Pearl GTL

Project
Shell Project No: HP-3000-QAT
Project Document Number: T- 4.234.572

Purchase Order Number:

2MH127

Tag/Item Number(s):

N/A

Unit(s):

ASU

PCWBS:

LINDE ENGINEERING

Contractor Project No:


Project Rev.: A

Page 2 of 8

5887

QATAR SHELL GTL PROJECT (PEARL)


C2 AIR SEPARATION UNITS CONSTRUCTION

15.02.09

Ready for Construction

SB

EO

AG

RFC

04.01.09

Company Comments Incorporated

SB

AB

AG

CCI

30.12.08

Issued for Company Comments

SB

AB

AG

ICC

18.12.08

Issued for Review

SB

EO

AG

IFR

25.11.08

Issued for Internal Review

SB

EO

AG

IIR

Date

Description

GAMA
Rev.
No.

Project
Rev
No.

Prepared Checked Approved


By
By
By
ORIGINATOR

Status

Document Title:

LINDEGINEERING AG

ITP FOR INSTALLATION OF GYPSUM BOARD


(BUILDINGS)
Document No.

Contractor

Gama Qatar Co. W. L. L.

LOC470
GAM

ITP

QAC

GTL

044

Org.
Code

Doc.
Type

Disc.
Code

Geogr.
Area

Seq.
No

Rev.
No

Project Document Number: T- 4.234.572

Vendor Code

Rev No: A

QSGTL PEARL PROJECT


C2 ASU Construction Works

ITP FOR INSTALLATION OF GYPSUM BOARD


(Buildings)
S. GAMA QATAR

X. CONTRACTOR QC

C. COMPANY

Document No.: GAM-ITP-QAC-GTL- 044


Date: 15.02.2009 Rev. E
A. THIRD PARTY (TPI)

I: INSPECTION / TEST
R: DOCUMENT ISSUED/REPORT REVIEW
S: SURVEILANCE
H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item

1.0
1.1
2.0
2.1

2.2
3.0

3.1

3.2

Activity

Test Frequency

METHOD STATEMENTS/PROCEDURES
Method Statements /
Prior to start of
Procedures
activity
Preparation

Reference Document

Acceptance Criteria

Responsible
Party

Verifying Documents

Subcontractor Method
Statements / Procedure

Project Requirements

QA/QC

Project Specifications
& Material Approval
Request

R R

Manufacturers
Technical data sheet,
certificates

QC Civil
Inspector

Manufacturers
Technical data
sheets & certificates

R R

Manufacturers
recommendation.

QC Civil
Inspector

Visual confirmation

S S

QC Civil
Inspector

GAM-QCR-QACGTL- 168

S S

QC Civil
Inspector

GAM-QCR-QACGTL-166

W S

MATERIALS CERTIFICATES
Verification of
Acoustical & rock wool
material.
Storage and handling
of Acoustical & rock
wool material.
INSPECTIONS
Environmental
Conditions
1. Ambient temp.

Inspection for surface


preparation ( Repairing
the surface of R.C.C
Wall)

T- 4.234.572

Rev. A

100%

100%

100%

100%

T.4.234582 , DEP
34.17.00.32-Gen & DEP
34.17.10.30-Gen
T.4.234.582 , DEP
34.17.00.32-Gen & DEP
34.17.10.30-Gen

T.4.234.582 , DEP
34.17.00.32-Gen & DEP
34.17.10.30-Gen

T.4.234.582 &
T.4.234.555

DEP 34.17.00.32Gen & DEP


34.17.10.30-Gen &
Manufacturers data
sheet
DEP 34.17.00.32Gen & DEP
34.17.10.30-Gen &
Manufacturers data
sheet

Page 4

QSGTL PEARL PROJECT


C2 ASU Construction Works

ITP FOR GYPSUM BOARD INSTALLATION


(Buildings)
S. GAMA QATAR

X. CONTRACTOR QC

C. COMPANY

Document No.: GAM-ITP-QAC-GTL- 044


Date: 15.02.2009 Rev. E
A. THIRD PARTY (TPI)

I: INSPECTION / TEST
R: DOCUMENT ISSUED/REPORT REVIEW
S: SURVEILANCE
H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item

Activity

Test Frequency

Reference Document

Acceptance Criteria

Responsible
Party

Verifying Documents

100%

T.4.234.582 , DEP
34.17.00.32-Gen & DEP
34.17.10.30-Gen

T.4.234.555 Procedure for


Building works

QC Civil
Inspector

GAM-QCR-QACGTL-168

W S

T.4.234.582 &
Manufacturers
recommendation

Manufacturers
recommendation &
RFC drawings

QC Civil
Inspector

GAM-QCR-QACGTL-168

T.4.234.582 &
Manufacturers
recommendation

Manufacturers
recommendation &
RFC drawings

QC Civil
Inspector

GAM-QCR-QACGTL-168

W S

T.4.234.582 &
Manufacturers
recommendation

Manufacturers
recommendation

QC Civil
Inspector

GAM-QCR-QACGTL-168

Visual confirmation

Site Engineer &


QC Civil
Inspector

Check Records &


Punch List

3.3

Inspection for
installation of framing
system

3.4

Inspection for
Installation of Conduits
(If applicable)

100%

3.5

Inspection for 40mm


thick rock wool
insulation

100%

3.6

In process inspection
of Gypsum Board
Installation system

100%

3.7

Final inspection & Punch


Listing

T- 4.234.572

Rev. A

100%

Mechanical Completion
Documentation

Page 5

QSGTL PEARL PROJECT


C2 ASU Construction Works

ITP FOR GYPSUM BOARD INSTALLATION


(Buildings)
S. GAMA QATAR

X. CONTRACTOR QC

C. COMPANY

Document No.: GAM-ITP-QAC-GTL- 044


Date: 15.02.2009 Rev. E
A. THIRD PARTY (TPI)

I: INSPECTION / TEST
R: DOCUMENT ISSUED/REPORT REVIEW
S: SURVEILANCE
H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item

3.8

Activity

Disposal of high risk


wastes such as rock
wool waste & gypsum
board waste.

T- 4.234.572

Rev. A

Test Frequency

100%

Reference Document

Acceptance Criteria

T.13.377.450Construction waste
Management Procedure

Check & ensure in


Hazard area
,flammable area any
paint material

Responsible
Party

Verifying Documents

Visual

S S

Site Engineer

Page 6

QSGTL-PEARL GTL PROJECT


C2-ASU-Construction Project
Inspection Form for Surface
Preparation(Buildings)
GAM-QCR-QAC-GTL-166
Rev. O

Date :

GAM-ITP-QAC-GTL-

Location Bldg/Area:
Drawing No:
Tag No and Tag description :

Item

Details of Activity

Remarks

Sign off will Confirm Released to Next activity


GAMA QATAR
Name

Signature

Date

LINDE

QSGTL or its PMC

QSGTL PEARL PROJECT


C2 ASU Construction Works
FORM NO: GAM-QCRQAC-GTL-168 Rev. O

Gypsum Board , Suspended Ceiling Date:


works & Rock Wool Installation
ITP No: GAMITPQACGTLCheck List

Report No:
Item description:
Item location/area:
Drawing reference:

Ambient Temp. :

Tag No & Description:

Ref.

DETAIL OF ACTIVITY

GYPSUM BOARD WORK


Dimensionally correct plumb, level and
square etc ... complete.
Screws, Anchors, U-Channels, Studs,
Brackets fixing.
Application of Joint Filler or joint tape etc
... complete.

1.1
1.2
1.3
2
2.1
2.2
2.3

Hangers, channels, studs, furring correctly


spaced, braced. Plumbed and level
Material application and jointing correctly
installed at ceilings, openings and fittings
Trims are installed level and clean.

4
5

Work area is clean and free from debris

3.1
3.2
3.3

REMARKS

SUSPENDED CEILING

ROCK WOOL INSULATION ( Roof &


Wall)
Positioning, grouting and curing in accord
with codes of practice and vendor
instructions
Finish with plumb, level, clean and free
from spalls
Gaps and coursing, expansion joints,
stained joints are in accord with the
relevant drawing and specifications
All works are Completed with final
touch-ups

COMPLIANCE
YES
NO
N/A

SIGN OFF AS ACCEPTED


GAMA QATAR
Name

Signature

Date

LINDE

QSGTL or its PMC