LM2X Installation

IWP15

Generator Lube Oil Skid Installation

GE ENERGY

GENERAL GUIDELINES
Purpose/Scope

This work package encompasses all


requirements for installing the Generator Lube
Oil (GLO) skid, to include foundation preps,
setting skid, connecting piping, ship loose
items and grounding the skid.
Precautions
Only trained and authorized persons shall be permitted to
operate a hoist/crane. Lifting equipment shall not be loaded
beyond its rated load capacity. This includes
superimposed weight on load block or hooks and any
lifting devices such as chains and slings. If hoisting
equipment is used in placing and leveling equipment,
assure it is rated to support, as minimum, the total gross
weight of equipment to be lifted. Hoisting equipment
rated between two and four times the weight of
machinery to be lifted will provide a comfortable safety
margin.

5. Special Tooling Equipment


Crane/Hoist
Hoisting Equipment

References
General Arrangement Main Unit xxx200
Lift Arrangement xxx225
Site specific sub skids engineering drawings
Suggested Manpower and Duration
1 Rigger
1 Electrician
1 Millwright
1 Crane Operator
1 Helper
Duration One Day

Avoid damaging piping, fittings, flanges, and paint or


protective coatings. When transporting rotating
machinery, maintain the rotating axis as horizontally
level as possible. Avoid subjecting equipment to
excessive shock.

TASK START DATE

Contractor Representative

TASK COMPLETION DATE

Customer Representative

GE Representative

Printed Name:

Printed Name:

Printed Name:

Printed Title:

Printed Title:

Printed Title:

GE Representative
Signature/Date:

Rev 0

Signature/Date:

Signature/Date:

Page 1 of 2

LM2X Installation
GE ENERGY

Generator Lube Oil Skid Installation

PREREQUISITES
1.

INITIALS

DATE

INITIALS

DATE

Verify IWP04 Set Generator has been completed.


TASKS

2.

IWP15

Check foundations and anchor bolts against drawings.


Verify concrete has cured in accordance with the project design specifications.
Verify anchor bolts are positioned correctly in accordance with drawings.

3.

Remove dust, oil, and foreign materials by sanding and/or wire brushing.

4.

Set shims to level skid prior to setting. Height of shim must be in accordance with
engineering drawings.

5.

Set and Level Generator Lube Oil (GLO) Skid on foundation.

6.

Connect skid grounds.

7.

Secure skid with foundation bolts and tighten nuts in accordance with engineering
drawings.

8.

Install piping.

9.

Install remaining ship loose items.

10.

Verify the following records have been completed;


Equipment Installation Log
Concrete Specifications
Auxiliary Skid Survey Data
Fastener Torque Records
Ground-Earthing Inspection

Rev 0

Page 2 of 2