Você está na página 1de 528

Presents

PMP Certification Test Preparation


PMBOK Fifth Edition

PMP Prep: PMBOK 5th - 2013

The PMP Certification Test Preparation


Objectives
Provide a framework for structuring the Project
Management Body of Knowledge;
Identify the most generally accepted practices
within the discipline of project management;

Reveal Exam Tips;


Explain how to apply for and take the PMP exam

Page i

PMP Prep: PMBOK 5th - 2013

The World of Business Management Consultants


Bristol
Brussels
Houston

Istanbul
Singapore

Warsaw Moscow
Chicago
Bristol Frankfurt
Milan
Phoenix Washington DC
Atlanta
Lisbon

Vancouver

Seoul
Tokyo
Beijing Taipei
Shanghai
Hong Kong

Mumbai

Page iii

PMP Prep: PMBOK 5th - 2013

Our Learning Institutions

Page iv

PMP Prep: PMBOK 5th - 2013

Three Day Course Schedule

Day One
Introduction and overview
of PMI, PMP and PMBOK

Day Two

Planning Processes
(continued)

Day Three
Monitoring & Controlling
Processes
Closing Processes

Initiating Processes

Professional Responsibility
Executing Processes
Planning Processes
Practice Test

Preparing for the PMP

Practice Test

Sample Test

Page vii

PMP Prep: PMBOK 5th - 2013

Introduction and Overview of the PMP

PMP Prep: PMBOK 5th - 2013

Organization of this Workbook

The PMBOK Fifth Edition is organized by Knowledge Area.


We believe that people learn the same way
they work on-the-job: by project phases.

So, this Test Preparation workbook is organized


chronologically, start to finish, from Initiating a
project through to Closing the project.

Page 1

PMP Prep: PMBOK 5th - 2013

Organization is Chronological

Monitoring &
Controlling Processes
Planning
Processes

Closing
Processes

Initiating
Processes

Executing
Processes

Page 1

PMP Prep: PMBOK 5th - 2013

New Test and New PMBOK Edition

The PMBOK 5th Edition was released in January


2013. The test changed again on July 31, 2013.
A new Knowledge Area was introduced:
Stakeholder Management.

Page 2

PMP Prep: PMBOK 5th - 2013

The T&T CD ID is E1091


and Awards 11 PDUs

Qualification Requirements

PMTestOnline is C4070
and Awards 11 PDUs

Graduate, 4-Year Degree


A minimum of 4500 hours PM
experience within the past 8
years

+
Non-Graduate, or 2-Year Degree

35 contact hours
(PDUs) of PM
education

Eligibility to take
the PMP
examination

A minimum of 7500 hours PM


experience within the past 8
years

This Course ID is E1078


and Awards 24 PDUs
Page 2

PMP Prep: PMBOK 5th - 2013

PMBOK Fifth Edition and the New Test


The PMBOK Fifth Edition was introduced in January 2013, and the
new fifth edition test started on July 31, 2013.
The PMP examination consists of 200 questions, with a four hour
time limit

Thats 72 seconds (or 1.2 minutes) per question

This training course will give you everything you need,


with a little self-study, to pass the PMP examination

Visit www.pmi.org, download PMP Certification Handbook

Page 2

PMP Prep: PMBOK 5th - 2013

PMBOK 5th Edition PMP Test Domain Content

Project Initiation
Project Planning
Project Execution
Project Monitoring & Control
Project Closing

13%
24%
30%
25%
8%

To pass, you need to get a minimum of 122


questions correct out of 200 questions (61%)
Pass rate on the 4th Edition test is about 74%

Page 2

PMP Prep: PMBOK 5th - 2013

Apply to PMI to take the test,


Schedule a date with Prometric
Submit your application to Project Management Institute (PMI)
http://www.pmi.org/Certification/Project-Management-Professional-PMP.aspx
Log in with your User Name and Password
Follow the instructions

Schedule a test date with Prometric


http://www.prometric.com/PMI/default.htm

Control is through audit


http://www.pmi.org/info/PDC_PMPHandbook.pdf
PMI may audit when you pay your exam fee to PMI. If you cancel or reschedule
within 30 days of the test, there is a fee of $70; within 2 days, you forfeit the entire fee.
Candidates have three (3) opportunities to pass the exam in one year. If they
do not pass any, they must wait one (1) year from the date of the last attempt.

Page 3

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions requiring experience more than study
You are advised that a major purchased part on your project
will be delayed. What do you do?
A.
B.
C.
D.

Ignore it. It will go away


Notify your boss
Let the customer know about it and talk over options
Meet with the team and identify alternatives

D. Meet with the team and identify alternatives

Page 4

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Information that does not matter (distractors)
Study show that every time you double the production of
widgets, unit cost goes down by 10%. Based on the study,
the company concludes that the production of 4,000 widgets
will cost $19,000. This illustrates:
A.
B.
C.
D.

Learning curve effects


Law of diminishing returns
The 80/20 rule
Bottoms up cost estimating

A. Learning curve effects

Page 4

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions designed to make you make you think carefully
The theory optimum quality level is obtained when
Incremental revenue from product improvement equals
incremental cost to secure it comes from
A.
B.
C.
D.

Quality control analysis


Marginal analysis
Standard quality analysis
Conformance analysis

B. Marginal Analysis

Page 4

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions using unfamiliar words and expressions
Parking places, corner office/door, and a key to the executive
bathroom are example of:

A.
B.
C.
D.

Perquisites
Overhead
Herzbergs motivators
Entitlements

A. Perquisites (aka Perks)

Page 5

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions requiring understanding of the subject matter
Decomposing deliverables into smaller manageable activities
Is complete when:

A.
B.
C.
D.

Project justification has been established


Change requests have occurred
Cost and duration estimates can be developed for each work
element at this level
Each work element is found in the WBS dictionary

C. Cost and duration estimates can be developed


for each work element at this level

Page 5

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions requiring study (memorization) more than
experience
Conflict resolution techniques that may be used on a project
include:
A.
B.
C.
D.

Withdrawing, compromising, controlling, and forcing


Controlling, forcing, smoothing, and withdrawing
Confronting, compromising, smoothing, and directing
Smoothing, confronting, forcing and withdrawing

D. Smoothing, confronting, forcing and withdrawing

Page 5

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


New thinking about a known topic

In a matrix organization, information dissemination is most


likely to be effective when?
A.Information flows both horizontally and vertically
B.The communication flows are kept simple
C.There is inherent logic in the type of matrix selected
D.Project managers and functional managers socialize

A. Information flows both horizontally and vertically

Page 6

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions requiring calculation and knowledge of formulae
A project was estimated to cost $1.5 million and scheduled to last
six months. After three months, the earn value analysis shows
the following:
BCWP (EV) = $650,000
BCWS (PV) = $750,000
ACWP (AC) = $800,000
What are the schedule and cost variances?
A.
B.
C.
D.

SV = +$100,000 - - - CV = +$150,000
SV = +$150,000 - - - CV = -$100,000
SV = -$50,000 - - - - CV = +$150,000
SV = -$100,000 - - - -CV = -$150,000

D. SV=-S100,000 : CV=-$150,000
Page 6

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions designed to take up your time
Youve been engaged to manage a project. The estimated cost of the
project is $1,000,000. The project sponsor has approved this amount.
Your earned value calculations indicate that the project will be
completed on time and under budget by $200,000. Based on your
calculation, your personal profit will decrease by $2,000. Given
estimated decrease in personal profit, what action should you take?
A.
B.
C.
D.

Invoice for the full $1,000,000 based on contract and to cover profit
Add tasks to improve the outcome and increase the actual project cost
Inform the end-user that you can add features to the project in order to
use the entire budget
Communicate the projected financial outcome to the project sponsor

D. Communicate the outcome to the project sponsor

Page 6

PMP Prep: PMBOK 5th - 2013

Types of questions to expect


Questions using acronyms you need to understand
There are several different types of network analysis tools for
determining critical path. Which method for analysis is also called
Method of Moments?
A.
B.
C.
D.

GERT
CPM
PERT
Monte Carlo

C. PERT (Program Evaluation and Review Technique)

Extra

PMP Prep: PMBOK 5th - 2013

Mapping Process Groups to Knowledge Areas


Process Groups
Knowledge Areas
4. Project Integration
Management

Initiating
4.1 Develop Project Charter

Planning
4.2 Develop Project
Management Plan

Executing
4.3 Direct & Manage
Project Work

Monitoring &
Controlling
4.4 Mon/Ctrl Proj Work
4.5 Perform Integrated
Change Control

5. Project Scope
Management

5.1
5.2
5.3
5.4

Plan Scope Mgt.


Collect Requirements
Define Scope
Create WBS

5.5 Validate Scope


5.6 Control Scope

6. Project Time
Management

6.1
6.2
6.3
6.4
6.5
6.6

Plan Schedule Mgt.


Define Activities
Sequence Activities
Est. Activity Resources
Est. Activity Durations
Dev. Schedule

6.7 Control Schedule

7. Project Cost
Management

7.1 Plan Cost Mgt.


7.2 Estimate Costs
7.3 Determine Budget

8. Project Quality
Management

8.1 Plan Quality Mgt.

8.2 Perform Quality


Assurance

9. Project Human
Resource
Management

9.1 Plan Human


Resource Mgt.

9.2 Acquire Project Team


9.3 Develop Project Team
9.4 Manage Project Team

8.3 Control Quality

PMBOK 5th Edition,


Table 3-1, Page 61

10.1 Plan Communications


Management

11. Project Risk


Management

11.1 Plan Risk Management


11.2 Identify Risks
11.3 Perform Qualitative
Risk Analysis
11.4 Perform Quantitative
Risk Analysis
11.5 Plan Risk Response

12. Project Procurement


Management

12.1 Plan Procurement Mgt.

12.2 Conduct Procurements

12.3 Control Procurements

13.2 Plan Stakeholder


Management

13.3 Manage Stakeholder


Engagement

13.4 Control Stakeholder


Engagement

Page 17

13.1 Identify Stakeholders

4.6 Close Project


or Phase

7.4 Control Costs

10. Project
Communications
Management

13. Project Stakeholder


Management

Closing

10.2 Manage Communications

10.3 Control Communications

(47 Processes)

11.6 Control Risks

12.4 Close Procurements

PMP Prep: PMBOK 5th - 2013

Mind Maps: Integration

Handout

PMP Prep: PMBOK 5th - 2013

Mind Maps: Scope

Handout

Scope

PMP Prep: PMBOK 5th - 2013

Time

Handout

PMP Prep: PMBOK 5th - 2013

Mind Maps: Cost

Handout

PMP Prep: PMBOK 5th - 2013

Project
Quality
Management
Mind Maps: Quality

Handout

PMP Prep: PMBOK 5th - 2013

Mind Maps: Human Resource

Handout

PMP Prep: PMBOK 5th - 2013

Communication

Handout

PMP Prep: PMBOK 5th - 2013

Risk

Handout

PMP Prep: PMBOK 5th - 2013

Procurement

Handout

PMP Prep: PMBOK 5th - 2013

Stakeholders

PMP Prep: PMBOK 5th - 2013

So, what is a project?


A project is a temporary endeavor undertaken to create a
unique product, service or result.
A program is a group of related projects, subprograms,
and program activities managed in a coordinated way to
obtain benefits not obtainable from managing them
individually.
A portfolio is a collection of projects, programs, and
operations managed as a group to achieve strategic
objectives.
An operation is an organizational function performing the
ongoing execution of activities that produce the same
product or provide the same repetitive service

Page 7

PMP Prep: PMBOK 5th - 2013

The Triple Constraint, plus some.

PMBOK 5th Edition, Page 6

Resource

Scope

(Budget)

(Planned Results)

Schedule
(Time)

Page 8

PMP Prep: PMBOK 5th - 2013

Organizational Governance: Linkages


PMBOK 5th Edition, Page 7

Strategic Planning
Management by Projects

Portfolio
Management

Management of
Operations

Program
Management

Project
Management

Processes,
Tools, Metrics

Page 8

PMP Prep: PMBOK 5th - 2013

Organizational Governance: Linkages


VISION

Mission

Organizational Strategy &


Goals
High-Level
Operations Planning
& Management

Project Portfolio
Planning &
Management

Management of On-Going
Operations
(recurring activities)

Management of Authorized
Programs & Projects
(projectized activities)

(producing value)

(increasing value production capability)

Organizational Resources
Page 9

PMP Prep: PMBOK 5th - 2013

Comparison: Project, Program & Portfolio


Organizational Project Management
Project

Programs

Portfolios

Scope

Projects have defined objectives. Scope is


progressively elaborated throughout the
project life cycle.

Programs have a larger scope and provide


more significant benefits.

Portfolios have an organizational scope


that changes with the strategic objectives
of the organization.

Change

Project managers expect change and


implement processes to keep change
managed and controlled.

Program managers expect change from


both inside and outside the program and
are prepared to manage it.

Portfolio managers continuously monitor


changes in the broader internal and
external environment.

Planning

Project managers progressively elaborate


high-level information into detailed plans
throughout the project life cycle..

Program Managers develop the overall


program plan and create high-level plans to
guide detailed planning at the component
level.

Portfolio managers create and maintain


necessary processes and communication
relative to the aggregate portfolio.

Management

Project managers manage the project team


to meet the project objectives.

Program managers manage the program


staff and the project managers; they
provide vision and overall leadership.

Portfolio managers may manage or


coordinate portfolio management staff, or
program and project staff that may have
reporting responsibilities into the aggregate
portfolio.

Success

Success is measured by product and project


quality, timeliness, budget compliance, and
degree of customer satisfaction..

Success is measured by the degree to


which the program satisfies the needs and
benefits for which it was undertaken..

Success is measured in terms of aggregate


investment performance and benefit
realization of the portfolio.

Project managers monitor and control the


work of producing the products, services,
or results that the project was undertaken to
produce.

Program managers monitor the progress of


program components to ensure the overall
goals, schedules, budget and benefits of the
program will be met.

Portfolio managers monitor strategic


changes and aggregate resources
allocation, performance results, and risk of
the portfolio.

Monitoring

Page 10

PMP Prep: PMBOK 5th - 2013

How do projects come about?

PMBOK 5th Edition, Page 10

Projects can come about in the following ways:


Market demand
Strategic opportunity
Social need
Environmental
Customer request
Technological advance
Legal requirement

More on selection methods later

Page 10

PMP Prep: PMBOK 5th - 2013

The Project Management Office (PMO)


A PMO is an organizational structure:
standardizes project governance processes,
facilitates the sharing of resources,
develops methodologies, tools and techniques.
Responsibilities can range from providing support
functions to direct management of projects.
Projects supported by a PMO may not be related,
other than being managed together
Project Manager
focuses on specific project objectives
controls assigned project resources
manages the constraints

Page 12

PMOs
manages major program scope changes
optimizes shared resources across all projects
manages methodologies, standards, overall risk

PMP Prep: PMBOK 5th - 2013

Types of Project Management Offices (PMO)

Supportive. Consulting role , e.g., supplying templates, best practices,


training, computer information, and lessons learned from other projects.
Control from this type of PMO is low.

Controlling. Provide support and require compliance, e.g., PM methodologies,


specific templates-forms-tools, or conformance to governance.
Control from this type of PMO is moderate.

Directive. Control projects by managing projects.


Control from this type of PMO is high.

Exam
Tip

Page 12

PMP Prep: PMBOK 5th - 2013

Project-Based Organizations (PBO)

PBOs can be created by various organizations


(functional, matrix, projectized).
They can diminish hierarchy since work is measured by
results rather than position or politics.

PBOs do a majority of their work as projects rather


than as a function, but can have functional support
areas.

Page 13

PMP Prep: PMBOK 5th - 2013

Role of the Project Manager


Project Managers
Role is to achieve project objectives. Understanding tools and
techniques is not enough. It requires general management
skills, and:
Knowledge of project management,
Performance or accomplishment,
Personal behavior and effectiveness when performing
the project including attitude, personality characteristics,
and leadership.

Page 15

PMP Prep: PMBOK 5th - 2013

The Role of the PMBOK

Project Management
Body of Knowledge

PMBOK Guide

Interpersonal
Skills

General
Management
Knowledge and
Skills

Page 15

Application Area
Knowledge,
Standards and
Regulations

Understanding
the Project
Environment

PMP Prep: PMBOK 5th - 2013

Organizational Structures
Organizational
Structures

Project
Characteristics

PMBOK Fifth Edition, Page 22

Matrix

Functional
Weak Matrix

Balanced Matrix

Projectized
Strong Matrix

Project Managers
Authority

Little or None

Low

Low to
Moderate

Moderate to
High

High to
Almost Total

Resource
Availability

Little or None

Low

Low to
Moderate

Moderate to
High

High to
Almost Total

Functional
Manager

Functional
Manager

Mixed

Project
Manager

Project
Manager

Project
Managers Role

Part-Time

Part-Time

Full-Time

Full-Time

Full-Time

Project Management
Administrative Staff

Part-Time

Part-Time

Part-Time

Full-Time

Full-Time

Who Manages
the Budget?

Page 16

PMP Prep: PMBOK 5th - 2013

Organizational Influences
Exam
Tip

Exam questions deal with matrix forms.

Strong matrix:
Weak matrix:
Balanced matrix:
Tight Matrix:

Page 17

PMBOK Fifth Edition, Page 22

The balance of power rests with the project manager.


The balance of power rests with the functional manager.
The power is balanced between the functional and the project managers.
Beware here. It has nothing to do with the matrix organization. It refers to
locating the project teams offices in the same room. Watch for this one!

PMP Prep: PMBOK 5th - 2013

Organizational Structure

PMBOK Fifth Edition, Page 22

Chief
Executive

Functional Organization

Functional
Manager

Functional
Manager

Project
Coordination

Functional
Manager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff engaged in project activities

Page 18

PMP Prep: PMBOK 5th - 2013

Organizational Structure

PMBOK Fifth Edition, Page 23

Chief
Executive

Weak Matrix

Functional
Manager

Functional
Manager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff engaged in project activities

Page 18

Functional
Manager

Project
Coordination

PMP Prep: PMBOK 5th - 2013

Organizational Structure

PMBOK Fifth Edition, Page 24

Chief
Executive

Balanced Matrix

Functional
Manager

Functional
Manager

Staff

Staff

Staff

Staff

Staff

Staff

Project
Manager

Staff

Staff

Staff engaged in project activities

Page 19

Functional
Manager

Project
Coordination

PMP Prep: PMBOK 5th - 2013

Organizational Structure

Chief
Executive

Strong Matrix

Functional
Manager

Functional
Manager

Functional
Manager

Manager of Project
Managers

Staff

Staff

Staff

Project Manager

Staff

Staff

Staff

Project Manager

Staff

Staff

Staff

Project Manager

Staff engaged in project activities

Page 19

PMBOK Fifth Edition, Page 24

Project
Coordination

PMP Prep: PMBOK 5th - 2013

Organizational Structure

Chief
Executive

Projectized

Project
Manager

Project
Coordination

Page 20

PMBOK Fifth Edition, Page 25

Project
Manager

Project
Manager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff engaged in project activities

PMP Prep: PMBOK 5th - 2013

Organizational Structure

Chief
Executive

Composite

Functional
Manager

Functional
Manager

Functional
Manager

Manager of Project
Managers

Staff

Staff

Staff

Project Manager

Staff

Staff

Staff

Project Manager

Staff

Staff

Staff

Project Manager

Project B
Coordination

Page 20

PMBOK Fifth Edition, Page 26

Staff engaged in project activities

Project A
Coordination

PMP Prep: PMBOK 5th - 2013

The Organization and its Environment


These are INPUTS to Processes
Organizational Process Assets (OPA)
OPA are assets available to the project team: (1) processes and
procedures, and (2) corporate knowledge bases. They include
plans, processes, policies, procedures, lessons learned, historical
information, schedules, risk data, and earned value data.
What have we got?
Enterprise Environmental Factors (EEF)
EEF are conditions not under the control of the team. They include
government or industry standards, organization culture,
infrastructure (facilities & equipment), human resources,
marketplace conditions, risk tolerance, politics, communication
channels, data bases, and PMIS.
What is out there?

Page 21

PMP Prep: PMBOK 5th - 2013

Stakeholders
Stakeholders are persons or organizations who may affect, be affected, or perceive that
that they are affected by a decision, activity or outcome of the project. They:
May be actively involved in the project or have interests affected by the project,
May exert influence over the project/team to satisfy strategic business objectives.
Project Governance is an oversight function aligned with the organizations governance
model and includes the project life cycle. Governance is alignment of the project with
stakeholders needs or objectives. It is critical to management of stakeholder
engagement, maximizing the value of project outcomes, and aligning projects to the
business strategy.
The Project Manager should manage the influences of stakeholders regarding project
requirements to ensure successful outcome.

Who are your stakeholders? Can you name them?


See PMBOK Fifth Edition, Pages 32-33

Pages 22-23

PMP Prep: PMBOK 5th - 2013

The Project Sponsor

The Project Sponsor is the person or group who


provides resources and support for the project
and is accountable for enabling success. The
sponsor promotes the project and serves as
spokesperson to management. They play a
significant role in project initiation and the
development of the initial scope and charter

Page 22

PMP Prep: PMBOK 5th - 2013

Project Life Cycle

Cost and Staffing Level

Starting
a Project

Organizing
and
Preparing

Project
Charter

Executing the Work

Project
Management Plan

Closing a
Project

Accepted
Deliverables

Archived
Project
Documents

Time

Page 24

PMP Prep: PMBOK 5th - 2013

Stakeholders Influence Over Project Performance

Concept

Planning

Execution

Close-Out

Value
Uncertainty (Risk)
Amount at Stake

Influence of Stakeholders

Time
Page 24

PMP Prep: PMBOK 5th - 2013

Process Groups are not Project Phases


Project Phases or Life Cycle
(Phase-end reviews of deliverables are called
Stage Gates, Phase Exits, or Kill Points)
INPUTS:
Requirements
Specification

Market
Knowledge

Basic
Concept

Technology
Appreciation

Departments
Expertise

Key Technical
Risks

Feasibility
Study

Laboratory
Model

IDEA

Basic
Concept

Requirements
Specification
Key Risk
Assessment

Marketing
Prototype
Documentation

Proof of
Principle

Proof of
Principle

Development

Production
Technology

Prototype
Product

Product
Quantity

Production
Documentation

Beta Test
Models

Trials

Production
Documentation

Production

User
Reaction

LAUNCH

Product
Quantity

Beta Test
Models

OUTPUTS:

Phased System Development Life Cycle (SDLC) to Launch

Page 25

PMP Prep: PMBOK 5th - 2013

Process Groups are not Project Phases


Process Groups
Plan

Do

Walter Shewhart,
modified
by Edwards Deming
Act

Exam
Tip

PMBOK Fifth Edition, Pages 42-43

Check

Monitoring
Monitoring
&&
Controlling
Processes
Controlling
Processes
Planning
Planning
Processes
Processes

Closing
Processes
Processes

Initiating
Initiating
Processes

Executing
Executing
Processes
Processes
Links between Process Groups in a Phase
Page 26

PMP Prep: PMBOK 5th - 2013

Process Groups are not Project Phases


Begin

Charter

Handover

End

Project Lifecycle

Phase 1

Page 26

Phase 2

Phase 3

Phase 4

PMP Prep: PMBOK 5th - 2013

Understand the Differences Between:


PMBOK Fifth Edition, Pages 42-46

Phase-to-Phase Relationships

Predictive Life Cycles


Iterative and Incremental Life Cycles

Adaptive Life Cycles

Page 26

PMP Prep: PMBOK 5th - 2013

Overview of Project Integration Chapter 4 of the PMBOK


by Knowledge Area

Page 28

4.1

Develop Project Charter

4.2

Develop Project Management Plan

4.3

Direct and Manage Project Work

4.4

Monitor and Control Project Work

4.5

Perform Integrated Change Control, and

4.6

Close Project or Phase

PMP Prep: PMBOK 5th - 2013

Initiating Process Group


by Chronology

Page 31

PMP Prep: PMBOK 5th - 2013

PMBOK Fifth Edition, Page 61


Process Groups
Knowledge Areas
4. Project Integration
Management

Initiating
4.1 Develop Project Charter

Monitoring &
Controlling

Executing

Planning
4.2 Develop Project
Management Plan

Initiating
4.3 Direct & Manage
Project Work

4.4 Mon/Ctrl Proj Work


4.5 Perform Integrated
Change Control

5. Project Scope
Management

5.1
5.2
5.3
5.4

Plan Scope Mgt.


Collect Requirements
Define Scope
Create WBS

5.5 Validate Scope


5.6 Control Scope

6. Project Time
Management

6.1
6.2
6.3
6.4
6.5
6.6

Plan Schedule Mgt.


Define Activities
Sequence Activities
Est. Activity Resources
Est. Activity Durations
Dev. Schedule

6.7 Control Schedule

4.1

13.1 Identify Stakeholders

7.1 Plan Cost Mgt.


7.2 Estimate Costs
7.3 Determine Budget

8. Project Quality
Management

8.1 Plan Quality Mgt.

8.2 Perform Quality


Assurance

9. Project Human
Resource
Management

9.1 Plan Human


Resource Mgt.

9.2 Acquire Project Team


9.3 Develop Project Team
9.4 Manage Project Team

7.4 Control Costs

8.3 Control Quality

10. Project
Communications
Management

10.1 Plan Communications


Management

11. Project Risk


Management

11.1 Plan Risk Management


11.2 Identify Risks
11.3 Perform Qualitative
Risk Analysis
11.4 Perform Quantitative
Risk Analysis
11.5 Plan Risk Response

12. Project Procurement


Management

12.1 Plan Procurement Mgt.

12.2 Conduct Procurements

12.3 Control Procurements

13.2 Plan Stakeholder


Management

13.3 Manage Stakeholder


Engagement

13.4 Control Stakeholder


Engagement

Page 28

13.1 Identify Stakeholders

4.6 Close Project


or Phase

Develop Project Charter

7. Project Cost
Management

13. Project Stakeholder


Management

Closing

10.2 Manage Communications

10.3 Control Communications

11.6 Control Risks

12.4 Close Procurements

PMP Prep: PMBOK 5th - 2013

Initiating Process Group


Initiation results in:

GO

NO GO
DECISION

Page 30

PMP Prep: PMBOK 5th - 2013

Initiation: Project Integration Management


4.1 Develop Project Charter
Inputs

Project statement of work


Business case
Agreements
Enterprise environmental factors
Organizational process assets

Page 31

Tools &
Techniques

Outputs

Expert judgment
Facilitation techniques

Project charter

PMP Prep: PMBOK 5th - 2013

4.1 Develop Project Charter


Develop Project Charter is the process of
developing a document that formally
authorizes the existence of a project
and provides the project manager with
the authority to apply organizational
resources to project activities.
The project manager is assigned early in
the project, during charter development.
ALWAYS before start of planning.

Page 31

Exam
Tip

PMP Prep: PMBOK 5th - 2013

4.1 Develop Project Charter

Project
Initiation

Customer
Requirements

Problem
Opportunity
Business Need

Page 32

Commitment to go

ahead
Project Charter
Project Manager
assigned

Project
Planning

PMP Prep: PMBOK 5th - 2013

4.1 Develop Project Charter


Input: Project Statement of Work (SOW)
PMBOK Fifth Edition, Page 68

States the Business Need and CostBenefit analysis in the Business Case.
What triggered the project?
Documents the characteristics of the
end product
Is progressively elaborated throughout
the project life cycle
Includes the Strategic Plan, a factor
when making project selection
decisions
Should describe both what the deliverable is and what it is not
With the project scope statement, the SOW protects against both scope
creep and feature creep
Page 32

PMP Prep: PMBOK 5th - 2013

4.1 Develop Project Charter


Input: Business Case, Strategic Plan
PMBOK Fourth Edition, Page 75

Strategic planning analyzes an organizations strengths, weaknesses,


opportunities, and threats (SWOT) to determine long-range objectives and
strategies for reaching them. Strategic planning often involves predicting
future trends, including the need for new products and services.

Senior management considers


each projects contribution to the
strategic goals and its alignment
with the strategic plan before
deciding to undertake, continue,
suspend, or terminate projects

Page 33

PMP Prep: PMBOK 5th - 2013

4.1 Develop Project Charter


Input: EEF and OPA
PMBOK Fifth Edition, Page 70

These are INPUTS to Develop Charter


Enterprise Environmental Factors (EEF)
Factors not under the control of the team that influence or
constrain the charter process. EEF include government or industry
standards, organization infrastructure, marketplace conditions, etc.
What is out there?

Organizational Process Assets (OPA)


OPA are standard processes, policies, and corporate knowledge:
lessons learned, historical information, templates and other
documents.
What have we got?

Page 33 & 34

PMP Prep: PMBOK 5th - 2013

4.1 Develop Project Charter


Output: Project Charter
PMBOK Fifth Edition, Page 71

Exam
Tip

Page 35

PMP Prep: PMBOK 5th - 2013

How do projects come about?

Suggested
Projects

Page 35

Project Selection
Techniques
Net Present Value
Return on Investment
Internal Rate of Return
Benefit/Cost Ratio
Opportunity Cost

Selected
Projects

PMP Prep: PMBOK 5th - 2013

Project selection methods

Economic Models

Exam
Tip

Net Present Value: net economic value (per year) of a project in terms of
present-year monies.

A higher overall net present value is better within cash flow constraints.
Expected Present Value: Risk-adjusted NPV
Return on Investment (ROI): income divided by investment.
A higher ROI is better.
Payback Period: the amount of time it will take to recover the cost of the
project. A faster payback period is better.
Internal Rate of Return (IRR) or Hurdle Rate:
the rate of return for the investment in the
project. Organizations may have a minimum rate
of return (or hurdle rate).

A higher rate of return is better

Page 37

PMP Prep: PMBOK 5th - 2013

Project selection methods Economic Models


FV
Net Present Value (NPV)

=
(1+r)n

Where, FV = Future Value


r = Interest Rate
n = Number of Time Periods

Average Earnings After Tax


Return on Investment (ROI) =

Page 37

Average Investment

= ARR
(Accounting Rate of
Return)

Internal Rate of Return (IRR) :

Solve the NPV equation for r (hurdle rate)


when present value of cash in equals
present value of cash out (i.e., at breakeven)

Benefit Cost Ratio

Benefits should exceed costs. The higher


BCR wins.

PMP Prep: PMBOK 5th - 2013

Project selection methods Example Question


Opportunity Cost:
A has NPV of $45K, B has NPV of $75K,
what is the Opportunity Cost of selecting Project B?
Answer: $45K. Opportunity cost is what you gave up
when you made your selection

Exam
Tip

Page 37

Many things on the Exam are not in the PMBOK.


A lot of these are cost questions. Only Present Value
shows up on more than one question.

PMP Prep: PMBOK 5th - 2013

Exercise Net present Value

TIME PERIOD (YR)

Page 38

AMOUNT ($)

PRESENT VALUE AT
10% INTEREST RATE

50

45

100

83

300

225

PMP Prep: PMBOK 5th - 2013

Exercise Accounting Standards

Net Present
Value
IRR
Payback
Period
Benefit Cost
Ratio

Page 38

Which Project
Would You
Pick?

PROJECT A

PROJECT B

$95,000

$75,000

13%

17%

16 months

21 months

2.79

1.3

PMP Prep: PMBOK 5th - 2013

Project Selection Methods Weighted Scoring


Removes personal bias, is more objective, and considers
relative importance of different evaluation factors
n

1)
2)
3)
4)
5)
6)

Page 39

determine the evaluation factors


assign a numerical weight to each factor
rate the projects on each criterion
multiply each rating by its weighting
total the weighted ratings to compute an overall score
highest number project wins

Si = sijwj
j=1

PMP Prep: PMBOK 5th - 2013

Project Selection Methods Decision Models


$12,000

Decision Trees: Define all the possible


outcomes, the probability of each, and
its value. Choose the best alternative.

$10,000

$8,000

}
}

$10,200

$10,000

$12,000

Forced Choice: Decision makers


choose among alternatives, often by
pair-wise comparisons, selecting the
one preferred and discarding the rest.

Page 39

PMP Prep: PMBOK 5th - 2013

Initiation: Project Stakeholder Management


PMBOK Fifth Edition, Section 13.1, Page 393

13.1 Identify Stakeholders


Inputs

Project charter
Procurement documents
Enterprise environmental factors
Organizational process assets

Page 40

Tools &
Techniques

Stakeholder analysis
Expert judgment
Meetings

Outputs

Stakeholder register

PMP Prep: PMBOK 5th - 2013

13.1 Identify Stakeholders

It is critical for project success to

identify the stakeholders early in the


project, and to analyze their levels of
interest, expectations, importance
and influence
Stakeholders should be classified
according to their interest,
involvement and influence in the
project

Who are your stakeholders? Make sure you can name them?

Page 40

PMP Prep: PMBOK 5th - 2013

Stakeholder Analysis

Tools and Techniques

Position people on the Power/Influence Grid


GU

Think about who is essential for support:

BG

high

Think about how to identify all stakeholders:


Brainstorming (free or structured)
Interviews
Past
Utilize the project team
Develop, Monitor, Focus, Stabilize

Power

Who are the most influential people?


How much will your project affect them?
How are they likely to react to your project?
Who is effected by the projects objectives?

AB
L
medium

CF

AR

JH

low
Resistor

Bystander

Change
Agent

Influence
Note: The 5th Edition lists several classification models:
Power/Interest Grid
Power/Influence Grid
Influence/Impact Grid
Salience Model
Understand the similarities and differences.

Pages 42 and 43

PMP Prep: PMBOK 5th - 2013

Planning Process Group

Page 45

PMP Prep: PMBOK 5th - 2013

PMBOK Fifth Edition, Page 61


Process Groups
Knowledge Areas
4. Project Integration
Management

Initiating
4.1 Develop Project Charter

Planning
4.2 Develop Project
Management Plan

5. Project Scope
Management

5.1
5.2
5.3
5.4

Plan Scope Mgt.


Collect Requirements
Define Scope
Create WBS

6. Project Time
Management

6.1
6.2
6.3
6.4
6.5
6.6

Plan Schedule Mgt.


Define Activities
Sequence Activities
Est. Activity Resources
Est. Activity Durations
Dev. Schedule

24
Plans

7. Project Cost
Management

7.1 Plan Cost Mgt.


7.2 Estimate Costs
7.3 Determine Budget

8. Project Quality
Management

8.1 Plan Quality Mgt.

9. Project Human
Resource
Management

9.1 Plan Human


Resource Mgt.

10. Project
Communications
Management

10.1 Plan Communications


Management

11. Project Risk


Management

11.1 Plan Risk Management


11.2 Identify Risks
11.3 Perform Qualitative
Risk Analysis
11.4 Perform Quantitative
Risk Analysis
11.5 Plan Risk Response

12. Project Procurement


Management

12.1 Plan Procurement Mgt.

13. Project Stakeholder


Management

Page 28

13.1 Identify Stakeholders

13.2 Plan Stakeholder


Management

Executing
4.3 Direct & Manage
Project Work

Monitoring &
Controlling

Planning

4.4 Mon/Ctrl Proj Work


4.5 Perform Integrated
Change Control

Closing
4.6 Close Project
or Phase

4.2
Develop Project Management Plan
5.5 Validate Scope
5.1
Plan Scope Management
5.6 Control Scope
5.2
Collect Requirements
5.3
Define Scope
5.4
Create WBS 6.7 Control Schedule
6.1
Plan Schedule Management
6.2
Define Activities
6.3
Sequence Activities
6.4
Estimate Activity
Resources
7.4 Control
Costs
6.5
Estimate Activity Durations
6.6
Develop Schedule
8.2 Perform Quality
8.3 Control Quality
7.1
Assurance Plan Cost Management
Estimate
Costs
9.27.2
Acquire Project
Team
9.37.3
Develop Project
Team
Determine Budget
9.4 Manage Project Team
8.1
Plan Quality10.3
Management
10.2 Manage Communications
Control Communications
9.1
Plan Human Resource Management
10.1 Plan Communications Management
11.6 Control Risks
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
Plan Risk Response
12.211.5
Conduct Procurements
12.4 Close Procurements
12.3 Control Procurements
12.1 Plan Procurement Management
13.4 Control Stakeholder
13.3 Manage Stakeholder
13.2
Plan Stakeholder
Management
Engagement
Engagement
PMP Prep: PMBOK 5th - 2013

Planning is Iterative

Although the constraints of text and page layout force us to


depict the planning process as a linear sequence of activities, this
is not true and probably should not be practiced as such in reality.
Planning is, in fact, an iterative activity. The various planning
processes interact with each other; later processes may cause you
to rethink the execution and output of earlier processes.
Replanning at phase gates is called progressive elaboration or
rolling wave planning.

Exam
Tip

Page 45

Planning is done by the Project Team

PMP Prep: PMBOK 5th - 2013

Project Planning
Dont over-plan and dont under-plan
(Your challenge is to match the degree of planning to the demands of the project).

Document, distribute, and maintain the plan


(Youre not the only one who is going to use the plan)

Page 46

PMP Prep: PMBOK 5th - 2013

Planning: Integration Management


4.2 Develop Project Management Plan
Inputs

Project charter
Outputs from other processes
Enterprise environmental factors
Organizational process assets

Page 47

Tools &
Techniques

Expert judgment
Facilitation techniques

Outputs

Project management plan

PMP Prep: PMBOK 5th - 2013

4.2 Develop Project Management Plan


Develop Project Management
Plan is the process of defining,
preparing, and coordinating all
subsidiary plans and integrating
them into a comprehensive
project management plan.
It is the central document that
defines the basis of all project
work.

Page 47

PMP Prep: PMBOK 5th - 2013

The Project Management Plan


Input: Outputs from Other Processes
Output: The PM Plan
The other 23 planning processes are integrated to create the project
management plan. Updates to any plans require an update to the PM plan. Think
of the PM plan as a bucket into which all the other plans drip until it is full.

Plan Scope Management


Collect Requirements
Define Scope
Create WBS
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Plan Cost Management
Estimate Costs

Pages 45 & 49

Determine Budget
Plan Quality Management
Plan Human Resource Management
Plan Communications Management
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Response
Plan Procurement Management
Plan Stakeholder Management
PMP Prep: PMBOK 5th - 2013

The Project Management Plan


Subsidiary Plans

Documents that flow from these planning processes are called Subsidiary Plans.
These documents, also controlled by the Integrated Change Control process.

Scope Management Plan


Requirements Management Plan
Schedule Management Plan
Cost Management Plan
Quality Management Plan

Page 49

Process Improvement Plan


Human Resource Plan
Communications Management Plan
Risk Management Plan
Procurement Management Plan
Stakeholder Management Plan

PMP Prep: PMBOK 5th - 2013

Differentiation: PM Plan and Project Documents


Project Management Plan

Project Documents

Change management plan

Activity attributes

Project staff assignments

Communications management plan

Activity cost estimates

Project statement of work

Configuration management plan

Activity duration estimates

Quality checklists

Cost baseline

Activity list

Quality control measurements

Cost management plan

Activity resource requirements

Quality metrics

Human resource management plan

Agreements

Requirements documentation

Process improvement plan

Basis of estimates

Requirements traceability matrix

Procurement management plan

Change log

Resource breakdown structure

Scope baseline

Project scope statement

WBS

WBS dictionary

Change requests

Resource calendars

Quality management plan

Forecasts

Cost forecast

Schedule forecast

Risk register

Requirements management plan

Issue log

Schedule data

Risk management plan

Milestone list

Seller proposals

Schedule baseline

Procurement documents

Source selection criteria

Schedule management plan

Procurement statement of work

Stakeholder register

Scope management plan

Project calendars

Team performance assessments

Stakeholder management plan

Project charter
Project funding requirements
Project schedule
Project schedule network diagrams

Work performance data


Work performance information
Work performance reports

Page 50

PMP Prep: PMBOK 5th - 2013

Planning: Project Scope Management


5.1 Plan Scope Management
Inputs

Project management plan


Project charter
Enterprise environmental factors
Organizational process assets

Page 51

Tools &
Techniques

Expert judgment
Meetings

Outputs

Scope management plan


Requirements management
plan

PMP Prep: PMBOK 5th - 2013

Project Scope Management


Ensures that the project includes all the work required,
and only the work required, for the project to complete
successfully. It defines and controls what is and is not in
the project (the positive and negative scope items).

If it is not in the scope, it is not in the WBS


The Scope Baseline includes:
1. Project scope statement (SOW)
2. Work breakdown structure (WBS)
3. WBS dictionary

Page 51

PMP Prep: PMBOK 5th - 2013

Plan Scope Management


5.1.1 Inputs

Outputs of Previous Processes:


Project Management Plan
Project Charter

+
Always Inputs:
EEF
OPA

Page 52

PMP Prep: PMBOK 5th - 2013

Plan Scope Management


5.1.3 Outputs
Scope Management Plan
Part of the project management plan
Defines how the scope will be defined, developed,
controlled, and verified.
Requirements Management Plan
Also part of the project management plan
Describes how requirements will be analyzed,
documented, and managed
Includes configuration management, requirements
prioritization, metrics, and traceability.

Page 53

PMP Prep: PMBOK 5th - 2013

Planning: Scope Management

PMBOK Fifth Edition, Section 5.2, Page 110

5.2 Collect Requirements


Inputs

Scope Management Plan


Requirements Management
Plan
Stakeholder Management Plan
Project Charter
Stakeholder Register

Page 54

Tools &
Techniques
Interviews
Focus Groups
Facilitated Workshops
Group Creativity Techniques
Group Decision Making
Techniques
Questionnaires and Surveys
Observations
Prototypes
Benchmarking
Context Diagrams
Document Analysis

Outputs

Requirements documentation
Requirements traceability
matrix

PMP Prep: PMBOK 5th - 2013

5.2 Collect Requirements

Tools and Techniques


Interviews
Focus Groups
Facilitated Workshops
Group Creativity Techniques
Group Decision Making Techniques
Questionnaires and Surveys
Observations
Prototypes
Benchmarking
Context Diagrams
Document Analysis

Page 48

Collecting Requirements is the process of


determining, documenting, and
managing stakeholders needs and
requirements to meet project objectives
Requirements include the quantified and
documented needs and expectations of
the sponsor, customer and other
stakeholders
Requirements must be detailed enough
to allow precise measurements during
Project Execution.

PMP Prep: PMBOK 5th - 2013

5.2.1 Collect Requirements


Tools and Techniques to define features and functions

Interviews: talk with all stakeholders, checklists


Focus groups: talk with prequalified stakeholders
Facilitated workshops: allow key cross-functional stakeholders to define

Exam
Tip

product/project features and to reconcile differences.


Joint Application Design/Development (JAD): software
Quality Function Deployment (QFD): new products, manufacturing
Voice of the Customer (VOC): when QFD collects client needs

Group creativity techniques (see list on next page)


Group decision making techniques
Questionnaires and surveys: written sets of questions
Observations: job shadowing
Prototypes: working model
Benchmarking: comparing to best practices
Context Diagrams: a scope model
Document Analysis: analyzing existing documentation
Pages 55-57

PMP Prep: PMBOK 5th - 2013

5.2.2 Collect Requirements

Exam
Tip

Tools and Techniques: Group Creativity Techniques

Brainstorming:

a technique to generate multiple ideas on requirements.


Does not include voting or prioritization., but is often
used with creative methods that do.

Nominal Group
Technique:

enhances brainstorming with a voting process


to rank the best ideas.

Delphi Technique:

questionnaires are sent to experts: anonymous.


responses are compiled, prioritized, and sent back.
A method for building consensus.

Idea/Mind Mapping:

a graphical method to consolidate brainstorm ideas


show commonality and differences: generate new ideas

Affinity Diagram:

gathering lots of ideas and sorting them into groups


analyze to identify patterns within data

Multicriteria Decision
Analysis:

uses a decision matrix to establish criteria (risk,


uncertainty, valuation), evaluate, and rank many ideas.

Page 56

PMP Prep: PMBOK 5th - 2013

5.2.2 Collect Requirements


Tools and Techniques: Group Decision-Making Techniques

Page 57

Unanimity:

everyone agrees. Example: Delphi Technique.

Majority:

more than 50% agree.

Plurality:

largest block in the group decides.

Dictatorship:

one person decides. Example: Forced Choice.

PMP Prep: PMBOK 5th - 2013

5.2.3 Collect Requirements


Outputs

Requirements
Documentation:

progressively elaborated
record: how each requirement meets the business
need. explicit, measurable, accepted in writing

Traceability Matrix:

a table linking requirements to their origin


traces then over the project life cycle a structure
for managing scope changes
Example Requirements Traceability Matrix

Page 58

PMP Prep: PMBOK 5th - 2013

Planning: Scope Management

PMBOK Fifth Edition, Section 5.3, Page 120

5.3 Define Scope


Inputs

Scope management plan


Project charter
Requirements documentation
Organizational process assets

Page 59

Tools &
Techniques

Expert judgment
Product analysis
Alternatives generation
Facilitated workshops

Outputs

Project scope statement


Project documents updates

PMP Prep: PMBOK 5th - 2013

5.3 Define Scope


... process required to ensure that the project includes all the work
required, and only the work required, to complete the project successfully.
Documents the features and functionality of the product, service, or result

Exam
Tip

Page 59

Exam
Tip

Know and understand for exam


Objectives = Agreement by all parties
PMI-ism: give customer No more - No less
Controls what IS and what IS NOT in project

Giving the customer more than they ask for is Gold Plating. PMI does not
approve of Gold Plating.
Currently only 26% of projects succeed, concentrate on doing the agreed
scope of work.
You may see a variety of questions relating to this in Scope and Quality areas.

PMP Prep: PMBOK 5th - 2013

Requirements vs. Scope

PMBOK Fifth Edition, Page 121

Not all of the requirements identified in Collect


Requirements may be included in Define Scope.
Define Scope selects the final project requirements.
Scope is progressively elaborated. Detailed scope is
determined one iteration at a time.
Exam
Tip

Page 60

PMP Prep: PMBOK 5th - 2013

5.3.1 Define Scope


Inputs

t
rojec
e
the p ) and th t
W
c
s ar e
uisite work (SO the proje
q
re
re
of
d for
e
o P tement
e
e (n nalysis
s
sta
a
c
n
ta
ess
atio
busin st/ benefi or justific
o
ority
and c t purpos e ctiv es
auth
rojec ble obje anager,
P
ra
o
tm
easu
rojec
ct
je
o
o M signed p ibility
r
ts, p
s
s
o A d r espon quiremen
an
nes
el re d risks
v
to
e
s
-l
e
igh
mil
, an
o H scription dget and
de
ry bu s factors and their
a
m
um
ces
ons
o S tical suc
nizati
ri
orga
o C nctional
ns or
f sp o
n
u
o F rticipatio thority o
u
a
pa
d
n
a
am e
o N

+
+

Outputs of Previous Processes:


Scope Management Plan
Requirements Documentation
Always an Input:
OPA

There have been as many as 20 Input, Tools, and Output questions


on past tests (10%). We want you to get these right!
(One person had 40 ITO questions on his test)
Pages 60 & 61

PMP Prep: PMBOK 5th - 2013

5.3.2 Define Scope


Tools and Techniques

Almost always a Tool:


Expert Judgment

Alternatives Generation
develop options using
brainstorming, lateral thinking,
alternatives analysis, etc.

Facilitated Workshops
key players reach understanding
of the project objectives and
their limits.

Product Analysis
Translate objectives
into deliverables

Page 61

PMP Prep: PMBOK 5th - 2013

5.3.2 Define Scope

PMBOK Fifth Edition, Section 5.3, Page 122

Tools and Techniques: Product Analysis, Value Analysis Example

Cost/Benefit Analysis

Page 61

Benefits:

Costs:

increased revenue
capital assets
regulatory compliance
strategic positioning

liquid assets consumed


resources occupied
deferred opportunities

PMP Prep: PMBOK 5th - 2013

5.3.3 Define Scope

PMBOK Fifth Edition, Section 5.3, Page 123

Outputs

Subject matter document:

Includes

Project Scope Statement

+
Documents Updates:
Stakeholder register
Requirements docs
Traceability matrix

Page 62 & 63

PMP Prep: PMBOK 5th - 2013

5.3.3 Define Scope


Exam
Tip

Remember the difference between the


Charter and the Scope Statement:
the charter contains high-level information,
the scope statement is a detailed description
of the scope elements.
See table 5-1, PMBOK Fifth Edition, Section 5.3, Page 124

Both are progressively elaborated throughout the project

Page 62

PMP Prep: PMBOK 5th - 2013

5.3 Define Scope

Sponsor
Scope
Statement

Product scope description


Acceptance criteria
Deliverables
Project exclusions
Constraints
Assumptions

Summary

Charter

Project
Manager

High level

PMP Prep: PMBOK 5th - 2013

Planning: Scope Management


5.4 Create WBS
Inputs

Scope management plan


Project scope statement
Requirements documentation
Enterprise environmental factors
Organizational process assets

Page 64

Tools &
Techniques

Decomposition
Expert judgment

Outputs

Scope baseline
Project document updates

PMP Prep: PMBOK 5th - 2013

5.4 Create WBS


The Work Breakdown Structure is the process of subdividing project
deliverables into smaller, more manageable components.
It is a hierarchical decomposition of the total scope of work done by the
project team to satisfy the objectives and create the deliverables.
If it is not in the scope, it is not in the WBS, and vice versa.
This is called the 100% rule.
The Scope Baseline includes:
1. Project scope statement (SOW)
2. Work breakdown structure (WBS)
3. WBS dictionary

Exam
Tip

Page 64

PMP Prep: PMBOK 5th - 2013

5.4 Create WBS

PMBOK Fifth Edition, Page 129

At the lowest level of the WBS, work


can be properly scheduled, cost estimated,
monitored and controlled
The WBS is critical to project success
The WBS is very important
The lowest level WBS components are
called Work Packages

City Gentrification

Preparation

Work Packages

Page 67

Mark
Holes

Dig
Holes

Tree Planting

Plant
Trees

Landscaping

Fill
Holes

Lay Turf

Water
Soil

PMP Prep: PMBOK 5th - 2013

5.4.1 Create WBS

PMBOK Fifth Edition, Page 127

Inputs

Outputs of Previous Processes:


Scope Management Plan
Project Scope Statement
Requirements Documentation

+
Always Inputs:

Page 65

EEF

(industry WBS standards)

OPA

(procedures, templates, lessons


learned, files)

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS

PMBOK Fifth Edition, Page 128

Tools and Techniques

Decomposition
Decomposition is the subdivision of deliverables into smaller, more
manageable components until they are defined to the work package
level, where schedule and cost can be reliably estimated
without going to level that takes more effort to administer than is
worthwhile.
Decomposition may be difficult for work to be done far in the future,
so the team does rolling wave planning.
Parts of the WBS done by a supplier are known as the contract work
breakdown structure (CWBS). Each component in a WBS should be
assigned to a department, and sorting by organizational unit creates
an Organizational Breakdown Structure (OBS).

Page 66

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Tools and Techniques

Whole Project

001

Main Divisions

Activity
Deliverables
Work Packages

Page 67

100

200

210

220

230

221

222

231

240

300

250

251

310

252

320

321

400

330

322

410

411

420

412

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Tools and Techniques: Example

Chronological
Typical
Project

Study

Concept

Prototype

Pilot

Production

Project
Management

Typical
Project

Functional

Sales

Page 67

Qualification

Product
Engineering

Purchasing

Quality
Control

Job Shop

Manufacturing
Department

Project
Management

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Tools and Techniques: Example of WBS by Phase
Seagram
MIS
Project

Project
Definition

Page 68

Analysis

Design

Construction

Implementation

Functional
Requirements
Definition

Design &
Integration

User
Procedures &
Training

Training & User


Acceptance

Process &
Package
Evaluation

Installation

Program
Generation
& Testing

User Sign
Off

Analysis
Check Point

Design
Check Point

Development
Sign Off

Support

Project
Management

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS

PMBOK Fifth Edition, Page 131-132

Outputs
Work not included in the WBS is outside the scope of the project.
This is called the 100% rule.
People who do the work must create their part of the WBS.

The work breakdown structure is a KEY document. It provide for


hierarchical summation of cost, schedule and resource
information, sometimes called rolling up the WBS.
Rules of thumb are applied to the size of a work package:
the 80-hour and 2-week rules.

Heuristics

Exam
Tip

Include all project work and all aspects of the project deliverables.
Remember, the scope of the project is always greater than the
scope of the product alone!

Page 69

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Outputs, example of software to create WBS

Page 70

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Outputs, The WBS Dictionary, PMBOK Fifth Edition, Page 132

WBS Dictionary

Controls what work is done,


when, by whom, for how much.
Created with help of the team
member.

Creating a WBS
(Post-It Note Process)
Who?

Est. Hours

Task A Specs. & Req.


Start Date
Page 70

Stop Date

Task Description
Project Title: ___________________________________
Task Title: ___________ Charge Number: ___________
Task Leader: _______________
Department: ________________
Project Manager: ____________

Task:
Scheduled Start: _____
Scheduled Completion: _____
Description: ___________________________________
______________________________________________
______________________________________________
______________________________________________
End Requirements: _____________________________
______________________________________________
______________________________________________
Budget:
Labor
_____________
_____________
_____________

Hours
Other Direct
________ _____________________
________ _____________________
________ _____________________

Work Package Completed: _______________________


Hours Expended: ________

Date Completed: ______

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Do not confuse WBS with other breakdown structures

Page 71

WBS: a deliverable-oriented hierarchical decomposition of the work to


be executed by the project team to accomplish project objectives and
to create required deliverables.

OBS: Organizational Breakdown Structure: a hierarchical view of the


project organization showing how work packages relate to functional
departments in the performing organization, i.e., a departmental
breakdown for the project.

BOM: Bill of Material: a hierarchical tabulation of parts to fabricate a


manufactured product.

RBS: Risk Breakdown Structure: a hierarchical depiction of identified


risks arranged by risk category.

Resource Breakdown Structure (another RBS?): a hierarchical view of


resources by type used on the project.

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


OBS: Organizational Breakdown Structure
Project

Cost Accounts provide a


way to control how
functional organizations
to charge to projects.

Page 71

Comp. #1

Comp. #2

Assembly

Cost
Account

Cost
Account

Parts

Cost
Account

Cost
Account

Comp. #2

Electrical

Comp. #1

Production

Cost
Account

Cost
Account

Mechanical

Engineering

Company

Manufacturing

WBS Codes show


functional managers
exactly what their
people are doing on
the project.

Design

Cost
Account

Cost
Account

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Outputs

Exam
Tip

W.B.S.

Phrases about WBS that have been answers on the


exam:

Graphical picture of the project

Identifies all tasks

Foundation upon which the project is built

Is VERY important

Page 72

Forces you to think through all aspects of the project

A WBS can be re-used for other projects

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


Outputs, WBS
The structure of the WBS should reflect the way the
project work will be performed and managed

The WBS should be broken down to the level of


detail needed to provide control of the work (80
hour and 2 week rules)
Smart PMs know they need to manage the pieces,
not the whole project.
Each element of the WBS should be given a unique
identifier that codes its position in the WBS and any
parent/child relationship among WBS elements

Each WBS element should have an associated deliverable or set of deliverables


that allow an indication of work progress and completion

Page 72

PMP Prep: PMBOK 5th - 2013

5.4.2 Create WBS


WBS Terminology
Chart of Accounts: a numbering system
used to monitor costs by category (e.g.,
labor, supplies, travel)
Code of Accounts: The collection of
unique identifiers for each WBS element
Cost Account: A code that allows a
functional group to charge for work on a
specific element of project work
Work Order: A request for a functional
group to work on a specific element of a
project
Work Package: An element of work or deliverable at the lowest level of the WBS
(relates to tasks or activities on most projects) -- may be subdivided into tasks or
activities by team members on larger projects.

Page 73

PMP Prep: PMBOK 5th - 2013

Planning: Project Time Management

PMBOK Fifth Edition, Page 145

6.1 Plan Schedule Management


Inputs

Project Management Plan


Project Charter
Enterprise environmental factors
Organizational process assets

Page 74

Tools &
Techniques

Expert judgment
Analytical techniques
Meetings

Outputs

Schedule management plan

PMP Prep: PMBOK 5th - 2013

6.1 Plan Schedule Management

Plan Schedule Management is the process of establishing policies,


procedures, and documentation for planning, developing, managing,
executing and controlling the project schedule.
It defines how schedule contingencies will be reported and assessed.

Page 74

PMP Prep: PMBOK 5th - 2013

6.1.1 Plan Schedule Management

PMBOK Fifth Edition, Page 146

Inputs

Outputs of Previous Processes:


Project Management Plan
(includes the Scope Baseline)

Project Charter

+
Always Inputs:

Page 74

EEF

(resource availability, scheduling


tool, commercial databases)

OPA

(reporting tools, lessons


learned, control tools, closure)

PMP Prep: PMBOK 5th - 2013

6.1.2 Plan Schedule Management


Tools and Techniques

Expert Judgment
Analytical Techniques
(techniques to estimate and schedule the
project, PM software, fast track or crash,
risk assessment)

Meetings
(to develop the plan)

Page 75

PMP Prep: PMBOK 5th - 2013

6.1.3 Plan Schedule Management


Outputs

Schedule Management Plan


(model development, accuracy, units,
procedures, control thresholds,
performance measurement rules, report
formats, process descriptions)

Page 76

PMP Prep: PMBOK 5th - 2013

Planning: Project Time Management

PMBOK Fifth Edition, Page 149

6.2 Define Activities


Inputs

Schedule Management Plan


Scope baseline
Enterprise environmental factors
Organizational process assets

Page 77

Tools &
Techniques

Decomposition
Rolling wave planning
Expert judgment

Outputs

Activity list
Activity attributes
Milestone list

PMP Prep: PMBOK 5th - 2013

6.2 Define Activities


Activity definition identifies specific actions at the work package level of the
WBS to produce the deliverables. Work packages have smaller elements
called schedule activities that have to be planned, i.e., estimated, scheduled,
executed and monitored & controlled, to meet project objectives.

The best way to think about activity definition is that the outputs are

ACTIONS to be done.

Page 77

PMP Prep: PMBOK 5th - 2013

6.2 Define Activities


City Gentrification

Preparation

Work Packages

Actions

Page 80

Mark
Holes

Dig
Holes

Tree Planting

Plant
Trees

Fill Holes

Landscaping

Lay Turf

Water
Soil

Check ground
Measure distances
Nail stakes

PMP Prep: PMBOK 5th - 2013

6.2.1 Define Activities


Inputs

Outputs of Previous Processes:


Schedule Management Plan
Scope Baseline
(Scope Statement, WBS, and WBS
Dictionary)

+
Always Inputs:
EEF

(culture, commercial databases,

PMIS)

OPA

(lessons learned, processes,


templates, activity procedures)

Page 78

PMP Prep: PMBOK 5th - 2013

6.2.2 Define Activities


Tools and Techniques

Decomposition
Subdividing work packages into actions or work effort
necessary to complete the deliverable of the work package.
These actions or work effort are sometimes called schedule
activities.

Rolling Wave Planning


(see next page)

Expert Judgment (Always a tool)

Page 78

PMP Prep: PMBOK 5th - 2013

6.2.2 Define Activities


Tools and Techniques

Rolling Wave Planning


Rolling wave planning is progressive elaboration of the plan throughout the
project life cycle. Work accomplished in the near term is planned in detail at
a low level of the WBS, while work far in the future is planned at a higher
level of the WBS. Therefore, schedule activities can exist at various levels in
the project life cycle. For example, in the initiation stage where strategic
planning is done, activities might be kept at the milestone level. As each
project phase is completed, rolling wave planning means that the next phase
can now be planned in more detail as more is known about the detail
activities.

Page 78 & 79

PMP Prep: PMBOK 5th - 2013

6.2.1 Define Activities


Definitions
Exam
Tip

Sometimes PMP Candidates do not understand the


subtle distinction between an Activity Definition and a
Work Breakdown Structure (WBS). This may help:

Page 79

Activity Definition

Outputs are
ACTIONS TO BE DONE

W.B.S.

Outputs are
DELIVERABLES
(Tangible Items)

PMP Prep: PMBOK 5th - 2013

6.2.3 Define Activities


Outputs
City Gentrification

Preparation

Mark
Holes

Activity List

Page 80

Dig
Holes

Tree Planting

Plant
Trees

Fill Holes

Landscaping

Lay Turf

Water
Soil

1. Check ground
2. Measure distances
3. Nail stakes

PMP Prep: PMBOK 5th - 2013

Planning: Time Management

PMBOK Fifth Edition, Page 153

6.3 Sequence Activities


Inputs

Schedule management plan


Activity list
Activity attributes
Milestone list
Project scope statement
Enterprise environmental factors
Organizational process assets

Page 82

Tools &
Techniques

Precedence diagramming
method (PDM)
Dependency determination
Leads and lags

Outputs

Project schedule network


diagrams
Project documents updates

PMP Prep: PMBOK 5th - 2013

6.3 Sequence Activities


Activity Sequencing
Activity sequencing means identifying and documenting logical relationships
among project activities. Think NETWORKS !
Accurate and complete activity sequencing is critical to developing schedules.
Schedule activities (actions) can be sequenced to develop the project schedule.

The project planning team should work together to clarify the sequence of
activities and dependencies. It is usually more effective to have the team do
some form of manual activity sequencing before turning to project
management software for scheduling.

Page 82

PMP Prep: PMBOK 5th - 2013

6.3 Sequence Activities


Activities are commonly sequenced using the Precedence
Diagramming Method (PDM) which allows finish-to-start,
finish-to-finish, start-to-start and start-to-finish
Finish-to-start is the most common type of relationship
There are three types of dependencies mandatory
dependencies, discretionary dependencies and external
dependencies
Lead and lag times add realism to the schedule (you Lead In
to fast track, and Lag out to add a gap between activities)

Page 82

PMP Prep: PMBOK 5th - 2013

6.3.1 Sequence Activities


Inputs

Schedule Management Plan


Activity List
(activities or actions to be sequenced)

Activity Attributes
(activities have durations, resources, and costs
associated and are used for schedule development)

Milestone List
(A significant event in a project. The list identifies all
milestones and if they are mandatory (contractual)
They have zero duration.

Project Scope Statement


EEF and OPA

Page 83

PMP Prep: PMBOK 5th - 2013

6.3.2 Sequence Activities


Tools and Techniques, Precedence Diagramming Method (PDM)

Dependencies used in PDM


F-S
Activity B

Activity A

F-F
Activity C
S-S
Activity D
S-F

Page 84

Activity E

PMP Prep: PMBOK 5th - 2013

6.3.2 Sequence Activities


Tools and Techniques, Precedence Diagramming Method (PDM)
also called Activity on Node

Lead in
Lag out

Finish-to-Start (most often used)


Finish-to-Finish
Start-to-Start
Start-to-Finish (rarely used)

A-B; B-C; etc.


B-E
B-D
F-C

Start

Finish
D

Exam
Tip

No repetitive activities or conditional loops! No Dummies!


Often used for Three Point Estimates (PERT) and Critical Path Method
(CPM) analysis

Page 84

PMP Prep: PMBOK 5th - 2013

6.3.2 Sequence Activities


Tools and Techniques, Arrow Diagramming Method (ADM)
also called Activity on Arrow [ Not in Fifth Edition, may be on test ]

2
Start

Page 85

6
D

Finish

Finish-to-Start only (need additional nodes for leads and lags)


No repetitive activities or conditional loops
May use dummy activities
Nodes numbered, activities lettered, numbers above arrows are duration
Often used for Three Point Estimates (PERT) and Critical Path Method
(CPM) analysis

Exam
Tip

PMP Prep: PMBOK 5th - 2013

6.3.2 Sequence Activities


Tools and Techniques, Conditional Diagramming Method
Graphical Evaluation and Review Technique (GERT)

Not in the Fifth Edition, But has been on recent tests


Scrap
Rework
Manufacture

Inspect

Inspect

Package

Ship

Allows repetitive activities (looping back) and conditional branches


Combines features of flow diagrams and decision tree models

Not in Book

PMP Prep: PMBOK 5th - 2013

6.3.2 Sequence Activities


Tools and Techniques, Dependency Determination

Mandatory Dependencies (Hard Logic):


Dependencies based on technological constraints, such as not
being able to paint a wall before it is constructed

Discretionary Dependencies (Soft Logic):


Dependencies based on management preference, such as
delaying one task until another is completed in order to use
the same resources on both.

External Dependencies:
Dependencies based on external constraints such as a
required inspection before proceeding to the next activity.

Internal Dependencies:
Dependencies within the project teams control, such as
not testing a product until the product is fully assembled.
Page 86

PMP Prep: PMBOK 5th - 2013

6.3.2 Sequence Activities


Tools and Techniques

Applying Leads and Lags


A lead allows acceleration of the successor activity (you
lead in to fast track a project).
For example, a team of technical writers can begin writing the
second draft of a large document 15 days before they finish
the first draft. When scheduling, this is accomplished with a
finish-start relationship and a 15 day lead time.

Exam
Tip

A lag directs a delay in the successor activity (you lag out to


allow a waiting time).
For example, you have to wait 10 days to discover infant
mortality of new semiconductor chips. This is accomplished
using a finish start relationship and a 10 day lag time.

Page 87

PMP Prep: PMBOK 5th - 2013

6.3.2 Sequence Activities


Tools and Techniques

o A hammock is a summary level activity


representing a group of related
activities
o A subnet or fragnet is a sub-project of
a larger network diagram
o A hanger is an unintentional break in
the network diagram usually due to
omitting either activities or logical
relationships

Page 87

PMP Prep: PMBOK 5th - 2013

6.3.3 Sequence Activities


Outputs

Project Schedule Network Diagrams


(a graphical representation of activities showing
dependencies)

Project Documents Updates


(include activity lists and attributes, milestone list, and
risk register)

F-S
Activity B

Activity A

F-F
Activity C
S-S
Activity D
S-F

Page 88

Activity E

PMP Prep: PMBOK 5th - 2013

Planning: Time Management

PMBOK Fifth Edition, Page 160

6.4 Estimate Activity Resources


Inputs

Schedule management plan


Activity list
Activity attributes
Resource calendars
Risk register
Enterprise environmental factors
Organizational process assets

Page 89

Tools &
Techniques

Expert judgment
Alternative analysis
Published estimating data
Bottom-up estimating
Project management software

Outputs

Activity resource
requirements
Resource breakdown
structure
Project documents updates

PMP Prep: PMBOK 5th - 2013

6.3 Estimate Activity Resources


Estimate Activity Resources is the
process of estimating the type and
quantities of material, human
resources, equipment or supplies
required to perform each activity.
There are five tools and techniques:
Expert judgment
Alternative analysis
Published estimating data
Bottom-up estimating
Project management software

Page 89

PMP Prep: PMBOK 5th - 2013

6.3.1 Estimate Activity Resources


Inputs

Schedule Management Plan


Activity List
(Activities that need resources)

Activity Attributes
(data for estimating resources)

Resource Calendars
(periods when resources are available and skill level)

Risk Register
(shows events that impact resource availability)

Activity Cost Estimates


EEF and OPA

Pages 89-90

PMP Prep: PMBOK 5th - 2013

6.3.1 Estimate Activity Resources


Inputs, Resource Calendars
Resource calendars document the time periods when
each team member can work on the project. To do this
we must have a good understanding of the persons
schedule conflicts, including holiday time and
commitments to other projects. We document active
and idle time for each person over the life of the project
and show the results in a project histogram. Resources
include people, material, equipment and facilities.

Page 78

PMP Prep: PMBOK 5th - 2013

6.3.2 Estimate Activity Resources


Tools and Techniques

Expert Judgment
Alternative Analysis
(Different people, skills, equipment, tools, make-buy)

Published Estimating Data


(data for estimating resources)

Bottom-Up Estimating
(Estimating at the bottom level of the WBS and adding
[aggregating] to the top. Yields best accuracy)

Project Management Software


(a scheduling tool helps plan, manage resource pools,
and develop resource estimates)

Pages 90-92

PMP Prep: PMBOK 5th - 2013

6.3.2 Estimate Activity Resources


Tools and Techniques
Alternative Analysis
Brainstorming: a method of joint creative thinking that first records and
considers all possible options/solutions without judgment before proceeding to
critical evaluation of the project/product requirements.
Nominal Group Technique: enhances brainstorming with a voting process to
rank the best ideas for further brainstorming or prioritization.
Delphi Technique: questionnaires are sent to a group of experts who provide
answers and are kept anonymous. Responses are compiled, prioritized, and
sent back for another round of requirements gathering. A method for building
consensus.
Idea/Mind Mapping: a graphical method of consolidating brainstorm ideas to
show commonality and differences and to generate new ideas.

Affinity Diagram: gathering large numbers of ideas and sorting them into
groups for review and analysis they help to identify patterns within data.

Post-It Note Process: A Method For Bottoms Up Estimating


The WBS dictionary describes the detailed content of the WBS work packages.

WBS Dictionary =

Task Description

(PMBOK 3rd Edition, Page 117)

Controls what work is done,


when, by whom, for how much.
Created with team members
help

Creating a WBS
(Post-It Note Process)
Who?

Est. Hours

Task A Specs. & Req.

Project Title: ___________________________________


Task Title: ___________ Charge Number: ___________
Task Leader: _______________
Department: ________________
Project Manager: ____________

Task:
Scheduled Start: _____
Scheduled Completion: _____
Description: ___________________________________
______________________________________________
______________________________________________
______________________________________________
End Requirements: _____________________________
______________________________________________
______________________________________________
Budget:
Labor
Hours
Other Direct
_____________ ________ _____________________
_____________ ________ _____________________
_____________ ________ _____________________
Work Package Completed: _______________________

Start Date

Page 91

Stop Date

Hours Expended: ________

Date Completed: ______

PMP Prep: PMBOK 5th - 2013

6.3.3 Estimate Activity Resources


Outputs
Activity Resource Requirements
The output of resource planning is a set of resource requirements. The resource
requirements describe what types of resources are required and in what
quantities for each element of the WBS. The list of resource requirements will be
used for staff acquisition and procurement planning. Develop Schedule
determines when the resources are needed.

Resource Breakdown Structure


This is a hierarchical structure of identified resources, sorted by category and
type. When limited to people resources, it is sometimes referred to as a project
organization chart.

Project Documents Updates


Updates include activity list, activity attributes, and resource calendars

Page 92

PMP Prep: PMBOK 5th - 2013

Planning: Time Management

PMBOK Fifth Edition, Page 166

6.5 Estimate Activity Durations


Inputs
Schedule management plan
Activity list
Activity attributes
Activity resource requirements
Resource calendars
Project scope statement
Risk register
Resource breakdown structure
Enterprise environmental factors
Organizational process assets

Page 93

Tools &
Techniques

Expert judgment
Analogous estimating
Parametric estimating
Three-point estimating
Group decision-making
techniques
Reserve analysis

Outputs

Activity duration estimates


Project documents updates

PMP Prep: PMBOK 5th - 2013

6.5 Estimate Activity Durations

PMBOK Fifth Edition, Page 166

Estimates may be obtained in the


following ways:
Expert judgment
Analogous estimating
Parametric estimating
Three-point estimates
Group decision-making
A contingency reserve (or time
reserve, or buffer) may be used to
account for schedule uncertainty

Page 93

PMP Prep: PMBOK 5th - 2013

6.5 Estimate Activity Durations


Definition: Estimating the number of work periods needed to complete
each activity with estimated resources.
The team members should make the estimate.
Estimates: (1) amount of work to complete each activity, (2) number of
resources to be applied, and (3) number of work periods needed to finish
each activity.
Duration estimates are progressively elaborated.

Rolling Wave applies to duration estimating


Estimating duration includes elapsed time as well as work time.

Page 93

PMP Prep: PMBOK 5th - 2013

6.5.1 Estimate Activity Durations


Inputs

Pages 94-96

Schedule management plan


Activity list
Activity attributes
Activity resource requirements
Resource calendars
Project scope statement
Risk register
Resource breakdown structure
Enterprise environmental factors
Organizational process assets

PMP Prep: PMBOK 5th - 2013

6.5.2 Estimate Activity Durations

PMBOK Fifth Edition, Page 169

Tools and Techniques, Estimating Methods


Analogous Time Estimating (a form of expert judgment):
Estimating the time to do tasks or to do a current project by extrapolating
from actual cost of a previous project. Also called top-down time estimating.
Inexpensive but may also be inaccurate.

Parametric Time Estimating:


Using a statistical relationship to predict project times, e.g., activity
multiplied by productivity rate predicts time standards, or number of
drawings multiplied by labor hours per drawing calculates drawing duration.

Expert Judgment:
By the project team, or other experts, e.g., rolling up the
WBS time estimates to get a project total.

Who?

Task A

Reserve Analysis (Contingency):


Project Teams can incorporate additional
time into projects for schedule risk
contingency or buffer. Qual. (%) or Quant.
(Monte Carlo)
Page 98

Est. Hours

Start Date

Exam
Tip

Stop Date

People doing the work create time & cost estimates

PMP Prep: PMBOK 5th - 2013

6.5.2 Estimate Activity Durations

PMBOK Fifth Edition, Page 170

Tools and Techniques, Analysis Methods


Critical Path Method (CPM)

One time estimate per task = most likely duration.


The emphasis is on controlling cost and leaving schedule flexible.
Used on ADM (AOA) diagrams, can have dummies.
Is used on PDM diagrams also, but they have no dummies

Three Point Estimates (PERT=Program Evaluation and Review Technique)

Sometimes
called Method
of Moments

te =

Sometimes
called Beta
Distribution

Pessimistic + Optimistic + (4 x Most Likely)

Pessimistic - Optimistic
Standard
=
Deviation
6
Page 98

Exam
Tip

Uses a weighted average to estimate activity and project durations.


Provides variance estimates for duration dates.
Emphasis is on controlling schedule and leaving cost flexible
Used on ADM (AOA) diagrams, can have dummies.
Is used on PDM diagrams also, but they have no dummies

Variance =

Pessimistic - Optimistic

6
PMP Prep: PMBOK 5th - 2013

6.5.2 Estimate Activity Durations


Tools and Techniques, Duration Estimates

o = most optimistic completion time


p = most pessimistic completion time
m = most likely completion time
te =

o + 4m + p

15

3-Point or
PERT
Analysis

16 17 18 19 20 21 22 23 24

6
(te) =

po
6

te 1 <=> 68% probability


te 2 <=> 95.5% probability
te 3 <=> 99.7% probability
Page 99

19 1days with 68% confidence


19 2 days with 95.5% confidence
19 4 days with 99.7% confidence

Quantitative Estimate
Indication of Range
Indication of Confidence
PMP Prep: PMBOK 5th - 2013

Exercise
Calculate the following values using PERT
Task

Opt

Likely

Pess

PERT

Std. Dev

Variance

14

27

47

28.166

5.5

30.25

41

60

89

61.666

64

39

44

48

43.833

1.5

2.25

29

37

42

36.5

2.166

4.693

Assuming that the tasks listed above make up the entire critical path for the project,
how long will the project take? 170.2 days 10.1 days (add the variances and take square root)
Page 99

PMP Prep: PMBOK 5th - 2013

Planning: Time Management

PMBOK Fifth Edition, Page 172

6.6 Develop Schedule


Inputs
Schedule management plan
Activity list
Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity duration estimates
Project scope statement
Risk register
Project staff assignments
Resource breakdown structure
Enterprise environmental
factors
Organizational process
assets

Page 101

Tools &
Techniques
Schedule network analysis
Critical path method
Critical chain method
Resource optimization
techniques
Modeling techniques
Leads and lags
Schedule compression
Scheduling tool

Outputs

Schedule baseline
Project schedule
Schedule data
Project calendars
Project management plan
updates
Project documents updates

PMP Prep: PMBOK 5th - 2013

6.6 Develop Schedule


Develop Schedule is the process of analyzing activity sequences, durations,
resource requirements and schedule constraints to create the project schedule
Schedule Network Analysis

A technique to generate the


project schedule employing
various analytical
techniques such as critical
path, critical chain, what-if
analysis and resource
optimization

Pages 103-105 & 110

Critical Path Method

Critical Chain Method

A method used to estimate


minimum duration and
flexibility in network paths.
Calculates theoretical early
and late start and finish
dates for all activities
without regard to resource
limitations, using forward
and backward pass analysis

Allows the team to place


buffers on any network
path to account for limited
resources and duration
uncertainties. The resourceconstrained critical path is
the critical chain. A project
buffer can be placed at the
end of the critical chain,
and feeding buffers can be
places on non-critical legs
that feed into the critical
chain.

PMP Prep: PMBOK 5th - 2013

6.6 Develop Schedule

Page 101

Determines planned start and finish calendar dates for project activities

Schedule development is iterative and continuously elaborated

Requires review of duration and resource estimates to create a schedule

Creates a baseline against which to track progress

PMP Prep: PMBOK 5th - 2013

6.6.2 Develop Schedule


Tools and Techniques, Schedule Network Analysis
Network analysis is a technique that generates the project schedule. It employs
a schedule model and includes CPM, critical chain method, what-if analysis and
resource optimization to calculate early and late start and finish dates.

Critical Path Method (CPM)


One time estimate per task = most likely duration.
The emphasis is on controlling cost and leaving schedule flexible.

Three Point Estimates (PERT=Program Evaluation and Review Technique)


Uses a weighted average to estimate activity and project durations.
Provides variance estimates for duration dates.
Emphasis is on controlling schedule and leaving cost flexible
te =

Pessimistic + Optimistic + (4 x Most Likely)

Pessimistic - Optimistic
Standard
=
Deviation
6
Page 103

Variance =

Pessimistic - Optimistic

6
PMP Prep: PMBOK 5th - 2013

6.6.2 Develop Schedule


Tools and Techniques, Critical Path Method (CPM)
CPM calculates early and late start and finish dates for activities using forward and
backward pass analyses through the network paths. The early and late start and
finish dates may not be the same on different network paths since total float may
be positive, negative, or zero. Total float provides schedule flexibility.
Critical paths have either zero or negative total float. The definition of Critical
Path is the longest addition of activity durations on a path from start to finish. It is
also defined as the shortest period of time in which the project can be completed.

Exam
Tip

The definition of Total Float is the total amount of time a schedule activity can be
delayed from its early start date without delaying the project finish date. CPM
calculates total float by determining the difference between early finish and late
finish dates, or early and late start dates. Also known as slack, float, or project
float.

Free Float is the amount of time a schedule activity can be delayed without
delaying the early start date of its successor.
Page 96

PMP Prep: PMBOK 5th - 2013

Slack Analysis
If you have a network with parallel paths and one leg has slack,
when you create the schedule, do you take the slack at the end
of that leg or at the start?
JIT
12 days
9 days

16 days
13 days

6 days
Slack

16 days

12 days

OR

6 days
Slack

9 days

13 days

When first laying out a schedule, put the slack at the end of
the shorter leg. It helps with resource leveling and recovery if
something happens to either of the two shorter legs during
execution. Dont schedule projects JIT.
Page 103
PMP Prep: PMBOK 5th - 2013

Example of Critical Path Method


2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

10

B
11
1

15

Path A, B, D = 25
16

Start
1

15

30
Finish

D
5

16
6

10

15

C
6

30

Path A, C, D = 30

15

Legend

Early
Early
Start Duration Finish

Activity Name
Late
Start

Total
Float

Late
Finish

Critical Path
Non-Critical Path
Page 105
PMP Prep: PMBOK 5th - 2013

3 Weeks

6.6.2 Develop Schedule

Sales Aids &


Brochure
Production

2 Weeks

Critical Path Method

Support
1 Week
Brochures

2 Weeks

0 Week

4 Weeks

0 Week

Training

Go/No Go
Decision

Advertising

Go/No Go
Launch

1 Week

2 Weeks

1 Week

Definition

Margin

Acceptance

5 Weeks

1 Week

Training

Program
Launch

4 Weeks
Stock
Profile
7 Weeks

The critical path is the longest addition of


durations over a network.
It is the shortest period of time the project can
be done.
A project may have more than one critical path
The critical path may change as the project
progresses
Critical Path may be found using CPM, ThreePoint, or Monte Carlo analyses.
Page 106

DBT Stocking &


Measuring Sys

12 Weeks
Sales

PMP Prep: PMBOK 5th - 2013

Calculate the Critical Path


1

2 days
Activity C

3
5

9
5

4
5

6
1 day
Activity D

5
7

number above the node is the earliest possible start date


number below the node is the latest possible start date
critical path is where earliest start date = latest start date
Page 106

Prep:
5
PMP
PMP
Prep:PMBOK
PMBOK
4th - 2013

Critical Path: Related terms


Early Start Date is the earliest date that uncompleted activities can be started given the
network logic and any schedule constraints
Early Finish Date is the earliest date that uncompleted activities can be finished given
the network logic and any schedule constraints
Late Start Date is the latest date that an activity can begin without compromising a
specified milestone (generally the project finish date)
Late Finish Date is the latest date than an activity can finish without compromising a
specified milestone (generally the project finish date)
Total Float is the amount of time an activity can be delayed from its scheduled start
date without delaying the project finish date, or violating a schedule constraint. Also
know as float, slack, or project float
Free Float is the amount of time an activity can be delayed without delaying the early
start of any following activities
Slack Time or Total Float = Late Finish Date - Early Finish Date, or Late Start - Early Start

Page 107

PMP Prep: PMBOK 5th - 2013

Calculating Critical Path and Float


Critical Path (C-E-F) = 24
Total Float in A-D-F = 14
Total Float in B-E-F = 9
Free Float of A = 0 (5-0-5)
Free Float of B = 2 (5-0-3)
Free Float of D = 14 (21-5-2)

0
9

TF = 14
FF = 14

5
19

3 3
B
12

0 12 12
C
0

Page 108

Free float: The


difference between
early start of
predecessor and early
start of successor,
minus the estimated
time of the predecessor

A
14

TF = 9
FF = 2

------ = Forward Pass


------ = Backward Pass

TF = 14
FF = 0

12

5
19

2 7
D
21

12 9 21
E
12

21 3 24
F
21
24

21

TF = 0
FF = 0

PMP Prep: PMBOK 5th - 2013

Exercise
(1) Draw the network diagram and find the critical path
Work
Package

Preceding
Activity

START

Estimate in
Months
0

START

START

D,A

F,E

(2) Find the slack of task A-F-B path, and of the D-E-G-H-C
path from the answer above.

END

C,B

Answer: A-F-B = 15 Months, D-E-G-H-C = 1 Month

Page 109

E
D

START
F

END

Answer: The critical path (project duration) is 33 months

PMP Prep: PMBOK 5th - 2013

Exercise: ADM
There may be 5-7 questions on network diagrams on the exam. Here is an example of a
form of question that has a table of information and four questions that relate to it:

B: (0 - 2)
C: (1 - 3)
(2 - 3)
E: (2 - 5)
D: (3 - 4)
F: (3 - 5)
G: (5 - 6)

Estimate
In Weeks
3
9
3
Dummy
2
2
1
4

H: (4 - 6)

Work Package
(Nodes)
A: (0 - 1)

C=3
A=3

0
B=9

D=2

3
Dummy

F=1
5

H=2

G=4

E=2

1. What tasks are on the critical path?


The critical path is B, E, G. (Note that 0, 1, 2, 3, 4, 5, and 6
are nodes in the AOA or ADM Diagram). Critical Path = 15
Weeks.

B-Dummy-F-G also becomes critical


2. If the duration of task F changes to 2 weeks, what is the effect on the project?
3. What task(s) must be completed before task D begins? Tasks A, B and C
4. If the management tells you to complete the project two weeks early, what is the project float?
Does the critical path change? Float is -2 weeks. No CP change unless Crashed or Fast Tracked
Page 109

PMP Prep: PMBOK 5th - 2013

6.6.2 Develop Schedule


Tools and Techniques, Critical Chain Method
Critical chain modifies the schedule to account for limited resources. Initially
the critical path of a network is calculated using activity duration estimates.
Then, resources are applied and the resulting schedule may be resource
limited. The critical chain method adds duration buffers that are non-work
activities. The planned activities are then scheduled to their latest start and
finish dates. Instead of managing total float, critical chain focuses on managing
the buffer durations and the resources applied to the planned activities.

Pages 110

PMP Prep: PMBOK 5th - 2013

Example of Critical Chain Method

Start

Activity A

Activity B

Feeding
Buffer

Activity C

Activity D

Activity E

Activity G

Feeding
Buffer

Activity F

Legend

Pages 110

Project
Buffer

Finish

Critical Chain Link


Non-Critical Link

PMP Prep: PMBOK 5th - 2013

6.6.2 Develop Schedule


Tools and Techniques, Resource Optimization: Leveling and Smoothing

The resource histogram is a time-phased display of the amount of


project work assigned to each resource (PMBOK Fourth Edition, Page 156)
Resource plans are best when resource requirements
increase and decrease without variations
Month 1

Month 2

Month 3

Scheduling Tool

Month 4

1.5

1.0

0.5

Product Manager

May be used at the individual or group level


May be used to detect over-allocation of resources
Avoid over-allocation, under-allocation, and peaks and valleys
Pages 111

PMP Prep: PMBOK 5th - 2013

Network Analysis and Resource Leveling


Critical Path: A-D-F
and
B-E-F

C
4

2
Start

3
1

Page 112

F
4 Days Slack

1
4

Work Force Required

Finish

Work Force Available


Each Day: 4 People

Work Force

Duration in Days

1
5

E
6

Days

2
PMP Prep: PMBOK 5th - 2013

Network Analysis and Resource Leveling


2

C
4

2
Start

Work Force
Page 112

1
4

1
B

Finish

1
5

2 Days Slack

E
6

10

Days

PMP Prep: PMBOK 5th - 2013

6.6.2 Develop Schedule


Tools and Techniques, What if Scenario Analysis
What-If analysis is the process of evaluating scenarios and their effect on schedule,
i.e., what if a major component delivery is delayed? It assesses effect of adverse
conditions on the project schedule and helps with response planning.
Simulations calculate multiple project durations with different activity assumptions.
They use three-point estimates (PERT) to determine duration uncertainty. The most
common simulation uses Monte Carlo analysis. Possible activity durations are defined
and used to calculate outcomes for the total project. Simulations are valuable for
analyzing the sensitivity of the project to changes and for addressing the impact of
uncertainty in the network logic, duration of activities, and availability of resources.

Pages 113

PMP Prep: PMBOK 5th - 2013

Applying Leads and Lags

A lead allows acceleration of the successor activity (you


lead in to fast track a project).
A lag directs a delay in the successor activity (you lag out to
allow a waiting time).

Pages 114

Exam
Tip

PMP Prep: PMBOK 5th - 2013

6.6.2 Develop Schedule


Tools and Techniques, Schedule Compression

If you cant change the scope, there are two ways to meet schedule constraints:

Fast Tracking
A technique where activities or phases normally done in sequence
are done in parallel for at least a portion of their duration. Fast
tracking may result in rework and increased risk.
Exam
Tip

Crashing
A technique used to shorten the schedule duration for the least
incremental cost by adding resources.

Page 114

PMP Prep: PMBOK 5th - 2013

Exercise
1. What option below would you select to save three months on the
project assuming that the tasks listed below represent critical path?
There is no answer. The answer depends on whether cost or risk is most important.

Task

F
A
H
G
C

Original
Crash
Duration Duration
in months in months
14
12
9
7
3
2
7
6
11
8

Time
Savings
2
2
1
1
3

Original
Cost
in $
10,000
17,000
25,000
14,000
27,000

Crash
Cost
in $
14,000
27,000
26,000
16,000
36,000

Extra
Cost
in $
4,000
10,000
1,000
2,000
9,000

Extra
Cost in $
per mth
2,000
5,000
1,000
2,000
3,000

Risk
Impact
HIGH
LOW
LOW
HIGH
NONE

2 Lets assume that time is of most importance followed by cost.


Such questions are on the exam. What would be your answer?
The answer would be to select tasks F and H for an additional cost of $5,000.
If risk is second to time in importance the answer would be to select task C for
an additional cost of $9,000. The exam will probably not include risk column
because risk (nor quality) is not considered when most people crash or fast track
their projects. Without a risk column, simply pick the least cost alternative
Page 116

PMP Prep: PMBOK 5th - 2013

6.6.3 Develop Schedule


Outputs, Project Schedule

The Project Schedule may be presented in tabular form, however its more
often presented graphically using milestone charts, bar charts or project
schedule network diagrams. The schedule baseline is a specific version of the
project schedule that is accepted and approved by the project team. It is a
component of the project management plan

Page 117

PMP Prep: PMBOK 5th - 2013

6.6.3 Develop Schedule


Outputs, Project Schedule

Example Schedules
Example: Bar Chart, Gantt Chart
ID
1

Nov 9, '97
Tas k Name
Mark Out Site

Dig Foundation A

Dig Foundation B

Concrete Foundation A

Concrete Foundation B

Com plete Base at A

Erect Plinth

Erect Tower A

Erect Tower B

10

Erect Span

Nov 16, '97


Nov 23, '97
Nov 30, '97
Dec 7, '97
Dec 14, '97
Dec 21, '97
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Example: Milestone Chart

Page 117

PMP Prep: PMBOK 5th - 2013

The Project Schedule


May be represented by a Gantt chart, an activity network
diagram, or a milestone chart
Indicates the planned start and finish dates for each WBS
element
May also indicate early start, late start, early finish, and
late finish dates for each activity

Name

Duration
1w
Definition
30d
Feasibility
1w
Brochures
2w
Margin
4w
Stock Profile
2w
Support
2w
Training
1w
Acceptance
0d
Go/No Go Decision
35d
Program Development
3w
Sales Aids & Brochure
4w
Advertising
Training
5w
7w
DBT Stock & Measure
0d
1w
Program Launch
12w
Sales

Page 118

Month 1

Month 2

Month 3

Month 4

Month 5

Month 6

Sales Aids &


Brochure
Production

Month 7
Support

Brochures

Definition

Go/No Go
Decision

Training

Margin

Advertizing

Go/No Go
Launch

Acceptance
Training

Program
Launch

Stock
Profile

DBT Stocking &


Measuring Sys

Sales

PMP Prep: PMBOK 5th - 2013

Practice Test #1

Turn to page 387 in the workbook


There are 60 questions.
You have 72 minutes to complete
Answers are on page 404
Hint: Use scratch paper for answers,
so you can reuse the questions for practice

Page 387

PMP Prep: PMBOK 5th - 2013

Planning: Cost Management

PMBOK Fifth Edition, Page 195

7.1 Plan Cost Management


Inputs

Project management plan


Project charter
Enterprise environmental factors
Organizational process assets

Page 119

Tools &
Techniques

Expert judgment
Analytical techniques
Meetings

Outputs

Cost management plan

PMP Prep: PMBOK 5th - 2013

Plan Cost Management


Plan Cost Management is the process that establishes policies, procedures,
documentation for planning, expending, and controlling project costs.
This is a component of the project management plan.
Inputs

Project Management Plan


Information to develop the Cost Management Plan:

Scope baseline

Schedule baseline
Other information

Project Charter
(Provides a summary budget)

EEF and OPA

Page 120

PMP Prep: PMBOK 5th - 2013

Plan Cost Management


Tools and Techniques

Expert Judgment
Analytical Techniques
(Choosing options to fund the project: self-funding,
equity funding, or debt funding. Ways to finance
resources: make, buy, rent, or lease. Policies may
influence: ROI, payback period, internal rate of return,
discounted cash flow, and net present value.)

Meetings

Page 120

PMP Prep: PMBOK 5th - 2013

Plan Cost Management


Outputs

Cost Management Plan


units of measure,
level of precision,
level of accuracy (e.g., 10%),
organizational procedures (the WBS is a framework
for cost estimating),
control threshold (% deviation from the baseline
plan),
rules of performance measurement (EVM),
reporting formats (format and frequency of cost
reports),
process descriptions,
strategic funding, exchange rate fluctuations, and
cost recording.

Page 121

PMP Prep: PMBOK 5th - 2013

Planning: Cost Management

PMBOK Fifth Edition, Page 200

7.2 Estimate Costs


Inputs

Cost management plan


Human resource mgt. plan
Scope baseline
Project schedule
Risk register
Enterprise environmental factors
Organizational process assets

Page 122

Tools &
Techniques
Expert judgment
Analogous estimating
Parametric estimating
Bottom-up estimates
Three-point estimates
Reserve analysis
Cost of quality
Project management
software
Vendor bid analysis
Group decisionmaking
techniques

Outputs

Activity cost estimates


Basis of estimates
Project documents updates

PMP Prep: PMBOK 5th - 2013

7.2 Estimate Costs


Estimate Costs is the process of
developing an approximation of the
monetary resources needed to complete
project activities.
Usually they are expressed in monetary
terms, although other units of measure
such as person hours or staff days are
often used.
Costs include the resources to be charged
to the project which includes labor, but
may also include also materials,
equipment and facility fees and services.
Both direct and indirect costs should be
considered.

Page 123

PMP Prep: PMBOK 5th - 2013

7.2 Estimate Costs

PMBOK Fifth Edition, Page 201

Cost estimates are progressively elaborated during the course of the


project as additional detail becomes available. Accuracy increases
through the project life cycle.
For example, a project in the Initiation phase could have a rough
order of magnitude (ROM) estimate in the range of -25% to +75%.
Later in the project as more detail is known, estimates could narrow
to -5% to +10%.

Page 124

PMP Prep: PMBOK 5th - 2013

7.2.2 Estimate Costs


Inputs

Cost Management Plan


(how project costs will be managed and controlled)

Human Resource Management Plan


(project staffing plan, personnel rates, rewards/recognition)

Scope baseline
(Scope statement, WBS, and WBS dictionary)

Project Schedule
(type and quantity of resources and time required to
complete the work)

Risk Register
(negative risks cause near-term costs to increase and project
schedules may be delayed)

EEF and OPA


Pages 123-125

PMP Prep: PMBOK 5th - 2013

7.2.2 Estimate Costs


Inputs

Should be determined per unit of use (e.g., hours, meters, kilos)


Salaries should be known at the individual or group rate
Components of labor rates may include:
base rate
tax burden if applicable (as a percentage of base rate)
benefit burden if applicable (fixed or percentage of base rate)
allocation for overhead (percentage of burdened rate)
Charge Rate = [(Base Rate) * (Burden)] * Overhead

i.e., Charge Rate = [($30/hr) * (1.3)] * 1.8 = $70/hr.

Page 123

PMP Prep: PMBOK 5th - 2013

7.2.2 Estimate Costs


Tools and Techniques
Expert Judgment: consult with experts and obtain historical information.
Analogous Estimating: top-down estimating - a similar project is the basis of estimates
for the current one. It is most reliable when previous projects are similar.
Parametric Estimating: uses a statistical link between historical data and the current
project which is then used for calculation (e.g., cost per square foot).
Bottom-Up Estimating: the smaller the activity, the more accurate is the cost estimate.

Three-Point Estimates (PERT): a weighted average, more accuracy.

Ce =

o + 4m + p
6

Reserve Analysis: a contingency reserve may be used to account for cost uncertainty
Cost of Quality (COQ): determining costs incurred to assure quality

Project Management Software: simplifies cost estimating. Rapid alternatives evaluation


Vendor Bid Analysis: bids from suppliers help analyze what a project should cost
Group Decision-Making Techniques: Delphi or nominal group techniques improve cost
accuracy and the team commitment to cost estimates

Pages 126-129

PMP Prep: PMBOK 5th - 2013

7.2.2 Estimate Costs


Tools and Techniques

Analogous Cost Estimating (a form of expert judgment):


Estimating cost of a current project by extrapolation from actual cost of
a previous project. Also called top-down estimating. Inexpensive but
may also be inaccurate.

Parametric Cost Estimating:


The quantities for specific work multiplied by the resource rate can
estimate cost (number of drawings times cost per drawing, cost per line
of code, cost per square foot for types of construction).

Bottom-Up Estimating:
Rolling up the WBS estimates to get a project total.
Who?

Est. Hours

Task A
Start Date

Page 128

Exam
Tip

People doing the work create time & cost estimates

Stop Date

PMP Prep: PMBOK 5th - 2013

7.2.2 Estimate Costs


Tools and Techniques

3-Point
Analysis or
PERT

o = most optimistic cost estimate


p = most pessimistic cost estimate
m = most likely cost estimate
Ce =

o + 4m + p

(Ce) =

45 50 55 60 65 70 75 80 85 Hours

6
po
6

Ce 1 <=> 68% probability


Ce 2 <=> 95.5% probability
Ce 3 <=> 99.7% probability
Page 128

40

60 5days with 68% confidence


60 10 days with 95.5% confidence
60 20 days with 99.7% confidence

Quantitative Estimate
Indication of Range
Indication of Confidence

PMP Prep: PMBOK 5th - 2013

7.2.3 Estimate Costs


Outputs, Accuracy of Estimates
AACE International Cost Classification Recommended Practices
Class
5
4

3
2
1

Name
Rough Order of Magnitude
(ROM)
Concept

End Usage
Concept Screening

Level of Project Accuracy


Definition Range
0 to 2%

L: -20 to -50%
H: +30 to +100%
Study or Feasibility
1 to 15%
L: -15 to -30%
H: +20 to +50%
These
come
up
often
on
the
exam,
but
are
easy
Exam
Budget/Authorization
Budget Authorization
10 to 40%
L: -10 to -20%
Tip
to answer onceoryou
memorize the numbers. H: +10 to +30%
Control
Definitive/Control
Control or Bid/Tender
30 to 70%
L: -5 to +15%
H: +5 to +20%
Detail/Bid/Tender
Check Estimate or
50 to 100% L: -3 to -10%
Bid/Tender
H: +3 to +15%

PMI, PMBOK
Order of Magnitude Estimates:
(Usually made during Initiation Phase)
Budget Estimate:
(Usually made during the Planning Phase)
Definitive Estimate:
(Roll up of WBS? Rule of 80 hours or two weeks?)

Page 130

-25% to +75%
-10% to +25%
-5% to +10%

PMP Prep: PMBOK 5th - 2013

Planning: Cost Management

PMBOK Fifth Edition, Page 208

7.3 Determine Budget


Inputs
Cost management plan
Scope baseline
Activity cost estimates
Basis of estimates
Project schedule
Resource calendars
Risk register
Agreements
Organizational process assets

Page 131

Tools &
Techniques

Cost aggregation
Reserve analysis
Expert judgment
Historical relationships
Funding limit reconciliation

Outputs

Cost baseline
Project funding requirements
Project documents updates

PMP Prep: PMBOK 5th - 2013

7.3.1 Determine Budget


Determine Budget is the process of aggregating estimated costs of individual activities or
work packages to establish an authorized cost baseline.

The cost baseline is the time-phased project budget, but excludes management reserves.
Inputs

Pages 131-132

Cost Management Plan


Scope Baseline
Activity Cost Estimates
Basis of Estimates
Project Schedule
Resource Calendars
Risk Register
Agreements
Organizational Process Assets

PMP Prep: PMBOK 5th - 2013

7.3.2 Determine Budget


Tools and Techniques
Cost Aggregation: work package costs at the bottom of the WBS are summed
(aggregated) to the next level, then costs at this level are summed to higher levels,
etc. This is called rolling costs up the WBS to develop an overall cost budget.
Reserve Analysis: establishes both contingency reserves (unplanned changes due to
identified risks, known unknowns), and management reserves (unplanned changes to
Exam
project scope and cost, unknown unknowns). Reserves are NOT part of cost baseline,
Tip
and not part of earned value calculations, but are included in the budget.
Expert Judgment: budgeting information from prior, similar projects.
Historical Relationships: parametric analysis from historical sources can predict total
costs. Math models are used.
Funding Limit Reconciliation: funding limits may be set by the customer to which
spending must be reconciled. This might cause rescheduling and reallocation of
resources to regulate cash flow.
Pages 133-134

PMP Prep: PMBOK 5th - 2013

7.3.3 Determine Budget


Outputs, Cost Baseline, or Performance Measurement Baseline (PMB)

Cost Baseline: a time-phased budget (either by period or cumulative over


the life of the project) used to measure, monitor and control project costs.
Cost

Cost Baseline
Exam
Tip

BAC
Cumulative
Planned Value (PV)

Spending Plans
and Cash Flow
Plans are special
types of Cost
Baselines

Monthly Planned
Value (PV)
Time
Page 134

PMP Prep: PMBOK 5th - 2013

Project Budget Components


Project
Budget

Management
Reserve
Cost
Baseline

Control
Accounts

Contingency
Reserve
Work Package
Cost Estimates

Activity
Contingency Reserve

Activity Cost
Estimates

Total
Amount

Project Budget Component


2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

Page 135

PMP Prep: PMBOK 5th - 2013

7.3.3 Determine Budget


Outputs: Funding Requirements and Management Reserve

Project Budget

Cost
Cost Baseline
Cumulative Planned
Value (PV)

BAC

Management
Reserve

Exam
Tip

Cash Flow
Funding
Expenditures

Time

Page 136

PMP Prep: PMBOK 5th - 2013

The Project Management Plan


A Review
Think of the PM plan as a bucket into which all the other plans drip until it is full.

Plan Scope Management


Collect Requirements
Define Scope
Create WBS
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Plan Cost Management
Estimate Costs

Pages 45 & 49

Determine Budget
Plan Quality Management
Plan Human Resource Management
Plan Communications Management
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Response
Plan Procurement Management
Plan Stakeholder Management

PMP Prep: PMBOK 5th - 2013

Exercise
Make a list of items that go into a Project Plan in the spaces provided below :

PMP Prep: PMBOK 5th - 2013

Exercise
Make a list of items that go into a Project Plan in the spaces provided below :
Project Management Plan

Estimate Costs

Plan Scope Management

Determine Budget

Collect requirements

Plan Quality

Define Scope

Develop HR Plan

Create WBS

Plan Communications

Plan Schedule Management

Plan Risk Management

Define Activities

Identify Risks

Sequence Activities

Perform Qual. Risk Analysis

Est. Activity Resources

Perform Quant. Risk Analysis

Est. Activity Durations

Plan Risk Responses

Develop Schedule

Plan Procurement

Plan Cost Management

Plan Stakeholder Mgt.


PMP Prep: PMBOK 5th - 2013

Chapter 8: Project Quality Management


PMBOK Fifth Edition, Page 227

Knowledge Area
Quality management processes include:
8.1 Plan Quality Management: The process of identifying quality requirements/standards
for the project and its deliverables, and documenting how the project will demonstrate
compliance.
8.2 Perform Quality Assurance: The process of auditing the quality requirements, and
results from quality control measurements, to ensure that appropriate quality
standards and operational definitions are used.
8.3 Control Quality: The process of monitoring and recording results from executing quality
activities to assess performance and recommend changes.
Quality management here is compatible with ISO (International Organization for Standardization) as well as
Shewhart, Deming, Juran, Crosby, FMEA (Failure Modes and Effects Analysis), Customer Satisfaction, The
Voice of the Customer, Prevention over Inspection, COQ (Cost of Quality), and Continuous Improvement
(Total Quality Management, Six-Sigma, maturity models), and Management Responsibility.

Quality is the degree to which a set of inherent


characteristics fulfill requirements
Page 139

PMP Prep: PMBOK 5th - 2013

Chapter 8: Project Quality Management


Quality vs. Grade
Quality:

The degree to which a set of


inherent characteristics fulfill
requirements.

Grade:

Products that perform the same


function but have different technical
characteristics.

Exam
Tip

A product may be high quality (no obvious defects)


but low grade (limited number of features)

Page 139

PMP Prep: PMBOK 5th - 2013

Chapter 8: Project Quality Management


Precision vs. Accuracy
Exam
Tip

Precision

Consistency.

Accuracy

Correctness.

Precision: repeated measurements have little scatter.


Accuracy: measured value is close to the true value.
Precision

Accuracy

Page 140

PMP Prep: PMBOK 5th - 2013

Note to Test Takers


Quality is one of the most heavily
tested areas on the examination.
Study it completely during your
preparations to take the test!

Page 141

PMP Prep: PMBOK 5th - 2013

Planning: Project Quality Management


8.1 Plan Quality Management
Inputs

Project management plan


Stakeholder register
Risk register
Requirements documentation
Enterprise environmental factors
Organizational process assets

Page 142

Tools &
Techniques
Cost-benefit analysis
Cost of quality (COQ)
Seven basic quality tools
Benchmarking
Design of experiments
Statistical sampling
Additional quality planning
tools
Meetings

Outputs

Quality management plan


Process improvement plan
Quality metrics
Quality checklists
Project documents updates

PMP Prep: PMBOK 5th - 2013

8.1 Plan Quality Management

PMBOK Fifth Edition, Page 231

Plan Quality is the process of identifying


quality requirements and/or standards
for the project and its deliverables, and
documenting how the project will
demonstrate compliance.
The Quality Management Plan, which is
an output of this process, describes how
the project management team will
implement the quality policy and meet
the quality requirements.
Quality is planned, designed, and built into the project.
It is not inspected in.

Page 142

PMP Prep: PMBOK 5th - 2013

8.1.1 Plan Quality Management


Inputs

Project Management Plan, which includes:


Scope Baseline (Scope statement, WBS, and WBS dictionary),
Schedule & Cost Baselines, etc.

Stakeholder Register
Risk Register
Requirements Documentation
(stakeholder quality requirements)

EEF and OPA

Pages 142 & 143

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques

Cost-Benefit Analysis: compares COQ with expected benefits.


Cost of Quality (COQ): investment in preventing non-conformance to requirements.
Seven Basic Quality Tools: (1) cause and effect diagrams, (2) flowcharts, (3)
checksheets, (4) Pareto diagrams, (5)histograms, (6) control charts, (7) scatter
diagrams.
Benchmarking: comparing to similar projects to identify best practices.
Design of Experiments: statistical: what factors influence project variables?
Statistical Sampling: inspecting part of a batch to qualify the whole population.
Additional Quality Planning Tools: brainstorming, force field analysis, nominal group
technique, quality management and control tools.
Meetings

Pages 144 - 151

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality


Tools and Techniques: Quality Definitions

Conformance to Requirements, Specifications and Fitness For Use:

This one phrase will help you to answer about 4 questions on the exam.
Memorize it!

The PM should perform careful needs analysis of the stakeholders which


become foundations of the Scope

Gold Plating:

Exam
Tip

PMI does not support giving the customer extras.

Gold Plating adds no value to the project.

Exam questions have the team members coming to the PM with impressions of what
the customer would like.

Prevention over Inspection


Note: There may be 15 or more questions relating to definitions and control charts

Page 143

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality


Tools and Techniques: Cost of Quality (COQ)

Cost of Conformance

Cost of Nonconformance

Prevention Costs

Internal Failure Costs

(Build a quality product)

(Failures found by project team)

Training
Documentation processes
Equipment
Time to do it right

Rework
Scrap
External Failure Costs
(Failures found by the customer)

Appraisal Costs
(Assess the quality)

Testing
Destructive testing loss
Inspections

Money spent to avoid failures


Page 145

Liabilities
Warranty work
Lost business
Money spent because of failures
Exam
Tip

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Flowcharting

Cause & Effect, Ishikawa or Fishbone Diagrams


People

Not Following
Procedures

Material

Methods

Lack of Training

CAUSES

Transport

IT System

EFFECT

Procedure

Process Flowchart
Design

Yes

Review

OK?

Proceed

No

Revise
Page 145-146

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Flowcharting, SIPOC Model
Suppliers
____________
____________
____________

Inputs
____________
____________
____________

Process
____________
____________
____________

Outputs
____________
____________
____________

Input
Supplier

Customers
____________
____________
____________

Output
Process

Requirements and
Feedback Loop

Customer
Requirements and
Feedback Loop

Requirements List

Measurements List

Requirements List

Measurements List

____________
____________
____________

_____________
_____________
_____________

_____________
_____________
_____________

_____________
_____________
_____________

2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

Page 145-146

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management

% contribution (or frequency of occurrence)

Tools and Techniques: Pareto Diagrams and Design of Experiments

80%?

Paretos Law:

Design of Experiments:

80/20 Rule

Which factors may influence


specific variables?
What If Analysis

source
Page 147

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Histograms

A histogram shows central tendency, dispersion,


and shape of a statistical distribution.
1.5

1.0

0.5

Page 147

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Control Charts

A chart of process performance over time used to


determine if the process is in control or out of control

UCL

3
99.7%

.
.
.
.
.
.
.. . . . . .. . . .
. .. . .. . .
.. . . .
.
.
..
.
.
2
95.5%

Expected
Variation

Out of Control
(Assignable Cause)

1
68%

Normal
Distribution
Curve

Mean

LCL

in control
normal distribution of outcomes
due to common causes of variation
inherent in the process
Page 148

out of control
rule of seven, trends, and cycles
due to special causes of variation
external to the process
PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Control Chart

Hours recorded for this project


started on plan, but if the trend
continues, hours spent will drift
out of control.

Upper Spec. Limit


UCL
Plan or Mean
LCL
Lower Spec. Limit

Actual

Page 149

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Scatter Diagram

Page 149

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Scatter Diagram

Timecard Submission vs. Travel Days


Submission Days, Early (-), Late (+)

o o o o
o

o
o o o
o o o o

2
o

o o o o
o
5

0
0
-2

10

15

20

25

o
o

-4
o

-6
Total Travel Days in the Month

Page 150

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Seven Basic Quality Tools

2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

PMBOK Fifth Edition, Page 239

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Statistical Sampling

a technique for accepting or rejecting a larger population


by choosing a part of the population for inspection ...
Statistical sampling can reduce the cost of QC on a project.
The validity of statistical sampling depends on an
appropriate choice of sample items and sample size.
Sample size increases exponentially as the level of desired certainty
increases and the acceptable level of error decreases.
Sampling strategies include single samples from a lot, multiple small
samples from a lot, and double sampling methods where the size of the
second sample depends on the results of the first sample.

All sampling strategies involve some risk of producer error (type I error)
where acceptable lots are rejected based on a non-representative sample
or consumer error (type II error) where unacceptable lots are accepted
based on a non-representative sample.
Page 150-151

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality Management


Tools and Techniques: Additional Quality Planning Tools, Affinity Diagram

These include brainstorming, affinity diagrams, force field analysis, nominal


group techniques, matrix diagrams, flowcharts, and prioritization matrices.
Affinity Diagrams are useful for gathering large amounts of data (opinions, ideas etc.) and for organizing them into
groupings based on their relationship. An Affinity Diagram can help to identify patterns within data providing
recourse for further investigation or action.

Force Field Analysis looks at all the forces for and against a decision. In effect, it is a specialized method of
weighing pros and cons. You can plan to strengthen the forces supporting a decision, and reduce the impact of
opposition to it.

A nominal group technique is a structured process which identifies and ranks the major problems or issues that
need addressing.

Page 151

PMP Prep: PMBOK 5th - 2013

8.1.2 Plan Quality


Tools and Techniques: Additional Quality Planning Tools, Group Creativity

Brainstorming: a method of joint creative thinking that first records and


considers all possible options/solutions without judgment before
proceeding to critical evaluation of the project/product requirements.
Nominal Group Technique: enhances brainstorming with a voting process
to rank the best ideas for further brainstorming or prioritization.
Delphi Technique: questionnaires are sent to a group of experts who
provide answers and are kept anonymous. Responses are compiled,
prioritized, and sent back for another round of requirements gathering. A
method for building consensus.
Idea/Mind Mapping: a graphical method of consolidating brainstorm ideas
to show commonality and differences and to generate new ideas.
Affinity Diagram: gathering large numbers of ideas and sorting them into
groups for review and analysis they help to identify patterns within data.
Page 151

PMP Prep: PMBOK 5th - 2013

8.1.3 Plan Quality Management


Outputs

Quality Management Plan


Process Improvement Plan
(process boundaries, configuration, metrics, and targets for
improved performance)

Quality Metrics
Quality Checklists
Project Documents Updates
(stakeholder register, responsibility assignment matrix, WBS,
WBS dictionary, etc.)

Pages 152 & 153

PMP Prep: PMBOK 5th - 2013

8.1.3 Plan Quality Management


Outputs: Update Responsibility Assignment Matrix (RACI Chart)

R
A
C
I

Pages 155

=
=
=
=

Responsible
Accountable
Consulted
Informed

PMP Prep: PMBOK 5th - 2013

Chapter 9: Plan Human Resource Management


PMBOK Fifth Edition, Page 255

Knowledge Area
Project Human Resource Management processes include:
9.1 Plan Human Resource Management: The process of identifying and documenting
project roles., responsibilities required skills, reporting relationships, and creating a
staffing management plan.
9.2 Acquire Project Team: confirming HR availability and obtaining the team to complete
project activities.
9.3 Develop Project Team: improving competencies, team members interaction, and team
environment to enhance performance.
9.4 Manage Project Team: tracking team member performance, providing feedback,
resolving issues, and managing change to enhance project performance.

Human resource management includes the processes


that organize, manage, and lead the project team
The project management team (core, executive, or
leadership team) is a subset of the project team
and is responsible for leadership activities.
Page 155

Exam
Tip

PMP Prep: PMBOK 5th - 2013

Planning: Human Resource Management

PMBOK Fifth Edition, Page 258

9.1 Plan Human Resource Management


Inputs

Project management plan


Activity resource requirements
Enterprise environmental factors
Organizational process assets

Page 156

Tools &
Techniques

Organization charts and


position descriptions
Networking
Organizational theory
Expert judgment
Meetings

Outputs

Human resource management


plan

PMP Prep: PMBOK 5th - 2013

9.1 Plan Human Resource Management


PMBOK Fifth Edition, Page 258

Plan Human Resource Management is the


process of identifying and documenting
project roles, responsibilities, required skills
and reporting relationships and creating a
staffing management plan

Page 156

PMP Prep: PMBOK 5th - 2013

9.1.2 Plan Human Resource Management


Tools and Techniques: Organization Charts and Position Descriptions

Hierarchical Chart

Project Organization Chart. shows project team members related to their work on
the project. Simply substitute the name of the team member into the box of the WBS
Banking
Protocols

Customer
Services
(TM #1)
Product
Planning
(TM #11)
Sales
(TM #12)

Information
Tech. and IS
(TM #2)
System Analysis
(TM #21)
System Design
(TM #22)
System
Development
(TM #23)

Pages 158-159

Operations
(TM #3)

Training
(TM #31)
Integration
Protocols
(TM #32)

Regulatory
(TM #4)

Project
Management
(PM)

Treasury
(TM #5)

Legal
(TM #41)

Global Trans.
Services
(TM #51)

Accounting
Relations
(TM #61)

Filing &
Documentation
(TM #42)

Cash
Management
(TM #52)
Audit &
Inspection
(TM #53)

Strategic
Planning
(TM #62)

PMP Prep: PMBOK 5th - 2013

9.1.2 Plan Human Resource Management


Tools and Techniques: Organization Charts and Position Descriptions

Resource Breakdown Structure and Organizational Breakdown Structure

Resource Breakdown Structure breaks down projects by type of resource. It can


help track project costs and can contain categories other than human resources.

Organizational Breakdown Structure (OBS) is a depiction of the project


organization arranged to relate work packages to functional departments.

Pages 158-159

PMP Prep: PMBOK 5th - 2013

9.1.2 Plan Human Resource Management


Tools and Techniques: Organization Charts and Position Descriptions

Organizational Breakdown Structure


Project

Cost Accounts provide a


way to control how
functional organizations
to charge to projects.

Page 159

Comp. #2

Assembly

Cost
Account

Cost
Account

Parts

Production
Comp. #1

Cost
Account

Cost
Account

Comp. #2

Electrical

Comp. #1

Cost
Account

Cost
Account

Mechanical

Engineering

Company

Manufacturing

WBS Codes show


functional managers
exactly what their
people are doing on
the project.

Design

Cost
Account

Cost
Account

PMP Prep: PMBOK 5th - 2013

9.1.2 Plan Human Resource Management


Tools and Techniques: Organization Charts and Position Descriptions

Matrix Charts
Responsibility Assignment Matrix (RAM)
RAM (n.) a structure that relates the OBS to the WBS to ensure that
the scope of work components are assigned to a responsible person.

Tom

Bob

Gavin

Mary

Dave

PMI advocates that all roles and responsibilities on a project be


clearly assigned and be linked to scope and to the WBS.

Design

Lead

Support

Advise

Advise

Advise

Prototype

Support

Lead

Advise

Advise

Advise

Scale Up

Advise

Advise

Lead

Support

Support

Production

Advise

Advise

Advise

Lead

Support

Assembly

Advise

Advise

Advise

Support

Lead

R
A
C
I

=
=
=
=

Responsible
Accountable
Consulted
Informed

Often used for decision responsibilities or to resolve conflict.


Multiple RAMs at different levels of the project, also called LRCs.
Other responsibility charts: Resource Histogram, Resource Gantt
Chart - know these.

Page 160

PMP Prep: PMBOK 5th - 2013

9.1.2 Plan Human Resource Management


Tools and Techniques: Organization Charts and Position Descriptions

Text-Oriented Forms

Position Descriptions
show team member
responsibilities,
authority,
competencies, and
qualifications
outlined in a text
document. These can
be used for
Performance
Evaluations

Page 161

PMP Prep: PMBOK 5th - 2013

9.1.3 Plan Human Resource Management


Outputs

Human Resource Management Plan


roles and responsibilities, project organization charts,
staffing management plan:
Staff Acquisition
Resource Calendars
Staff Release Plan
Training Needs
Recognition and Rewards
Compliance

Safety.

Pages 162-163

PMP Prep: PMBOK 5th - 2013

9.1.2 Develop Human Resource Plan


Outputs: Resource Calendars,

PMBOK Fifth Edition, Page 265

Resource Histogram is a time-phased display of


the amount of project work assigned to each resource

Page 163

May be used at the individual or group level


May be used to detect over-allocation of resources
PMP Prep: PMBOK 5th - 2013

Chapter 10: Project Communications Management


PMBOK Fifth Edition, Page 287

Knowledge Area
Project Communications Management processes include:
10.1

Plan Communication Management: the process of developing an


appropriate approach and plan for project communications based on
stakeholders information needs and requirements,

10.2

Manage Communications: the process of creating, collecting, distributing,


storing, retrieving, and disposition of project information.

10.3

Control Communications - the process of monitoring and controlling


communications throughout the entire project life cycle to ensure
information needs of stakeholders are met.

Project Communications Management includes the processes


required to ensure timely and appropriate generation, collection,
distribution, storage, retrieval, and disposition of project information.

Page 164

PMP Prep: PMBOK 5th - 2013

Planning: Project Communications Management


10.2 Plan Communications Management
Inputs

Project management plan


Stakeholder register
Enterprise environmental factors
Organizational process assets

Page 165

Tools &
Techniques

Communication requirements
analysis
Communication technology
Communication models
Communication methods
Meetings

Outputs

Communications
management plan
Project documents updates

PMP Prep: PMBOK 5th - 2013

10.2 Plan Communications Management


PMBOK Fifth Edition, Page 289

Communications Management is so
important that it is sometimes included
as a major WBS element

Typical
Project

Study

Page 165

Concept

Prototype

Qualification

Pilot

Production

Project
Management &
Communications
Plan

PMP Prep: PMBOK 5th - 2013

10.2.2 Plan Communications Management


Tools and Techniques

Communications Requirements Analysis


Consider the following information as you plan your project
communications:
the project organization and stakeholder responsibility relationships
the functional departments involved in the project
the logistics: persons involved with the project and their locations
external information needs: communicating with external
stakeholders and the media

Communication Technology
Communications planning will be both enhanced and constrained by the
available communications technology.
urgency of need for the information
availability, ease of use, and cost of the technology
experience and expertise of the project staff and other stakeholders
life of the available technology relative to the length of the project
project environment. Does the team meet face-to-face or in a virtual
environment
Sensitivity and confidentiality of the information.

Pages 166-167

PMP Prep: PMBOK 5th - 2013

10.2 Plan Communications Management


Tools and Techniques

Plan Communications is the process of


determining the project stakeholder information
needs and defining a communication approach

The formula:
Channels =

N(N 1)
2

Reveals the number of possible channels


of communication in a group, where N is
the number of people in the group

Page 166-167

PMP Prep: PMBOK 5th - 2013

10.2.2 Plan Communications Management


Tools and Techniques

Try it .
If a project team of 5 people adds one
more person to the team, how many more
channels of Communication are there?

5 more
Page 167

PMP Prep: PMBOK 5th - 2013

10.2.2 Plan Communications Management


Tools and Techniques: Communication Models

Sending
Thinking

The basic model of communication is the


send-receive model which includes:
Encoding (translating ideas to language),
Transmit Message (transmitting),
Medium (methods used to transmit)
Noise (disruptions), and
Decoding (translate for receiver)
Acknowledge (receipt of message)
Feedback (back to sender).

Hearing
Articulating
Transmitting

Listening

Receiving

Feedback !!
Page 168

PMP Prep: PMBOK 5th - 2013

10.2.3 Plan Communications Management


Outputs: Communications Management Plan

The Communications Management Plan usually provides:

Page 169

Stakeholder communication requirements


Information to be distributed
Reason for the distribution
Time frame and frequency
Communication responsibilities

PMP Prep: PMBOK 5th - 2013

10.2.3 Plan Communications


Outputs: Communications Management Plan

documents a communication strategy for the project and describes:

Page 170

Stakeholder communication requirements


Which information flows from whom, when, via which media, and in what format.
Schedule and frequency for information collection and distribution.
Methods to convey information (memos, e-mail, press releases, etc.)
Resources for communication activities, including time and budget
Problem escalation procedure
Method for updating the communication plan
Flow charts of information flow
List of reports and meetings planned (schedule and attendees)
Communications constraints
Communications infrastructure for the project (who may talk to whom)

PMP Prep: PMBOK 5th - 2013

Chapter 11: Project Risk Management


PMBOK Fifth Edition, Page 309

Knowledge Area
Project Risk Management processes include:
11.1 Plan Risk Management: deciding how to approach, plan and execute risk management,
11.2 Identify Risks: which risks might affect the project and documenting their characteristics,
11.3 Perform Qualitative Risk Analysis: probability of occurrence and severity of impact,
11.4 Perform Quantitative Risk Analysis: numerically analyzing the effect of risks on
objectives,
11.5 Plan Risk Responses: developing options to enhance opportunities and reduce threats.
11.6 Control Risks: implementing risk response plans, tracking risks, monitoring residual risks,
ID new risks, and evaluating effectiveness throughout the project life cycle.

Project risk management includes the processes of


conducting risk planning, identification, analysis, response
planning, and monitoring and control on a project.
Page 171

PMP Prep: PMBOK 5th - 2013

Chapter 11: Project Risk Management


Project risk includes both threats to the projects objectives
(negative outcomes) and opportunities to improve on those
objectives (positive outcomes) - PMBOK Fifth Edition, page 310.
Uncertainty: An uncommon state of nature, characterized by
absence of information related to a desired outcome.
Risk Management: The process of identifying, analyzing and
responding to risk - maximizing positive events and minimizing
consequences of negative events.
Risk arises throughout a project and must be identified and
evaluated on a regular basis over the life cycle of the project.
Inputs to risk management process : All other planning processes,
including Create WBS and
Exam
Tip

Page 171

PMP Prep: PMBOK 5th - 2013

Planning: Project Risk Management

PMBOK Fifth Edition, Page 313

11.1 Plan Risk Management


Inputs

Project management plan


Project charter
Stakeholder register
Enterprise environmental factors
Organizational process assets

Page 173

Tools &
Techniques

Analytical techniques
Expert judgment
Meetings

Outputs

Risk management plan

PMP Prep: PMBOK 5th - 2013

11.1 Plan Risk Management


Plan Risk Management is the process of defining how to conduct
risk management activities for a project.
Risk planning should be commensurate with both the risks and the
importance of the project to the organization

Page 173

PMP Prep: PMBOK 5th - 2013

11.1.1 Plan Risk Management


Inputs

Project Management Plan


provides current state of risk-affected areas including
scope, schedule, and cost

Project Charter
high-level requirements

Stakeholder Register
EEF and OPA

11.1.2 Tools and Techniques: Analytical Techniques, Expert Judgment, and Meetings

Pages 174-175

PMP Prep: PMBOK 5th - 2013

11.1.3 Plan Risk Management


Outputs

Risk Management Plan, includes:


Methodology: Approaches, tools and data sources.
Roles and Responsibilities: Team member ownership for risk activities.
Budgeting: Funds needed for contingency reserves and management reserves.
Timing: When processes will be done, reserves applied, and how risk appears in schedule.
Categories: Risk groupings. The RBS looks at sources of risk, IDs and categorizes them.
Thresholds: What is the trigger? Stakeholders have different thresholds of risk tolerance,
define them, and the must be agreed by all.
Define P/I Levels: Qualitative (low to high) or probabilities.
Risk Matrix: Likelihood-Severity, or Probability-Impact.
Stakeholder Risk Tolerances: Progressively elaborated.
Reporting Formats and Tracking: Document risk, auditing, defines content of risk register.

Page 176

PMP Prep: PMBOK 5th - 2013

Planning: Project Risk Management

PMBOK Fifth Edition, Page 319

11.2 Identify Risks


Inputs
Risk management plan
Cost management plan
Schedule management plan
Quality management plan
Human resource mgt. plan
Scope baseline
Activity cost estimates
Activity duration estimates
Stakeholder register
Project documents
Procurement docs.
EEF
OPA

Page 177

Tools &
Techniques
Documentation reviews
Information gathering
techniques
Checklist analysis
Assumptions analysis
Diagramming techniques
SWOT analysis
Expert judgment

Outputs

Risk register

PMP Prep: PMBOK 5th - 2013

11.2 Identify Risks


Identify Risks is the process
of determining which risks
may affect the project and
documenting their
characteristics .
All project personnel should
be encouraged to identify
potential risks

Page 177

PMP Prep: PMBOK 5th - 2013

11.2.1 Identify Risks


Inputs

Risk Management Plan


provides risk responsibilities, risk breakdown structure

Pages 178

Cost, Schedule, Quality, and HR Management Plans


Scope Baseline (scope statement, WBS, WBS dictionary)
Activity Cost and Duration Estimates
Stakeholder Register
Project Documents (Charter, schedule, network, issue log)
Procurement Documents
EEF and OPA

PMP Prep: PMBOK 5th - 2013

11.2.2 Identify Risks


Tools and Techniques: Information Gathering Techniques

Brainstorming: a method of joint creative thinking that first records and


considers all possible options/solutions without judgment before proceeding
to critical evaluation of the project/product requirements.
Delphi Technique: questionnaires are sent to a group of experts who provide
answers and are kept anonymous. Responses are compiled, prioritized, and
sent back for another round of requirements gathering. A method for
building consensus.
Interviewing: experienced stakeholders and SME can identify risks
Root Cause Analysis: Cause and Effect analysis to find causes and develop
prevention actions.

Page 179

PMP Prep: PMBOK 5th - 2013

11.2.2 Identify Risks


Tools and Techniques: Checklist Analysis

Checklist Analysis:
Risk identification checklists are developed from previous
projects or lessons learned.
Lowest level of the WBS or RBS can be used as checklists.
Teams should explore items not on the checklist. It
should be pruned as it is progressively elaborated.
Review the checklist during project closure to incorporate
new lessons learned.

Page 180

PMP Prep: PMBOK 5th - 2013

11.2.2 Identify Risks


Tools and Techniques: Assumption Analysis

Assumption: a factor in the planning process considered to be


true, real, or certain, without proof or demonstration:

resource, equipment, and facilities availability


external timelines
technology compatibility
interpretation of legal and regulatory constraints

Assumption Analysis: explores the accuracy of


assumptions and identifies risks to the project
from inaccuracy, inconsistency, or incompleteness,
Assumptions involve risk -- identify the risk!
Page 180

PMP Prep: PMBOK 5th - 2013

11.2.2 Identify Risks


Tools and Techniques: Diagramming Techniques

Cause & Effect, Ishikawa or Fishbone Diagrams


People

Not Following
Procedures

Material

Methods

Lack of Training

CAUSES

Transport

Page 181

IT System

EFFECT

Procedure

PMP Prep: PMBOK 5th - 2013

11.2.2 Identify Risks


Tools and Techniques: Diagramming Techniques

An Influence Diagram is a visual representation of situations


showing causal influences, time ordering of events, or other
relationships among variables.

For example, Unit sales is a confluence point. What is the


probability that all activities leading into it and out of it will
happen at the scheduled time? It is a causal influence of risk.
Page 181

PMP Prep: PMBOK 5th - 2013

11.2.2 Identify Risks


Tools and Techniques: Diagramming Techniques

Influence Diagram
Project
Estimates

Risk
Condition

Project
Activity

Deliverables

2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

Page 181

PMP Prep: PMBOK 5th - 2013

11.2.3 Identify Risks


Outputs: Risk Register

Risk Register
a document where results of risk analysis and risk
response planning are recorded:
List of identified risks

EVENT may occur causing IMPACT

If CAUSE exists, EVENT may occur leading to EFFECT

List of potential responses

Page 182

PMP Prep: PMBOK 5th - 2013

Planning: Project Risk Management

PMBOK Fifth Edition, Page 328

11.3 Perform Qualitative Risk Analysis


Inputs

Risk management plan


Scope baseline
Risk register
Enterprise environmental factors
Organizational process assets

Page 183

Tools &
Techniques

Risk probability and impact


assessment
Probability and impact matrix
Risk data quality assessment
Risk categorization
Risk urgency assessment
Expert judgment

Outputs

Project documents updates

PMP Prep: PMBOK 5th - 2013

11.3 Perform Qualitative Risk Analysis


Perform Qualitative Risk Analysis
is the process of prioritizing risks for
further analysis or action by assessing
or combining their probability of
occurrence and impact.
The Perform Qualitative Risk Analysis
assesses priority of identified risks
using probability/Impact or
likelihood of occurrence/severity
analysis to determine impact on
project objectives if the risks occur.

Probability

Impact

Page 183

PMP Prep: PMBOK 5th - 2013

11.3.1 Perform Qualitative Risk Analysis


Inputs

Risk Management Plan


provides risk responsibilities, budget/schedule, P/I matrix,
stakeholder risk tolerance, etc.

Scope Baseline (scope statement, WBS, WBS dictionary)


Risk Register
EEF and OPA

Page 184

PMP Prep: PMBOK 5th - 2013

11.3.2 Perform Qualitative Risk Analysis


Tools and Techniques, Risk P/I Assessment

Risk Probability and Impact Assessment


Probability is the likelihood that a risk event will occur.
Impact is the effect (severity) on the objective (scope, schedule,
cost, quality, performance) if the risk event occurs.
These apply to specific risk events, not to the overall project.
High likelihood and high consequence defines a risk that must be
managed aggressively, or must be mitigated.

Risks with low P/I ratings will be included on a watch list.

Page 184

PMP Prep: PMBOK 5th - 2013

11.3.2 Perform Qualitative Risk Analysis


Tools and Techniques, Probability and Impact Matrix

Risk Probability and Impact Matrix


The risk matrix is one of the simplest and most effective tools
to analyze risk. It has probability (likelihood) on one axis and
impact (consequence or severity) on the other.
The scales can be either numeric or subjective.
The organization should determine the threshold
of risk that can be tolerated. This will determine:
high risk (red light),
moderate risk (yellow light), and
low risk (green light).
The score guides risk response actions.

Page 185

PMP Prep: PMBOK 5th - 2013

2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

11.3.2 Perform Qualitative Risk Analysis


Tools and Techniques: P/I Matrix
Project risk includes both threats to the projects objectives (negative outcomes) and
opportunities to improve on those objectives (positive outcomes) - PMBOK 5th Edition, 331.
Exam
Tip

Probability

Threats

Opportunities

0.90 0.05 0.09 0.18 0.36 0.72 0.72 0.36 0.18 0.09 0.05

0.70 0.04 0.07 0.14 0.28 0.56 0.56 0.28 0.14 0.07 0.04
0.50 0.03 0.05 0.10 0.20 0.40 0.40 0.20 0.10 0.05 0.03
0.30 0.02 0.03 0.06 0.12 0.24 0.24 0.12 0.06 0.03 0.02
0.10 0.01 0.01 0.02 0.04 0.08 0.08 0.04 0.02 0.01 0.01

0.05 0.10 0.20 0.40 0.80 0.80 0.40 0.20 0.10 0.05
Impact (ratio scale) on an Objective
Page 185

PMP Prep: PMBOK 5th - 2013

11.3.2 Perform Qualitative Risk Analysis


Tools and Techniques: Risk Matrix

Risk Legend
Unacceptable

Must Mitigate

High

Managed
Controlled

Medium

Low

Identified, no
contingent plan
Low

Medium

High

Likelihood (Probability)

Page 186

PMP Prep: PMBOK 5th - 2013

11.3.2 Perform Qualitative Risk Analysis


Tools and Techniques:
Industry Guidelines

Page 196

PMP Prep: PMBOK 5th - 2013

11.3.3 Perform Qualitative Risk Analysis


Outputs: Project Documents Updates

Project Documents Updates


Risk register

Assessments of P/I for each risk

Risk ranking

Risk categorization

Watch list for low probability risks

Assumptions log updates

Page 187

PMP Prep: PMBOK 5th - 2013

Planning: Project Risk Management

PMBOK Fifth Edition, Page 333

11.4 Perform Quantitative Risk Analysis


Inputs

Risk management plan


Cost management plan
Schedule management plan
Risk register
Enterprise environmental factors
Organizational process assets

Page 188

Tools & Techniques

Data gathering and


representation techniques
Quantitative risk analysis and
modeling techniques
Expert judgment

Outputs

Project documents updates

PMP Prep: PMBOK 5th - 2013

11.4 Perform Quantitative Risk Analysis


Perform Quantitative Risk Analysis
is the process of numerically analyzing the
effect of identified risks on overall project
objectives.
Perform Quantitative Analysis is used on
risks that have been prioritized by
qualitative analysis as substantially
impacting project objectives.

Page 188

PMP Prep: PMBOK 5th - 2013

11.4 Perform Quantitative Risk Analysis


Quantitative risk analysis
The Quantitative process analyzes priority risk events and assigns a
numerical rating. It also helps you make decisions in areas of uncertainty.
Quantitative Risk process uses techniques like Monte Carlo Simulation
and decision tree analysis to:
Quantify outcomes for the project and the probabilities.

Assess the probability of achieving project objectives


Identify priority risks by quantifying their contribution to overall
project risk.
Identify realistic cost, schedule, scope and quality targets, given the
project risks.
Determine the best project decision when some outcomes are
uncertain.

Page 188

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Data Gathering and Representation Techniques

Risk Interview
WBS Element

Optimistic

Most Likely

Pessimistic

Design

$4 M

$6 M

$10 M

Build

$16 M

$20 M

$35 M

Test

$11 M

$15 M

$23 M

Total Project

$31 M

$41 M

$68 M

Likelihood of completing the project at or below $41 million is


relatively low given the range and skew of the simulation results.
2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

Page 190

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Data Gathering and Representation Techniques

Probability Distributions

3-Point
Analysis or
PERT

o = most optimistic cost estimate


p = most pessimistic cost estimate
m = most likely cost estimate
Ce =

o + 4m + p

(Ce) =

45 50 55 60 65 70 75 80 85 Hours

6
po
6

Ce 1 <=> 68% probability


Ce 2 <=> 95.5% probability
Ce 3 <=> 99.7% probability
Page 190

40

60 5 hours with 68% confidence


60 10 hours with 95.5% confidence
60 20 hours with 99.7% confidence

Beta Distribution

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Quantitative Risk Analysis and Modeling Techniques

Sensitivity Analysis
Sensitivity Analysis helps determine which risks have the most impact on a project. A typical display
of sensitivity is the tornado diagram, which compares the importance of variables having high
uncertainty to those that are more stable.

Expected Monetary Value


Expected Monetary Value (EMV) calculates average outcomes on uncertain future scenarios. The
EMV of opportunities will be positive values, where those of risks may be negative. That is, when
evaluating alternatives during project selection, EMV that is most positive (the higher number) is
probably the best outcome. However, when alternative risks are evaluated, perhaps the lower
number (minimum risk) is best.

Decision Tree Analysis


Decision Tree Analysis is a common use of EMV analysis. It incorporates the cost of each available
choice, the probabilities in each path, and the outcomes. Solving the decision tree provides the
EMV for each alternative. As said before, in selecting competing projects the higher number may
give the best payback, but in evaluating risk alternatives, the lower number may be best.
Pages 191-193

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Quantitative Risk Analysis and Modeling Techniques
Sensitivity Analysis: Tornado Diagram

High
Risk 1

Variables

Low

Uncertainty

Risk 2
Risk 3
What is a Tornado Diagram?
The purpose of sensitivity analysis is to
identify which uncertainty variables have
the greatest impact on total value.
Why create a Tornado Diagram?
The tornado diagram helps identify
uncertainties with the highest economic
impact. (Risk-Adjusted NPV). 80% of the
total uncertainty can be discovered by using
the top 5-8 variables in the tornado diagram

Page 191

Uncertainty
at base
Values

Risk 4
Risk 5
(+) Positive Impact
(-) Negative Impact

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Quantitative Risk Analysis and Modeling Techniques
Expected Monetary Value (EMV)
$ 12,000

$ 10,200

$ 10,000
$ 8,000

$ 10,000

$ 12,000

Select B for lowest Risk


Page 192

PMP Prep: PMBOK 5th - 2013

Exercise
A Decision Tree : a common use of EMV analysis
0.6
Flagship store in
new mall
(-$1,000,000)

0.8
Renovate existing
store
(-$250,000)

Stronger
competition
(-$50,000)

Initial business
surge
(+$50,000)

-$230,000

0.2

Page 192

Answer:

-$960,000
0.4

New store or
renovation?

Increased shopper
traffic
(+$100,000)

Dwindling shopper
traffic
(-$100,000)

PMP Prep: PMBOK 5th - 2013

Exercise
Exam
Tip

EMV is the second most-tested topic on the


exam after the process of risk management

1. Test yourself:

You are planning modifications to a product line. Below is the


complete assessment of risks on the project Calculate the EMV of
your budgets reserve.

Page 193

30% probability that parts delivery will be delayed at a cost of


$50,000.

20% chance that the parts will be $10,000 less expensive.

25% likelihood that two parts will have interference fit,


resulting in extra cost of $3,500.

30% chance that production will be simpler, saving us $2,500.

5% probability that design defects will cause $5,000 in rework.

- $13,375

+
-

PMP Prep: PMBOK 5th - 2013

Exercise
2. Test yourself on a decision tree:
What is the EMV of A and B?

B
A

Answer: $42K+$6K = $48K

Page 193

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Quantitative Risk Analysis and Modeling Techniques
Modeling and Simulation

Monte Carlo Simulation


The most common simulation technique is Monte Carlo simulation.
Earlier in the workbook it was called What-If analysis, where a
computer is used to calculate a distribution of possible outcomes for
the total project.
For example, calculate multiple project durations with different sets
of activity assumptions and calculate a risk probability distribution.
For cost risk, simulations can use the WBS or cost breakdown
structure as its model.

For schedule risk, simulations use Precedence Diagramming Method


(PDM) models.

Page 193

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Quantitative Risk Analysis and Modeling Techniques
Modeling and Simulation

Monte Carlo Simulation


Uses the network diagram (PDM) and Three-Point Estimates as models to
simulate schedule impacts on the project, and the WBS as its model using
Three-Point estimates to simulate cost impacts, then performs the project
several times to determine uncertainty.
Indicates schedule risk by estimating probability that each task will
be on the critical path.

Accounts for task convergence - calculates increased schedule risk


where paths in a network diagram converge into one task.
Stakeholders (team) estimate cost ranges for each WBS element.
Simulation shows probability of meeting the most likely budget
estimate.

Page 194

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Tools and Techniques: Quantitative Risk Analysis and Modeling Techniques
Modeling and Simulation, Cost Risk Simulation
100%

Total Project Cost (cumulative)

50%
25%

Probability

75%

Mean = $46M

12%
$50M

0%

$41M
$30 M

$38M

$47M

$56M

$65M

Cost
The project is only 12% likely to meet the 41 million most likely
cost estimate. If the organization wants 75% chance of success, $50
million is required (at contingency of 22%, [$50M-41M)/$41M]).
Page 194

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis

Tools and Techniques: Quantitative Risk Analysis and Modeling Techniques


Modeling and Simulation

Monte Carlo Simulation


Road Closed
30% Mean Probability
of Project Failure

Running out
of Gas

Monte Carlo Simulation,


Overall Project Risk

Getting Stuck
in Snow Drift

5% Chance That
Probability is 75%

Page 195

.25

.5

.75

1.0

.25

.5

.75

1.0

PMP Prep: PMBOK 5th - 2013

11.4.2 Perform Quantitative Risk Analysis


Outputs: Project Documents Updates

Risk Register Updates include:


Probability analysis of the project

confidence levels and distributions are used to calculate cost


and time reserves.

Probability of achieving cost and time objectives

Priority list of quantified risks


Trends in risk analysis results

PMP Prep: PMBOK 5th - 2013

Planning: Project Risk Management

PMBOK Fifth Edition, Page 342

11.5 Plan Risk Responses


Inputs

Risk management plan


Risk register

Page 196

Tools &
Techniques

Strategies for negative risks


or threats
Strategies for positive risks
or opportunities
Contingent response
strategies
Expert judgment

Outputs

Project management plan


updates
Project documents updates

PMP Prep: PMBOK 5th - 2013

11.5 Plan Risk Responses


Plan Risk Responses is the process of
developing options and actions to
enhance opportunities and to reduce
threats to project objectives

Page 196

PMP Prep: PMBOK 5th - 2013

11.5.2 Plan Risk Responses


Tools and Techniques: Strategies for Threats or Opportunities

Avoid
Eliminate the threat by eliminating the cause.

Transfer
Contract the risk out. Transfer it to a third party with incentives, penalties,
warranties, bonding, .. , purchase insurance.

Mitigate

Negative
Risk or
Threats

Effect the probability and/or the impact of the risk.

Exam
Tip

Exploit
Eliminate uncertainty of upside risk to ensure opportunity happens

Positive
Risk or
Opportunities

Share
Third party helps to capture the opportunity

Enhance
Opposite of Mitigation. Proactively target and reinforce the trigger to
achieve a positive opportunity.

Acceptance
Know about the risk, but decide to accept the consequences if failure
occurs.

Pages 197-199

Knowledge and Research


Perform tests & simulations. Consult experts. Start risk tasks as
early as possible within available slack.

Both

PMP Prep: PMBOK 5th - 2013

11.5.3 Plan Risk Responses


Outputs: Contingency Reserve, Part of the Risk Register
A provision in the project plan to mitigate cost and/or schedule risk
May be calculated as a percent of baseline to allow for overruns
May be established as a separate fund for unforeseen problems
May have many different (and application area specific) names:
management reserve
contingency
May be assigned to any level of the WBS

Exam
Tip

PMI recommends a
minimum total
reserve of 10%

Page 200

PMP Prep: PMBOK 5th - 2013

11.5.3 Plan Risk Responses


Outputs: Project Documents Updates

Risk Register Updates include:

Risk owners and their responsibilities,


Agreed response strategies,
Actions to implement from the response strategy,
Trigger conditions and warning signs of risk occurrence,
Budget and schedule activities to implement the response,
Contingency plans and triggers that call for their execution,
Fallback plans for inadequate risk responses,
Residual risks remaining after response has been taken, and those
that have been deliberately accepted,
Secondary risks that arise from implementing a risk response,
Calculated contingency reserves,

Other Documents Updates:

Page 201

Assumption log updates.


Technical documentation updates,
Change requests processed

PMP Prep: PMBOK 5th - 2013

Chapter 12: Project Procurement Management


PMBOK Fifth Edition, Page 355

Knowledge Area
12.1 Plan Procurement Management: Documenting purchase decisions,
specifying the approach, and identifying potential sellers.
12,2 Conduct Procurements: Obtaining seller responses, selecting a
seller, and awarding a contract.
12.3 Administer Procurements: Managing procurement relationships,
monitoring contract performance, and making changes and
corrections as needed.
12.4 Close Procurements: Competing each project procurement.
Plan Procurement Management includes the processes necessary to purchase
or acquire products, services, or results needed from outside the project
team. It includes contract management and change control processes, as well
as administering contracts and obligations under the contracts.
Page 202

PMP Prep: PMBOK 5th - 2013

Chapter 12: Project Procurement Management

Procurement Process
Plan
Purchases &
Acquisitions

Plan
Contracting

Make or
Buy

Page 202

RFP/RFQ
Issued

Request
Seller
Responses

Q&A

Select
Sellers

Proposal
Received

Contract
Administration

Contract
Award

Contract
Closure

Substantive
Completion

PMP Prep: PMBOK 5th - 2013

Planning: Plan Procurement Management


12.1 Plan Procurements
Inputs
Project management plan
Requirements documentation
Risk register
Activity resource requirements
Project schedule
Activity cost estimates
Stakeholder register
Enterprise environmental
factors
Organizational process
assets

Page 203

Tools &
Techniques

Make-or-buy analysis
Expert judgment
Market research
Meetings

Outputs
Procurement management
plan
Procurement statement of
work
Procurement documents
Source selection criteria
Make-or-buy decisions
Change requests
Project documents updates

PMP Prep: PMBOK 5th - 2013

12.1 Plan Procurement Management


PMBOK Fifth Edition, Page 358

Plan Procurement Management is the


process of documenting project
purchasing decisions, specifying the
approach and identifying potential
sellers.

The plan procurements process involves


deciding whether to make-or-buy, the
consideration of potential sellers, and
the consideration of the risks involved

Page 202

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management


Inputs: Organizational Process Assets

Contract Types
There are several contract types that may be used, and the contract type determines how the
risk is shared between the buyer and the seller.

Page 204-206

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management

Fixed Price/Lump Sum Contracts:

Firm Fixed Price (FFP)


Fixed Price Incentive Fee (FPIF)
Fixed Price with an Economic Price
Adjustment (FP-EPA)

Cost Reimbursable Contracts:

Cost Plus Fixed Fee (CPFF)


Cost Plus Incentive Fee (CPIF)
Cost Plus Award Fee (CPAF)

Unit Price or Time & Materials Contracts (T&M)


Contracts are risk mitigation tools
Other professionals may handle the contract, but contracts
should not be created before the PM is assigned
Match the contract type to the type of project
Contract type will determine the balance of financial risk between
the buyer and the supplier.
Page 204-207

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management

Fixed Price (or Lump Sum) Type Contracts:


Used on well specified projects for which costs can be accurately
estimated. Cost risk is on the supplier. (includes FFP, FPIF, FP-EPA)

Cost Reimbursable Type Contracts:

Exam
Tip

Used on development projects for flexibility. Cost risk is on the buyer, so


establish administrative & reporting systems to allow both buyer and seller
visibility into costs. (Includes CPFF, CPIF, CPAF)

Time & Materials Type Contracts:


Used on projects where the deliverables are well defined, repetitive units
but the quantities are not yet known (e.g., identical pieces of equipment, or
labor hours and associated material costs includes overhead and burden)

Page 207

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management


Inputs: Organizational Process Assets
100%

0%

FFP

Client, Customer
or Buyer

FPEPA

On the exam, contract


questions are written
from the buyers
perspective

FPAF
FPIS
FPIF

RISK

RISK
CPIF
CPAF
CPFF

Contractor
or Seller

0%

Page 208

CS
COST

100%

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurements

Inputs: OPA
US Federal Acquisition Regulations (FAR 16.104)

FFP

Firm Fixed Price: A negotiated fixed price to produce the good or service.

FPEPA

Fixed Price with Economic Price Adjustment: Unstable market or labor

FPAF

conditions, price can be adjusted up or down with a ceiling

Fixed Price Award Fee: award amount related to a subjective judgment


of the quality of the contractor's performance.

FPIS

Fixed Price Incentive (Successive Targets): Contains production point (s)

FPIF

Fixed Price Incentive (Fee or Firm Target): target profit, and profit sharing

CPIF

Cost Plus Incentive Fee: positive profit incentives are negotiated.

CPAF

Cost Plus Award Fee: Award fee is earned for performance, quality,

CPFF

Cost Plus a Fixed Fee: Level of effort is unknown, fee is expressed as

CS
COST
Page 208

at which either a firm target and final profit formula can be negotiated.
formula are negotiated into contract, profit is adjusted upon contract completion.

timeliness, and cost effectiveness and can be earned in whole or in part.


percentage of estimated cost at time contract is awarded.
Cost Sharing: Development or research projects, contractor sees a commercial
benefit which they accept in lieu of fee.
Cost: Typically for R&D with nonprofit organizations, educational institutions,
and facilities contracts.
PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management


Tools and Techniques: Budget Implications

Page 209

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management


Tools and Techniques: Profit or Fees for Different Contracts

Page 209

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management


Tools and Techniques: Point of Total Assumption

Page 209

Exam
Tip

Is on the exam

PMP Prep: PMBOK 5th - 2013

Exercise
Incentive Fee Calculation
You may have to calculate both the Fee and the Final Price for the Exam!
Cost Plus Incentive Fee Calculation

Fee

Target cost
Target fee
Target price

$210,000
$ 25,000
$235,000

Sharing ratio
Actual cost

80/20
$200,000

$210,000 - $200,000 = $10,000 x 20% = $2000


$25,000 target fee + $2,000 = $27,000 fee

Final
Price

Page 210

$200,000 + $27,000 = $227,000

PMP Prep: PMBOK 5th - 2013

12.1.2 Plan Procurement Management


Tools and Techniques:

Make-or-Buy Analysis
A general management technique to determine whether work is best done by the project
team or purchased from an outside source. Considerations such as capability, risk, budget and
schedule are all considered as well as whether to purchase, lease or rent

Expert Judgment
Experts may be used in several areas. Technical experts will assess capability, inputs and
outputs. Purchasing experts will generate the criteria to select appropriate sellers, and legal
experts will focus on terms, conditions and issues

Market Research
Capabilities of industry and seller must be researched by information gained at conferences,
on-line, and other sources. Leverage mature technologies while balancing the risks with other
less mature technologies.

Meetings
Information exchange with potential bidders can benefit the project.

Page 206

PMP Prep: PMBOK 5th - 2013

12.1.3 Plan Procurement Management


Outputs: Procurement Management Plan, and
Procurement Statement of Work
A narrative description of products or services to be supplied under contract.
Provides the basis of agreement between buyer and supplier
Sufficient detail to allow prospective suppliers to determine
whether or not they can comply
Sufficient latitude for creative solutions only if appropriate
Each procurement requires a separate SOW. But one SOW
may cover many items in a single procurement
May be revised as the procurement progresses
Should be clear, concise, and unambiguous
May be developed by the project team or
supporting offices (or even the seller)
depending on policy and ability

Your best defense against procurement scope creep!


Page 211

PMP Prep: PMBOK 5th - 2013

12.1.3 Plan Procurement Management


Outputs: Procurement Documents
Procurement documents from the buyer:
TECHNICALLY-DRIVEN CONTRACTS:

Request for Proposal (RFP) - requests a detailed proposal on how the


work will be done, who will do it, . . . , basically a Project Execution Plan
from the contractor or seller.

PRICE-DRIVEN CONTRACTS:

Invitation for Bid (IFB, or RFB) - requests one price to do all the work.

Request for Quotation (RFQ) - Requests a price quote per item, per hour
charges, etc.

Procurement Terminology is not universal

Page 212

PMP Prep: PMBOK 5th - 2013

12.1.3 Plan Procurement Management


Outputs: Source Selection Criteria

Examples of source selection criteria are:


Understanding
of need

Life-cycle cost

Technical
capability

Risk

Management
approach

Technical
approach

Warranty

Financial
stability

Production
capacity

Business size
and type

Past
performance
of sellers

References

Intellectual
property rights

Proprietary
rights

Exam
Tip

The Contracting Officer or Administrator is the one with authority to change the contract
The Project Manager must understand the contract and manage its completion
The exam tests conflicts that arise between the two

Page 212

PMP Prep: PMBOK 5th - 2013

Notes on procurement for the exam


The exam questions are always from the buyers
perspective
Different words are sometimes used (vendor,
owner, contractor, subcontractor etc.)
A contract is a formal agreement
All requirements should be specifically stated in
the contract
Changes must be in writing and formally
controlled
The US Government backs all contracts by
providing a court system (this is a US exam)

Page 213

PMP Prep: PMBOK 5th - 2013

Planning: Project Stakeholder Management


PMBOK Fifth Edition, Section 13.2, Page 393

13.2 Plan Stakeholder Management


Inputs

Project management plan


Stakeholder register
Enterprise environmental factors
Organizational process assets

Page 314

Tools &
Techniques

Expert judgment
Meetings
Analytical techniques

Outputs

Stakeholder management
plan
Project documents updates

PMP Prep: PMBOK 5th - 2013

13.2 Plan Stakeholder Management

Plan Stakeholder Management is the


process of developing management
strategies to engage stakeholders
throughout the project life cycle,
based on the analysis of their needs,
interests, and impact on project
success.

It allows the project manager the


develop ways to engage stakeholders
in the project, to manage their
expectations, and to achieve the
project objectives.

Page 214

PMP Prep: PMBOK 5th - 2013

13.2 Plan Stakeholder Management


Tools and Techniques: Analytical Techniques

Engagement Level of Stakeholders


Engagement level of the stakeholders can be classified as follows:

Page 216

Unaware. of project and potential impacts


Resistant. Aware of project and impacts, and resistant to change
Neutral. Aware of project yet neither supportive nor resistant
Supportive. Aware of project/impacts and supportive to change
Leading. Aware of project/impacts and actively engaged in
ensuring success.

PMP Prep: PMBOK 5th - 2013

13.2 Plan Stakeholder Management


Tools and Techniques: Analytical Techniques

Stakeholder Engagement Assessment Matrix


Stakeholder
Stakeholder 1
Stakeholder 2

Unaware

Resistant

Neutral

Supportive Leading

D
C

Stakeholder 3

D
DC

Legend: C = Current Engagement


D = Desired Engagement

Exam
Tip

2013 PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Fifth Edition

Page 216

PMP Prep: PMBOK 5th - 2013

13.2 Plan Stakeholder Management


Outputs: Stakeholder Management Plan

This plan identifies the management strategies required to engage


stakeholders.
Desired engagement levels of key stakeholders,
Scope and impact of change to stakeholders,
Interrelationships and overlap between stakeholders,
Stakeholder communication requirements for the current phase,
Information to be distributed to stakeholders (language, format,
content, level of detail),
Timing and frequency for distributing the information,
Method for updating the stakeholder management plan as the
project progresses.

Page 217

PMP Prep: PMBOK 5th - 2013

Executing Process Group


PMBOK Fifth Edition, Page 79

Page 219

PMP Prep: PMBOK 5th - 2013

PMBOK Fifth Edition, Page 61


Process Groups
Knowledge Areas
4. Project Integration
Management

Initiating

Executing

4.1 Develop Project Charter

5. Project Scope
Management

Planning
4.2 Develop Project
Management Plan
5.1
5.2
5.3
5.4

4.3

Executing
4.3 Direct & Manage
Project Work

Plan Scope Mgt.


Collect Requirements
Define Scope
Create WBS

Direct and Manage6.1Project


Plan Schedule Mgt.
6.2 Define Activities
Work
6.3 Sequence Activities
6.4 Est. Activity Resources
8.2 Perform Quality Assurance
6.5 Est. Activity Durations
6.6 Dev. Schedule
9.2
Acquire
Project
Team
7. Project Cost
7.1 Plan Cost Mgt.
Management
7.2 Estimate Costs
9.3 Develop Project Team
7.3 Determine Budget
9.4
8. Project
Quality Manage Project Team
8.1 Plan Quality Mgt.
Management
10.2 Manage Communications
9.1 Plan Human
9. Project Human
Resource
Resource Mgt.
12.2 Conduct Procurements
Management
10. Project
10.1 Plan Communications
13.3 Manage Stakeholder
Communications
Management
Management
Engagement
11. Project Risk
11.1 Plan Risk Management

Page 28

4.6 Close Project


or Phase

6.7 Control Schedule

7.4 Control Costs

8.2 Perform Quality


Assurance

8.3 Control Quality

9.2 Acquire Project Team


9.3 Develop Project Team
9.4 Manage Project Team
10.2 Manage Communications

10.3 Control Communications

11.6 Control Risks

11.2 Identify Risks


11.3 Perform Qualitative
Risk Analysis
11.4 Perform Quantitative
Risk Analysis
11.5 Plan Risk Response

12. Project Procurement


Management
13. Project Stakeholder
Management

4.4 Mon/Ctrl Proj Work


4.5 Perform Integrated
Change Control

Closing

5.5 Validate Scope


5.6 Control Scope

6. Project Time
Management

Management

Monitoring &
Controlling

13.1 Identify Stakeholders

12.1 Plan Procurement Mgt.

12.2 Conduct Procurements

12.3 Control Procurements

13.2 Plan Stakeholder


Management

13.3 Manage Stakeholder


Engagement

13.4 Control Stakeholder


Engagement

12.4 Close Procurements

PMP Prep: PMBOK 5th - 2013

Executing: Integration Management

PMBOK Fifth Edition, Page 79

4.3 Direct and Manage Project Work


Inputs

Project management plan


Approved change requests
Enterprise environmental factors
Organizational process assets

Page 220

Tools &
Techniques

Expert judgment
Project management
information system
Meetings

Outputs

Deliverables
Work performance data
Change requests
Project management plan
updates
Project documents updates

PMP Prep: PMBOK 5th - 2013

4.3 Direct and Manage Project Work


Direct and Manage Project Work
is the process of leading and performing
the work defined in the project
management plan and implementing
approved changes to achieve the
projects objectives

Page 220

PMP Prep: PMBOK 5th - 2013

4.3 Direct and Manage Project Work


The activities of Direct and Manage Project Work include:

Page 220

Perform activities to accomplish project objectives,


Create deliverables,
Provide, train, and manage team members
Obtain materials, equipment, and facilities,
Implement methods and standards,
Establish communication channels,
Generate project date: cost schedule, technical, quality, and status to
facilitate forecasting,
Issue change requests and manage approved changes
(corrective action, preventative action, defect repair),
Manage risks and risk responses,
Manage sellers and contractors,
Manage stakeholders and their engagement, and
Collect and document lessons learned

PMP Prep: PMBOK 5th - 2013

4.3.1 Direct and Manage Project Work


Inputs: The Project Management Plan
The other 23 planning processes are integrated to create
the project management plan. Updates to any plans
require an update to the PM plan. Think of the PM plan as
a bucket into which all the other plans drip until it is full.

Page 221

Plan Scope Management


Collect Requirements
Define Scope
Create WBS
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Plan Cost Management
Estimate Costs

Determine Budget
Plan Quality Management
Plan Human Resource Management
Plan Communications Management
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Responses
Plan Procurement Management
Plan Stakeholder Management
PMP Prep: PMBOK 5th - 2013

4.3.2 Direct and Manage Project Work


Tools and Techniques
Expert Judgment
Expertise is provided by the project manager and the PM team, and
additional knowledge can be gained from a variety of sources inside
and outside of the organization.
PM Information System (PMIS)
The PMIS provides access to tools: scheduling tool, work authorization system,
configuration management system, information collection/distribution system, reporting
on key performance indicators (KPI), and interfaces to online automated systems.

Meetings
Meetings can include information exchange, brainstorming, option evaluation, or
decision making. Meetings are most effective when face-to-face. Virtual meetings (audio
or video-conferencing) require additional preparation and organization to be as effective
as face-to-face.
Page 222

PMP Prep: PMBOK 5th - 2013

4.3.3 Direct and Manage Project Work


Outputs
Deliverables
Any product, result or service identified in the PM Plan produced during project execution.

Work Performance Information


Status of project activities is routinely collected. It includes schedule progress, deliverable
status, quality requirements met, costs incurred, estimates to complete, lessons learned,
and resources used.
Change Requests
Changes are requested to expand or reduce scope, modify policies/procedures, costs,
budgets, quality, or schedules. They also include corrective action, preventative action,
defect repair, and document updates.
PM Plan Updates
Requirements, schedule, cost, quality, HR, communications, risk, procurement, and the
project baselines.
Project Document Updates: requirements, logs, risk register, and stakeholder register.

Page 223

PMP Prep: PMBOK 5th - 2013

Executing: Quality Management

PMBOK Fifth Edition, Page 242

8.2 Perform Quality Assurance


Inputs

Quality management plan


Process Improvement plan
Quality metrics
Quality control measurements
Project documents

Page 224

Tools &
Techniques

Quality management and


Control tools
Quality audits
Process analysis

Outputs

Change requests
Project management plan
updates
Project document updates
Organizational process assets
updates

PMP Prep: PMBOK 5th - 2013

8.2 Perform Quality Assurance


Perform Quality Assurance is
the process of auditing the
quality requirements and the
results from quality control
measurements to ensure
appropriate quality standards
and operational definitions
are used

Page 224

PMP Prep: PMBOK 5th - 2013

8.2.2 Perform Quality Assurance


Tools and Techniques: Quality Management and Control Tools

The Tools for Quality Planning should be used for Quality Assurance

Page 225

Benefit/Cost Analysis
Cost of Quality (COQ)
Control Charts
Benchmarking
Design of Experiments (DOE)
Statistical Sampling
Proprietary Methods

Flowcharting
Brainstorming
Force Field Analysis
Nominal Group Techniques
Matrix Diagrams
Priority Matrixes

PMP Prep: PMBOK 5th - 2013

8.2.2 Perform Quality Assurance


Tools and Techniques: Quality Management and Control Tools

In Addition, Use the Seven Quality Management and Control Tools


Affinity Diagrams
Process Decision Program
Charts (PDPC)
Interrelationship Digraphs
Tree Diagrams

Page 225

Prioritization Matrices
Activity Network Diagrams
Matrix Diagrams

PMP Prep: PMBOK 5th - 2013

The Seven Quality Management and Control Tools


PDPC

Affinity Diagram

No

Tree Diagrams

Yes

No

Yes

Interrelationship Digraph

No

No

Prioritization Matrices

Network Diagrams
PDM

Start

Finish
D

ADM

Start

C
Finish

FF

Matrix Diagrams

Page 226

PMP Prep: PMBOK 5th - 2013

8.2.2 Perform Quality Assurance


Tools and Techniques: Quality Audits

Quality Assurance (QA): the process of auditing quality requirements, and the
results from quality control (QC) measurements, to ensure quality standards and
operational definitions are used..
Quality assurance involves Quality Audits, and is done in Execution Processes.

Quality Control (QC): a process of monitoring and recording results (both product
and project management) of executing quality activities to assess performance and
to recommend necessary changes. Involves identifying ways to remove the causes of
quality defects.
Quality control involves inspection and requires an understanding of sampling
strategies, tolerances, and the causes of variation in a process. It is done in the
Monitoring and Controlling Processes.

Pages 227

PMP Prep: PMBOK 5th - 2013

8.2.1 Perform Quality Assurance


Tools and Techniques: Quality Audits

. . a structured review (audit) of the projects quality management


activities to determine if they comply with organizational and project
policies, processes, and procedures.
Quality audits may be random or scheduled
Quality audits may be performed internally or externally
Quality audits
Identify best practices and gaps or shortcomings
Share good practices with similar projects in the organization
Proactively assist to improve processes and raise team productivity
Contribute audit results to lessons learned archives.

Page 228

PMP Prep: PMBOK 5th - 2013

Practice Test #2

Turn to page 416 in the workbook


There are 68 questions.
You have 81 minutes to complete
Answers are on page 433
Hint: Use scratch paper for answers,
so you can reuse the questions for practice

Page 416

PMP Prep: PMBOK 5th - 2013

Executing: Human Resource Management


PMBOK Fifth Edition, Page 267

9.2 Acquire Project Team


Inputs

Human resources management


plan
Enterprise environmental factors
Organization process assets

Page 230

Tools &
Techniques

Pre-assignment
Negotiation
Acquisition
Virtual teams
Multi-criteria decision
analysis

Outputs

Project staff assignments


Resource calendars
Project management plan
updates

PMP Prep: PMBOK 5th - 2013

9.2 Acquire Project Team


Acquire Project Team is the process of
confirming human resource availability
and obtaining the team necessary to
complete project activities

Page 230

PMP Prep: PMBOK 5th - 2013

9.2.1 Acquire Project Team


Inputs: Project Management Plan, that includes:

Human Resource Management Plan


defining positions, skills, and competencies
project organization charts
when team members are needed

EEF and OPA

Page 231

PMP Prep: PMBOK 5th - 2013

9.2.2 Acquire Project Team


Tools and Techniques

The project manager should effectively negotiate and influence others who
are in a position to provide the required human resources for the project
Pre-Assignment
Project team members are selected in advance, perhaps where the project is part of
a proposal

Negotiation
The project manager may need to negotiate with functional managers or other
project managers to gain the staff required

Acquisition
Hiring or subcontracting team members from outside sources. This may involve
outsourcing work to another organization

Virtual Teams
Teams where the members may not be able to meet face-to-face because of
geographic or mobility limitations. Communication planning becomes increasingly
important in a virtual team environment
Pages 232-233

PMP Prep: PMBOK 5th - 2013

9.2.2 Acquire Project Team


Tools and Techniques

Multi-Criteria Decision Analysis


Criteria are used to rate potential team members. The criteria are weighted by
considering relative importance within the team.

Is the team member available to work in the time period needed?


Is the team members cost within the budget constraints?
Have the people done similar work before? Done it well?
Does the team member have the required competence?
Does the team member know the customer, worked on similar
projects, understand PM?
Skills.
Can they use project tools, or have appropriate training?
Attitude.
Can the team member work with others in a cohesive team?
International Factors. What is the location of the team member, time zones,
communication skills?

Pages 233

Availability.
Cost.
Experience.
Ability.
Knowledge.

PMP Prep: PMBOK 5th - 2013

Executing: Human Resource Management


PMBOK Fifth Edition, Page 273

9.3 Develop Project Team


Inputs

Human resource management


plan
Project staff assignments
Resource calendars

Page 235

Tools &
Techniques

Interpersonal skills
Training
Team-building activities
Ground rules
Co-location
Recognition and rewards
Personnel assessment tools

Outputs

Team performance
assessments
Enterprise environmental
factors updates

PMP Prep: PMBOK 5th - 2013

9.3 Develop Project Team

Develop Project Team is the process of


improving the competencies, team
interaction and the overall team
environment to enhance project
performance.
Teamwork is a critical factor for project
success, and developing effective project
teams is one of the primary responsibilities
of the project manager
Exam
Tip

Page 235

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Tools and Techniques:

Interpersonal Skills:
soft skills

Training:
activities designed to improve competencies of the
project team members
Team-Building Activities:
should be designed to help individual team members
work together effectively and establish good working
relationships.

Pages 236-237

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Tools and Techniques: Team Building Activities

Bruce Tuckman: The Five Stages of Team Development

Forming:

Team meets, learns about the project, understands


roles, but is independent, not open

Storming:

Team addresses project and methodology and must


be open in this phase or it can become destructive.

Norming:

Team works together, adjusts behaviors that are


supportive, and trust develops

Performing:

Team performs as well organized unit and works


through issues smoothly and effectively

Adjourning:

Team completes the work, celebrates their success,


and moves on from the project.

Page 238

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Tools and Techniques: Team Building Activities

The proper use of most project management tools & techniques


contribute to teambuilding, but PMI defines Team Building Activities as
actions taken specifically and primarily to improve team performance.
Facilitated off-site workshops
Inter-personal skills development
training and workshops
Communications training
(including listening skills)
Conflict resolution
Psychological preference
indicators such as Myers-Briggs
Physical challenge workshops
Planned team outings
Standing agenda item at review
meetings
Shared space, publicity, and
symbols to create a team identity
Page 238

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Other Tools and Techniques

Ground Rules: Discussing ground rules allows team


members to discover values important to one another, to
set clear expectation for team behavior, and to share their
commitment to the rules
Co-location: Physically locating team members in the same
physical location enhances team communication and
performance
Recognition and Rewards: Promote and reinforce desired
behaviors, and only desired behavior should be

rewarded.

What gets measured, gets done

Page 239

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Tools and Techniques: Recognition and Rewards

Exam
Tip

Herzbergs
Motivators

1.
2.
3.
4.
5.
6.

Achievement
Recognition
Work Itself
Responsibility
Advancement
Growth

Self Actualization = Achievement


Maslows
Hierarchy
of Needs

Self Esteem = Recognition


Social

Safety
Physiological
Page 239 & 241

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Tools and Techniques: Recognition and Rewards

A persons motivation and effectiveness


are influenced by three needs:

Exam
Tip

Page 239

McClellands
Theory of
Needs

Achievement
Affiliation
Power

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Tools and Techniques: Recognition and Rewards

prized assignments
responsibility
presentation opportunities
training opportunities-growth
flexible scheduling/days off

Recognition of achievement
better offices, new
equipment
bonuses, trips
promotions, pay raises

Be sure the link between performance and reward is


clear, explicit, timely, and achievable.
Be sure to reward desired behaviors more than
recovery from the results of undesired behaviors.

Consider cultural factors such as individualism vs.


collectivism in choosing rewards and giving
recognition (team vs. personal).

Page 240

PMP Prep: PMBOK 5th - 2013

9.3.3 Develop Project Team


Outputs: Team Performance Assessments

Position Descriptions
show team member
responsibilities,
authority,
competencies, and
qualifications outlined
in a text document.

Performance
Assessments
improvements in
individual skills
Improvements in
team behaviors
improvements in
project
performance
reduced staff
turnover rate.

Page 240

PMP Prep: PMBOK 5th - 2013

Executing: Human Resource Management


PMBOK Fifth Edition, Page 279

9.4 Manage Project Team


Inputs

Human resource management


plan
Project staff assignments
Team performance assessments
Issue log
Work performance reports
Organizational process assets

Page 242

Tools &
Techniques

Observation and conversation


Project performance appraisals
Conflict management
Interpersonal skills

Outputs

Change requests
Project management plan
updates
Project documents updates
Enterprise environmental
factors updates
Organizational process assets
updates

PMP Prep: PMBOK 5th - 2013

9.4 Manage Project Team


Manage Project Team
is the process of tracking team
member performance, providing
feedback, resolving issues and
managing team changes to
optimize project performance

Team members are accountable both to their


functional manager and to their project manager.
Exam
Tip

Page 242

Effective Management of the dual reporting relationship


is the responsibility of the Project Manager
PMP Prep: PMBOK 5th - 2013

9.4.1 Manage Project Team


Inputs:

Human Resource Management Plan


responsibilities, project organization, staffing management
plan.

Project Staff Assignments


Team Performance Assessments
Issue Log
Work Performance Reports
project status, project forecasts, schedule/cost/quality
control, scope validation, future HR requirements

Scope Baseline (scope statement, WBS, WBS dictionary)


OPA

Page 242-243

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Project Performance Appraisals, Roles and Responsibilities

Exercise
Fill in the last column with PM (Project Manager), T (Team member) or SM (Senior/Functional
Management) as to who is most appropriate to solve the problem listed under the situation
column. Understanding of these questions will help with your with your Situation Questions:
Situation

Page 245

Two project team members are having a disagreement -

There is a change to the overall project deliverables

A boss is trying to pull a team member off the project to do other work

The project manager does not have the authority to get things done

There are not enough resources to complete the project

The team is unsure of what needs to happen when

A task needs more time and will cause the project to be delayed

A tasks needs more time without causing the project to be delayed

Who Solves the


Problem
(PM/T/SM)?

T
SM
T
SM
SM
PM
SM
PM
PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Project Performance Appraisals, Roles and Responsibilities

Exercise

Page 245

A team member is not performing -

SM

10

The team is not sure who is in charge of the project

SM

11

There is a talk that the project may be no longer needed

12

Senior management provides an unrealistic schedule requirement

13

The team is in conflict over priorities between tasks

14

The project is behind schedule

15

A team member determines that another method is needed to complete the


task within its scope of work -

SM
SM
PM
PM
T

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Powers of a Project Manager

Expert:
Reward:
Formal:
Referent:
Penalty:

Powers of the P.M.

How Earned?

recognition by others
giving rewards to others
power based on the position
refer to authority of management
ability to penalize team members

On your own
PMs Position
PMs Position
Others Position
PMs Position

Exam
Tip

Principles of Project Management, PMI, ISBN: 1-880410-30-3

Page 246

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Conflict Management

Conflict Resolution
Best to Worst
1.
2.
3.
4.
5.

Collaborate/Problem Solving:
Compromise/Reconcile:
Withdraw/Avoid:
Smooth/Accommodate:
Force/Direct:

solving the real problem


solutions that satisfy all parties
retreating or postponing a decision
emphasis on agreement rather than differences
one viewpoint at the expense of another

Exam
Tip

Principles of Project Management, PMI, ISBN: 1-880410-30-3

Page 246

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Conflict Management

Factors for Conflict Resolution

Importance and intensity of conflict

Time pressure to resolve

Position taken by persons involved

Motivation to resolve, long and short term


Exam
Tip

Page 246

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Conflict Management

Sources of Conflict
(order of priority)
Exam
Tip

1. Schedules
2. Project priorities
3. Resources

4. Technical opinions
5. Admin. Procedures
6. Cost
7. Personality

Principles of Project Management,


PMI, ISBN: 1-880410-30-3

Page 247

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Interpersonal Skills

The Fourth Edition was the first time the soft skills have been given
special recognition by PMI in the guidebook.
Exam
Tip

Page 247

Please refer to Appendix X3 in the Fifth Edition for a listing of


interpersonal skills important to project management. PMI said these
skills were too large to cover in-depth in the PMBOK. This makes it a ripe
source for questions on the fifth edition test.

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Leadership

Leadership focuses team efforts toward a common goal. Leaders get


things done through other people. They develop trust and respect, not
fear and submission.

Page 248

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Performance Impact

Tools and Techniques: Leadership, the Team Performance Curve

High-Performance
Team
Real
Team

Working
Group

Potential
Team

PseudoTeam

Team Effectiveness

Katzenbach and Smith


The Wisdom of Teams
Page 249

PMP Prep: PMBOK 5th - 2013

9.3.2 Develop Project Team


Tools and Techniques: Team Building Activities

A high performing team is:


A small group of people
with complimentary skills
committed to a common
purpose, performance
goals and methods
for which they hold
themselves accountable
and take the risk of
conflict

Page 236 and 249

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Communication and Influencing

Communication
Communication is one of the biggest contributors to project success or failure.
Exam
Tip

Geert Hofstede: Cultural Dimensions (national cultural differences)


Myers Briggs: Personality Test
The Sender-Receiver Model (mentioned earlier)
Conflict resolution is part of communication (mentioned earlier)

Influencing

Lead by example, follow through with commitments


Clarify how decisions will be made
Use a flexible style, adjust to the situation (Situational Leadership)
Apply your power skillfully and cautiously
Influence: What you think you have until your try to use it Joan Welsh

Page 250

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Decision Making

Decision Making Styles

Factors Affecting Style

Command
Consultation
Consensus
Random (coin flip)

Time constraints
Trust
Quality
Acceptance
Exam
Tip

Six-Phase Problem Solving Model


1.
2.
3.
4.
5.
6.
Page 251

Problem Definition: explore, clarify, and define the problem


Solution Generation: brainstorm solutions and discourage early decisions
Ideas to Actions: define evaluation criteria, rate pros/cons, select one
Solution Plan: involve team for acceptance and commitment
Evaluation Plan: implement, analyze, evaluate, lessons learned
Evaluation Outcome: was the problem solved? Goals achieved?
PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Negotiation

Negotiating Skills and Behaviors


1.
2.
3.
4.
5.
6.
7.

Page 250-251

Exam
Tip

Analyze the situation


Differentiate between wants and needs by both parties
Focus on interests and issues, not positions
Ask high and offer low (but be realistic). Do you have a BAFO?
When making a concession, act like you are yielding something of
value. Dont just give in.
Both parties should feel like they won (win-win). Never let the
other party leave feeling they have lost.
Do a good job of active listening and articulating

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Appendix X3, Covey, Dinsmore, Levin, Verma

Seven Habits of Highly Effective People


Stephen R. Covey, 2004

Exam
Tip

Habit 1: Be Proactive: Principles of Personal Choice


Habit 2: Begin with the End in Mind: Principles of Personal Vision
Habit 3: Put First Things First: Principles of Integrity & Execution
Habit 4: Think Win/Win: Principles of Mutual Benefit
Habit 5: Seek First to Understand, Then to be Understood
Habit 6: Synergize: Principles of Creative Cooperation
Habit 7: Sharpen the Saw: Principles of Balanced Self-Renewal
(The Eighth Habit: From Effectiveness to Greatness;
Find your voice and inspire others to find theirs)

Page 252

PMP Prep: PMBOK 5th - 2013

9.4.2 Manage Project Team


Tools and Techniques: Trust Building

Trust Building
Open and direct communications to resolve problems
Inform all stakeholders when commitments are at risk

Engage directly with the team, ask a lot of questions


Be direct and explicit about what you need or expect
Do not withhold information

Be receptive to innovation
Look beyond your own interests
Demonstrate true concern for others

Page 253

Exam
Tip

PMP Prep: PMBOK 5th - 2013

Executing: Communications Management


PMBOK Fifth Edition, Page 297

10.2 Manage Communications


Inputs

Communications management
plan
Work performance reports
Enterprise environmental factors
Organizational process assets

Page 255

Tools &
Techniques

Communication technology
Communication models
Communication methods
Information management
systems
Performance reporting

Outputs

Project communications
PM plan updates
Project documents updates
Organizational process assets
updates

PMP Prep: PMBOK 5th - 2013

10.2 Manage Communications


Manage Communications is the
process of creating, collecting,
distributing, storing, retrieving,
and the ultimate disposition of
project information in
accordance with the
Communications Management
Plan.

Page 255

PMP Prep: PMBOK 5th - 2013

10.2.1 Manage Communications


Inputs: Includes the Communications Management Plan
Communication Management Plan
describes how communications will be planned,
structured, monitored and controlled.

Stakeholder communication requirements

Which information flows from whom, when, via which media, and in what format.

Schedule and frequency for information collection and distribution.

Methods to convey information (memos, e-mail, press releases, etc.)

Resources for communication activities, including time and budget

Problem escalation procedure

Method for updating the communication plan

Flow charts of information flow

List of reports and meetings planned (schedule and attendees)

Communications constraints

Communications infrastructure for the project (who may talk to whom)

Performance Reports
Organizes and summarizes information on project
status and progress
May have different reports for different stakeholders,
each to the level of detail and in the format and
frequency appropriate to the stakeholder
Includes cost, schedule, quality and scope accomplishment and variance
information
Reports the results of variance analysis, trend analysis, and earned value
analysis. Generally involves charts such as bar charts (e.g., Gantt charts)
and S-curves (e.g., earned value charts) to summarize data and facilitate
reporting by exception.

Caution: Ensure a consistent data date,


ideally from a common set of data

Performance Reports
Purpose of Performance Reports:
to detect problems in time to take corrective or preventive
action
to reduce customer and management anxiety
to share project information within the project team

Guidelines for Performance Reports:


keep the report short, matching its length to
the projects complexity and the audiences
needs
use a consistent template and format
use visual elements such as charts and graphs

Criteria for Performance Reporting:


gives timely, complete, and accurate information
doesnt add more administrative overhead than
its worth
is acceptable and useful to all participants
gives warning of problems in time for preventive
or corrective actions
is easily understood by those who have a need to
know

More on these reports later . . .


Page 256

PMP Prep: PMBOK 5th - 2013

10.2.2 Manage Communications


Tools and Techniques
Communication Technology
Technology can vary from project-to-project and throughout the life
cycle of the same project. The team must ensure that the technology is
appropriate for the information being communicated.

Communication Models
The choice of communication model must be appropriate for the project
and any barriers (noise) are identified and managed.

Communications Methods
Methods to communicate can take place through many media. Effective
and efficient use of each requires appropriate communication skills:
Written and oral, listening and speaking
Internal (in the project) and external (client, public)
Formal (reports) and informal (memos, e-mail, IM, telecon)
Vertical (up/down the org.) and horizontal (with peers)

Page 257

PMP Prep: PMBOK 5th - 2013

10.2.2 Manage Communications


Tools and Techniques
Information Management Systems
A variety of tools are available for managing and distributing information:
Hard copy documents: letters, memos, reports, and press releases
Electronic communication media: e-mail, fax, IM, voice mail, telephone, video, web
conferencing, web sites, web publishing, FTP sites, intranet
Electronic PM tools: web interfaces for scheduling , PM software, Skype, meeting software,
virtual office software, portals, and collaborative work management tools.

Performance Reporting
This is collecting and distributing performance information (status reports, progress
measurements, and forecasts). It includes periodic analysis of baseline versus actual data to
communicate progress and to forecast project results. Simple reports show percent complete
or status dashboards (scope, schedule, cost, quality). More elaborate reports may include:
Analysis of past performance
Analysis of forecasts (including time and cost)
Status of risks and issues
Work completed during the period
Work to be completed during the next period
Summary of changes approved, etc.

Page 258

PMP Prep: PMBOK 5th - 2013

Executing: Procurement Management


12.2 Conduct Procurements
Inputs

Project management plan


Procurement documents
Source selection criteria
Seller proposals
Project documents
Make-or-buy decisions
Procurement statement of work
Organizational process assets

Page 260

Tools &
Techniques
Bidder conferences
Proposal evaluation
techniques
Independent estimates
Expert judgment
Advertising
Analytical techniques
Procurement negotiations

Outputs

Selected sellers
Agreements
Resource calendars
Change requests
Project management plan
updates
Project documents updates

PMP Prep: PMBOK 5th - 2013

12.2 Conduct Procurements

Conduct Procurements is the


process of obtaining seller
responses, selecting a seller and
awarding a contract.

It may involve developing a short


list of qualified sellers which are
then subject to further
information

Page 260

PMP Prep: PMBOK 5th - 2013

12.2.1 Conduct Procurements


Inputs

Understand the following Inputs for the test:


Procurement Management Plan: How procurement processes will be managed
Procurement Documents:
Used to request proposals from sellers, audit trail
Source Selection Criteria:
Used to rate and scope proposals
Seller Proposals:
Evaluated to select the successful seller
Project Documents:
Risk Register and contract decisions on risk
Make-or-Buy Decisions:
Will the work be done internally or be acquired?
Procurement Statement of Work: Clearly stated goals and requirements
OPA:
Company supplier lists

Pages 260-261

PMP Prep: PMBOK 5th - 2013

12.2.2 Conduct Procurements


Tools and Techniques

Bidder Conferences Assembling all


prospective vendors in a single meeting, with
information disseminated and individual bids
later received
Proposal Evaluation Techniques
Comparison of alternative proposals on the
basis of vendor responses. Weighted Scoring
is a commonly used technique
Independent Estimates Use of an outside
professional to provide a benchmark
estimate of costs in advance of receiving
proposals
Expert Judgment Experts from various
disciplines may be used to evaluate and
advise on proposals

Pages 262-263

Weighting System
Removes personal bias, is more objective, and considers
relative importance of different evaluation factors
1) determines the evaluation factors
2) assigns a numerical weight to each factor
3) rates the prospective sellers on each criterion
4) multiplies each rating by its weighting
5) totals the ratings to compute an overall score

Typical factors include technical,


management, and cost factors
Avoid overly complicated rating models

PMP Prep: PMBOK 5th - 2013

12.2.2 Conduct Procurements


Tools and Techniques
Advertising Advertising in selected
newspapers or trade publications.
Government may require advertising of
certain kinds of contracts.
Analytical Techniques evaluate readiness of
a seller, examine past performance for risks.
Procurement Negotiations The project
manager may not be the lead negotiator in
many cases, but will provide technical and
project clarification.

Pages 263-264

PMP Prep: PMBOK 5th - 2013

12.2.2 Conduct Procurements


Tools and Techniques: Procurement Negotiations

undertaken to clarify structure, requirements,


and contract terms so that mutual agreement on
contract terms can be reached prior to signing.

responsibilities and authorities (Who Will Negotiate?)


pricing, payments, and payment schedules
penalty terms
deliverables -- specifications, quantities, quality, timing
applicable laws, standards, regulations, and other requirements
technical and management approaches
copyright and ownership issues; data rights
Ethical Negotiations: each party is honest with the other,
regardless of expectations related to future work.

Page 264

PMP Prep: PMBOK 5th - 2013

12.2.3 Conduct Procurements


Outputs
Selected Sellers:
Sellers who are competitive and have
negotiated a draft contract
Agreements:
A legal agreement between Buyer and Seller,
mutually binding. It includes many
requirements and terms that you should
remember, including Incoterms and ADR.
Read this section carefully.

Page 265

PMP Prep: PMBOK 5th - 2013

12.2.3 Conduct Procurements


Outputs: Types of Contracts

Fixed Price (or Lump Sum) Type Contracts:


Used on well specified projects for which costs can be accurately
estimated. Cost risk is on the supplier. (includes FFP, FPIF, FP-EPA)

Cost Reimbursable Type Contracts:

Exam
Tip

Used on development projects for flexibility. Cost risk is on the buyer, so


establish administrative & reporting systems to allow both buyer and seller
visibility into costs. (Includes CPFF, CPIF, CPAF)

Time & Materials Type Contracts:


Used on projects where the deliverables are well defined, repetitive units
but the quantities are not yet known (e.g., identical pieces of equipment, or
labor hours and associated material costs includes overhead and burden)

Page 266

PMP Prep: PMBOK 5th - 2013

Executing: Stakeholder Management


PMBOK Fifth Edition, Page 404

13.3 Manage Stakeholder Engagement


Inputs

Stakeholder management plan


Communications management
plan
Change log
Organizational process assets

Page 268

Tools &
Techniques

Communication methods
Interpersonal skills
Management skills

Outputs

Issue log
Change requests
Project management plan
updates
Project documents updates
Organizational process assets
updates

PMP Prep: PMBOK 5th - 2013

13.3 Manage Stakeholder Engagement


Manage Stakeholder Engagement is the
process of communicating and working with
stakeholders to meet their needs, address
issues as they occur, and foster stakeholder
engagement in project activities throughout
the project life cycle.
Managing stakeholders increases the
likelihood of project success by ensuring
they clearly understand project goals,
objectives, benefits, and risk.
Test items in this process are Inputs/Tools and Techniques/Outputs, and
understanding the issues and change logs.

The Project Manager (PM) is responsible for engaging and managing


stakeholders.
Pages 268

PMP Prep: PMBOK 5th - 2013

Monitoring & Controlling Process Group


PMBOK Fifth Edition, Page 86

Page 273

PMP Prep: PMBOK 5th - 2013

PMBOK Fifth Edition, Page 61


Process Groups
Knowledge Areas
4. Project Integration
Management

Initiating

4.4

7. Project Cost
Management

8. Project Quality
Management

9. Project Human
Resource
Management
10. Project
Communications
Management
11. Project Risk
Management

4.5
5.5
5.6
6.7
7.4
8.3
10.3
11.6
12.3
13.4

12. Project Procurement


Management
13. Project Stakeholder
Management

Page 28

Executing

Monitoring and Controlling

4.1 Develop Project Charter

5. Project Scope
Management

6. Project Time
Management

Planning

13.1 Identify Stakeholders

4.2 Develop Project


Management Plan

5.1
5.2
5.3
5.4

4.3 Direct & Manage


Project Work

Plan Scope Mgt.


Collect Requirements
Define Scope
Create WBS

4.4 Mon/Ctrl Proj Work


4.5 Perform Integrated
Change Control

Closing
4.6 Close Project
or Phase

5.5 Validate Scope


5.6 Control Scope

Manage and Control


Mgt.
6.1 Plan Schedule
Project
Work
6.2 Define Activities
Activities
6.3 Sequence
Perform
Integrated
6.4 Est. Activity Resources
6.5 Est. Activity Durations
Change
Control
6.6 Dev. Schedule
Validate
Scope
7.1 Plan Cost
Mgt.
7.2 Estimate Costs
Control
Scope
7.3 Determine
Budget
8.2 Perform Quality
8.1 Plan Quality
Mgt.
Control
Schedule
Assurance
9.1 Plan Human
9.2 Acquire Project Team
Control
Costs
Resource Mgt.
9.3 Develop Project Team
Control Quality 9.4 Manage Project Team
10.1 Plan Communications
10.2 Manage Communications
Management
Control
Communications
11.1 Plan Risk
Management
Control
Risks
11.2 Identify Risks
11.3 Perform
Qualitative
Control
Procurements
Risk Analysis
11.4 Perform Quantitative
Control
Stakeholder
Risk Analysis
11.5 Plan Risk Response
Engagement
12.1 Plan Procurement Mgt.
12.2 Conduct Procurements
13.2 Plan Stakeholder
Management

Monitoring &
Controlling

13.3 Manage Stakeholder


Engagement

6.7 Control Schedule

7.4 Control Costs

8.3 Control Quality

10.3 Control Communications

11.6 Control Risks

12.3 Control Procurements

12.4 Close Procurements

13.4 Control Stakeholder


Engagement

PMP Prep: PMBOK 5th - 2013

M&C: Integration Management

PMBOK Fifth Edition, Page 86

4.4 Monitor and Control Project Work


Inputs

Project management plan


Schedule forecasts
Cost forecasts
Validated changes
Work performance information
Enterprise environmental factors
Organizational process assets

Page 274

Tools &
Techniques

Expert judgment
Analytical techniques
Project management
information system
Meetings

Outputs

Change requests
Work performance reports
Project management plan
updates
Project documents updates

PMP Prep: PMBOK 5th - 2013

4.4 Monitor and Control Project Work

Monitor and Control Project


Work is the process of tracking,
reviewing and reporting the
progress to meet the
performance objectives defined
in the project management plan.
Control includes determining
corrective action, preventative
action or defect repair and
following up on actions taken to
resolve performance issues

Page 274

PMP Prep: PMBOK 5th - 2013

4.4 Monitor and Control Project Work


Taken together, the controlling processes monitor project progress and performance
against the plan and provide the appropriate response to deviations from plan. These
responses frequently require changes to the project plan; hence, project planning,
project execution, and project control form a triad of process groups that are
repeated throughout the project life cycle at each phase gate.

Project monitoring and control is more than earned value


Many project management technicians and some inexperienced project managers
equate project control with earned value. While earned value is an essential part of
project control, it is only a part. Fully integrated project control draws from several
knowledge areas and calls upon all of the leadership, communication, and negotiation
skills of the project manager.

Project monitoring and control is more than data collection


Another common, practical problem is confusing data collection with project control.
Project control is more than just collecting data about project performance; it also
requires analyzing the data, evaluating the meaning of the data and any variances,
taking appropriate corrective actions, and related record keeping.

Page 273

PMP Prep: PMBOK 5th - 2013

4.4 Monitor and Control Project Work


This process is part of Project Integration Management knowledge area,
along with Integrated Change Control. This process involves monitoring
all processes: initiating, planning, executing, and closing.
Monitoring &
Controlling Processes
Planning
Processes

Closing
Processes

Initiating
Processes

Executing
Processes

Page 274

PMP Prep: PMBOK 5th - 2013

4.4.1 Monitor and Control Project Work


Inputs: The Project Management Plan (Another Reminder)

The other 23 planning processes are integrated to create the project


management plan. Updates to any plans require an update to the PM plan. Think
of the PM plan as a bucket into which all the other plans drip until it is full.

Page 275

Plan Scope Management


Collect Requirements
Define Scope
Create WBS
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Plan Cost Management
Estimate Costs

Determine Budget
Plan Quality Management
Plan Human Resource Management
Plan Communications Management
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Response
Plan Procurement Management
Plan Stakeholder Management
PMP Prep: PMBOK 5th - 2013

4.4.1 Monitor and Control Project Work


Other Inputs:

Schedule Forecasts
using schedule variance (SV) and schedule performance index
(SPI) to compute estimate to complete (ETC)

Cost Forecasts
using cost variance (CV) and cost performance index (CPI) to
compute estimate at completion (EAC)

Validated Changes
Work Performance Information
collected data is analyzed and transformed into work
performance information

EEF and OPA

Page 275-276

PMP Prep: PMBOK 5th - 2013

Work Performance Information


Status of deliverables
Implementation of change requests
Forecasts: variance, trend, and earned value
information, estimates at completion (EAC),
schedule forecasts, index information
(SPI, CPI, TCPI).
Generally involves Gantt charts and S-curves.
Includes cost, schedule, quality and scope
accomplishment and variance information

Page 276

PMP Prep: PMBOK 5th - 2013

4.4.1 Monitor and Control Project Work


Tools and Techniques:

Expert Judgment
Analytical Techniques
regression analysis, grouping methods
causal analysis root cause, FMEA, trends, etc.

Validated Changes
PMIS and Meetings

Page 277

PMP Prep: PMBOK 5th - 2013

M&C: Integration Management

PMBOK Fifth Edition, Page 94

4.5 Perform Integrated Change Control


Inputs

Project management plan


Work performance reports
Change requests
Enterprise environmental factors
Organizational process assets

Page 279

Tools &
Techniques

Expert judgment
Meetings
Change control tools

Outputs

Approved change requests


Change log
Project management plan
updates
Project documents updates

PMP Prep: PMBOK 5th - 2013

4.5 Perform Integrated Change Control


Perform Integrated Change Control
is the process of reviewing all
change requests, approving
changes and managing changes to
deliverables, organizational process
assets, project documents and the
project management plan; and
communicating their disposition.
Sometimes a Change Control Board
(CCB) is responsible for approving
or rejecting changes, as approved
by the customer or sponsor.
Configuration Control focuses on the specification of deliverables and
processes.
Change Control focuses on changes to project documents, deliverables or
baselines.
Page 279-280

PMP Prep: PMBOK 5th - 2013

4.5 Perform Integrated Change Control


Change Control System

A set of procedures that describes how modifications to the


project deliverables and documentation are managed and
controlled, including:

Page 280

requesting changes
reviewing the implications of changes requests
approving or rejecting changes
communicating changes
maintaining a change log - comprehensive list of changes

PMP Prep: PMBOK 5th - 2013

4.5.2 Perform Integrated Change Control


Tools and Techniques: Configuration Management

A set of processes and procedures to ensure that the


documentation of the product and the actual
product remain consistent with each other:

Exam
Tip

Glossary Definition:
The configuration management system is a collection of procedures used
to identify and document the functional and physical characteristics of a
product or component. It:
controls changes to these characteristics,
records/reports each change,
audits the products to verify conformance to requirements.
documentation, tracking, and approval levels
validates the impact, and
communicates them to stakeholders.
Page 281

PMP Prep: PMBOK 5th - 2013

4.5.1 Perform Integrated Change Control


Inputs: Work Performance Reports

Reports of interest include:


resource availability,
schedule/cost data,
earned value management (EVM) reports, and
Burnup or burndown charts.
A burnup chart tracks how much
work is done.

Page 281

A burndown chart tracks how much


work remains on your project and
whether or not you will hit the deadline.

PMP Prep: PMBOK 5th - 2013

4.5.1 Perform Integrated Change Control


Inputs: Change Requests are NOT Change Orders

Change Requests: oral or written, formal or informal, may or may not


be implemented

Change Orders: formal request for change to approved project plan;


typically used for projects performed under contract
Exam
Tip

Beware of the Constructive Change Order -- an oral or written


communication from a perceived authority that the project team may
(possibly legally) respond to as equivalent to a written change order.
A Functional Manager wants to make a change in the project. What is the first
thing a PM should do?
A Senior Manager decides the scope of work should be changed. What is best
to do?
Answer: Evaluate the impact on the project. Meet with the team to discuss
alternatives, before deciding to use reserves and meet with management.
The Exam lists incorrect choices, like: meet with the customer first or meet
with management first The correct answer is evaluate first

Page 282

PMP Prep: PMBOK 5th - 2013

4.5.2 Perform Integrated Change Control


Tools and Techniques: Change Control Meeting
Approved or Rejected Change Requests

In some projects, changes are controlled by a Change Control Board (CCB),


And implemented by the Project Team
A Change Control Board (CCB) is:
A formally chartered group responsible for reviewing, evaluating,
approving, delaying, or rejecting changes to the project, and for recording
and communicating such decisions.

Page 283

Reviews and approves or rejects change requests


May also be responsible for defining the change request process,
communicating change decisions, and managing the implementation
of approved changes.
Power and responsibilities should be reviewed and agreed to by
stakeholders

PMP Prep: PMBOK 5th - 2013

M&C: Scope Management


5.5 Validate Scope
Inputs

Project management plan


Requirements documentation
Requirements traceability matrix
Verified deliverables
Work performance data

Page 285

Tools &
Techniques

Inspection
Group decision-making
techniques

Outputs

Accepted deliverables
Change requests
Work performance
information
Project documents updates

PMP Prep: PMBOK 5th - 2013

5.5 Validate Scope


PMBOK Fourth Edition, Page 123

Validate Scope
is the process of
formalizing acceptance
of the completed
project deliverables.
Scope validation is
different from quality
control in that
validate scope is
primarily concerned
with the acceptance of
the deliverables

Page 285

PMP Prep: PMBOK 5th - 2013

5.5.3 Validate Scope


Outputs: Accepted Deliverables

These have all been answers on the test:


Customer feedback on a more detailed basis
Done at the end of each Project Phase

Results in formal acceptance


Exam
Tip

The questions on the exam are vague on Scope Validation.


Read them carefully.
One question asks for: the key aspect of scope validation
Answer: customer acceptance of project efforts.
The answer does not involve correctness of the work.

Page 287

PMP Prep: PMBOK 5th - 2013

M&C: Scope Management

PMBOK Fifth Edition, Page 136

5.6 Control Scope


Inputs

Project management plan


Requirements documentation
Requirements traceability matrix
Work performance data
Organizational process assets

Page 288

Tools &
Techniques

Variance analysis

Outputs
Work performance
information
Change requests
Project management plan
updates
Project documents updates
Organizational process assets
updates

PMP Prep: PMBOK 5th - 2013

5.6 Control Scope


Control Scope is the process
of monitoring the status of the
project and product scope and
managing changes to the
scope baseline
Uncontrolled changes are
often referred to as Scope
Creep.

Page 288

PMP Prep: PMBOK 5th - 2013

5.6.1 Control Scope


Inputs

The primary inputs to Control Scope are:

Project management plan


Requirements documentation
Requirements traceability matrix
Work performance data
Organizational process assets

The project management plan includes the following to control scope:

Page 288

The scope baseline


Scope management plan
Change management plan
Configuration management plan
Requirements management plan

PMP Prep: PMBOK 5th - 2013

5.5.2 Control Scope


Tools and Techniques: Variance Analysis

a comparison of actual results to planned results for the purpose of early


problem detection ...
Cost, schedule, scope, and quality variances
are most typical but they can also include
resources and risk variances.
Both positive and negative variances need
analysis
Should involve an evaluation of cause and
impact
Becomes an input to change control process
for generating corrective actions

Pages 290

PMP Prep: PMBOK 5th - 2013

5.5.2 Control Scope


Outputs: Work Performance Information

Pages 291

PMP Prep: PMBOK 5th - 2013

M&C: Time Management

PMBOK Fifth Edition, Page 185

6.7 Control Schedule


Inputs

Project management plan


Project schedule
Work performance data
Project calendars
Schedule data
Organizational process assets

Page 292

Tools &
Techniques
Performance reviews
Project management
software
Resource optimization
techniques
Modeling techniques
Leads and lags
Schedule compression
Scheduling tool

Outputs
Work performance
information
Schedule forecasts
Change requests
Project management plan
updates
Project documents updates
Organizational process
assets updates

PMP Prep: PMBOK 5th - 2013

6.7 Control Schedule


Control Schedule is the process
of monitoring the status of
project activities to update
project progress and manage
changes to the schedule baseline
to achieve the plan

Page 292

PMP Prep: PMBOK 5th - 2013

6.7.1 Control Schedule


Inputs

The inputs to Control Schedule are:

Project management plan


Project schedule
Work performance data
Project calendars
Schedule data
OPA

To control schedule, the project management plan includes:


The schedule management plan
The schedule baseline

Page 292

PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Performance Reviews

PV = Planned Value (was BCWS) (1)


EV = Earned Value (was BCWP) (2)
AC = Actual Cost (was ACWP) (3)

(1)
(2)
(3)

requires a performance baseline


requires a way to measure value of
work completed (earned value)
requires a way to collect actual
costs at work package level

AC
Actual Cost

Cost,
Hours,
or Work
Products

PV
Planned Value
SV
Schedule
Variance

CV
Cost
Variance

EV
Work Performed
(Earned Value)

Time
t When Planned
t Actual

Pages 294-295

PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Variance Analysis

a comparison of actual results to planned results for the purpose of early


problem detection ...
Cost, schedule, scope, and quality variances
are most typical but they can also include
resources and risk variances.
Both positive and negative variances need
analysis
Should involve an evaluation of cause and
impact
Becomes an input to change control process
for generating corrective actions

Pages 294-295

PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Corrective Action

Changes to align future project performance with the project plan.


Corrective actions should be based on what-if evaluations and may
be the result of formal replanning. Corrective actions complete the
loop between project control and project execution:
* Taking action to expedite schedules, such
as assigning more or different resources or
overlapping tasks
* Delaying a purchase to protect cash flow
* Invoking planned risk responses when risk
events occur

Page 294

PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Trend Analysis

a tool that uses mathematical


techniques to forecast future
outcomes based on past results

may be used to monitor quality


(product), cost and schedule
performance of a project

provides a high-level overview that


indicates whether or not more
detailed information is needed

Page 295

The Rule of Seven: 7 data


points all above or below the
mean, or all increasing or
decreasing, indicate a trend
PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Project Management Software

Page 206

PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Resource Optimization Techniques

The resource histogram is a time-phased display of the amount of


project work assigned to each resource (PMBOK Fifth Edition, Page 189-190)
Resource plans are best when resource requirements
increase and decrease without variations
Month 1

Month 2

Month 3

Month 4

1.5

1.0

0.5

Product Manager

Page 296

PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Modeling Techniques

Page 297

PMP Prep: PMBOK 5th - 2013

6.7.2 Control Schedule


Tools and Techniques: Schedule Compression

Activity
A
B
C

Normal Normal
Time
Cost
4 wks
3 wks
2 wks

12,000
6,000
4,000

Crash
Time

Crash
Cost

Crash
(wks)

2 wks
2 wks
1 wks

15,000
7,000
5,500

2 wks
1wks
1 wks

Crash Cost
Total
Crash Cost per week

3,000
1,000
1,500

1,500
1,000
1,500

Fast Tracking
Paralleling - Activities or phases normally be done in sequence are performed in
parallel for at least a portion of their duration. fast tracking can result in rework and
increased risk.
Exam
Tip

Crashing
A technique to shorten the schedule duration for the least incremental cost by adding
resources. Works only for activities on the critical path. May result in increased risk
and/or cost.
Page 298

PMP Prep: PMBOK 5th - 2013

M&C: Cost Management

PMBOK Fifth Edition, Page 215

7.4 Control Costs


Inputs

Project management plan


Project funding requirements
Work performance data
Organizational process assets

Page 300

Tools &
Techniques

Earned Value Management


Forecasting
To-complete performance
index (TCPI)
Performance reviews
Project management software
Reserve analysis

Outputs
Work performance
information
Cost forecasts
Change requests
Project management plan
updates
Project documents updates
Organizational process
assets updates

PMP Prep: PMBOK 5th - 2013

7.4 Control Costs


Control Costs is the process of
monitoring the status of the
project to update the project
costs and managing changes to
the cost baseline

Page 300

PMP Prep: PMBOK 5th - 2013

7.4.1 Control Costs


Inputs: Project Management Plan (Cost Management Plan & Cost Baseline)
A time-phased budget (either by performance period or summed cumulatively
over the life of the project) used to monitor and control project costs.
Cost

Cost Performance Baseline


Exam
Tip

BAC
Cumulative
Planned Value (PV)

Spending Plans
and Cash Flow
Plans are special
types of Cost
Baselines

Monthly Planned
Value (PV)
Time

Page 301

PMP Prep: PMBOK 5th - 2013

7.4.1 Control Costs


Inputs: Project Funding Requirements and Management Reserve

Project Budget

Cost

EAC (forecasted cost)

Cost Baseline
Cumulative Planned
Value (PV)

BAC

}
Management
Reserve

Exam
Tip

Cash Flow
Funding
Expenditures

Time

Page 302

PMP Prep: PMBOK 5th - 2013

7.4.1 Control Costs


Inputs: Work Performance Data

Organizes and summarizes information on project


status and progress

It includes data on activities that have started , their


progress, and which deliverables have been finished
Includes cost, schedule, scope accomplishment and variance information

Includes data on costs authorized and costs incurred

Caution: Ensure a consistent data date,


ideally from a common set of data

Page 302

PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: Earned Value Management (EVM)

Exam
Tip

Earned value management (EVM), also known as earned


value technique (EVT) compares Earned Value (EV or BCWP)
to both Planned Value (PV or BCWS) and Actual Cost (AC or
ACWP) to analyze cost control, resource management, and
production. Cost control determines the cause of a variance,
its magnitude, and if corrective action is needed.

CV at the end of a project is BAC minus total actual cost. SV


at the end of a project is zero, because all of the planned
values will have been earned.
CPI and SPI are efficiency indicators.

Page 303 & 305

PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: Earned Value Management (EVM)

Definition of Terms
PV

Planned Value

Value of work planned to be done at any point in time.

AC

Actual Cost

How much did we spend to get the work done at a point in time?

EV

Earned Value

Planned value of the work we completed at any point in time.

BAC

Budget at Completion

How much did we budget for the whole project?

EAC

Estimate at Completion

Given our progress, what is our forecast of the total project cost?

ETC

Estimate to Complete

How much more do we estimate the job will cost?

VAC

Variance at Completion

How much over/under budget will we be?

Page 304

PMP Prep: PMBOK 5th - 2013

Tools and Techniques: Earned Value Management (EVM) - Equations


CV

Cost Variance

CV = EV AC

Negative = Over budget,


Positive = Under budget

SV

Schedule Variance

SV = EV PV

Negative = Behind schedule,


Positive = Ahead of schedule

CPI

Cost Performance Index

CPI =

SPI

Schedule Performance
Index

SPI = EV
PV

EAC

Estimate at Completion
(4 formulas)

EAC =

Definition:
At this time in the project,
what is the forecast of
total project cost?

Page 304

EV
AC

BAC
CPI

Less than 1.0 = Over budget


Greater than 1.0 = Under budget
Less than 1.0 = Behind schedule
Greater than 1.0 = Ahead of schedule
Used when EV trend is typical (CPI will be the
same for the rest of the project)

EAC = AC + (BAC-EV)

Used when EV trend is atypical (CPI will


change to follow the planned rate, or PV line)

EAC = AC + ETC

Actual cost plus bottom-up estimate to


complete by the team. (plan is no longer valid,
re-estimate the plan)

EAC = AC + (BAC-EV)
(CPI x SPI)

Used when both CPI and SPI influence the


remaining work. Assumes negative cost
performance and need for firm schedule.
PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: Earned Value Management (EVM) - Equations
ETC

Estimate to Complete

ETC = EAC - AC

The expected cost to finish all the remaining


work. If work is proceeding on plan, use this
this to calculate the work remaining

ETC= Re-estimate

Bottom up re-estimate by the team

TCPI = BAC-EV
BAC-AC

Less than 1.0 = Easier to complete


Greater than 1.0 = Harder to complete
(Value of work remaining divided by the value
of the budget remaining)

TCPI
Based
on
BAC
Based
on
EAC

Cost efficiency that must


be maintained to
complete the project on
plan (BAC).

TCPI = BAC-EV
EAC-AC

Cost efficiency that must


be maintained to
complete the current EAC.
VAC

Page 305

VAC = BAC-EAC

Variance at Completion

Less than 1.0 = Easier to complete


Greater than 1.0 = Harder to complete
(Value of work remaining divided by
calculated estimate to complete, ETC)
At the end, how much more or less than plan
will we have spent?
PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: Earned Value Management (EVM)
Work Products
Money

$3,000

Hours

300

EAC

Deliverables.

30
Projected
Overrun

$2,000

200

20
Cost
Variance
(CV)

$1,000

100

BAC
AC

PV

(Baseline)

Schedule Variance (SV)

10
EV

0
1

Weeks
Page 307

PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: EVM, The Easy Way to Remember It

Page 307

EV (BCWP) comes first in every formula.

If it is a variance - it is EV minus something

If it is an index - it is EV divided by something

If the question relates to cost - use AC

If the question refers to schedule - use PV

Negative is either behind schedule or over budget


( For example: CV = -30% = over budget)

Positive is either ahead of schedule or under budget

PMP Prep: PMBOK 5th - 2013

Exercise

Project Status at the end of Week 2


Task A
Task B
Task C

100% complete
25% complete
0% complete

Dimensions of Project Performance

AC = 140 hours
AC = 80 hours
AC = 0 hours

Try It:
Schedule Variance

-50 hours
____________

Cost Variance

-70 hours
____________

Cost at Completion
(Typical)
Cost at Completion
(Atypical)

PV

Planned Value

AC

Actual Cost

EV

Earned Value

Schedule Variance =

EV - PV

Cost Variance

EV - AC

EVc/ACc

CPIc

Estimated (Cost)
at Completion
(EAC): Typical

733 hours
____________
570 hours
___________

ACc

Estimated (Cost)
at Completion =

(BAC-EVc)]
CPIc

ACc + (BAC-EVc)

(EAC): Atypical

WBS

Cum. Hrs.
500

EVc

= 150 hours
200 hours
SV = - 50 hours
PVc =

EVc = 150 hours


ACc = 220 hours
CV = - 70 hours

50
400

50

A
100

300

Task A

Task B

Task C

100 Hrs

200 Hrs

200 Hrs

PV
BCWS
100

B
200

100

Cost at Completion
(Atypical)

100

100

Cost at Completion
(Typical)
1

Page 308

= 220 + (500 -150)


= 570 hours

2
3
Time, weeks

= 220 + [(500-150)/(150/220)]
= 733 hours
= BAC/CPI

PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: Forecasting
EAC Based on ETC by the Team
EAC = AC + Bottom-Up ETC

EAC Forecast where Future Work is at Same Rate of Work Shown in the Baseline Budget
Past costs were atypical, and future work will be at the same rate of expenditure as in the baseline budget.
EAC = AC + (BAC - EV)

EAC Forecast where Future Work will not Change from Actual
Past costs were typical of what will happen in the future.
EAC = BAC/CPI

Same as:
EAC = AC + [(BAC EV)]/CPI]

EAC Forecast where Future Work be Modified by both CPI and SPI
Future work will be at the same rate of expenditure as in the original baseline budget, but is modified by
both of the indexes. It assumes the project is in a cost overrun situation and there is a requirement to meet
a firm schedule commitment. It is useful when schedule is a factor affecting future work. The weighting of
CPI and SPI can be varied according to the PMs judgment (80/20, 50/50, etc.)
EAC = AC + [(BAC EV)/(CPI x SPI)]

Page 309

PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: To-Complete Performance Index (TCPI)

TCPI is used to determine if the BAC or the EAC can be reasonably achieved

It measures future cost performance needed achieve either a target BAC or


target EAC. Calculate the reasonableness of BAC first. If it is obvious that the
BAC is no longer viable, the project manager should consider the
reasonableness of achieving the forecasted EAC.
To Achieve a Target EAC

To Achieve a Target BAC


TCPI (BAC) =

TCPI (BAC) =

Page 310

Work Remaining
Funds Remaining

TCPI (EAC) =

BAC - EV
EAC - AC

BAC - EV
BAC - AC

PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: To-Complete Performance Index (TCPI)

The TCPI is compared to the cumulative CPI to determine if a target EAC is


reasonable, e.g., within plus/minus 0.05 of the cumulative CPI (some
management groups allow plus/minus 0.10). If a TCPI delta exceeds 0.05, the
target EAC may be overly optimistic. If a TCPI delta is lower than 0.05, the target
EAC may be overly conservative.
Given a TCPI of 1.1, the simple definition is: for every dollar spent from here to
the end of the contract, a dollar and ten cents worth of budgeted work must be
completed (or earned) to achieve the target EAC. Likewise a TCPI of 0.95 means:
for every dollar spent from here to the end of the contract, only 95 cents worth
of budgeted work must be completed or earned.

Page 310

PMP Prep: PMBOK 5th - 2013

7.4.2 Control Costs


Tools and Techniques: To-Complete Performance Index (TCPI)

To-CompletePerformance
Performance Index
Index
To-Complete
Status Date

+
TCPI (BAC)

Baseline Plan

1.00

TCPI (EAC)

Pages 310

Cumulative CPI

PMP Prep: PMBOK 5th - 2013

M&C: Quality Management

PMBOK Fifth Edition, Page 248

8.3 Control Quality


Inputs

Project management plan


Quality metrics
Quality checklists
Work performance data
Approved change requests
Deliverables
Project documents
Organizational process
assets

Page 315

Tools & Techniques

Seven basic quality tools


Statistical sampling
Inspection
Approved change requests
review

Outputs

Quality control
measurements
Validated changes
Verified deliverables
Work performance information
Change requests
Project management plan
updates
Project documents updates
Organizational process
assets updates

PMP Prep: PMBOK 5th - 2013

8.3 Control Quality


Perform Quality Control is
the process of monitoring
and recording results of
executing the quality
activities to assess
performance and
recommend necessary
changes

Page 315

PMP Prep: PMBOK 5th - 2013

8.3.1 Control Quality


Inputs: Are straight forward, read them, but remember:

Quality Assurance (QA): the process of auditing quality requirements, and the
results from quality control (QC) measurements, to ensure quality standards and
operational definitions are used..
Quality assurance involves Quality Audits, and is done in Execution Process.

Quality Control (QC): a process of monitoring and recording results (both product
and project management) of executing quality activities to assess performance and
to recommend necessary changes. Involves identifying ways to remove the causes of
quality defects.
Quality control involves inspection and requires an understanding of sampling
strategies, tolerances, and the causes of variation in a process. It is done in the
Monitoring and Controlling Process.

Pages 316

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques
The first seven (7) Tools & Techniques in this section are
called the Seven Basic Tools of Quality - know these for the
test!

Exam
Tip

Page 319

Cause and Effect Diagram


Control Charts
Flowcharting
Histograms
Pareto Diagrams
Checksheets
Scatter Diagram

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Cause and Effect Diagram

Cause & Effect, Ishikawa or Fishbone Diagrams

People

Not Following
Procedures

Material

Methods

Lack of Training

CAUSES

Transport

Page 319

IT System

EFFECT

Procedure

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Control Charts

A chart of process performance over time used to


determine if the process is in control or out of control

UCL

3
99.7%

.
.
.
.
.
.
.. . . . . .. . . .
. .. . .. . .
.. . . .
.
.
..
.
.
2
95.5%

Expected
Variation

Out of Control
(Assignable Cause)

1
68%

Normal
Distribution
Curve

Mean

LCL

in control
normal distribution of outcomes
due to common causes of variation
inherent in the process
Page 320

out of control
rule of seven, trends, and cycles
due to special causes of variation
external to the process
PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Control Charts

Hours recorded for this project


started on plan, but if the trend
continues, hours spent will drift
out of control.

Upper Spec. Limit


UCL
Plan or Mean
LCL
Lower Spec. Limit

Actual

Page 321

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Flowcharting

Process Flowchart
Yes

Design

Review

Proceed

OK?
No

Revise

Page 321

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality

% contribution (or frequency of occurrence)

Tools and Techniques: Pareto Charts

Pareto Diagram:
80%?

a histogram, ordered by
frequency of occurrence, that shows the percent
contribution of each category of identified cause to
the overall quality defects in a product or process.

Pareto Analysis:

Pareto diagrams help


project teams identify the vital few factors that
account for most quality problems from the more
numerous trivial many factors.
Paretos Law:

Design of Experiments:

80/20 Rule

Which variables have influence


over the outcome.
What If Analysis

source
Pages 321-322

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Run Chart

a tool that uses mathematical


techniques to forecast future
outcomes based on past results
may be used to monitor quality
(product), cost and schedule
performance of a project
provides a high-level overview that
indicates whether or not more
detailed information is needed

Page 322

The Rule of Seven: 7 data


points all above or below the
mean, or all increasing or
decreasing, indicate a trend

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Scatter Diagram

Page 323

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Statistical Sampling

a technique for accepting or rejecting a larger population


by choosing a part of the population for inspection ...
Statistical sampling can reduce the cost of QC on a project.
The validity of statistical sampling depends on an
appropriate choice of sample items and sample size.
Sample size increases exponentially as the level of desired certainty
increases and the acceptable level of error decreases.
Sampling strategies include single samples from a lot, multiple small
samples from a lot, and double sampling methods where the size of the
second sample depends on the results of the first sample.

All sampling strategies involve some risk of producer error (type I error)
where acceptable lots are rejected based on a non-representative sample
or consumer error (type II error) where unacceptable lots are accepted
based on a non-representative sample.
Page 324

PMP Prep: PMBOK 5th - 2013

8.3.2 Control Quality


Tools and Techniques: Inspection Techniques

An evaluation of whether or not the project results


conform to the latest specifications and requirements ...
Types of Inspection :

measuring
examining
auditing
testing
acceptance testing
reviewing
walk-throughs

Inspection generally takes place throughout


the projects lifecycle. Be sure to plan for it
accordingly and to include it in the WBS.

Page 325

PMP Prep: PMBOK 5th - 2013

M&C: Communications Management


PMBOK Fifth Edition, Page 303

10.3 Control Communications


Inputs

Project management plan


Project communications
Issue log
Work performance data
Organizational process assets

Page 328

Tools &
Techniques

Information management
systems
Expert judgment
Meetings

Outputs

Work Performance
information
Change requests
Project management plan
updates
Project documents updates
Organizational process
assets updates

PMP Prep: PMBOK 5th - 2013

10.3 Control Communications


Control Communications is the
process of monitoring and
controlling communications
throughout the entire project
life cycle to insure the
information needs of the
project stakeholders are met.

Page 328

PMP Prep: PMBOK 5th - 2013

10.3.1 Control Communications


Inputs: Work Performance Data

Earned Value Management: Test Yourself


How much work is done so far?

How much work did we plan to have done so far?


When do we now estimate the project will be done?
How much have we spent for what weve achieved?
How much did we plan to spend for what weve achieved?

How much do we now estimate the project will cost to complete?

Page 329

PMP Prep: PMBOK 5th - 2013

10.3.3 Control Communications


Outputs: Work Performance Information
Earned Value Management: The Data

Variance Analysis
PV = Planned Value (was BCWS) (1)
EV = Earned Value (was BCWP) (2)
AC = Actual Cost (was ACWP) (3)

a comparison of actual results to planned results for the purpose of early


problem detection ...

(1) requires a performance baseline


(2)
(3)

requires a way to measure value of


work completed (earned value)
requires a way to collect actual
costs at work package level

AC
Actual Cost

Cost, schedule, scope, and quality variances


are most typical but they can also include
resources and risk variances.
Both positive and negative variances need
analysis
Should involve an evaluation of cause and
impact
Becomes an input to change control process
for generating corrective actions

Cost,
Hours,
or Work
Products

Total
Variance

PV
Planned Value

SV
Schedule
Variance

CV
Cost
Variance

EV
Work Performed
(Earned Value)

Time
t When Planned
t Actual

Trend Analysis

Page 332

a tool that uses mathematical


techniques to forecast future outcomes
based on past results

may be used to monitor quality


(product), cost and schedule
performance of a project

provides a high-level overview that


indicates whether or not more detailed
information is needed

The Rule of Seven: 7 data


points all above or below the
mean, or all increasing or
decreasing, indicate a trend

PMP Prep: PMBOK 5th - 2013

M&C: Risk Management

PMBOK Fifth Edition, Page 349

11.6 Control Risks


Inputs

Project management plan


Risk register
Work performance data
Work performance reports

Page 335

Tools &
Techniques

Risk reassessment
Risk audits
Variance and trend analysis
Technical performance
measurement
Reserve analysis
Meetings

Outputs

Work performance
information
Change requests
Project management plan
updates
Project documents updates
Organizational process
assets updates

PMP Prep: PMBOK 5th - 2013

11.6 Control Risks


Control Risks is the process of
implementing risk response
plans, tracking identified
risks, monitoring residual
risks, identifying new risks
and evaluating risk process
effectiveness throughout the
project

Page 335

PMP Prep: PMBOK 5th - 2013

11.6.1 Control Risks


Inputs

The Risk Management Plan Includes:


Methodology: Approaches, tools and data sources.
Roles and Responsibilities: Team member ownership for risk activities.

Risk Register

Budgeting: Funds needed for contingency reserves and management reserves.


Timing: When processes will be done, reserves applied, and how risk appears in schedule.

Sources of risk, potential risk event, and risk symptoms

Categories: Risk groupings. The RBS looks at sources of risk, IDs and categorizes them.

Opportunities to pursue, opportunities to ignore

Thresholds: What is the trigger? Stakeholders have different thresholds of risk tolerance,
define them, and the must be agreed by all.

Threats to respond to, threats to accept

Planned risk responses and how contingencies will be implemented

Define P/I Levels: Qualitative (low to high) or probabilities.

Risk reserves

Risk Matrix: Likelihood-Severity, or Probability-Impact.

Responsibilities for risk management

Stakeholder Risk Tolerances: Progressively elaborated.

Plan for ongoing risk identification,


quantification, and response development

Reporting Formats and Tracking: Document risk, auditing, defines content of risk register.

Work Performance Reports


Purpose of Performance Reports:
to detect problems in time to take corrective or preventive
action
to reduce customer and management anxiety
to share project information within the project team

Guidelines for Performance Reports:


keep the report short, matching its length to
the projects complexity and the audiences
needs
use a consistent template and format
use visual elements such as charts and graphs

Page 335-236

Criteria for Performance Reporting:


gives timely, complete, and accurate information
doesnt add more administrative overhead than
its worth
is acceptable and useful to all participants
gives warning of problems in time for preventive
or corrective actions
is easily understood by those who have a need to
know

PMP Prep: PMBOK 5th - 2013

11.6.2 Control Risks


Tools and Techniques: Variance and Trend Analysis

Variance Analysis
a comparison of actual results to planned results for the purpose of early
problem detection ...

Cost, schedule, scope, and quality variances


are most typical but they can also include
resources and risk variances.
Both positive and negative variances need
analysis
Should involve an evaluation of cause and
impact
Becomes an input to change control process
for generating corrective actions

Page 338

Trend Analysis

a tool that uses mathematical


techniques to forecast future outcomes
based on past results

may be used to monitor quality


(product), cost and schedule
performance of a project

provides a high-level overview that


indicates whether or not more detailed
information is needed

The Rule of Seven: 7 data


points all above or below the
mean, or all increasing or
decreasing, indicate a trend

PMP Prep: PMBOK 5th - 2013

11.6.2 Control Risks


Tools and Techniques: Reserve Analysis

A provision in the project plan to mitigate cost and/or schedule


risk
May be calculated as a percent of baseline to allow for overruns
May be established as a separate fund for unforeseen problems
May have many different (and application area specific) names:
management reserve
contingency
May be assigned to any level of the WBS, or RBS cause.

Exam
Tip

PMI recommends a
minimum total
reserve of 10%

Pages 339

PMP Prep: PMBOK 5th - 2013

11.6.3 Control Risks


Outputs: Updates and Change Requests

Implementing contingency plans or workarounds


requires change to the project plan.
Workaround is defined as a response to a threat
that has occurred, for which a prior response had
not been planned or was not effective.
Change requests can include corrective and
preventive actions.

Change Control System


A set of procedures that describes how modifications to
the project deliverables and documentation are managed
and controlled, including:

requesting changes
reviewing the implications of changes requests
approving or rejecting changes
communicating changes
maintaining a change log - comprehensive list of changes

Exam
Tip

Was on
my test

Contingency =
Pre-Planned

Pages 339

PMP Prep: PMBOK 5th - 2013

Exam
Tip

Exercise
Risk Monitoring and Control

The exam often asks questions such as:


What do you do with non-critical risks?

Answer: Document and revisit frequently

Would you select only one risk response strategy?

Answer: No, a combination of choices

What risk activities would you do during Execution?


.

Answer: Watch for non-critical risks that


become more important

What is most important to address in team meetings? Answer: Risk


How would risk be addressed in team meetings?

Answer:

Status of risks?, Any new


risks?, Any change to the
order of importance?

Which are more frequent, contingency plans


or workarounds?

Answer:

With proper risk management


Workarounds become less
frequent than contingency plans.

PMP Prep: PMBOK 5th - 2013

M&C: Procurement Management

PMBOK Fifth Edition, Page 379

12.3 Control Procurements


Inputs

Project management plan


Procurement documents
Agreements
Approved change requests
Work performance reports
Work performance data

Page 341

Tools &
Techniques
Contract change control
system
Procurement performance
reviews
Inspections and audits
Performance reporting
Payment systems
Claims administration
Records management
system

Outputs

Work performance
information
Change requests
Project management plan
updates
Project documents updates
Organizational process
assets updates

PMP Prep: PMBOK 5th - 2013

12.3 Control Procurements


Control Procurements is the
process of managing
procurement relationships,
monitoring contract performance
and making changes and
corrections to contracts as
appropriate

Page 341

PMP Prep: PMBOK 5th - 2013

12.3.1 Control Procurements


Inputs

Procurement Statement of Work

Match Contract Type to the Project

A narrative description of products or services to be supplied under contract.

Provides the basis of agreement between buyer and supplier


Sufficient detail to allow prospective suppliers to determine
whether or not they can comply
Sufficient latitude for creative solutions only if appropriate

Each procurement requires a separate SOW. But one SOW


may cover many items in a single procurement
May be revised as the procurement progresses
Should be clear, concise, and unambiguous
May be developed by the project team
or supporting offices (or even the seller)
depending on policy and ability

Your best defense against procurement scope creep!

Pages 342-343

Fixed Price (or Lump Sum) Type Contracts:


Used on well specified projects for which costs can be accurately
estimated. Cost risk is on the supplier. (includes FFP, FPIF, FP-EPA)

Cost Reimbursable Type Contracts:

Exam
Tip

Used on development projects for flexibility. Cost risk is on the buyer,


so establish administrative & reporting systems to allow both buyer and
seller visibility into costs. (Includes CPFF, CPIF, CPAF)

Time & Materials Type Contracts:


Used on projects where the deliverables are well defined, repetitive units
but the quantities are not yet known (e.g., identical pieces of equipment, or
labor hours and associated material costs includes overhead and burden)

PMP Prep: PMBOK 5th - 2013

12.3.1 Control Procurements


Inputs: Approved Change Requests

Change Requests/ Change Orders / Constructive Change Orders -know the differences
Use the Change Control System and Change Control Board

Approved / Unapproved -- document all changes


Re-plan and update the documentation (including risk)

Contractors may use change orders to get well

Page 343

PMP Prep: PMBOK 5th - 2013

12.3.2 Control Procurements


Tools and Techniques: Contract Change Control System

Contract Change Control System


Defines the process by which the contract can be modified. It is
part of the Integrated Change Control system, and includes
paperwork, tracking systems, dispute resolution conditions, and
approval levels for authorization.
If the buyer terminates the contract for cause, convenience, or
default, it is done in accordance with the termination and change
control sections of the contract.
Contract changes usually also involve changes in either contract
pricing or schedule or both. Disputed changes may require
mediation or legal resolution.

Page 345

PMP Prep: PMBOK 5th - 2013

12.3.3 Control Procurements


Tools and Techniques: Contract Change Control System

Example
Contract Change Control System
modifying the contract

Note:

Exam questions - How is project control different in a contracted


environment? Answers may include:

When working under a contract, the PMs success depends not solely on
success of team members, but on the culture and procedures of the buyers company.

Page 348

: A Process for

(PMBOK Fourth Edition, Page 338)

You need to deal with a different companys set of procedures


It is not as easy to see the problems
A greater reliance on reports to determine if a problem exists
A greater reliance on relationships between Buyer and Sellers PMs.

PMP Prep: PMBOK 5th - 2013

12.3.2 Control Procurements


Tools and Techniques: Claims Administration

Claims Administration
Contested changes and constructive changes are those where the
buyer and seller cannot agree on payment for the change, or
cannot agree that the change even occurred. These become claims,
disputes, or appeals.
If not settled by the parties, it may be subject to dispute resolution
procedures in the contract, e.g., arbitration dispute resolution
(ADR), and can be started either before or after contract closure.
The preferred method of settlement is negotiation.

Page 345

PMP Prep: PMBOK 5th - 2013

12.3 Control Procurements


EXERCISE
CONTRACT INTERPRETATION WHICH WINS
In each line, circle the item that would win in a dispute over contract interpretation !
Contract Language

OR

A memo describing changes after the contract is signed

Contract Language

OR

A memo signed by both parties before the contract is signed that


describes what was agreed to during negotiations

Contract terms and conditions

OR

Scope of work

Common definition

OR

The intended meaning (without supplying a definition)

Industry use of the term

OR

Common use of term

Special provisions

OR

General provisions

Typed over wording on contract

OR

A handwritten comment on the contract that is also initialed

Numbers

OR

Words

Detailed terms

OR

General terms

It depends on the Order of Precedence Clause in the contract !

Page 350

PMP Prep: PMBOK 5th - 2013

M&C: Project Stakeholder Management


PMBOK Fifth Edition, Page 409

13.4 Control Stakeholder Engagement


Inputs

Project management plan


Issue log
Work performance data
Project documents

Page 351

Tools &
Techniques

Information management
systems
Expert judgment
Meetings

Outputs

Work performance
information
Change requests
Project management plan
updates
Project documents updates
Organizational process
assets updates

PMP Prep: PMBOK 5th - 2013

13.4 Control Stakeholder Engagement


Control Stakeholder
Engagement is the process of
monitoring overall project
stakeholder relationships and
adjusting strategies and plans for
engaging stakeholders. This
process will increase the
efficiency and effectiveness of
engaging stakeholders as the
project evolves.
The Project Manager (PM) is
responsible for engaging and
managing stakeholders.

Page 351

PMP Prep: PMBOK 5th - 2013

13.4.2 Control Stakeholder Engagement


Tools and Techniques: Information Management Systems

Information Management Systems


A variety of tools are available to the PM for capturing and
distributing information on cost schedule and performance.
Reports can be consolidated from several systems for
distribution.
Examples are table reporting, spreadsheet analysis, and
presentations. Dashboard graphics can be used for visual
presentation of project performance

Page 352

PMP Prep: PMBOK 5th - 2013

Closing Process Group

Page 355

PMP Prep: PMBOK 5th - 2013

PMBOK Fifth Edition, Page 61


Process Groups
Knowledge Areas
4. Project Integration
Management

Initiating
4.1 Develop Project Charter

5. Project Scope
Management

Planning
4.2 Develop Project
Management Plan
5.1
5.2
5.3
5.4

Executing

Closing

4.3 Direct & Manage


Project Work

Plan Scope Mgt.


Collect Requirements
Define Scope
Create WBS

Monitoring &
Controlling
4.4 Mon/Ctrl Proj Work
4.5 Perform Integrated
Change Control
5.5 Validate Scope
5.6 Control Scope

6.2
6.3
6.4
6.5
6.6

Define Activities
Sequence Activities
Est. Activity Resources
Est. Activity Durations
Dev. Schedule

7. Project Cost
Management

7.1 Plan Cost Mgt.


7.2 Estimate Costs
7.3 Determine Budget

8. Project Quality
Management

8.1 Plan Quality Mgt.

8.2 Perform Quality


Assurance

9. Project Human
Resource
Management

9.1 Plan Human


Resource Mgt.

9.2 Acquire Project Team


9.3 Develop Project Team
9.4 Manage Project Team

7.4 Control Costs

8.3 Control Quality

10. Project
Communications
Management

10.1 Plan Communications


Management

11. Project Risk


Management

11.1 Plan Risk Management


11.2 Identify Risks
11.3 Perform Qualitative
Risk Analysis
11.4 Perform Quantitative
Risk Analysis
11.5 Plan Risk Response

12. Project Procurement


Management

12.1 Plan Procurement Mgt.

12.2 Conduct Procurements

12.3 Control Procurements

13.2 Plan Stakeholder


Management

13.3 Manage Stakeholder


Engagement

13.4 Control Stakeholder


Engagement

Page 28

4.6 Close Project


or Phase

4.6 Close Project or Phase


Mgt.
6.1 Plan Schedule
6.7 Control Schedule
12.4
Close Procurements

6. Project Time
Management

13. Project Stakeholder


Management

Closing

13.1 Identify Stakeholders

10.2 Manage Communications

10.3 Control Communications

11.6 Control Risks

12.4 Close Procurements

PMP Prep: PMBOK 5th - 2013

Closing: Integration Management

PMBOK Fifth Edition, Page 100

4.6 Close Project or Phase


Inputs

Project management plan


Accepted deliverables
Organizational process assets

Page 355

Tools &
Techniques

Expert judgment
Analytical techniques
Meetings

Outputs

Final product, service or result


transition
Organizational process assets
updates

PMP Prep: PMBOK 5th - 2013

4.6 Close Project or Phase


Close Project or Phase is
the process of finalizing
all activities across all of
the Project Management
Process Groups to
formally complete the
project or phase

Page 355

PMP Prep: PMBOK 5th - 2013

4.6 Close Project or Phase


The PM reviews all information from previous phase
closures to ensure that all work has been done and
objectives have been met. The scope baseline (scope,
WBS and WBS dictionary) is reviewed to ensure
completion.
If a project is terminated before completion, procedures
are established to investigate and document why the
action was taken.
Stakeholders are engaged in the process.

Page 355

PMP Prep: PMBOK 5th - 2013

4.6.1 Close Project or Phase


Inputs: The Project Management Plan (Another Reminder)

The other 23 planning processes are integrated to create the project


management plan. Updates to any plans require an update to the PM plan. Think
of the PM plan as a bucket into which all the other plans drip until it is full.

Page 356

Plan Scope Management


Collect Requirements
Define Scope
Create WBS
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Durations
Develop Schedule
Plan Cost Management
Estimate Costs

Determine Budget
Plan Quality Management
Plan Human Resource Management
Plan Communications Management
Plan Risk Management
Identify Risks
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
Plan Risk Response
Plan Procurement Management
Plan Stakeholder Management
PMP Prep: PMBOK 5th - 2013

4.61 Close Project or Phase


Inputs: Accepted Deliverables

These have all been answers on the test:


Customer feedback on a more detailed basis
Done at the end of each Project Phase (not PM phase)

Results in formal acceptance


Exam
Tip

The questions on the exam are vague on Scope Validation.


Read them carefully.
One question asks for: the key aspect of scope validation
Answer: customer acceptance of project efforts.
The answer does not involve correctness of the work.

Page 357

PMP Prep: PMBOK 5th - 2013

4.63 Close Project or Phase


Outputs: Final Product, Service, or Result Transition

Final Product, Service, or Result Transition


The output of Close Project or Phase is the transition of
what the project was authorized to produce. If it is a
phase closure, it is the intermediate product, service or
result of that phase. Formal acceptance includes
receiving a formal statement that the requirements of
the project or phase have been met.

Pages 358

PMP Prep: PMBOK 5th - 2013

4.63 Close Project or Phase


Outputs: Organizational Process Assets Updates

Organizational Process Assets Updates


Closure will include storage of project documentation using the configuration
management system. OPA updated during closure include:
Project Files
Assemble a complete set of project records from all processes for archiving, and updating
historical databases. Examples include: the PM plan, scope, cost, schedule, calendars, risk
registers, change documents, risk responses, and risk impact.

Project or Phase Closure Documents


Documentation showing project completion (or termination) and transfer of deliverables.
During closure, the PM reviews closure documents from all prior phases, acceptance
documents from Validate Scope and the contract to ensure that all requirements are
completed.

Historical Information
Lessons learned are transferred to archives for future use. This can be information on issues
and risks as well as techniques that worked well and can be applied to future projects.
Pages 359

PMP Prep: PMBOK 5th - 2013

Closing: Project Procurement Management


PMBOK Fifth Edition, Page 386

12.4 Close Procurements


Inputs

Project management plan


Procurement documents

Page 360

Tools &
Techniques

Procurement audits
Procurement negotiations
Records management system

Outputs

Closed procurements
Organizational process assets
updates

PMP Prep: PMBOK 5th - 2013

12.4 Close Procurements


Close Procurements is the
process of completing each
procurement.
Contract closure involves
verification that all the work and
deliverables produced under
contract were acceptable.

In multi-phase contracts, the


term of the contract may only
apply to the end of each phase,
and this process would close
phase-end contracts.

Page 360

PMP Prep: PMBOK 5th - 2013

12.4 Close Procurements


Contract closure involves verification that all the work and
deliverables produced under contract were acceptable. It also
involves updating records to as-built and archiving this information
for future use. In multi-phase contracts, this process closes phaseend contracts.
Early termination of a contract (or a portion) can result from mutual
agreement of the parties or from default of one of the parties, or for
convenience of the buyer. Rights and responsibilities of the parties
are controlled by the terminations clause.
Buyer may have the right to terminate all or part of a contract for
cause or convenience at any time, but buyer may have to
compensate seller for preparations, partial completions, and
completed/accepted work

Page 360

PMP Prep: PMBOK 5th - 2013

12.4.2 Close Procurements


Tools and Techniques: Procurement Negotiations

Negotiation is the primary goal for settling


disputes
If this cannot be achieved, use Alternative
Dispute Resolution (ADR) Mediation or
Arbitration

Litigation is the LEAST desirable option.

Page 327

PMP Prep: PMBOK 5th - 2013

4.6 and 12.4


Close Project/Phases and Close Procurements

Be prepared for as many as sixteen questions on these topics:


Inputs and Outputs
How Close Project is similar/different from Close Contract
(Close Procurements has similar work to Close Project, but
with more attention on documentation, completion of files
and verification/acceptance.)

PMP Prep: PMBOK 5th - 2013

10.2 Plan Communications


One More Time: It was on my examination twice

Plan Communications is the process of


determining the project stakeholder information
needs and defining a communication approach

The formula:
Channels =

N(N 1)
2

Reveals the number of possible channels


of communication in a group, where N is
the number of people in the group

Page 166-167

PMP Prep: PMBOK 5th - 2013

Professional Responsibility

Page 365

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Professional Responsibility
was introduced into the
PMBOK in version in its third
edition. It requires project
managers to consider legal and
ethical issues, and at all times
to focus on professionalism and
advancement of the profession
of project management

Page 365

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Think about Legal, ethical and professional behavior when
answering exam questions
You will be challenged with multiple situational questions
Read PMI Member Ethical Standards: Member Code of Ethics and
Member Standards of Conduct, PMP Code of Professional Conduct
Follow the law, follow bylaws and cooperate on ethics investigations
The PMI prefers that ethics be handled through infractions without
resorting to formal procedures
Focus on professionalism, integrity, responsibility, selfimprovement, fairness, honesty and communication
Balance stakeholders interests

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Read Pages 365-366 Carefully

Clarifying Information

Pages 365-66

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Code of Professional Conduct 2006
CHAPTER 1. VISION AND APPLICABILITY
1.1
Vision and Purpose
As practitioners of project management, we are committed to doing what is right and honorable. We set high
standards for ourselves and we aspire to meet these standards in all aspects of our livesat work, at home, and
in service to our profession.
This Code of Ethics and Professional Conduct describes the expectations that we have of ourselves and our fellow
practitioners in the global project management community. It articulates the ideals to which we aspire as well as
the behaviors that are mandatory in our professional and volunteer roles.
The purpose of this Code is to instill confidence in the project management profession and to help an individual
become a better practitioner. We do this by establishing a profession-wide understanding of appropriate
behavior. We believe that the credibility and reputation of the project management profession is shaped by the
collective conduct of individual practitioners.
We believe that we can advance our profession, both individually and collectively, by embracing this Code of
Ethics and Professional Conduct. We also believe that this Code will assist us in making wise decisions, particularly
when faced with difficult situations where we may be asked to compromise our integrity or our values.
Our hope that this Code of Ethics and Professional Conduct will serve as a catalyst for others to study, deliberate,
and write about ethics and values. Further, we hope that this Code will ultimately be used to build upon and
evolve our profession.

1.2

Persons to Whom the Code Applies

The Code of Ethics and Professional Conduct applies to:


1.2.1 All PMI members
1.2.2 Individuals who are not members of PMI but meet one or more of the following criteria:
.1 Non-members who hold a PMI certification
.2 Non-members who apply to commence a PMI certification process
.
.3 Non-members who serve PMI in a volunteer capacity.
Page 367

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Code of Professional Conduct 2006
CHAPTER 2. RESPONSIBILITY
2.1 Description of Responsibility
Responsibility is our duty to take ownership for the decisions we make or fail to make, the actions we take or fail
to take, and the consequences that result.

2.2 Responsibility: Aspirational Standards


As practitioners in the global project management community:
2.2.1 We make decisions and take actions based on the best interests of society, public safety, and
the environment.
2.2.2 We accept only those assignments that are consistent with our background, experience, skills,
and qualifications.
2.2.3 We fulfill the commitments that we undertake we do what we say we will do.
2.2.4 When we make errors or omissions, we take ownership and make corrections promptly.
When we discover errors or omissions caused by others, we communicate them to the
appropriate body as soon they are discovered. We accept accountability for any issues resulting
from our errors or omissions and any resulting consequences.
2.2.5 We protect proprietary or confidential information that has been entrusted to us.
2.2.6 We uphold this Code and hold each other accountable to it.

Page 369

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Code of Professional Conduct 2006
2.3 Responsibility: Mandatory Standards
As practitioners in the global project management community, we require the following of
ourselves and our fellow practitioners:
Regulations and Legal Requirements
2.3.1 We inform ourselves and uphold the policies, rules, regulations and laws that
govern our work, professional, and volunteer activities.
2.3.2 We report unethical or illegal conduct to appropriate management and, if
necessary, to those affected by the conduct.
Ethics Complaints
2.3.3 We bring violations of this Code to the attention of the appropriate body for
resolution.
2.3.4 We only file ethics complaints when they are substantiated by facts.
2.3.5 We pursue disciplinary action against an individual who retaliates against a
person raising ethics concerns.

Page 370

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Code of Professional Conduct 2006
CHAPTER 3. RESPECT
3.1 Description of Respect
Respect is our duty to show a high regard for ourselves, others, and the resources entrusted to us.
Resources entrusted to us may include people, money, reputation, the safety of others, and natural
or environmental resources.
An environment of respect engenders trust, confidence, and performance excellence by fostering
mutual cooperation.
3.2 Respect: Aspirational Standards
As practitioners in the global project management community:
3.2.1 We inform ourselves about the norms and customs of others and avoid engaging in
behaviors they might consider disrespectful.
3.2.2 We listen to others points of view, seeking to understand them.
3.2.3 We approach directly those persons with whom we have a conflict or disagreement.
3.2.4 We conduct ourselves in a professional manner, even when it is not reciprocated.
3.3 Respect: Mandatory Standards
As practitioners in the global project management community, we require the following of
ourselves and our fellow practitioners:
3.3.1 We negotiate in good faith.
3.3.2 We do not exercise the power of our expertise or position to influence the decisions or
actions of others in order to benefit personally at their expense.
3.3.3 We do not act in an abusive manner toward others.
3.3.4 We respect the property rights of others.
Page 371

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Code of Professional Conduct 2006
CHAPTER 4. FAIRNESS

4.1 Description of Fairness


Fairness is our duty to make decisions and act impartially and objectively. Our conduct must be free from
competing self interest, prejudice, and favoritism.

4.2 Fairness: Aspirational Standards


As practitioners in the global project management community:
4.2.1
We demonstrate transparency in our decision-making process.
4.2.2
We constantly reexamine our impartiality and objectivity, taking corrective action as appropriate.
4.2.3
We provide equal access to information to those who are authorized to have that information.
4.2.4
We make opportunities equally available to qualified candidates.

4.3 Fairness: Mandatory Standards


As practitioners in the global project management community, we require the following of ourselves and our
fellow practitioners:

Conflict of Interest Situations


4.3.1 We proactively and fully disclose any real or potential conflicts of interest to the appropriate
4.3.2

Page 372

stakeholders.
When we realize that we have a real or potential conflict of interest, we refrain from engaging in
the decision-making process or otherwise attempting to influence outcomes, unless or until:
we have made full disclosure to the affected stakeholders; we have an approved mitigation
plan; and we have obtained the consent of the stakeholders to proceed.
PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Code of Professional Conduct 2006
Favoritism and Discrimination
4.3.3 We do not hire or fire, reward or punish, or award or deny contracts based on personal
considerations, including but not limited to, favoritism, nepotism, or bribery.
4.3.4 We do not discriminate against others based on, but not limited to, gender, race, age, religion,
disability, nationality, or sexual orientation.
4.3.5 We apply the rules of the organization (employer, Project Management Institute, or other
group) without favoritism or prejudice.

Page 373

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Code of Professional Conduct 2006
CHAPTER 5. HONESTY
5.1 Description of Honesty
Honesty is our duty to understand the truth and act in a truthful manner both in our communications and in
our conduct.

5.2 Honesty: Aspirational Standards


As practitioners in the global project management community:
5.2.1 We earnestly seek to understand the truth.
5.2.2 We are truthful in our communications and in our conduct.
5.2.3 We provide accurate information in a timely manner.
5.3 Honesty: Mandatory Standards
As practitioners in the global project management community, we require the following of ourselves and our
fellow practitioners:
5.3.1 We do not engage in or condone behavior that is designed to deceive others, including but
not limited to, making misleading or false statements, stating half-truths, providing information
out of context or withholding information that, if known, would render our statements as
misleading or incomplete.
5.3.2 We do not engage in dishonest behavior with the intention of personal gain or at the expense
of another.

Page 373-274

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
Read Pages 375-377 Carefully

History of the Standard

Glossary

Pages 375-377

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
P.M.P Code of Professional Conduct
I. Responsibilities to the Profession
A. Compliance with all organizational rules and policies.
1. Responsibility to provide accurate and truthful representations concerning all information directly or
indirectly related to all aspects of the PMI Certification Program, including and not limited to the following:
examination applications, test item banks, examinations, answer sheets, candidate information, and
professional development program reporting forms.
2. Upon a reasonable and clear factual basis, responsibility to report possible violations of the professional code
of conduct by individuals in the field of project management.
3. Responsibility to cooperate with PMI concerning ethics violations and the collection of related information.
4. Responsibility to disclose to clients, customers, owners, or contractors, significant circumstances that could be
construed as a conflict of interest, or an appearance of impropriety.

B. Candidate/Certificant Professional Practice.


1. Responsibility to provide accurate, truthful advertising and representations concerning qualifications,
experience, and performance of services.
2. Responsibility to comply with laws, regulations, and ethical standards governing professional practice in the
state/province and/or country when providing project management services.

C. Advancement of the Profession.


1. Responsibility to recognize and respect intellectual property developed or owned by others, and to otherwise
act in an accurate, truthful, and complete manner, including, all activities related to professional work and
research.
2. Responsibility to support and disseminate the professional code of conduct to other PMI certificants.
Page 378

PMP Prep: PMBOK 5th - 2013

Professional Responsibility
P.M.P Code of Professional Conduct
I. Candidate/Certificant Responsibilities to Customers and the Public
A. Qualifications, experience, and performance of professional services.
1. Responsibility to provide accurate and truthful representations to the public in advertising,
public statements, and in the preparation of estimates concerning costs, services, and
expected results.
2. Responsibility to maintain and satisfy the scope and objectives of professional services,
unless otherwise directed by the customer.
3. Responsibility to maintain and respect the confidentiality of sensitive information obtained
in the course of professional activities or otherwise where a clear obligation exists.
B. Conflict of interest situations and other prohibited professional conduct.
1. Responsibility to ensure that a conflict of interest does not compromise legitimate interests
of a client or customer, or influence/interfere with professional judgments.
2. Responsibility to refrain from offering or accepting inappropriate payments, gifts, or other
forms of compensation for personal gain, unless in conformity with applicable laws or
customs of the country where project management services are being provided.

Page 378

PMP Prep: PMBOK 5th - 2013

Professional responsibility
Types of Questions to Expect
You are building a water treatment facility. Routine tests indicate
that there are contaminants in the water but that they have an
extremely low risk of causing sickness. As a project manager you
should:
A. Inform the public that a detailed examination has been ordered
to determine the extent to which the problem exists
B. Do nothing because there is an extremely low risk except for
some effects on small children or the elderly
C. Tell the public there is no problem, except for small children and
the elderly who should boil their water before drinking it
D. Educate the public about the advances in water treatment
technology and the industry efficiency and safety record
A. Inform the public

PMP Prep: PMBOK 5th - 2013

Professional responsibility
Types of Questions to Expect
A KEY activity to defining

customer satisfaction is to define:

A. Business Use
B. Requirements
C. Product Specificity
D. Change Control
B. Requirements

PMP Prep: PMBOK 5th - 2013

Professional responsibility
Types of Questions to Expect
When it appears that a design error will interfere with technical
performance objectives, the PREFERRED response is to:
A. Decrease the performance value to equal the assessed value
B. Develop alternative solutions to the problem
C. Increase the specified value to set a new performance goal
D. Reduce the overall technical complexity of the project

B. Develop alternative solutions to the problem

PMP Prep: PMBOK 5th - 2013

Professional responsibility
Types of Questions to Expect
What is the MOST effective practice to ensure that cultural and
ethical differences do not impede the success of your multi-national
project?
A. Co-Locating
B. Training
C. Forming
D. Teaming
B. Training

PMP Prep: PMBOK 5th - 2013

Professional responsibility
Types of Questions to Expect
Negotiating across international cultures involves mutual
interdependence between parties. The negotiations MUST be
conducted in an atmosphere of:
A. Mutual trust and cooperation
B. Generalities and vagueness
C. Sincerity and compassion
D. Uncertainty and caution
A. Mutual trust and cooperation

PMP Prep: PMBOK 5th - 2013

PMP Certification Test Preparation

PMP Prep: PMBOK 5th - 2013

New Test and New PMBOK Edition

The PMBOK 5th Edition was released in January


2013. The test changed again on July 31, 2013.
A new Knowledge Area was introduced:
Stakeholder Management.

Page 2

PMP Prep: PMBOK 5th - 2013

The T&T CD ID is E1091


and Awards 11 PDUs

Qualification Requirements

PMTestOnline is C4070
and Awards 11 PDUs

Graduate, 4-Year Degree


A minimum of 4500 hours PM
experience within the past 8
years

+
Non-Graduate, or 2-Year Degree

35 contact hours
(PDUs) of PM
education

Eligibility to take
the PMP
examination

A minimum of 7500 hours PM


experience within the past 8
years

This Course ID is E1078


and Awards 24 PDUs
Page 2

PMP Prep: PMBOK 5th - 2013

PMBOK Fifth Edition and the New Test


The PMBOK Fifth Edition was introduced in January 2013, and the
new fifth edition test started on July 31, 2013.
The PMP examination consists of 200 questions, with a four hour
time limit

Thats 72 seconds (or 1.2 minutes) per question

This training course will give you everything you need,


with a little self-study, to pass the PMP examination

Visit www.pmi.org, download PMP Certification Handbook

Page 2

PMP Prep: PMBOK 5th - 2013

PMBOK 5th Edition PMP Test Domain Content

Project Initiation
Project Planning
Project Execution
Project Monitoring & Control
Project Closing

13%
24%
30%
25%
8%

To pass, you need to get a minimum of 122


questions correct out of 200 questions (61%)
Pass rate on the 4th Edition test is about 74%

Page 2

PMP Prep: PMBOK 5th - 2013

Apply to PMI to take the test,


Schedule a date with Prometric
Submit your application to Project Management Institute (PMI)
http://www.pmi.org/Certification/Project-Management-Professional-PMP.aspx
Log in with your User Name and Password
Follow the instructions

Schedule a test date with Prometric


http://www.prometric.com/PMI/default.htm

Control is through audit (when you pay)


http://www.pmi.org/info/PDC_PMPHandbook.pdf
PMI may audit when you pay your exam fee to PMI. If you cancel or reschedule
within 30 days of the test, there is a fee of $70; within 2 days, you forfeit the entire fee.
Candidates have three (3) opportunities to pass the exam in one year. If they
do not pass any, they must wait one (1) year from the date of the last attempt.

Page 3

PMP Prep: PMBOK 5th - 2013

Taking the PMP examination


Ensure you
have the
required
experience

Ensure you
have 35
PDUs

AND

Join the
PMI (if you
havent)

Send in
your
application

Schedule
exam at
Prometrics

Study
hard for
about 2
weeks

Take the
exam
and pass

www.pmi.org

Complete a
PMP Prep
course

PMP Prep: PMBOK 5th - 2013

Applying to Take The Exam

Apply using the PMI web site.


http://www.pmi.org/Certification/Project-Management-ProfessionalPMP.aspx

Using the PMI web site to complete the application is fast and easy. Turn
around to approval is normally just a few days, but it may take a little
longer.

Sometimes your test center may not have an opening for a few weeks.

On the computerized test, the questions are in English, but pop-up screens
will aid you in understanding the question in your native language. This
feature must be requested by you in your application.

In some countries, the test may be given on paper, in English, not in your
native language.

PMP Prep: PMBOK 5th - 2013

Taking the PMP examination

Number of Questions:

200

Time for the Exam:

4 Hours

To Pass: you must get about 122 of 200 questions correct About 61%

Questions are randomly generated, 4-option, multiple choice.

Questions not answered are wrong - answer all questions.

Dont be surprised if some long questions are early in the exam


and you get behind on time.

Breaks are allowed, but extra time is NOT allotted for them.

In most test centers you must sign out and sign back in, which takes time

Page 345

PMP Prep: PMBOK 5th - 2013

Reasons people fail the exam


They do not read all the questions
correctly
They do not read all the choices in
each question
They are too nervous
They have not studied enough or use
source books other than the PMBOK
They believe they can rely purely on
experience
They have not taken a PMP prep
course like this one

Page 346

PMP Prep: PMBOK 5th - 2013

Taking the PMP examination


Go to the test center before the day of your test, find where it is, look at the
testing room, talk to the administrator.

Bring your PMI authorization e-mail or letter to the test site.


Bring a picture identification.
PMI has recently decided not to allow any personal calculators in the testing
room. A pop-up calculator is available on the computer. If that is awkward for
you to use, ask the administrator to provide a calculator for you.
You will be given scrap paper, pencils, and in some test centers, earplugs.

All personal items will be safely stored for you and cannot be taken into the test
room.

Page 346

PMP Prep: PMBOK 5th - 2013

Taking the PMP examination


Upon entering the test room, you will be given 15 minutes to use the computer
tutorial and to become familiar with the commands. You can mark questions on
the computer and return to the marked questions later, or you can review
every question.
Use the entire 15 minutes to write information you need to remember on the
scratch paper.
You will see one question on the screen at a time.
Many people finish the exam ahead of the 4-hour limit and return to marked
questions for review/correction.
When you finish the exam or when the time limit is expired, your answers are
immediately graded. The computer tells you if you pass. A temporary
certificate is printed at the test center, and you immediately become a PMP.
PMI will post a formal certificate to you later.
If you do not pass, PMI will be notified and will send you information about
retaking the exam. See PMIs website about the additional fee.
Page 346

PMP Prep: PMBOK 5th - 2013

Hints on Test Questions

Choices like A or B and never and always have been removed.

Watch out for distractors - choices that are true, but not the best answer.

There are about 45 to 75 what should you do in this situation questions.

Most people feel unsure about 50 of the 200 questions.

You must be familiar with PMI-specific definitions. A big trick to success on the exam is to try to
use PMIs perspective, not your experience. If that does not work, then use your training and life
experiences.

Read the last sentence of each question first. What is the question asking?

Read ALL FOUR answers, without making a choice.

Read the whole question. Understand the topic and descriptors. Read the last sentence AGAIN,
then eliminate two of the four answers.

Read the last sentence AGAIN, then pick the best of the two remaining answers.

About 8 to 12 questions deal with PMBOK step-by-step processes and the input/output to
processes.

There have been less than 8 earned value questions on the exam in the last three years.

Use all the exam time; do not leave early unless you have reviewed each question twice.

Page 347

PMP Prep: PMBOK 5th - 2013

Practice Test #3
CONGRATULATIONS !!!
You have just completed more
than the entire PMP Test!
You have done 228 questions
Turn to page 449 in the workbook
There are 100 questions.
You have 120 minutes to complete
Answers are on page 475
Hint: Use scratch paper for answers,
so you can reuse the questions for practice
Page 403

PMP Prep: PMBOK 5th - 2013

Let us know when you pass, and


Send us surprises you remember !

PMP Prep: PMBOK 5th - 2013

Você também pode gostar