Escolar Documentos
Profissional Documentos
Cultura Documentos
A commercial study comparing price for various offshore wind foundation technologies
www.quartzco.com
www.mecintelligence.com
COPENHAGEN
INDIA
Ryesgade
112,
Udyog3A
Vihar Phase 4
2200 Copenhagen
122015
Gurgaon N
Denmark India
Haryana,
T: +45 33 17 00 00
T: +91124 480 2700
STOCKHOLM
DENMARK
Birger Jarlsgatan
7
Nordre
Fasanvej 113,
2
111 45
Stockholm
2000
Frederiksberg
Sweden
Copenhagen,
Denmark
T: +46 (0)8 614 19 00
T: +45 3543 3277
OSLO
Wergelandsveien 21
0167 Oslo
Norway
T: +47 22 59 36 00
SUMMARY
New foundation designs could be cost effective as compared to conventional designs and also
reduce vessel demand for construction
New foundation
designs could be
10 percent to 30
percent cheaper
as compared to
conventional
designs
Foundation cost are primary driven by Material and installation costs with 65-85 % share of the total cost and have been
considered in this study
New foundation designs have lower costs as turbines become larger and installed in deeper sea
For 6 MW, new foundations are ~4-20% lower in material cost when compared to monopiles & jackets while for turbine sizes 8
MW and larger, new designs reduce the cost by ~21-24%
Installation cost does not vary much in comparison to material costs, but can be a bottleneck in timely execution of the OW
farm. New foundation designs can reduce the installation cost by ~50% as compared to the conventional designs
Mono-suction bucket is cost effective for 4-6 MW turbine size at lower to medium depths, while CraneFree Gravity is most
suitable for even larger turbines at medium to larger depths
Cost reduction potential of 5-15% is observed for foundations at select 5 farms in Europe. However, developers need to manage
risk and other associated premium costs with appropriate contracting
II
New foundation
designs could
lead to major
oversupply in the
vessels market
Currently there are 43 installation vessels suitable for offshore wind construction in EU; daily rate ranges between EUR 70k to
290k
The current vessel days are just enough to meet the demand from conventional foundations
In <800 tonne lifting category, new foundations eliminate the need for higher capacity vessel to meet the increase
In, 800-1200 tonne lifting category, new foundation adoption increases the vessel oversupply by 141% percent by 2020
In >1200 tonne lifting category, new foundations increase the vessel oversupply by 32% percent by 2020
INTRODUCTION
Innovation is being driven to reduce the high cost of energy from offshore wind planned in EU
No. Of Foundations
1.493
1.245
5,9
EWEA, 2013
1.050
5,5
954
4,8
654
2,9
286
1,3
2015
2016
2017
2018
2019
2020
1.8
10
6.3
5.6
2.5
2.8
4-6 MW
6-8 MW
2015
2016
2017
2018
2019
2020
INTRODUCTION
New foundation designs claim to reduce the cost of foundation and also of the entire offshore
windfarm
1
LOW MATERIAL COSTS
100
Planning &
Miscellaneous
100%
9%
Grid
Connection
Foundation
100%
11%
16%
Material
Cost
2
INSTALLATION COSTS
50-60%
OTHER ADVANTAGES
Noise mitigation regulations compliance
Wind
Turbine
64%
Cost breakup of
OW Installation
Installation
Cost
15-25%
Others
15-20%
Reusable designs
Cost Breakup of
OW Foundation
* Others include risks, insurances, noise mitigation, sea fastening, onshore logistics etc.
Easier decommissioning
INTRODUCTION
Three new designs have been considered to compare their cost effectiveness against the
conventional monopiles and jackets
Commercial Designs
Monopile
Structural Design
Fabrication
Installation
Prominent Projects
Jacket
Steel lattice frame
with piles
Column of steel
New Designs
CraneFree Gravity
(CFG)
Concrete base
with steel column
Easier to fabricate
Cutting and Rolling of
steel
Difficult to fabricate
Requires extensive
welding at joints
Requires fabrication
yard to be setup at port
for mass production
Complex design,
difficult to fabricate
Requires intensive
welding at joints
Installation through
OW construction
vessels with significant
lifting capabilities
Requires drilling/pilling,
grouting, scour
protection
Installation through
OW construction
vessels with significant
lifting capabilities
Requires drilling/piling,
grouting, scour
protection
Installation through
Tugboats and position
assisting OW vessels
Requires sand
ballasting, scour
protection
Installation through
Tugboats, OW
construction vessels;
through specialized
suction pump
Requires OW
construction vessels
with significant lifting
capabilities
Installation through
suction action of three
suction pumps working
in tandem
Prototype at:
Fecamp, FR
Prototype at:
Dogger Bank, UK
Frederikshavn, DK
Prototype at:
Borkum Riffgrund 1
London Array, UK
Horn Rev I, DK
Nordsee One, DE
Egmond aan Zee, NL
Ormonde, UK
Alpha Ventus, DE
Thronton Bank, BE
Beatrice, UK
The three new innovative designs considered for the analysis, benchmark their two main advantages:
Material cost effectiveness
Alternative installation techniques and cost savings
INTRODUCTION
Material and installation costs are the largest cost constituents with 65-85 % share of the total cost
and have been considered in this study
Indicative cost breakup of a typical OW foundation
In Scope
Depend on design
Out of Scope
Depend on market factors, driven by
local needs
100%
50-60%
15-25%
5%
15-20%
Total
Material Cost
Material used to
manufacture the
foundation, e.g.
Different types of
steel
Concrete
Others
Installation Cost
Installation at
offshore site using
Installation
vessels
Drilling/pilling/
suction pumps,
Sand ballasting,
Grouting, Scour
protection
Others
Other costs
Includes costs that are
due to design advantages
but are not game
changer* in light of
comparisons
Noise mitigation
Decommissioning
Market Costs
Noise mitigation
Onshore logistics
Sea-fastening
Risk premiums
Insurances
Profit margins
Note: Cost shares vary in a broad range due to varying foundation design, risks and insurances based on local industries experience, and contracting models
* Game changers refers to large cost shares which have potential to change the COST based analysis
Source: MEC+ analysis
Relative
quantity used
Low
Material cost depends upon the quantities and unit prices of variable types of materials
used in the foundations
High
Material Cost
Materials
Utilisation in design
Unit Rate
(EUR per tonne)
7.800
Secondary Steel
Monopile
Jacket
CraneFree
Gravity (CFG)
Mono Suction
Bucket (MSB)
Suction Bucket
Jacket (SBJ)
Boat
landing, Jtubes, platforms
etc.
Boat
landing, Jtubes, platforms
etc.
Boat
landing, Jtubes, platforms
etc.
Boat
landing, Jtubes, platforms
etc.
Bottom bucket,
middle interconnecting lid
Jacket body,
3 suction
buckets
Higher Grade
Primary Steel
Primary Steel
Concrete
Miscellaneous
3.200-4.500
1.600
Monopile,
Transition
piece
Jacket body,
Transition
piece
4 pre-piles
Top
cylindrical
structure, bottom
skirt
Top
shaft
Bottom
cement
gravity structure
Sand
ballasting
material: 62.500
EUR/foundation
170
7 Source: Scholar articles and thesis from various research institutions, Industry expert inputs, foundation manufacturers, MEC+ analysis
The quantity of material used in foundation is driven mainly by the depth of the seabed and turbine
size
Various factors affect the weight
of the foundation and in turn the
material cost
Monopile (6 MW)
Jacket (6 MW)
CFG
MSB
5.000
SBJ
Monopile (8 MW)
Jacket (8 MW)
2.500
10
20
30
40
50
60
3.000
Turbine Size
0
10
Others
Physical condition e.g.
Seabed, Weather
No. Of Foundations
20
30
40
50
60
For 6 MW, new foundations have ~4-20% lower material cost when compared to monopiles &
jackets
..While the cost reflects a different trend due to variable mix of
material component
By weight, the new designs are similar to monopiles and jackets (up
to 30 m)
Steel quantity* for different foundation designs for 6 MW
Tonnes
Monopile
Tonnes
Jacket
MSB
SBJ
EUR mil.
3.000
Monopile
Jacket
CFG
MSB
SBJ
2.000
Introduction of
XL/XXL monopiles
-20%
3
1.000
-4%
10
20
30
40
50
60
10
20
30
40
50
Depth (in m)
Note: CFG uses steel in upper cone, cylindrical tower and reinforced bars for concrete cone. The steel quantity graph excludes the reinforced bars. Steel tonnage for CFG not
available for >4MW turbine sizes;
* Monopiles steel tonnage includes monopile, TP and secondary structures; Jacket includes lattice structure, TP, pre-piles, secondary structure; MSB includes bucket/skirt,
lid, shaft, secondary structure; SBJ includes 3 buckets, lattice structure, secondary structure
9 Source: MEC+ analysis
60
For turbine sizes 8 MW and larger, new designs reduce the cost by ~21-24%
Jacket
MSB
SBJ
Tonnes
EUR mil.
3.000
Monopile
Jacket
CFG
MSB
SBJ
6
Introduction of
XL/XXL monopiles
2.000
-24%
-21%
1.000
10
20
30
40
50
10
60
20
30
40
50
Depth (in m)
Note: CFG uses steel in upper cone, cylindrical tower and reinforced bars for concrete cone. The steel quantity graph excludes the reinforced bars. Steel tonnage for CFG not
available for >4MW turbine sizes;
* Monopiles steel tonnage includes monopile, TP and secondary structures; Jacket includes lattice structure, TP, pre-piles, secondary structure; MSB includes bucket/skirt,
lid, shaft, secondary structure; SBJ includes 3 buckets, lattice structure, secondary structure
10 Source: MEC+ analysis
60
Installation cost depends on the various processes, unique to each foundation design,
affecting its installation duration and cost
Low
High
Installation Process
Upending/
Lowering
Pilling
Drilling
Required
Scour
Protection
Total Days
2-3
4-6
Grouting
Sand
Ballasting
Duration
1-2*
Cost
* Days are estimated based on assumption that there are no delays like supply chain delays, unavailability of vessels/boats
1-2*
2-3*
New foundation
designs can be
installed in 1-3 daysdecreasing the total
time for installation of
foundations
Installation cost do not vary much as compared to the material cost, but can be a bottleneck in timely
execution of the OW farm
4,5
4,0
3,5
3,0
2,5
2,0
1,5
1,0
0,5
0,0
Monopile Jacket
CFG
MSB
SBJ
* Configuration used for determining cost: Turbine size= 6 & 8 MW, Depth= 0 to 60 m, Distance= 0 to 90 km, Seabed= soft for pilling & rocky for drilling, Wind farm size = 50-100
** Configuration for calculating typical cost: Turbine size= 6 MW, Depth= 30 m, Distance= 0 -30 km Seabed= soft, Wind farm size = 50-100
12 Source: MEC+ analysis
New foundation designs can reduce the installation cost by ~50% as compared to the conventional
designs
Indicative installation cost in for different foundation types*
Euro millions per Foundation
0,56
Average for
conventional designs
0,42
EUR mil
0,19
(50%)
0,33
0,31
0,27
Jacket
Monopile
MSB
CFG
* All calculations done for base case configuration (Turbine size = 6MW, Depth = 30 m, Distance = 0-30 km, Sea Type = North Sea, Wind farm size = 50-100, Seabed = Soft)
SBJ
COST ANALYSIS
Cumulative cost of material and installation indicates that new foundations could be a more cost
effective solution than traditional designs for higher turbine sizes and greater depths
For a 6 MW turbine, CFG and MSB would offer cost advantage than the conventional Monopile and Jacket foundations at depths > 30m
CFG, a gravity based design could potentially be the most economical foundation design at all depths for turbine sizes > 6MW
Jacket
CFG
MSB
SBJ
EUR mil.
6 MW
8 MW
10
20
30
40
50
60
10
20
30
Depth (in m)
Note: *All calculations done for base case configuration (Distance = 0-30 km, Sea Type = North Sea, Wind farm size = 50-100, Seabed = Soft)
40
50
60
05-10%
10-15%
15-20%
20-25%
>25
Most cost effective offshore wind foundations across different project configurations
Figure in the grid depicts the lowest cost foundation (within 10% error margin)
Depth
20 m
30 m
40 m
50 m
60 m
6 MW
8 MW
10 MW
Turbine size
4 MW
10 m
15
Note: 1. Cost includes mainly material cost, seabed preparation costs, installation costs. However, cost doesnt include EPC margins, profits, insurance costs, manpower expenses,
transportation costs incurred from manufacturing location to the port
2. CFG is not applicable for depth <15 m, as the structure would be too light to be stable at lower depths
3. All calculations done for base case configuration (Distance = 0-30 KM, Sea Type = North Sea, Wind farm size = 50 - 100, Seabed = Soft)
* The cost reduction potential has been estimated based on the comparison of the lowest cost design to the monopile cost for depths <30 m and with jacket cost for
depths >30 m
Material
Seabed Prep
Turbine size: 5 MW
Average depth: 47,5
m (40 55 m)
Turbine size: 7 MW
Seabed: Rocky
Average depth: 30 m No. of turbines: 60
(24 - 36 m)
Distance: 6,7 KM
Seabed: Soft
No. of turbines: 213
Distance: 22 KM
M
J
CFG
MSB
SBJ
4,7
4,3
3,6
4,2
5,7
M
J
CFG
MSB
SBJ
4,6
4,0
3,4
0,0
0,0
Wikinger, Germany
Turbine size: 6 MW
Average depth: 35m
(25 - 45 m)
Seabed: Soft
No. of turbines: 70
Distance: 35 KM
M
J
3,4
3,6
CFG
3,3
MSB
SBJ
2,8
4,7
Saint-Nazaire, France
Turbine size: 6 MW
Average depth: 17,5
m
Turbine size: 4 MW
Average depth: 20 m
Seabed: Medium
No. of turbines: 80
Distance: 12 KM
M
J
3,0
3,2
CFG
3,1
MSB
SBJ
Seabed: Soft
No. of turbines: 90-150
Distance: 23 KM
M
J
2,7
2,8
CFG
2,6
4,3
MSB
SBJ
Note: This mapping is based on the results of the cost simulation model built by MEC+, Transportation cost is computed from the nearest manufacturer
*Since practical application of the suction bucket concepts in rocky seabed are highly unlikely, the cost comparisons are therefore not shown
16 Source: MEC+ analysis, The Wind Power database
2,9
2,3
3,8
RISK ANALYSIS
Developers need to manage risk and other associated premium costs with appropriate
contracting
Contracting
Structure
Multi contract
EPCM
Package EPC
Project EPC
Brief Description
Value proposition
to developer
No risk premium
attached and has
full project control
Construction
management is
out sourced
Limited EPC
capabilities
needed, which
takes time and are
costly to develop
Construction
contracts are given
out in packages of
turbines,
foundations, etc
Limited EPC
capabilities
needed, which
takes time and are
costly to develop
Cost
* The definition of risks is limited to systematic project risks inherent in the business and excludes unexpected weather, geotechnical & political risks
** Suitability is based on the key need to manage risk at project level for the developer or contractor
17 Source: MEC+ analysis
Low
High
Suitable
foundation**
SUMMARY
New foundation designs could be cost effective as compared to conventional designs and also
reduce vessel demand for construction
New foundation
designs could be
10 percent to 30
percent cheaper
as compared to
conventional
designs
Foundation cost are primary driven by Material and installation costs with 65-85 % share of the total cost and have
been considered in this study
New foundation designs have lower costs as turbines become larger and installed in deeper sea
For 6 MW, new foundations are ~4-20% lower in material cost when compared to monopiles & jackets while for turbine
sizes 8 MW and larger, new designs reduce the cost by ~21-24%
Installation cost does not vary much in comparison to material costs, but can be a bottleneck in timely execution of the
OW farm. New foundation designs can reduce the installation cost by ~50% as compared to the conventional designs
Mono-suction bucket is cost effective for 4-6 MW turbine size at lower to medium depths, while CraneFree Gravity is
most suitable for even larger turbines at medium to larger depths
Cost reduction potential of 5-15% is observed for foundations at select 5 farms in Europe. However, developers need to
manage risk and other associated premium costs with appropriate contracting
II
New foundation
designs could
lead to major
oversupply in the
vessels market
Currently there are 43 installation vessels suitable for offshore wind construction in EU; daily rate ranges between EUR 70k to
290k
The current vessel days are just enough to meet the demand from conventional foundations
In <800 tonne lifting category, new foundations eliminate the need for higher capacity vessel to meet the increase
In, 800-1200 tonne lifting category, new foundation adoption increases the vessel oversupply by 141% percent by 2020
In >1200 tonne lifting category, new foundations increase the vessel oversupply by 32% percent by 2020
VESSEL DEMAND-SUPPLY
Currently there are 43 installation vessels suitable for offshore wind construction in EU; daily rate
ranges between EUR 70k to 290k
Supply of OW vessels in Europe
# of vessels by lifting categories
Jack Ups(Vessels+Barges)
Cranes(Sheerleg+Monohull)
HLV(HLVs+WIVs)
EUR
millions
14
0,30
12
0,25
10
0,20
8
0,15
6
0,10
4
0,05
0,00
0-400
400-800
800-1200
1200-1600
1600-2000
>2000
19 Source: Ballast Nedam, IT Power UK, Windpower Offshore, News articles and research papers, MEC+ analysis
0-400
400-800
800-1200
1200-1600
1600-2000
>2000
VESSEL DEMAND-SUPPLY
The planned OW pipeline is prone unavailability risk of appropriate installation vessel, if conventional
foundations are considered to scale with expected demand thereby impacting costs
Scenario I: Vessel supply demand based on installation of only conventional designs
In Vessel Days
0 - 800 tonne
Crane lifting
capacity
Demand
Supply
>1200 tonne
10.000
7.670
6.494
5.609
4.569
5.000
4.060
3.703
3.212
3.029
2.779
2.089
2.006
1.595
0
2015
2016
2017
2018
2019
2020
136
2015
2016
2015
Minor Shortfall
3.534
2.920
2016
2017
2018
2019
2020
Shortfall
721
2017
2018
2019
2020
Minor Shortfall
Note: The complete process will take about 5 days on average for installation of conventional foundations with 2.5 days in turbine installation. The standard turbine weights has
been considered in estimating the demand for turbine installation. Demand from OW O&M has not been considered.
Note 2: Demand for vessels is estimated on the construction/installation start year of the OW farms. Lifting cranes vessels are expected to operate for 10-11 months a year
20 Source: Windpower, Wind energy update, NREL, Offshore Wind Energy Cost Modelling By Mark J Kaiser, Brian F Snyde, MEC+ analysis
VESSEL DEMAND-SUPPLY
In <800 tonne lifting category, though the demand is less than supply except slight increase in 2019,
new foundations eliminate the need for higher capacity vessel to meet the increase
New foundation
designs considered
Excessive
Supply
Supply
Shortage
Scenario 1:
Conventional designs are installed in the planned OW farms till 2020
Scenario 2:
Most cost effective foundation is considered; including the innovative
foundations; post 2017*
3.000
3.000
2.000
2.000
1.176
1.000
1.000
-1.000
-1.000
-2.000
-2.000
-1.925
-2.037
-2.462
-3.000
-2.791
-3.000
-3.465
-3.465
-3.471
-4.000
-4.000
-4.405
-4.223
-4.405
-4.488
-5.000
-5.000
2015
2016
2017
2018
2019
2020
2015
2016
2017
2018
2019
Note: The complete process will take about 5 days on average for installation of conventional foundations with 2.5 days in turbine installation. The standard turbine weights has
been considered in estimating the demand for turbine installation. Demand from OW O&M has not been considered. Average days for installation of new foundation
designs is 2. CFG does not require a lifting vessel
Note 2: Demand for vessels is estimated on the construction/installation start year of the OW farms. Lifting cranes vessels are expected to operate for 10-11
months a year
21 Source: MEC+ analysis
2020
VESSEL DEMAND-SUPPLY
In, 800-1200 tonne lifting category, vessel demand declines significantly post 2016 due to the
introduction of new foundations, reducing risk of cost overruns by using higher capacity vessels
New foundation
designs considered
Supply
Shortage
3.000
Scenario 2:
Most cost effective foundation is considered; including the innovative
foundations; post 2017*
3.000
2.397
2.000
2.000
848
1.000
848
1.000
-433
Excessive
Supply
-1.000
-1.000
-1.617
-2.000
-2.000
-3.000
-1.945
-2.151
-3.000
-3.212
-3.212
-2.940
-3.212
-4.000
-3.212
-4.000
-5.000
-5.000
2015
2016
2017
2018
2019
2020
2015
2016
2017
2018
2019
Note: The complete process will take about 5 days on average for installation of conventional foundations with 2.5 days in turbine installation. The standard turbine weights has
been considered in estimating the demand for turbine installation. Demand from OW O&M has not been considered. Average days for installation of new foundation
designs is 2. CFG does not require a lifting vessel
Note 2: Demand for vessels is estimated on the construction/installation start year of the OW farms. Lifting cranes vessels are expected to operate for 10-11
months a year
22 Source: MEC+ analysis
2020
VESSEL DEMAND-SUPPLY
In >1200 tonne lifting category, marginal high demand in 2017 could be reduced by new foundation
designs and no supply risk would be envisaged, preventing the minor delay risk expected
New foundation
designs considered
Supply
Shortage
Scenario 1:
Conventional designs are installed in the planned OW farms till 2020
3.000
3.000
2.000
2.000
1.000
Excessive
Supply
Scenario 2:
Most cost effective foundation is considered; including the innovative
foundations; post 2017*
1.000
614
-1.000
-1.000
-2.000
-2.000
-2.199
-3.000
-2.920
-2.784
-2.920
-2.920
-4.000
-3.000
-2.920
-2.784
-2.838
-2.920
-2.920
-2.920
2015
2016
2017
2018
2019
2020
-4.000
-5.000
-5.000
2015
2016
2017
2018
2019
2020
Note: The complete process will take about 5 days on average for installation of conventional foundations with 2.5 days in turbine installation. The standard turbine weights has
been considered in estimating the demand for turbine installation. Demand from OW O&M has not been considered. Average days for installation of new foundation
designs is 2. CFG does not require a lifting vessel
Note 2: Demand for vessels is estimated on the construction/installation start year of the OW farms. Lifting cranes vessels are expected to operate for 10-11
months a year
23 Source: MEC+ analysis
APPENDIX
Abbreviations used
OW
Offshore Wind
EPC
TP
Transition piece
EUR
Euro
MP
Monopiles
Jackets
CFG
CraneFree Gravity
MSB
SBJ
metre
KM
Kilometre
NM
Nautical mile
GW/MW
24
APPENDIX
This report has been prepared by MEC Intelligence using a wide range of resources and databases. MEC Intelligences internal databases on OW farms and OW
installation vessels have been the base for the analysis. Extensive secondary research through continues wind industry monitoring through news and press
releases, primary research with OW EPC contractors, foundation designers, vessel operators and independent OW experts in the industry have all contributed to
the depth of the analysis conducted.
For any further queries, please contact:
Jacob Jensen
(jj@mecintelligence.com)
Sidharth Jain
(sidharth@mecintelligence.com)
Disclaimer
The information contained herein has been obtained from sources believed to be reliable. MEC Intelligence disclaims all warranties as to the accuracy,
completeness or adequacy of such information. MEC Intelligence shall have no liability for errors, omissions or inadequacies in the information contained herein or
for the interpretation thereof. Therefore MEC is not liable for any indirect, incidental, consequential damage or loss of revenues or profits in any case.
25
MEC+ experience and resources are a valuable asset for insights in offshore wind strategy decisions
MEC+ provides insights by combining its granular data, cost and forecasting models, and primary information along with deep experience and understanding
of players and concepts. Client assurance is guaranteed in the results with high-touch transparent processes.
MEC+ has done more than 60 analyses in the offshore wind industry covering demand, supply, business models for contracting strategies, WTG, foundations,
cables, vessels, installation concepts, and O&M
MEC+ approach
leverages the rich
resources that the
firm has access to
Expert contacts
Our work has led to a strong network of
relations with industry experts who have
deep offshore experience.
26
The team at MEC Intelligence has published industry leading reports on the maritime, energy and clean-tech industries.
In addition, multiple insights have been published to provide perspectives on the market.
27