JOB HAZARD ANALYSIS

HOW TO USE THIS FORM :


1) Crew performing task reviews ALL generic JHA considerations.
2) Review previous JHA update(s) for useful information which will help this task.
3) Create new JHA update with generic form and ALL considerations for this task.
4) Carry out task as per plan. If any conditions change ---STOP & RE-ASSESS.
5) File JHA update for future reference.

Installation/Facility
Location
Associated Work Permit Type
Associated Work Permit Number
Electrical Isolation Certificate Number
Physical Isolation Certificate Number

WORK ACTIVITY

JHA Cross-Reference Number

Job
Step
1

Description of
Job Step
Preparation before task
duty

SYNCHRONIZATION TEST FOR 11kV SWITCHGEAR

Potential
Hazards
- Miss in communication
- Uncompetent person
- Tools and equipment
without inspection
- Working without PTW
- Working without full
PPE compliance

Potential
Impact
- Wrong information
- Head injury
- Electrocution
- Equipment damage

Control
Measures
- PTW shall be applied before
start work.
- Safety briefing during toolbox
meeting and before starts works.
- Proper planning & follow work
method before work.
- All workers must be attend
safety induction.
- Tool and equipment must be
valid inspection.
- Only competent person
authorised (i.e. chargeman B4,
B0, fire watcher, first aider, etc.)
- Strict access control to be
implemented, limit number of
people within MV room. Just
authorized people can entering
MV room. Just maximum 8
person only allowed to go within
MV room.
- All activity inside cable cellar
(cable room) area not permitted
during the work. Ensure to
clearance cable cellar area from
worker and lock entrance to the
cable cellar area.
- Chargeman to ensure energy
isolation for other switchgear not
related to the activity already
maintain safely as per LOTO
procedure.

Recovery
Measures
- Fire watcher to
standby when work
on going.
- First aider to
standby during work.
- ERT team to be alert
for this work.

Utility
EDG & SS100

Result
Acceptable

JOB HAZARD ANALYSIS


- Rubber mat already installed.
2

Secondary Test
(Using multi meter)

- Electrocution
(i.e: wrong in
connecting the probe)
- Fail to follow work
procedure

- Physical injury

- Follow JMS.
- Ensure barricade & signage
covered barrier of work.
- Ensure good communication
with work team and others (HT
radio)
- Authorised person only can
enter MV room.
- Full supervision by work leader
and Receiving Authority.
- Mandatory PPE to be used
within MV room.
- Chargeman shall used arc flash
protection and probe phase tools.

- Fire watcher to
standby when work
on going.
- First aider to
standby during work.
- ERT team to be alert
for this work.

Acceptable

Primary Test
- 11Kv Testing Work
- Breaker Take Out
- 11Kv Bus Bar check

- Pinch point
- Electrocution
(i.e: wrong in
connecting the probe)
- Explosion/Fire (Arc
flash)
- Ergonomic
- Heat stress

- Hand & fingers injury.


- Fatality.
- Back Bone injury.
- heat stroke.

- Follow JMS.
- Ensure barricade & signage
covered barrier of work.
- Ensure good communication
with work team and others (HT
radio)
- Authorised person only can
enter MV room.
- Full supervision by work leader
and Receiving Authority.
- Mandatory PPE to be used
within MV room.
- Chargeman shall used arc flash
protection and probe phase tools.
- Aware pinch point area.
- Ensure work area barricade &
sigange.
- Ensure good communication
with work team and others by
using HT radio. Clear
communication between team at
EDG with team at MV room.
- Ensure equipment and circuit
ready discharge.
- Only competent person
(chargeman B4) to handling work
and testing.
- Practice buddy system and
correct technic for manual
handling.
- Strict access control to be
implemented, limit number of

- Fire watcher to
standby when work
on going.
- First aider to
standby during work.
- ERT team to be alert
for this work.

Acceptable

JOB HAZARD ANALYSIS


people within MV room. Just
authorized people can entering
MV room. Just maximum 8
person only allowed to go within
MV room.
- Ensure take (10-15) minute rest
after completion of each testing
stage.

Housekeeping

- Obstruct access
- Ergonomic
- Sharp object

L - LIKELIHOOD

EGORY

- Trip and Falls


- Physical Injury

CATEGORY

Remote

LOW

UM

Possible

MEDIU
M

Probable

HIGH

SAFER WAY TO COMPLETE THE JOB?


E ALTERNATIVES WITH LESS RISK?

DEFINITIONS
No Injury

No Damage

No Pollution

First Aid
Injury
Lost Time
Injury

Minor
Damage
Major
Damage

Minor
Pollution
Major
Pollution

- Fire watcher to
standby when work
on going.
- First aider to
standby during work.
- ERT team to be alert
for this work.

Acceptable

RESULT

R - RATING

S - SEVERITY

DEFINITION

- Clear/remove all equipment


from access way.
- Ensure working area cleans,
clear and safe.
- Practice buddy system and
correct technic for manual
handling.
- Eliminate and secure parts of
sharp objects.
- Wear mandatory PPE.

6-9

UNACCEPTABLE

3-4

TOLERABLE

1-2

ACCEPTABLE

LIKELIHOOD

Você também pode gostar