Escolar Documentos
Profissional Documentos
Cultura Documentos
2.
3.
4.
B1
T1
B2
Transformer
Protection Zone
T2
B4
B6
Feeder
Protection Zone
B9
G1
B12
B8
B3
B5
T2
B7
B10
G2
F2
B11
F1*
Motor
B15
B14
T4
B13
Transformer
Protection Zone
Nature
Of Faults
Electrical
Economic
Power System
Characteristics
Functional
Importance of Equipment
Sensibility
To Instability
Physical
Maintenance
facilities
Distance between
Relaying Points
Accommodation
Operating
Condition
Current
Transformer
Voltage
Transformer
Capital Cost
Of Equipment
Effect of
Fault 0n other
Equipment
Fault Set.
And Time of
Operation
Treatment
Of System
Neutral
Stability
of
Protection
Relative Cost
Of Protection
System
Relay and
Ancillary
Equipment
Effect of
Fault 0n other
Equipment
Effect of
Fault 0n other
Equipment
Reliability
Selectivity or Discrimination
Speed
Simplicity
Economic
VALUE
COST
OF
VALUE
PENCE
/UNIT
RELIABILITY
CB
TC
Tripping direction
Station
Battery
NC
VTs
CT
Relay
Protected
Circuit
PG FOULT
PP. FOULT
PPG FOULT
PPP.
FOULT
Time
CT
CT
CB
CB
PT
PT
Feeder
Feeder
TC
TC
Serine
Serine
TC
TC
Indication
Indication
Power S.
Power S.
AC
AC
Relay
Relay
DC
DC
etc
etc
-
Electromagnet Relay
Plunger type
Hung Armature Type
Induction Relay
Disc type
Cup Type
Operates T
1
IP
If
O
Restrains
Re(I)
Very Inverse
Extremely Inverse
Time
Inverse
Instantaneous
Time of relay R1
Time of relay R2
CDT
CDT
Distance
3
2
B3
1
B2
B1
G
F
For the fault shown, the relay tripping breaker B1 operate quickly at time T1,
Followed by the relay controlling B2 and B3 so that B1 operates before B2
and B2 before B3. Therefore, the operating time T2 of the relay at bus 2 can be
expressed as:
T2 = T1 + CDT
(1)
CDT = ( Operating time of breaker B1) + (error margin) (2)
Similarly, the operating time T3 of the relay at bus 3 can be expressed as
T3 = T2 + CDT
(3)
EXAMPLE :
Show the one line diagram of a 13,2 kV radial system 3 phase. The maximum (threephase) fault currents at buses 1, 2, 3, are 2400, 2700, and 3000 A respectively.
The operating time of each relay is six cycles.
Use three CO-7 relays per breaker and determine the CTS and TDS of each delay.
I3
CT
R3
I2
600/5
CT
I1
R2
400/5
S3 = 7,5 MW
CT
R1
300/5
S2 = 2,5 MW
Solution
The load currents at each of the three bus are:
I l1
4.5 x10 6
196.82 A
3,
3 13.2 x10
Il 2
2,5 x10 6
306.17 A
3
3 13,2 x10
Il3
7.5 x10 6
634.21A
3
3 13,2 x10
S1 = 4,5 MW
Using the given CT ratio, the corresponding relay currents due to load currents can
be found as:
196.82
I l . R1
3,28 A
300 / 5
306,17
I l .R 2
3,83 A
400 / 5
634,21
I l .R 3
5,29 A
600 / 5
The available CTS setting for the CO-7 relay are given in Figure are: 4,5,6,7, 8, 10 and 12 A.
Therefore, the CTS setting for the relay R1, R2, and R3 are select as:
CTS1 = 4 A
CTS2 = 4 A
CTS3 = 6 A
Operating time
5
Time dial setting
11
4
10
3
5
8
6
2
3
2
1
1
1/2
0 1
8 10
12 14 16 18 20
TDS setting for each relay using the maximum fault current . Relay R1 is at the end
of the radial system.
The fault current as seen by the relay R1 can be determined as:
I f , R1
2400
40 A
300 / 5
I f , R1
40
10
CTS1 4
Since the fastest possible operation is desirable, the smallest TDS is selected.
Therefore, the TDS for relay R1 is
TDS1 =
The operating time for relay R1 can be read from the associated curve in figure as
T1 = 0, 15 s
In order to set relay R2 as a backup relay, to respond to the balanced three phase
fault at bus 1, it is assumed that the error margin is 0,3. Therefore, its operating
time T2 can be found from equation (1) and (2)
T2 = T1 + 0,1 + 0,3 = 0.55 s
The fault current for a fault bus 1 as a multiple of the CTS at bus 2 can be found from
f R1
CTS
40
10
Therefore, from the characteristics given in figure , for the relay R2 for 0,55 s operating time
And 10 ratio, the TDS can be determined us
TDS2 = 2,3
The next step is to determine the setting for relay R3. A three phase fault at bus 2 produces a fault
Current of 2700 A. Therefore,
2700
33,75 A
I f , R2
400// 5
and
f R2
CTS
33,75
8,44
4
A new curve for the time dial setting of 2,3 can be drawn in figure between the two curves shown for
The time dial setting of 2 and 3, then the operating time of relay R2 can be found from this new curve
for the associated multiple of the CTS as 0,60 s.
Therefore, permitting the same CDT for relay R3 to respond to a fault at bus 2 as for relay R2
responding to a fault at bus 1,
f R2
CTS
3000
4,17
(600/5) 6
Therefore, for relay R3 for 1,0 s operating time and a 4,17 ratio, the TDS can be determine as
TDS3 = 2,8
Conclusion
1. The evaluate short circuit of the protection system therefore we
have to utilize characteristic over current relay , adjustable
settings on all inverse-time relays.
a. The current Tap Settings (CTSs)
b. The Time Dial Settings (TDSs)
2 A three-phase fault under maximum generation causes the
maximum fault current and a line to line fault, where as
under minimum generation it causes minimum fault
current. Thus, the relay must respond to the fault current
between these two extreme values.
3 The time interval that necessary between to adjacent relay
is called the Coordination Delay Time (CDT). It is the
minimum interval that permits a relay and its circuit
breakers to clear a fault its operating zone
4. The over load protection therefore, setting relay bus on
nominal current less than current transformer setting, see
example