Escolar Documentos
Profissional Documentos
Cultura Documentos
1000MWp Plant data portion of the entire electric grid power (more than
5%), one can't disregard its influence on the grid
Number of collectors 20,000
Collector dimensions 20mx12m stability, and the energy supplied must respect
Area of collector 240 msq
standards of utility power plants. This is not possible
Collector power 50 KWp
Plant aperture 4 kmsq for large solar plants because of the inherent
Real estate covered 10 kmsq
fluctuating power delivered by the sun. Thus, a storage
Energy production in Israel 2 B KWh
@2394 KWh/msq/year facility is required to ensure steady state power
Energetic Concentration 500 suns
delivery to the grid.
Two axis tracking mount
The energy sources (solar plant, baseload and storage)
Advantage of CPV System must generate and supply the entire energy demand
The CPV system has the following advantages:
during day and night.
1. The land required is 100KW per 1000msq
As the solar plant capacity is built up along the years, it
2. The land can have slopes up to 10%
will start delivering energy during the day only. This is
3. The land can be rocky
the case we are dealing with. After the production
4. The land can have dual use
capacity increases beyond the day consumption, excess
5. The CAPEX is less than $0.5/KW (a 2000MW/y
power is stored in the batteries and delivered during
production line will cost less than $1,000M)
night. During the day, the storage plant is used to keep
The issue of land availability is of major importance
a continuous supply of energy to the grid during
for large systems in general, and more specifically for
intermittent cloudy periods.
Israel.
The storage process is reversible and the cycle loss
The CPV system uses half the land required by other
(charge – discharge) is reasonable (75% efficiency).
technologies. The first four attributes supports this
The storage plant capacity is built in parallel with the
statement
solar plant capacity. This is the place to state that ANY
PV or CPV plants with an installed capacity in excess
Project Status
MST has completed in August 2009 the development of of 5-10% of the grid power needs a storage capacity
a 50KWp tracker that is installed in Arad and supplying identical to their capacity to protect against grid
electricity to the grid. See Figure 1. The measured collapse in case of power loss due to clouds.
company) a preliminary design of a highly automated Israel and will be produced and supplied by them in
1500MWp production line. This design and the proposal cooperation with MST. The estimated production cost
from subcontractors are at the basis of the cost estimate of the storage batteries is $650/KW within 6 years.
0.15
capacity of 2000MW per year.
We assume that the production lines will be completed
0.10
2000
demand is doubling the power and energy within 30 The year 4 we install 1000MWp and 1000MW storage
years (compound increase of 2.42% per annum). and thereafter 2000MW per year of each, during an
Our aim is to produce within 15 years solar energy additional period of 10 years.
electricity that constitutes 50% of the energy required The reason that the amount of storage is identical to the
by the grid, namely 40Bkwh, during the day only. This amount of solar is that the storage must provide full
means that we have to install within 15 years instantaneous backup to the solar power.
who plans to transform the private car vehicles into and storage, compared with the projected grid power
CPV solar plants Storage plants Grid capacity Years after start
Cash in hand accumulated M$
Credit Line required
Figure 4: Accumulated installed solar power and storage 10000
0
produced energy.
-5000
M$
-10000
90000
-15000
80000
70000
-20000
60000 -25000
50000 -30000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
40000
Years after start
30000
20000
10000
Figure 6: Cash status before Tax, 0% interest.
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
The maximum exposure with no interest is at years 10
Solar produced energy Grid required energy Years after start
to 14 at a level of $25B. The credit line is zero at year
Figure 4: Solar Energy produced and required 18.
Produced energy as % of required
60%
40%
In order to cover the increased tariff required by the
30%
solar energy (See Figure 2), the tariff of IEC must be
20%
increased.
10%
The calculation of the new tariff took into account the
0%
additional cost of solar energy ($0.2/kwh instead of
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Figure 5: Solar Energy produced as % of required Figure 7 depicts the IEC tariff to achieve this.
One can see that during 17 years the tariff increase is
Figures 4 and 5 depict the result of the installation rate from $0.12/kwh to $0.16/kwh. The blue tariff is the
defined in Figure 3. One can see that after 14 years in projected tariff increase for fossil electricity production
2023, we supply 50% of the required energy at that of 2% per year. One can see that the required tariff to
During 6 additional years, without additional projected tariff escalation. After year 17 the tariff drops
50%.
5
Tariff required to cover solar energy cost $/kwh
Funding. Solar energy infrastructure is funding
Basic present tariff $0.12/kwh
0.20
intensive. As we have shown, a credit line of about
0.18 $25B is required to execute the proposed plan. The
0.16
0.10
0.00
20% of the required installation rate required by this
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
6,000
4,000
2,000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Hurdles to overcome
Land. A 1000 MWp CPV solar plant requires 10 kmsq
(10,000 dunam) of land. 20,000MWp require 200
kmsq of land. This figure represents 1% of Israel area
or 1.6% of the Negev area.
Land exists and must be provided in a timely manner to
allow building this project. Regulatory bureaucratic
issues must be solved in a timely manner.
6
Summary and conclusions The project will handsomely reward the Country and
the People by providing freedom of energy supply,
The Energy is a major issue to ensure Israel's long term
saving on foreign currency expense and providing tens
existence.
of thousands of new jobs mainly in the Negev
The world projected Energy crisis threatens Israel
This industry will develop into a major Export one.
within a 30 years timeframe.
The sun is the only energy resource of Israel.
The CPV system developed by MST in Israel has the
The solution is there and The Government
technical and financial attributes to solve this problem. must only stand up to the challenge.
The Government should adopt this project as a It is its duty to do so.
National Infrastructure project, facilitate its funding
and allocate it the adequate National priorities.