Escolar Documentos
Profissional Documentos
Cultura Documentos
Project
Shell Project No: HP-3000-QAT
Project Document Number: T.4.250.903
2MH127
Tag/Item Number(s):
N/A
Unit(s):
ASU
PCWBS:
LINDE ENGINEERING
Contractor Project No :
Project Rev.: O
Page 2 of 20
5887
11.03.2008
RO
EE
ZG
ICC
21.02.2008
RO
EE
ZG
IFR
17.02.2008
RO
EE
ZG
IIR
Date
Description
GAMA
Rev.
No.
Project
Rev
No.
Status
Document Title:
LINDEGINEERING AG
Contractor
LOC470
GAM
MTS
MEC
GTL
008
Org.
Code
Doc.
Type
Disc.
Code
Geogr.
Area
Seq.
No
Rev.
No
Vendor Code
Rev No: O
Doc. Title
Q A T A R
Date/Rev. No :
TABLE OF CONTENTS
1.
INTRODUCTION _______________________________________________________5
1.1.
GENERAL_______________________________________________________________ 5
1.2.
SCOPE _________________________________________________________________ 5
1.3.
PURPOSE_______________________________________________________________ 5
2.
REFERENCE __________________________________________________________5
3.
DEFINITIONS __________________________________________________________6
4.
RESPONSIBILITIES ____________________________________________________7
5.
4.1.
4.2.
4.3.
4.4.
4.5.
4.6.
4.7.
5.2.
5.3.
5.4.
5.5.
5.6.
5.7.
5.8.
WELDING ______________________________________________________________ 10
5.9.
PWHT _________________________________________________________________ 10
5.10.
REWORK ______________________________________________________________ 10
5.11.
NDE___________________________________________________________________ 10
5.12.
6.
7.
HSSE _______________________________________________________________12
8.
ATTACHMENTS ______________________________________________________12
8.1.
T.4.250.903 REV-C
Page 4 of 20
Doc. Title
Q A T A R
Date/Rev. No :
1. INTRODUCTION
1.1.
GENERAL
This document describes the methods proposed to be used for the prefabrication of spools.
1.2.
SCOPE
This method statement defines responsibilities within GAMA-QATAR for the prefabrication of
spools
1.3.
PURPOSE
The purpose of this method statement is to ensure correct and safe implementation of
project specifications and the procedures for the prefabrication of spools.
2. REFERENCE
ASME B 31.3
ASME Sec. V
ASME Sec. IX
ASME Section II, Part C
T-13.377.441
T-13.377.438
Process Piping
Non Destructive Examination
Welding and Brazing Qualification
Specification for Welding Rods, Electrodes & Filler Metals
Quality Control Requirements for Welding
Specification for Traceability, Alloy Verification and Material
Substitution
T.4.250.931
DEP 30.10.60.18
DEP 31.38.01.11
DEP 31.38.01.31
T-4.250.930
T-4.234.542
T-4.250.927
T-4.250.928
T-4.250.932
T-4.250.938
T-4.250.939
T-4.250.913
T.4.250.940
T.4.250.920
T.13.377.360
T.4.250.935
T.4.129.857
T.4.129.872
T.4.129.868
T.4.095.303
T.4.250.903 REV-C
Page 5 of 20
Doc. Title
Q A T A R
T.4.095.807
T.4.219.660
T.4.129.855
T.4.184.595
T.4.129.859
T.4.129.854
T.4.129.864
T.4.129.850
T.4.129.860
T.4.129.865
T.4.129.856
T.4.129.861
T.4.129.866
T.4.129.871
T.4.129.656
T.4.129.852
T.4.129.861
T.4.129.867
T.4.129.853
T.4.129.863
ANSI / ASME B 16.25
Date/Rev. No :
3. DEFINITIONS
Company
Contractor
Sub Contractor
Contract
QCP
ITP
QA/QC
WPS
PQR
PWHT
CS
TT
CN
RT
MSDS
RAT
T.4.250.903 REV-C
Page 6 of 20
Doc. Title
Q A T A R
JSA
TBT
RA
PT
MT
T
NDE
NDT
Date/Rev. No :
4. RESPONSIBILITIES
As per organisation chart, starting from Site Manager and ends at welding, piping foremen
level, including QC personnel, all the people within this link is responsible for execution of
this method statement.
Site Manager, Assistant Site Manager and Mechanical Works Coordinator are responsible
for the fulfilment of this procedure.
4.1. PIPE PREFABRICATION SUPERVISOR
Pipe Prefabrication Supervisor is responsible for implementation of piping works in
accordance with schedule, procedures, specifications, priorities and isometrics issued
for construction.
4.2. PLANNING ENGINEER
Planning engineer is responsible for planning the spool fabrication according to
priorities of piping activities of site, informing Spoolgen Supervisor to provide the spool
drawings and Isogen data accordingly. He is also responsible to release the request of
piping materials according to fabrication schedule.
4.3. FABRICATION ENGINEER(S) AND FOREMEN
They shall ensure safe and efficient working environment, monitor plant and equipment
requirements and ensure that the productivity and the quality are maintained by their
subordinates. They are responsible for ensuring proper material, welding consumables
and welding procedures are applied.
4.4. PIPING ENGINEERS
Are responsible for:
- Ensuring proper documentation and control of spool drawings used for fabrication.
- Request piping materials as per schedule.
- Liaise with contractor representative(s) to solve related technical issues.
- Coordinate with other sections and disciplines on site.
4.5. WELDING SUPERVISOR AND FOREMEN
Welding Supervisor and foremen are responsible to ensure the quality of welding, for
the safe working practices of welders, adherence to approved correct welding
procedure. They will ensure corresponding welding consumables and responsible to
following the consumable stock and ordering them. They are also responsible in
monitoring the welders productivity.
T.4.250.903 REV-C
Page 7 of 20
Doc. Title
Q A T A R
Date/Rev. No :
5. METHOD OF EXECUTION
5.1.
PIPE CUTTING
Spool drawings approved by GAMA-Qatar and LINDE ENGINEERING AG QC
departments will be released by planning engineer to fabrication engineer(s) according
to priorities of erection and fabrication. The Spool lengths will be determined according
to the pipes in stock and these lengths will be stated in the erection drawing, as a
result there will be minimum length adjustment during site erection.
Fabrication (piping) engineer will prepare cutting plan for pipes accordingly, request
the pipes, fittings from material supervisor and will give the same information to cutting
foreman.
Cutting foreman will arrange cutting and planning activities according to RFC drawings.
CS and TT pipes will be cut to the length either by cutting disc or by saw cutting or by
plasma cutting or by motorized flame cutting or by automatic pipe cutting & beveling
machines. After flame cutting a min. 2mm material will be removed from the cut
surface by grinding. Ref. DEP 31.38.01.31 for cutting and beveling preparation.
CN pipes will be cut to the length either by inox cutting disc or by plasma cutting or by
inox saw cutting or automatic pipe cutting & beveling machines with inox apparatus.
Flame cutting of CN is not allowed.
Marking for traceability: Identification mark that is composed of spool number, part/pos.
number, quality and heat number of the pipe will be written on the part with a
permanent marker by the operator who cuts it. Permanent free of chloride markers or
markers suitable to S.S. will be used to for heat nos. traceability in S.S. Pipes.
T.4.250.903 REV-C
Page 8 of 20
Doc. Title
Q A T A R
Date/Rev. No :
T.4.250.903 REV-C
Page 9 of 20
Doc. Title
Q A T A R
Date/Rev. No :
T.4.250.903 REV-C
Page 10 of 20
Doc. Title
Q A T A R
Date/Rev. No :
Radiography shall be taken normally at night hours and in dedicated area specified for
the work.
On approval of RT joints by LINDE ENGINEERING AG, the same shall be offered for
radiography on specified format to NDE contractor.
All joints to be RT checked shall be tagged with Blue ribbon for identification.
The RT operator shall remove the Blue ribbon on completion of radiography.
The radiography film shall be submitted the next day for approval to LINDE
ENGINEERING AG.
Repair joints if any shall be tagged with Red ribbon.
Radiography repair shall be carried out under the supervision of welding inspector and
reoffered as above.
After NDT clearance, prefabricated spools shall be released for painting/storage.
Prefabricated and painted spools shall be released to field on request with traceability.
Before releasing for painting there should be a check by piping QC for any distortion.
The Piping spools should be tagged with line no. & spool no. for traceability.
5.12. MATERIAL HANDLING AND STORAGE
Raw pipes and fittings will be transported from the warehouse/yard to the shop yard
using mobile cranes, trailers and boom trucks.
Handling of the pipe materials/spools inside the shop shall be with E.O.T. crane, fork
lifts and manual trolleys.
Spools shall be shifted from the shop to the radiography area to painting/storage/field,
painting to storage with mobile crane, trailer and forklifts.
Spools shall be stacked on wooden sleepers with identification markings on top.
Spools shall be stacked unit wise and area wise.
Register shall be maintained for storage showing spools numbers stored in each
location and issue to site.
All open ends of spools shall be covered using end caps/plastic sheets or suitable
material.
All flange faces shall be protected with wooden/plastic covers.
T.4.250.903 REV-C
Page 11 of 20
Doc. Title
Q A T A R
Date/Rev. No :
6. QUALITY ASSURANCE
A Quality Assurance System shall be operated conforming to related standards. Controls
and checks shall be established and documented through relevant QCP T-4.250.935, ITP
T-4.250.920 and relevant QCRs.
7. HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan
Industrial City and International standards, codes, LINDE ENGINEERING AG and QSGTL
and/or its PMC requirements and instructions.
In addition all employees and GAMA subcontractor employees on site will have through
GAMA Qatar Site Safety Induction, LINDE ENGINEERING AG Safety induction and
QSGTL Safety Induction for site safety, health, environmental and security prior to work
activities. Other training courses will be attended as required by LINDE ENGINEERING AG
or QSGTL and/or its PMC as required.
At a minimum a generic Risk Assessment will have been prepared by the RAT ranking the
hazards associated with project works and control measures to be taken to mitigate the
hazards to an acceptable level.
Each work scope or task will have a completed and approved JSA identifying the potential
hazards and control measures that will be implemented to protect people and environment.
The JSA (RA) will be used by Supervisor as the basis of conducting his daily Pre-Task
meeting and his weekly TBT.
In addition to the above, employees conducting survey works will wear required PPE and
highly visible vest where traffic or other hazards may exist. For additional safety
requirements for a particular or specific task please refer to the JSA prepared for that task.
8. ATTACHMENTS
8.1.
T.4.250.903 REV-C
Page 12 of 20
Q A T A R
JSA Members:
Job Performers:
Normal Approvals:
Name
Signature
Date
JSA by:
Job Supervisor:
Additional Approvals (Determined by Job Supervisor in correlation with Linde HSSE Manager).
Name
Signature
Date
Approval required for hazardous work detailed in the Linde Work Permit Procedure.
Changing conditions and emergency procedures
Stop work. Switch off equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees.
Missing employees are reported to Linde HSSE Dept. When all clear is given, check with Linde HSSE before returning to work.
LINDE EMERGENCY TELEPHONE NO.
HSSE MANAGER:
Pearl HOT LINE :
583 40 72
474 88 88
Q A T A R
ITEM
1
HAZARDS / POTENTIAL
CONSEQUENCES
Manual handling of 1.1 Personal injury, back
pipes materials.
injuries, muscle strains,
sprains.
ACTIVITY
Initial Risk
RISK
P C
RANK
1.2
Mechanical
movement to
laydown area
2.1
MED
1.1.3
1.1.4
1.1.5
1.2.1
1.2.2
3
LOW
1.3
Residual Risk
1.1.1
1.1.2
C
MED
Crushed injuries
MED
1.2.3
1.2.4
MAIN
ADDITIONAL
CONTROLS
CONTROLS
Worker to wear appropriate
1.1.3.1 Provision for lifting aids when
gloves.
practical.
Break the load into manageable
portions.
Lift with your legs not your back.
Use the buddy system, Get help.
Provide pictorial sign boards with
correct lifting position.
Adequate stacking of materials.
1.2.1.1 Remove unnecessary materials
Regular housekeeping practices
in the work place.
and removal of trash and
unnecessary items.
Maintain access and walk paths.
Housekeeping shall be a priority,
walk and work areas shall be kept
free of materials and supplies.
LOW
LOW
LOW
LOW
2.2
Falling materials.
2.2.1
2.2.2
D
HIGH
2.2.3
2.3
Lifting hazard
2.3.1
2.3.2
HIGH
2.3.3
2.3.4
2.3.5
2.3.6
2.3.7
2.3.8
3 Cutting of pipes
3.1
3.2
3.1.1
C
MED
3.2.1
LOW
LOW
LOW
LOW
LOW
3.3
3.3.1
3.3.2
3.4
3.5
Damage to eyes.
Personnel injury.
HIGH
3.3.3
3.4.1
B
LOW
Defective equipment.
3.5.1
LOW
3.5.2
3.5.3
3.6
Cylinders explosion or
Fire
3.6.1
3.6.2
3.6.3
D
MED
3.6.4
3.7
Fire hazard.
3.7.1
C
LOW
3.7.2
LOW
LOW
LOW
LOW
LOW
Alignment, fit-up,
and welding of
random lengths
pipes.
4.1
Grinding hazards
4.1.1
4.1.2
4.1.3
D
MED
4.1.4
4.2
Noise hazards.
4.3
Electric shock
4.2.1
LOW
4.4.1
LOW
Pinch point
4.4.2
4.5.1
B
4.6
Fire hazards
4.5
LOW
4.3.1
C
4.4
LOW
4.5.2
4.6.1
LOW
4.6.2
LOW
LOW
LOW
LOW
LOW
LOW
4.7
NDT Work
5.1
Grooving and
Threading at
Fabrication Shop
6.1
LOW
LOW
MED
LOW
LOW
LOW
LOW
LOW
Electric shock
LOW
6.3
Fall of materials.
D
6.2
MED
4.7.1 Use chain puller or chain block in 4.7.1.1 Use of A-frame connected to
lifting pipe during fit-up works.
the chain block.
4.7.2 Cable sling shall be inspected
4.7.1.2 Pipe jack to be used as
before use.
secondary support for the pipe.
4.7.3 Provide adequate supports to hold
pipe.
5.1.1.1 Discuss in HIP/ TBT.
5.1.2.1 Ensure all work shall be
supervised at all times.
5.1.3.1 Obtain Permit to Work.
6.4
Cuts injury
6.5
6.6
7.1
7.2
LOW
LOW
Overloading
7 Welding works
LOW
Electric shock
LOW
LOW
Burn Injury
LOW
LOW
LOW
LOW
LOW
7.3
7.4
MED
Arc rays
B
7.6
LOW
7.5
LOW
LOW
LOW
LOW
LOW
LOW