01 71 23 - FIELD ENGINEERING
May 2013
Project :
Location :
DIVISION
SECTION 01 71 23
GENERAL REQUIREMENTS
-
Field Engineering
Contractor shall pay for services of a licensed surveyor who shall fully and
completely layout all work required by the Contract.
B.
The Contractor shall furnish certifications from a licensed surveyor that all
portions of the work are located in accordance with Contract Requirements
and at elevations required thereby.
C.
Identify and locate existing control points, boundary lines, property lines,
corner stakes indicated on the drawings before starting work. Promptly
notify Project Representative of any discrepancies within twenty-four (24)
hours of discovery of same.
2.
Promptly verify and certify to lines and levels of any portion of subdivision
of work at any time it may be deemed necessary by the Project
Representative. Any deviation from the Drawings shall be certified to the
Project Representative within 24 hours of discovery of same.
3.
Locate and protect control points before starting work and preserve all
permanent reference points during construction.
a.
b.
c.
Field Engineering
01 71 23
of 2
Page
5.
6.
a.
Site improvements:
- Pavements
- Stakes for grading, fill and topsoil placement.
- Utility slopes and invert elevations.
b.
c.
d.
Field Engineering
01 71 23
of 2
Page