Prerequisites
Before revaluating at actual prices, you should do the following:
1.
SAP recommends you to set the period lock for actual activity allocation
(RKL).
2.
Set the period lock for actual indirect activity allocation (RKIL), so that you
can carry out the following steps on solidly based costs. Should it still be
necessary to carry out further activity allocations in Financial Accounting before
settlement, you must carry out the following steps once again.
3.
Calculate the overheads if there are internal CO receivers with periodic
settlement rules (PER rules). You cannot use percentage-based overhead
calculation in this case for secondary cost elements.
4.
If there are CO internal receivers with PER rules, carry out CO internal
settlement. The system settles all CO objects that have internal receivers.
5.
Carry out the splitting function.
6.
Calculate the price. The actual price is used for revaluation.
Procedure
1.
For revaluation at actual prices, choose the following:
From:
The following menu paths:
2.
3.
Internal orders
Cost Object
Controlling
Objects in the
project system
Caution
When using the cost object hierarchy, ensure that you revaluate activities
that were posted to cost object nodes in a cost object hierarchy before you
distribute the actual costs posted to it.
4.
1.
2.
3.
4.
Result
The system displays the revaluation results in a list. In addition to the selection
criteria and the processing parameters, the list header contains the following data:
Number of messages
Number of selected objects, whose status does not permit revaluation (with
an error message)