Escolar Documentos
Profissional Documentos
Cultura Documentos
In 1974 North Cormorant field accumulations were discovered by Shell U.K. The
field was initially owned by Shell U.K and Esso until 2008 when TAQA Britani
purchased it, along with several other North Sea assets. The purchase included all
equity, associated infrastructure and production licenses.
The North Cormorant platform was installed in 1981 and production commenced the
following year . It is a single fixed platform with steel jacket. The platform has two
production trains for separation of oil, gas and water. It has the design capacity to
process around 180,000 barrels of crude a day. The processed oil from North
Cormorant platform is sent to TAQA's Cormorant Alpha platform located in the South
Cormorant field. The oil is transported via the Brent System Oil Pipeline to the
Sullom Voe terminal for sale.
North Cormorant production rate was highest in its early years, rapidly increasing
from 1982 up until 1984 where production rates peaked. Productions rates then started
to decline sharply until 1991 when they reached a plateau. The decline was caused by
the reservoir pressure dropping off quickly, due to weak aquifer support.
Up until the exchange of operator in 2008 Shell U.K and Esso carried out a number of
developments in order to maintain reservoir production. Shell and Esso had more
profitable projects to concentrate on, so subsequently sold a number of their North
Sea assets to the smaller company TAQA. This included the whole Cormorant field.
Since ownership TAQA has been carrying out a number of development strategies
aimed at increasing production. Simultaneously upgrading platform facilities.
Introduction
The Cormorant field is located 95 miles northeast of the Shetland Islands at a depth of
about 500 ft in the U.K. North Sea. It was discovered by exploration well 211/26-1 in
1972; the fifth field to be discovered in the Northern North Sea. It straddles blocks
211/21a and 211/26a and is made up of four discrete accumulations spread along a
major N-S trending fault terrace. Oil is produced from the sandstones belonging to the
Brent Group. The sedimentary rocks comprising the Brent Group were deposited in a
fluvial-wave dominated delta system during the Middle Jurassic. The reservoir has a
typical gross thickness of 250-300 ft, locally increasing to 550 ft over faults active
during sedimentation. Reservoir porosity varies from 16-28%, with average
permeability ranging from tens of md to 1300md. The accumulation contains highly
under-saturated crude (34-36 API ) oil which was initially over pressurised by some
1000-1270 psi. (Gluyas, J.G, 2003)
For development purposes the whole Cormorant field was split in half; north and
south. The northern part is developed by the North Cormorant platform and the
southern part the south platform.
On 7 July 2008 TAQA Britani Ltd purchased several North Sea assets. The purchase
included all equity, associated infrastructure and production licenses relating to the
Tern, Eider, Cormorant North, South Cormorant, Kestrel and Pelican fields. The
420-million investment allowed for a number of projects designed to revive
production from these facilities and extend economic field life into 2020 and beyond.
(Taqa)
Within two years of taking over, oil production from the fields including Cormorant
North, increased from below 25,000 bbl/d in 2008 to 40,000 bbl/d, Some of this was
due to the re-establishment of the dormant drilling rigs on the North Cormorant
platform which led to five infill wells being drilled last year on the North Cormorant
field. (Gluyas, J.G, 2003)
In 2011 North Cormorant underwent a integrated control system replacement along
with water injection upgrades. This year, TAQA gained FDP approval and announced
that they aim to drill 2 new platform production wells into the North Cormorant Block
4 field. During the same drilling campaign 1 appraisal well will be performed on the
Cormorant East field, also drilled from the North Cormorant platform. The second
North Cormorant production well will be dependent upon the results from the
Cormorant East appraisal well. Should the appraisal well into Cormorant East
demonstrate a deep contact and well developed Brent sequence and if the FDP is
approved, then the appraisal well will be completed and a further injection well into
Cormorant East will be drilled. These activities will be performed at the expense of
the second North Cormorant production well. (Offshore Technology 2014)
The processed oil from North Cormorant platform is sent to TAQA's Cormorant
Alpha platform located in the South Cormorant field. The oil is then transported via
the Brent System Oil Pipeline to the Sullom Voe terminal for sale
Event
1972
1974
1975
1979
1981
1982
1983
1984
1984
1991
New year storm caused structural damage to the platform. (lost part of
the passive fire protection). Production shut down for around 6 weeks
in April and May. Third 3D seismic survey required.
1995
2008
2010
2011
2014
2018
Production
North Cormorant commenced production in February 1982. Liquids production has
been disappointing. Although flow and production rate was initially good the
reservoir pressure rapidly dropped. To counter this the drilling programme was altered
to include more water injection wells at an earlier stage. This had a consequence of
lowering North Cormorants production peak production from 122,655 barrels/day
1984 to 106,000 barrels/day in 1985. There after production continued to decline until
it reached at plateau of 30,000 barrels/day in 1991.
North Cormorant produces gas volumes in association with its oil. It started gas
production in 1982. It produced around 40mmcfd at peak. After fuel requirements
sales volumes are much less than this and peak sales production of 29mmcfd occurred
in 1986. (Wood Mackenzie 2003)
Oil and gas production from the Cormorant area was severely limited on 8 th April
1989. This was due to a gas leak on the Alpha platform. The accident occurred during
the time an emergency shut down valve was being installed on the gas export line that
leaves Cormorant Alpha. Gas production from Cormorant had been cut and a plug
fitted to the severed line during installation of the ESV. The plug became dislodged
resulting in the gas leak at the top of the C4 leg of the platform. An explosion took
place but no fire occurred along with no casualties. The Brent pipeline system which
pass through the C4 leg, before leaving for St Fergus were immediately shut down.
Production from all Cormorant fields recommenced 6 weeks later. (Offshore
technology 2011)
During 1991 a new year storm caused structural damage to the Cormorant North
platform. Causing it to lose a part of the passive fire protection. Production shut down
for around 6 weeks in April and May. (Gluyas, J.G, 2003)
As shown in the graph below. Oil production slipped steadily from a peak of
6,258.499 bbls/yr of oil in 1986 to below 522,488 bbls/yr in 2008. When TAQA
Britani took charge they initially broke the decline slightly increasing production to
641,758 in 2010. During 2011 and 2012 production dropped again to 463, 419bbls/yr.
In 2013 there was a slight increase in production to 509,516 bbls/yr. (Decca 2014)
Due to the current development by TAQA production is estimated to
increase.
(Taqa 2014)
Map
References
Cormorant East - Offshore Technology. 2014. Cormorant East - Offshore Technology.
[ONLINE] Available at: http://www.offshore-technology.com/projects/cormoranteast/
Cormorant oilfield - Wikipedia, the free encyclopedia. 2014. Cormorant oilfield Wikipedia, the free encyclopedia. [ONLINE] Available at:
http://en.wikipedia.org/wiki/Cormorant_oilfield. [Accessed 21 October 2014].
Decca. 2014 Department of Energy and Climate Change.
Gluyas, J.G, 2003. United Kingdom Oil and Gas Fields. 1st ed. USA: The Geological
Society of London
Home - OnePetro. 2014. Home - OnePetro. [ONLINE] Available at:
https://www.onepetro.org/
Mackenzie, Wood Mackenzie, 2003. Cormorant. UK Upstream Service
TAQA . 2014. TAQA . [ONLINE] Available at: http://www.taqaglobal.com.
[Accessed 21 October 2014].
DECLARATION