Escolar Documentos
Profissional Documentos
Cultura Documentos
855-857, 1991
Printed in Great Britain.
0960-1481/91 $3.00+.00
Pergamon Press plc
TECHNICAL NOTE
The potential of wind electricity generation in Bangladesh
M . SARKAR* a n d M . HUSSAIN
Department of Physics and Renewable Energy Research Centre, University of Dhaka,
Dhaka 1000, Bangladesh
INTRODUCTION
Bangladesh is one of the highly energy deficient countries in
the world. The per capita commercial energy consumption
in Bangladesh in 1981 was 35 KgOE [1] which is pretty low
even compared to that of neighbouring India (158 KgOE)
and Pakistan (I 79 KgOE). By 1985, electricity consumption
grew to 41 KgOE in Bangladesh but the disparity increased
further. Electricity which is only 10% of the commercial
energy and 2% of the total energy consumed is being produced here in different ways : hydro-electricity and electricity
generated using natural gas are the main sources in the eastern zone and in the western region oil burning generators
are used. In some islands such as Kutubdia Sandwip etc.
electricity is produced using small diesel generators (I0-100
kW). For one such station, it has been found [2] that the fuel
cost per kWh of electricity supplied is Tk.8.92 in 1982 which
is much higher than the national average fuel cost of Tk.0.83
in the same year. In this work an attempt has been made to
study the possibility of harnassing wind energy for electricity
production in Bangladesh.
An earlier study on wind speed and wind energy availability in Bangladesh [3] showed that in the western region
almost all meteorological stations have an average annual
wind speed of around 4 km/h except the station Jessore and
Faridpur where the average speed recorded in 8 km/h. In the
eastern side, the average speed is a little bit higher with the
exception of (i) the inland station Dhaka Airport where the
speed is much above average and (ii) the coastal station
Chittagong where the highest average speed (I3 km/h) has
been recorded. It is reported [4] that the average speed of
Sagar Islands in India which is near to Bangladesh is 19
km/h. During a brief survey with a hand anemometer, a
coastal area of Bangladesh (Char Jabbar) again showed high
wind speeds. So far as we know, there is no hourly wind
speed data of off-shore island coasts. But our guess is that
the wind speed in those areas should be at least equal to that
of Chittagong and might approach that for Sagar Islands.
An annual average wind speed of 13 km/h which has been
recorded in Chittagong might be useful in generating electricity economically under Bangladesh conditions. In this
paper, taking the data of Chittagong to be representative of
coastal areas we would like to show how much energy one
can get from three different types of wind generators having
cut-in wind speeds of 2, 3.5 and 4.5 m/s. The cost of the
energy produced by the machine which gives the maximum
energy output was then calculated and compared with that
of the diesel generators.
DATA COLLECTION AND RESULTS
For the station Chittagong, the Meteorological Department of Bangladesh collects hourly wind speed data with the
help of a vertical-axis cup anemometer. The data for the
period 1978-80 were collected manually from the log-book.
These were then averaged over three years to get the hourly,
monthly and annual speeds. Suposing that the wind machine
has a tower height of 60 ft the wind speed corresponding to
this height was computed from measurements made at a
lower height of 10 m using the formula
v, - \ h , /
The value of ct was taken from the literature [5]. Mani and
Mooley [4] made a systemic study of ct over different parts
of India. From that work, one can guess that for Chittagong,
the average value of ~ might be 0.3. In that case the overall
energy output will be 20% higher. We have chosen to make
a rather conservative estimate of the energy output with
lower ~t and possibly a lower wind speed.
The characteristics of three machines (22 kW, 16 kW,
1 kW) as found from the literature [6--8] are shown in Table 1.
Taking the average output energy for wind speeds in between
the cut-in and rated values to be linear, a straight line fit was
drawn. Corresponding to each hourly average speed for a
month the energy output for that particular hour was determined from that fit. All the hourly energy outputs were added
up to get the daily output which is again multiplied by the
total number of days of a month to get the monthly energy
856
Technical Note
Table 1. The characteristics of three machines found from the literature [6-8]
Name
Country
Holland
Australia
U.S.A.
Blade
material
Rated
power
(kW)
Rated
wind
speed
(m/s)
Fibre glass
Fibre glass
Wood
22
16
4
8.5
8.0
10.7
Blade
diameter No. of
(m)
blades
II.0
12.0
6.0
2
3
3
22 kW
16 kW
4 kW
January
February
March
April
May
June
July
August
September
October
November
December
19
23
25
60
60
93
108
99
23
4
0
3
8
11
18
40
42
55
62
56
21
6
3
5
5
7
7
18
15
29
36
29
5
0
0
0
Total
517
327
151
Cut in Furling
speed speed
(m/s)
(m/s)
3.5
2.0
4.5
24
-18.0
Output
Price
APPENDIX
The cost per kWh of energy produced by the 22 kW
machine has been calculated under the following assumptions [7] : (1) the life time of the machine (t) was assumed to
be 20 years, (2) the interest rate (r) and inflation rate (0
were taken to be 15% and 12% respectively, (3) operation,
maintenance and repair cost (Corer) was considered to be 25%
of the annual cost of the machine (machine price/life time),
(4) scrap value S was taken to be 10% of the machine price
and civil work and (5) investment (I) includes the machine
price plus its 20% for the civil work and other connections.
The present value o f costs (PVC) is [7]
1-1 +i-]
[-
[1+i']
['l+i]'
Technical Note
857
APRIL
FEBRUARY
JUNE
20-
/2
I
v
I/
:)
in
I-20
"~
.~.,. I
OCTOBER
AUGUST
DECEMBER
._I
<
Io
I--
0-20
I0-20 20-20
0-20
10-20
20-20
,/
0-20
10-20
20-20
TIME ( IN GMT)
Fig. 1. Hourly energy output (kW/m 2) for the wind machine Aeroman (22 kW) over the different months
of the year.
PVC = $50151.00.
From Table 2 the annual output of 22 kW machine is
517 [(D/2) 2] kWh = 49132 kWh where D is the diameter of
the blade. So the total output in 20 years = (49132x20)
kWh. Therefore, the cost per kWh = $50151/49132 20 =
$0.051 = Tk.68 (1 US$ = Tk.33.00). Even if only 40% of the
total output is available for consumption the cost per kWh
power supplied would be Tk.4.20.
REFERENCES
1. M. Hussain, Energy 12, 369 (1987).
2. B, Hezeltine, A report from Centre for Policy Research,