WORK PROCEDURE

PROJECT: PROJECT NAME


SECTION:
FOUNDATIONS
SUBJECT:
CONTROL OF SEWERAGE AND SURFACE WATER
DRAINAGE

Ref No. FOUN/06


PAGE 1 OF 2
DATE OF ISSUE
Dec.2012
BY:
QA/QC ENGINEER
APPROVED BY:
QHSE MANAGER
ACTION

1.

VERIFY

SCOPE
This procedure covers controls to be carried out during
construction of underground sewerage and surface
water drainage works.

2.

PROCEDURE

.1

All sewerage and surface water drainage works will be Project


carried out in accordance with the contract Engineer
specification and good practice.

Request
for
Informatio
n

Where specifications are not provided or are


incomplete, the matter shall be referred back to the
Consultant for additional information.
.2

Depending upon the complexity of the work, and the Project


requirements of the PQP, a method statement shall be Engineer
prepared and approved by the Consultant which shall
include:
i)
ii)
iii)
iv)
v)
vi)
vii)

.3

.4

Proposed plant and equipment.


Jointing technique.
Trench support (in case of deep excavation).
Manufacturers jointing and installation details
and test certificates (where relevant).
Sequence of activities.
Compaction method and quality of fill material.
Test plan.
Store-

keeper/Sit

Check delivery order and certificates against the e


specification and examine marks, labels and condition Engineer
of material and components.
Unload and handle materials and components with
care to minimise damage and soiling.

Storekeeper/Sit
e
Engineer

Method
Statement

WORK PROCEDURE
PROJECT: PROJECT NAME
SECTION:
FOUNDATIONS
SUBJECT:
CONTROL OF SEWERAGE AND SURFACE WATER
DRAINAGE

Ref No. FOUN/06


PAGE 2 OF 2
DATE OF ISSUE
Dec. 2012
BY:
QA/QC ENGINEER
APPROVED BY:
QHSE MANAGER
ACTIO
N

VERIFY

.5

.6

.7

.8

Before commencing excavation, fence or board the


area of work so as to prevent unauthorised access.
Provide
adequate
safeguards,
e.g.
gangways,
handrails, notices or direction boards and lighting at
night.
Contact local authority departments to obtain details
of existing underground services. Proper marking will
be employed on the site to avoid damage to any
adjacent services.

Provide adequate trench support to retain the sides of


excavations and ensure the safe and proper
construction of works and completion of backfilling.

Site
Engineer/
Safety
Officer
Site
Engineer

Site
Engr/Gen.
Foreman

FOUN/06/A,
Records/
Drawings
obtained
from local
department
s
FOUN/06/A

Site
Engr/Gen.
Foreman

Spoil heaps stacked material and vehicles to be kept at


a distance of more than the trench depth from the Site
Engr/Gen.
trench.
Foreman

.9

Temporary supports to excavations will be maintained


in position until sufficient backfill has been placed and Gen.
compacted to ensure the stability of the sides of the Foreman
excavation.

Test Plan

Site

.10

Employ the proper jointing method as recommended Engineer


by pipe manufacturer. Ensure that jointing faces are
dry, clean and free from soil or bedding particles.

.11

Finalise an intermediate test plan and water testing to


be done to check water tightness of pipeline.
QA/QC

3.

DOCUMENTATION

.1

Appendix FOUN/06A and Appendix FOUN/06/B, shall be


used to monitor drainage construction. Approval to
proceed will be given by the QA/QC.

Check
sheets

PROJECT: PROJECT NAME

SITE NO.:

CHECK SHEET FOR SEWERAGE AND SURFACE WATER


DRAINAGE
SUBCONTRACTOR:

Sheet No.

CLIENT

SECTION OF WORK ____________________________ LOCATION _________________

STAGE
PIPEWORK OR
CHANNEL

Checke
d
by

ITEM
1. Set line and level.
2. Check location of underground services
before
commencement of excavation.

DATE

SU
SE

3. Check inverts levels and gradients.


SU
4. Check correct diameter and material.
Also check the compatibility of pipes,
fittings and accessories for jointing e.g.
ring seals, solvent cements, lubricants.
SE

GULLEY
CONNECTION

5. Check position and no. of connections.

SE

6. Check availability of trench support


material.

GF

7. Check bedding and granular surround.

GF

8. Backfill to specification
material/compaction.
9. Ensure protection of laid pipeline from
damage by construction traffic.
10. Pipe run rodded and tested.

SE

APPROVAL TO PROCEED

QA/QC

1.
2.
3.
4.
5.

SE
SE/SU
GF
GF
GF

Check
Check
Check
Check
Check

SE
PE/MEP

correct gulley used.


position and level of gulley.
correct surround.
gulley grid.
gulley cleaned out.

APPROVAL TO PROCEED

QA/QC

QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site Engineer,


SU Surveyor, MEP MEP Coordinator, GF General Foreman

PROJECT: PROJECT NAME

SITE NO.:

CHECK SHEET FOR SEWERAGE AND SURFACE WATER


MANHOLES

Sheet No.

SECTION OF WORK: ____________________________ MANHOLE No: ______________

STAGE
PREPARATION

ITEM

Checke
d
by

1. Set position of manhole and base level.

SE/SU

2. Check base concrete.

GF

3. Check correct base rings (outlets).

SE

4. Check rings/reducer/step irons.

SE

5. Checks cover slab level and location of


opening.

SE

6. Check concrete surround.

GF

7. Check correct cover/brick


bedding/concrete haunch.

GF

8. Check manhole benching.

GF

9. Clean out manhole.

GF

DATE

APPROVAL TO PROCEED
QA/QC

QA/QC Quality Assurance/Quality Control, SE Site Engineer, SU, - Surveyor, GF General


Foreman