solvent wash to remove fatty/waxy substances, and subsequent
roughening with fine sandpaper (e.g. type No. 400).

C.8 Impact damage


Impact damage results in delaminations within the wall of a GRP pipe. GRP piping is
susceptible to damage at lower levels of energy than steel. Such damage may result in
resin cracking and delamination damage, which causes weepage of fluid through the pipe
wall. If the site of the impact damage is on the parent pipe material, research has shown
that the damage is generally non-propagating and results in little loss of structural strength.
For water-service applications, e.g. firewater, it may be acceptable to delay repair until a
convenient shutdown period.
There is a far greater risk of abrupt failure if the source of leakage is a joint. This is because
there may be no direct load transfer by fibres such that the strength of the joint is reliant on
the integrity of the resin or adhesive interface.

103

HOIS GP1 Issue 2


Severe impacts can cause the pipe to weep on application of pressure local to the impact
zone. Lower energy impacts can cause the pipe to weep at lower failure pressures than
undamaged pipe. The microstructure of the pipe wall at weepage failure involves both
matrix cracks and delaminations. The presence of delaminations from impact damage
provides more paths for the fluid to flow implying fewer through-thickness matrix cracks are
required to complete the fluid path through the pipe wall leading to weepage.

Impact
damage

Weepage
failure
point

Figure 28 Weepage (local) failure of an impact damaged GRP pipe

Figure 29 Delaminations between plies associated with impact damage

C.9 Adhesive joint failure


Adhesive joints are widely used in GRP pipework and are the most common source of
failures during installation and service. Issues can arise from poor installation of glued

104

HOIS GP1 Issue 2


joints, secondary overlaps, fittings (Tees, flanges, elbows), pipe wall damage, chemical
degradation or ageing, and degradation of in field lamination joints.
For composite joints the most common failure modes are adhesive bond failures or flange
cracking both potentially leading to leakage of the process fluid. Cracking issues in flanges
and joints after installation are often due to overstressing, poor alignment or poor joint
preparation. The adhesive in bonded joints ages and degrades by similar mechanisms to
the matrix.
The most common cause of failure is either lack of adhesive or poor quality bonding of the
adhesive to the GRP joint faces. Adhesively bonded joints will fail through pull out of the
connections due to axial loads.
Butt and wrap joints fail along the interface between the GRP pipe and the over-wrapped
joint. The failure is caused by pressure acting on the wrapped joint and will be weepage of
internal fluids along the interface. This is the common failure mode for most bonded
systems the bond will fail before the composite component.
Butt and wrap joints fail along the interface between the GRP pipe and the over-wrapped
joint. The failure is caused by pressure acting on the wrapped joint and will be weepage of
internal fluids along the interface. This is the common failure mode for most bonded
systems; the bond will fail before the composite component. Adhesively bonded joints will
fail through pull out of the connections due to axial loads. The most common cause of
failure is either lack of adhesive or poor quality bonding of the adhesive to the GRP joint
faces.

Figure 30 Photo of the female face of an adhesively bonded joint showing lack of adhesive
(dark areas)

105

HOIS GP1 Issue 2

Figure 31 Example of an adhesive bond failure of GRE pipework after installation - a


possible surge pressure failure (courtesy Petrobras).

Interface

Butt and wrap joint

Pipe

Figure 32 Butt and wrap joint showing the interface, the normal location for bond failure.

106

HOIS GP1 Issue 2

C.10 Flange cracking


Cracking of GRP may occur for a number of reasons. In most cases this is due to
overstressing of the joint during operation or as a consequence of poor design. Cracking
may also occur under thermal stresses arising from the curing process.

Figure 33 Example of cracking in flanged GRP component (courtesy Petrobras)

C.11 Erosion or wall loss


As noted above, GRP pipework used offshore has a good resistance to the environment,
enhanced by the corrosion protective veil in the outer layer and localised wall loss is not
normally encountered.
Under particular service corrosions, erosion or loss of wall thickness may occur. Wall loss
can also occur from blistering of the surface layers.

C.12 Cavitation
As with metallic components, composite piping can be subject to cavitation damage.

C.13 Lined composite components


The failure mode of internally pressurised lined (thermoplastic) composite components is
burst. The GRP will crack under load but weepage will not occur as the liner prevents

107

HOIS GP1 Issue 2


weepage of the contained fluid. Ultimately the GRP component will fail when the fibres can
no longer withstand the applied load.

Figure 34

Failure of a GRP lined bottle showing burst failure (significant fibre breakages)

C.14 Composite repairs


A growing application of GRE and CFRP composites is in composite overwrap repairs on
steel pipework. For through wall defects the composite repair will fail along the interface.
The failure mode is weepage of internal fluid caused by internal pressure. The failure is
usually along the steel/ composite interface and not failure of the composite repair material.
Relevant defect types here include delaminations (interfacial between composite and
substrate) and corrosion or pitting of underlying metal component. Composite repairs are
not specifically included within the scope of this document. Detailed guidance can be found
in ISO/TS 24817 produced by the AEA/ESR composite repair workgroup.

108

HOIS GP1 Issue 2

30 mm
diameter
through wall
defect
located at top
of bend

Failure location at the edge of the repair


weepage of internal fluid

Figure 35 Normal failure location of a composite overwrap repair

109

HOIS GP1 Issue 2

Appendix D
Examples of in-service degradation of
composite components

Figure 36 GRE Fire water system pipe damaged in service (through wall defect).
OD 60mm, WT 4mm Length 360mm

Figure 37 GRP oily waste pipe, 5 years service, weeping (from impact damage).
OD 159mm WT 5.5mm Length 975mm

110

HOIS GP1 Issue 2

Figure 38 Reverse osmosis RTR spools which exhibited pipe weepage during hydrotest.
1.5 and 4 HD flanges ANSI B16.5 Cl-150

Figure 39 GRV piping, one year in-service, SO2/ H2SO4 acid, wept from a manufacturing
defect. OD 65mm WT 5.6mm Length 385mm

111

HOIS GP1 Issue 2

Você também pode gostar