CONTENTS
1
INTRODUCTION............................................................................................... 2
1.1
QUALITY POLICY........................................................................................ 2
1.2
QUALITY OBJECTIVES................................................................................2
1.3
POLICY REVIEW......................................................................................... 3
1.4
MANAGEMENT RESPONSIBILITY................................................................4
1.5
CONTRACTORS SUBMITTALS....................................................................8
2.2
EARTHWORK........................................................................................... 12
2.3
CONCRETE WORK................................................................................... 15
2.4
2.5
BRICKWORK............................................................................................ 16
PREFACE.................................................................................................. 18
3.2
DOCUMENT CONTROL.............................................................................18
3.3
PROCUREMENT CONTROL.......................................................................19
3.4
3.5
PROJECT PROCESSES.............................................................................. 21
3.6
3.7
TEST PROGRAMME.................................................................................. 24
3.8
QUALITY RECORDS.................................................................................30
3.9
TRAINING................................................................................................ 33
Page | 1
INTRODUCTION
The Punjab Irrigated Agriculture Investment Program (PIAIP) is being financed jointly by the
Asian Development Bank (ADB) and the Government of Punjab. The Investment
Component of PIAIP includes Rehabilitation and Upgrading (R&U) of Pakpattan Canal,
Khadir Branch and Pakpattan Islam Link. After a Process of International Contract Bidding
(ICB), the contract is awarded to M/s Sinohydro NEL Joint Venture on the basis of fulfilling
the international standards of expertise in construction.
1.1
QUALITY POLICY
It is the policy of SINOHYDRO-NEL Joint Venture, to supply work and services of high and
consistent quality to its Clients. These will be in accordance with the SINOHYDRO-NEL
Joint Venture organisational goals, Clients requirements and expectations. This policy will
be reviewed at regular intervals to ensure that it is still up to date and relevant.
All operations shall be carried as per Standard Operating Procedures or Technical
Specifications provided by the client. Deviation from the procedures and specifications must
be first notified to the Management. Management is responsible for final approval of all
changes to procedures prior to implementation.
It is part of the SINOHYDRO-NEL Joint Venture training programme that this policy is
understood, implemented and maintained at all levels in the organisation.
This statement represents our commitment, on behalf of SINOHYDRO-NEL Joint Venture
to the Quality Policy.
Responsibilities
Project Manager is responsible to implement this policy at site.
1.2
QUALITY OBJECTIVES
Following are the Quality objectives based on the SINOHYDRO-NEL Joint Venture Quality
Policy;
Ensure the highest level of quality by maintaining supervised controls and written
instructions governing Quality Control procedures & practices.
Establish clearly defined responsibilities for compliance.
Page | 2
The Quality policy and Objectives are to be circulated to all departments and section Incharges at site, who will be responsible for its understanding, promulgation and
implementation. The Quality Policy is to be displayed at all the prominent places to facilitate
maximum exposure to the SINOHYDRO-NEL Joint Venture employees.
1.3
POLICY REVIEW
Policy Review responsibility at site is through a review committee consisting of PM and Incharge of the sections. This review committee is to periodically coordinate and control the
activities of the Quality System being carried out at site, review and evaluate the
performance of the Quality System and attainment of Quality objectives. The maximum
period between Policy Review meetings is two months. However, the meeting may be called
at any time when it is considered necessary on the direction of PM.
The agenda of the Policy Review meeting is prepared by QA/QC Manager in consultation
with the PM and distributed to the review committee well in time. The agenda covers but is
not limited to the following points:
Meeting Proceedings
Meeting is to proceed in the following manner:
Page | 3
Site Manager
He reports to the Project Manager for execution of production/construction, safety
and quality plans in his area of execution.
Helps in the preparation of Project Quality Plan in consultation with concerned
departments.
Controls & Supervises construction activities in his area of responsibility in
accordance with contractual requirements.
Co-ordinates with the field support groups, QA/QC and Safety for execution.
QA/QC Manager
The Quality Control (QC) Manager will be responsible for overseeing overall implementation
of Quality Control Plan and will coordinate all project testing, inspections and reporting
matters directly with the Project Manager and Site Manager. The QC Manager and all
workers have the authority to intercede directly and stop work due to any unsafe work
practices or site conditions.
Duties
Construction Manager
Construction Manager reports to Site Manager and is responsible to ensure accomplishment
of field activities in accordance with approved Methodology & specified requirements.
Manage construction field activities with the help of Site Engineer & supervisors. Coordinates with QA/QC for inspections, testing and identification of root causes against nonconformities.
Planning Engineer
Planning Engineer reports to the Site Manager in his discipline and is responsible to
schedule & detail planning of Resources against the specified scope of work. Monitor and
Control progress maintaining & reporting. Preparation and approval of execution
methodology from Consultant. Overall Control of Documentation flow to concerned sections.
Co-ordination among concerned departments, sections, Consultant and Client for necessary
arrangements and resources allocations.
Manager Admin
Manager Admin reports to Site Manager and is responsible to establish and maintain
administration system at site. Maintain personnel records, increments and pay allowances.
Co-ordinates with labor and social security departments. Ensures arrangements of
communication, transport, accommodation, messing, furniture and proper protocol for
guests and visitors.
HSE Manager
Page | 5
HSE Manager functionally reports to Head Safety and administratively to Site Manager and
is responsible to implement the Project Environmental Management Plan, SSEMP, safety
policy and Site HSE Plan. He is responsible to organize the Safety training program, ensure
availability of P.P.E, fire-fighting equipment. Preparedness for accidents & crisis
management.
Resource Management
All resource requirements at site are assessed on the basis of resource plans based on
contract specifications. These resource plans are used for identifying, estimating, scheduling
and allocating relevant resources. These plans are subject to multiple revisions, depending
upon the actual usage requirements. For further details please refer to Project Process
Control.
1.5
PURPOSE
The purpose of the Quality System at site is to establish and maintain SINOHYDRO-NEL
Joint Venture Consultant and Client specified Quality management system at Site.
RESPONSIBILITY
The PM at site is responsible to establish and maintain the Quality System. SINOHYDRONEL Joint Venture Quality System is based on a hierarchy of the Quality Policy, QA / QC
Plan, Specifications, Procedures & Methods, Analysis of Project Quality Records and Policy
Review.
QA / QC Plan
Policy Review
Page | 6
This Quality Assurance Plan (QAP) is an effort to outline the activities of the
SINOHYDRO-NEL Joint Venture in adequate details for the guidance of its staff and
other relevant Personnel during the construction activities of the project to satisfy
the requirements of Contract. It requires that individuals have clearly defined
responsibilities and lines of communication to enable all aspects of the work activities to be
assessed and accepted and if a problem is discovered, the solution is quickly found. QAP
cannot replace the experience of reasonable and responsible staff; however it can help them
in selection of timely and sequential line of various activities and in keeping and maintaining
retrievable record documentation. This QAP is specially designed for Rehabilitation and
Upgrading of Pakpattan Canal, Khadir Branch & Pakpattan Islam Link Project (Contract No.
PCSBIP/ICB- 01).
The SINOHYDRO-NEL Joint Venture is, in particular, responsible for the Quality
Control of the Works as per Contract Specification. Consultants supervision and
surveillance does not relieve the Contractor of his contractual obligations. The basic
purpose of QAP is to ensure that the Quality Control System is in place and
performing to the requirements of Contract documents during the construction
period.
The quality requirements are based on provisions for technical specifications as per contract
documents for Rehabilitation and Upgrading of Pakpattan Canal, Khadir Branch &
Pakpattan Islam Link Project. Maximum efforts have been exerted in making QAP an
acceptable and tangible document for all levels of execution and supervisory staff and
novice to experience. Technical notes are provided at places to develop field staffs
approach and insight for a useful and effective supervision, without undermining adherence
to the contract specification.
The Contract Documents are the basis for this QAP, therefore, where an ambiguity is
detected between the procedures and requirements of QAP and content of Contract
Documents then the later takes the precedence.
The following are the objectives while formulating QAP.
To define and adopt a sequential and systematic quality assurance line of action with
participation of the other stake holders for ensuring of all submittals, procurement,
execution of works and other on and off site construction activities. These activities may
Page | 7
also include material supply, testing and reporting envisaged in the specification of the
project.
To define the assignment and responsibilities of the Contractors field staff and other
relevant personnel at site with respect to Quality Assurance of the project vis-a-vis the
Contractors Quality Control Programme and their interaction with the client and the
Consultant.
2.1
2.1.1
CONTRACTORS SUBMITTALS
Objective
The objective of this Section is to guide the field staff of the SINOHYDRO-NEL Joint
Venture regarding different submissions to be made in the form of check requests, test
requests, approval requests and authorization requests for execution of work. These
submissions will be made by for methodological construction execution works.
2.1.2
Applicability
The Contract Documents for Rehabilitation and Upgrading of Pakpattan Canal, Khadir
Branch & Pakpattan Islam Link Project require the Contractor to submit certain documents
to the Consultants, i.e. before, during and after the execution of the works. These
documents / write-ups may include;
Operation and Maintenance Manual for mechanical equipment (As per Contract
specifications)
Manufacturers Certificates for various Construction Materials like water stops, bearing
pads, expansion joint fillers and sealants.
The submittals for various items of Project Works are provided in the checklist CKL-1.1
Checklist for Contractors Submittals for the guidance of the Contractors field staff.
Page | 8
Document Format
Contractors work
Programme including
arrangements, order
and timings
Contractors Format
Details of the
Programme and
Resource Schedule
Contractors Format
1.3
Contractors Format
Prior to commencement
of works
1.4
Contractors Quality
Control Programme
Contractors Format
Prior to commencement
of works
1.1
1.2
Submittal
As per Specification
As per Specification
These submissions shall be made by the Contractor to The Engineer for prior detailed
review and agreement/advice.
* Letter of Acceptance.
Page | 9
Submittal
Document Format
2.1
Contractors Format
Prior to Construction of
diversion works
2.2
Materials Source
Approval*
Contractors Format
Prior to commencement
of component of work
2.3
Quality Control/
Assurance Tests to be
submitted direct to The
Engineer
Contractors Format
As per requirements of
specifications and QAP
2.4
Contractors Format
Prior to start of
Construction.
These submissions shall be made by the Contractor to The Engineer for detailed
review and agreement/advice.
Page | 10
Sr. No.
Submittal
Document Format
3.1
Method Statement
Contractors
Format
Prior to Construction
3.2
Manufacturers
Format
3.3
BB-01
3 days Prior to
Commencement of
fabrication of Re-Steel
3.4
As per requirements of
specifications.
3.5
Manufacturers Certificate
for Rubber water stops,
bearing pads joint filler
and sealants
Manufacturers
Format
Prior to procurement
3.6
Contractors
Format
Prior to start of
Construction
These submissions shall be made by the Contractor to The Engineer for detailed
review and agreement/advice.
Page | 11
2.2
EARTHWORK
2.2.1
Objective
Construction Equipment
Selection of type of excavation and compaction equipment must be done wisely keeping in
view the bulk of work and efficiency of the equipment and that the selected equipment is
capable and adequate to perform the required earthwork. The following may be deployed as
per the nature of work involved;
Excavators
Dozer
Dump Trucks
Motor Graders
Water Bowser
Dewatering Arrangements
Compactors(Rollers)
2.2.3 Inspection
Setting out details on site as per design will be the responsibility of the field staff. The
Consultants through their own field staff shall check the setting-out accuracy, survey
control for NSL and design levels by joint survey with Contractor. These surveys shall be
Page | 12
If the Contractor encounters wet or slush, he is required to report to the Consultants Site
Engineer who will jointly inspect the site, evaluate according to Earthwork Sub Clause of
Technical Specifications of Contract Documents and submit their recommendations for
approval by the Engineer.
The Control of moisture and compaction of soils in the embankment of canals and
compacted earth consists of inspection of the material used, checking the amount and
uniformity of the soil moisture, maintaining the thickness of layer, and finally determining
the percentage of relative Dry Density of the compacted fill.
The relative Dry Density of the compacted fill is determined on the basis of Field Density
Tests and the Reference Laboratory Compaction Tests. The Field Density Tests shall be
performed by the Contractors staff as and when directed by the Engineer In-charge or
Site Inspectors.
Tests at critical areas shall be carrying out by Consultants staff and verified in
Consultants Field Laboratory.
The Maximum and Minimum Dry Density Test results (from external laboratory) are used
as Reference Laboratory Tests for cohesion less sandy soils.
The soils having less than 12% passing No. 200 sieve are defined as sandy or noncohesive soils.
The Site Inspector should see that all perishable matter and any soil which may become
unstable upon saturation, such as highly organic soils, loose silts, very fine sands/silts
and expansive clays etc. are not present in the foundations. These soils either need to
be removed or improved to the extent necessary to provide a safe, stable foundation or
sub-grade under operating conditions.
A good bond between the foundation and first layer of fill is achieved by moistening the
foundation rather than using a very wet embankment layer.
Page | 13
For Quality Assurance (QA) of earthwork operations the Staff shall proceed in
accordance with CKL-1.2(1) Checklist for Structural Excavations and CKL-1.2(2)
Checklist for Canal Earthworks.
doubtful.
Areas of doubtful density are sometimes detected by observation. Possible locations of
insufficient compaction include:
The junction between areas of mechanical tamping and rolled earth fill
embankment along abutments or cut-off walls.
Areas where less than specified number of roller passes were made.
Areas where oversized rock which has been overlooked, is contained in the fill.
2.2.4
Description
Backfill around
Structures above
foundation level
Special Backfill
and Fill beneath
Structures
(Foundations)
Foundation under
Canal
Embankment /
Sub-grade for
Lining
Canal
Cohesive Soils
Cohesionless
Soils
70% Relative
Density
80% Relative
Density
70% Relative
Density
70% Relative
Page | 14
Embankments
(Main or Branch)
Disty/Minor
embankments
Density
Density
70% Relative
Density
Page | 15
2.2.5
The recommended tests, their procedures, frequency and the required facilities
for an effective quality control/assurance of earthwork are presented in Section
3.7 Test Programme. The contractors field staff is required to ensure that these
tests are performed as per specified frequencies in the recommended
laboratories or at site. The field tests should be performed in the presence of the
Engineers site Inspector and the results recorded immediately on completion of
the test, duly signed by the authorized representative of the Contractor and
Consultants. An independent record of the tests should also be maintained
by consultants field staff, in addition to the submittals of the Contractor.
S
1.
2.
3.
4.
Issues
Record/Re
porting
Document
Engineers
Rep.
Action by
Survey &
Level
Book and
Ref. to
Section 3.7
Contractors
Surveyor
5.
Lab
Technician
Ref.
Section 3.7
6.
Deployment
Equipment.
Lab
Technician
Ref.
Section 3.7
of
proper
7.
8.
Lab
Technician
Ref.
Section 3.7
Complete
information
about
condition of soil i.e. dry, wet or
slush.
Check
by
physical
inspection
and
record
observations.
Lab
Technician
Ref.
Section 3.7
Lab
Technician
Ref.
Section 3.7
9.
10.
Final
levels
of
excavated
surfaces and record entries.
Check by Survey Control and
make record entries.
Engineers
Rep.
Contractors
Surveyor
Survey &
Level
Book and
Ref.
Section 3.7
All actions should be taken in accordance with the Contract Specifications and
Contractors Work Methodology as approved by the Engineer.
1.
2.
3.
Issues
Action by
Record/Re
porting
Document
4.
5.
Final
levels
of
excavated
Engineers
Rep.
Contractors
Surveyor
Survey &
Level
Book and
Ref. to
Section 3.7
Deployment
equipment.
Lab
Technician
Ref.
Section 3.7
7.
Clearing,
Grubbing
and
Stripping. Ensure by physical
inspection.
Lab
Technician
Ref.
Section 3.7
8.
Lab
Technician
Field Lab.
Ref.
Section 3.7
9.
Lab
Technician
Ref.
Section 3.7
10.
Lab
Technician
Ref.
Section 3.7
of
proper
All actions should be taken in accordance with the Contract Specifications and
Contractors Work Methodology as approved by the Engineer.
2.3
CONCRETE WORK
2.3.1
Objective
Objective of this section is to provide the recommended guidelines, sequential
inspection procedures and other relevant information to the field staff of the
Contractor for their guidance in quality assurance of reinforced concrete and prestressed concrete pertaining to the permanent works being executed at site.
2.3.2
Applicability
This section covers Plain Cement Concrete (P.C.C.), Reinforced Cement
Concrete (R.C.C.) and pre-stressed concrete works for permanent structures as
well as pre-cast works as shown on the drawings and as directed by The
Engineer.
2.3.3
Construction Equipment
The Contractor must ensure that the equipment is adequate to perform the
concrete work.
2.3.4
Inspection
Classes of Concrete
Concrete for several structures and part thereof shall have 28-day compressive
strength of 6 12 cylinders at least equal to the minimum allowable strength
shown in the following Table:
Cl
Cylinder Strength
N/mm2
4000 Psi
27.58
3000 Psi
20.67
1500 Psi
10.34
C
* Actual Mix Ratio will be determined after Concrete Mix Design carried out in
accordance with relevant Sub-Clauses of Technical Specifications of Contract
Documents.
2.3.6
Lean Concrete
General Use
Nominal Maximum
Aggregate Size
"
"
2.3.7
The concrete mix design for each class of concrete in addition to mix proportion
will also provide water-cement ratio by weight (exclusive of water absorbed by
the aggregate) which will be determined on the basis of producing concrete
having suitable workability, density, impermeability, durability and the required
strength.
2.3.8
Issue
Actio
Record/Re
n by
Physically
inspect
all
the
Reinforcement Steel procured by the
contractor and confirm adherence to
the
Specifications
by
Test
Procedures.
Physically inspect, cement procured
by the contractor and confirm
adherence to the Specifications by
Test Procedures.
Lab
Tech
nicia
n
Lab
Tech
nicia
n
Lab
Tech
nicia
n
Lab
Tech
nicia
n
Lab
Tech
nicia
n
Lab
Tech
nicia
n
Lab
Tech
nicia
n
Lab
Tech
nicia
n.
Lab
Tech
nicia
n.
porting
Document
Manufactu
rers
Certificate
and/or
External
Lab.
Format.
Manufactu
rers
Certificate
and/or
External
Lab.
Format.
Ref.
Section
3.7
Ref.
Section
3.7
Ref.
Section
3.7
Ref.
Section
3.7
Ref.
Section
3.7
Ref.
Section
3.7
Ref.
Section
3.7
2.4
2.4.1
Applicability
This Section covers the placing of stone pitching and stone apron at the
Construction Equipment
2.4.4
Excavators
Dump Trucks
Water Bowser
Dewatering arrangements
Inspection
Base Filter Layer under Stone Pitching shall consist of well graded material
as specified in BOQ and shown on the Drawings.
The Stones individually shall weigh between 40-120 lbs with 80% shall be 80
lbs or larger and not more than 5% shall weigh less than 40 lbs.
All interstices in Stone Pitching/Apron shall be well filled with rock Spalls. The
rock Spall shall be rock fragments size between 2 inches and 4 inches.
The surface over which the base filter is to be placed shall be trimmed to the
proper lines and grades and shall be moistened with water and tamped or
rolled with suitable tools or equipment for the purpose of forming a firm
foundation. Wherever over-excavation occurs it shall be backfilled with
specially compacted fill.
The base filter layer shall be placed to a uniform thickness and finished to
reasonably smooth and even surface.
Stone used in the Stone Pitching/Apron shall be clean rough quarry stone and
shall be essentially free from dust, clay, vegetative matter and other
deleterious materials. The stone shall be hard, tough, durable, dense,
resistant to the action of water and air, and suitable in all respects for the
purpose intended. The stones shall be hand packed and placed and bedded
in such a manner that the completed stone pitching is stable and without
tendency to slide.
Stone shall be placed so as not to project above neat lines shown on the
drawings.
2.4.5
Quality of Stone
While performing control over procurement and placement of stone and filter material,
the following characteristics of stone and filter material from the specifications must be
observed.
The loss in Los Angles Abrasion Test for large size Aggregates
(ASTM-C535-96) should not exceed 10% by weight at 200 revolutions or 40%
by weight at 1000 revolutions.
The loss in Los Angles Test for small size Aggregates (ASTM-C131-96)
should not exceed 10% by weight at 100 revolutions or 40% by weight at 500
revolutions.
The Specific Gravity of stone (Saturated Surface Dry basis) shall be more
than 2.60.
2.4.6
Sr.
Issue
Action by
No.
Document
1.
2.
3.
Record/Reporting
Contractors
4.
5.
Cont. site
engineer
Test Results on
External Lab.
Format or Field
Lab.
6.
Cont. site
engineer
7.
Ensure
Cont. site
by
Physical
Inspection
- Contractors
Surveyor
8.
engineer
Cont. site
engineer
All actions should be taken in accordance with Part Two, Contract Specifications and
Contractors work methodology as approved by the Engineer.
2.5
2.5.1
BRICKWORK
Objective
Applicability
This Section covers the construction of Brickworks for brick masonry and brick lining for
various Structures, being executed by the Contractor.
2.5.3
Construction Equipment
The Resident Engineer must leave the selection of construction equipment to the
Contractor.
2.5.4
The Consultants field staff will take appropriate action as recommended in the checklist
CKL-1.5 Checklist for Brickwork.
2.5.5
Quality of Bricks
All bricks in oven-dried condition should not absorb more than one sixth of
its weight when soaked for one hour in water at 70 0 F to 800 F and should
show no efflorescence on subsequent drying.
2.5.6
Each brick for lining should have standard size (9 x 4.5 x 3) first class.
Mortar Composition
Mortar for all brickwork should have mix ratio as specified in BOQ and sufficient water to
produce the proper consistency.
2.5.7
Mortar Sand
Water
The water used for preparation of mortar should be free from objectionable quantities of
silt, organic matter alkali, salts and other impurities.
Issues
1.
2.
Check
by Survey Control
and
Dimensional
Inspection,
complete
setting out/layout as per drawings.
3.
Action by
Record/Reporting
Document
Ref. Section 3.7
- A.R.E. Rep.
FR-02 for
comments
- Contractors
Surveyor
4.
External Lab or
Field Lab Format
5.
A.R.E./Site
Inspector/ Cont.
site engineer
6.
A.R.E./Site
Inspector/ Cont.
site engineer
7.
A.R.E./Field Lab.
3.1
PREFACE
SINOHYDRO-NEL Joint Venture is, in particular, responsible for the Quality Control of
the Works as per Contract Specifications. Consultants supervision and surveillance does
not relieve the Contractor of his contractual obligations. The basic purpose of this plan is
to ensure that the Quality Control System is in place and performing to the requirements
of Contract documents, during the construction period.
The quality requirements are based on technical specifications as per contract
documents for Rehabilitation and Upgrading of Pakpattan Canal, Khadir Branch and
Pakpattan Islam Link. Maximum efforts have been exerted in making QCP (Quality
Control Plan) an acceptable and tangible document for all levels of execution and
supervisory staff and novice to experience.
The Contract Documents are the basis for this Plan, therefore, where an ambiguity is
detected between the procedures and requirements of QCP and content of Contract
Documents then the latter takes the precedence.
3.2
DOCUMENT CONTROL
3.2.1 Purpose
The purpose of site document and data control is to ensure that all the quality system
documents are properly numbered reviewed and approved prior to issue and
communication. They are available at the appropriate locations and changes to them are
properly documented, authorized and indicated.
3.2.2 Responsibility
Document Controller at site is responsible for the control of all data and documents.
Document Controller is responsible for following;
3.2.3
All Incoming correspondence from Consultant & client shall be separately filed
and issue the copies to the concerned persons. A separate register / electronic file shall
be maintained. All incoming correspondence from sub-contractor / supplier shall be filed
separately in different folder for each & necessary action. All outgoing correspondence to
Consultant & Clients shall have complete reference.
3.2.4
Contractual Documents
All original contract documents shall be in the custody of Head office in Lahore. A
copy shall be available at site for reference.
3.2.5 Internal Distribution
As soon as information received from the Consultant or Client, Project Manager shall
mark the distribution as required for necessary action / information; if the information
needs to be passed to subcontractor it shall be forwarded with a copy along with a
covering letter to subcontractor / supplier for their action.
3.2.6 Traceability
All documents shall be filed in a systematic / functional way marking index, contents of
the file, project so as to trace the required document. A master index shall be maintained
by the Document controller.
3.2.7 Confidentiality of Documents
All documents shall be controlled by document controller only and shall be kept in a
separate room with lock and key facility so that no unauthorized personnel can access to
document room.
3.3
PROCUREMENT CONTROL
3.3.1 Purpose
To ensure that procurement / purchasing activity at site conforms to SINOHYDRO-NEL
JOINT VENTURE procedures and agreed/specified requirements.
3.3.2 Scope
This procedure applies to Supplier evaluation & SINOHYDRO-NEL JOINT VENTURE
action, procurement of products, documents and verification of purchased products.
3.3.3 Responsibilities
The In-charge Procurement at Site is responsible for the following:
Civil
Mechanical
Electrical
Services of sub-contractors
3.3.5
In order to get the desired progress, Procurement In-charge is responsible for managing
procurement activities. The SINOHYDRO-NEL JOINT VENTURE will obtain source
approval; submittals will include the name and address of all manufacturers and suppliers,
test results showing complete compliance with the Specifications and specified Standards,
the date of manufacture and storage condition, shelf life if appropriate. In addition, the
Contractor shall provide representative samples of the materials of sufficient size such that
the Engineer may perform all specific tests. Once source approval has been granted by
the Engineer all deliveries of the material to the site must in turn be submitted for approval
accompanied by all relevant test reports to show full compliance of the material with the
Specifications. Where the required tests cannot be performed at the site laboratory, then
the Contractor shall arrange for independent testing at a laboratory approved by the
Engineer, to be performed to show that the material complies with the Specifications. Cost
of such testing shall not be reimbursed.
3.3.6
Services of Sub-Contractors
SINOHYDRO-NEL JOINT VENTURE will endeavor to perform all the major works by his
own team but few specialized jobs, like specialized Mechanical gates etc. are planned to
be awarded to the specialized sub-contractor after the prior approval from the Client /
Engineer. SINOHYDRO-NEL JOINT VENTURE will be fully responsible for any part of
the works performed by him or his subcontractor(s) and for the acts and omission of the
subcontractor.
3.4
3.4.1 Purpose
To establish and maintain a unique identification and record system to trace the history,
location, quality and application of the material. To identify the material during all stages
of construction through the drawings & specifications and processes.
3.4.2 Scope
This procedure is applied for this project, including project management and project Site.
3.4.3 Responsibilities
Store in-charge & Store Keeper at site are responsible to ensure that construction
material records are maintained and procedures followed to establish a unique
identification and traceability for each material.
3.4.4 Procedures
Site Stores is to ensure that all items are properly identified with their unique
identification names and codes. The Store in-charge is responsible to ensure that all
quality records and documentation used for the transaction of materials include their
proper identification.
The Construction Manager(s) at site are responsible to ensure that the following
identification and traceability procedures are followed:
The Material on the project Site is to be marked with a unique Identification method for
its proper recognition, identification of location, product and materials by reference to the
drawings and specifications. The Construction Managers along with his project team is
responsible to identify the need & methods of these unique identifications.
The work done during the tenure of the Project is to be appropriately documented to
ensure that all inter-related activities, material and products are traceable to each other
and their sources.
3.5
PROJECT PROCESSES
3.5.1 Purpose
To provide a system for effective Project planning, Execution and Control of various
project processes during construction phase of the project.
3.5.2 Scope
This procedure is applicable to the following processes at site.
a) Project Quality Management.
Project Planning.
Organization.
Methods.
Specifications.
Process Validation.
Execution
Methods & Specifications
The client as a basis has provided standard execution procedures and
specifications for preparation of work methodology. Methodology is to be
prepared by the Planning Section in each discipline in consultation with field staff.
The Methodology is to be prepared for each execution process, reviewed by
Project Manager. During the start of every project activity, Consultant validated
and approved Methods are to be made part of the Quality Control Plan (QCP).
Inspection and Testing
Inspection and Testing shall to be incorporated in the methods, which shall be
applied after validation by the consultant. The Site execution is responsible to
proceed according to the Method while QA/QC team is responsible to apply
during each process. Approved third-party inspection and testing facilities may be
utilized if required. The procedure and applicable records are explained in the
section dealing with Inspection and testing.
Process Validation
In order to ensure appropriate level of conformance to the process validation, the
site QA/QC team shall plan and execute internal audits of the site from time to
time.
3.5.7
3.6.1 Purpose
To ensure a system for calibration and maintenance of Inspection, Measuring and
Testing Equipment (IMTE) at Site.
3.6.2
Scope
This system applies to all activities where IMTEs are used for inspection and testing of
parameters that directly effect the quality.
3.6.3 Responsibilities
QA/QC Manager is responsible for ensuring that the Calibration of all Inspection,
Measuring and Testing Equipment (IMTE).
3.6.4 Procedure
Standard procedures will be followed to assure that test and measuring devices used to
test, or accept materials or components are calibrated at specified intervals to maintain
the proper accuracy. Devices used shall be of a proper range, type and sensitivity to
reliably measure the parameters being evaluated. The calibration of such devices shall
be documented and shall be performed using certified measurement standards and
submitted to the Engineer for approval. All IMTE are to be maintained at site in a
calibrated condition. In case an IMTE is found to be out of calibration, it is to be
segregated from the others and put out of service in the Site store in an area marked
OUT OF CALIBRATION.
3.7
TEST PROGRAMME
Soil
Max. and Min. index densities, ASTM D-4253 and ASTM D-4254
b)
c)
Specific gravity and absorption of aggregates, ASTM C-127 and ASTM C128
Stone
Compaction Tests
Soundness of Aggregate
TESTING ARRANGEMENTS/EQUIPMENTS
3.7.3
The Contractor for an individual contract package shall be responsible for providing the
equipment and carrying out these tests in accordance with the Technical Specifications
under the direct supervision and guidance of the Consultants supervision staff.
The contractor is required to provide and readily make available at construction site the
following equipment,
Earthwork:
Sand - Cone Density Apparatus, complete with base plate and sand bottle.
Speedy Moisture Tester capacity 20.0 gm. Moisture range 0 20% complete with
electronic balance and plastic carrying case.
Concrete Work:
Cylinder moulds for concrete 6 dia. Complete with tamping rod (5/8 in dia 20
long) and mallet.
Slump Test Equipment complete with tamping rod 5/8 dia and 24 long.
Curing Tanks These shall be constructed close to the construction site for
storing concrete cylinders till their transportation to the Laboratory for testing.
Note:
The Contractor shall ensure that sufficient No. of the above equipment is
available at site to satisfy the testing requirements of the quantum of work.
3.7.4
3.7.5
The Contractors shall be responsible for providing and transporting the test
specimens to the laboratory under the guidance and supervision of the
Consultants Resident Engineer.
The contractors shall bear the cost of these tests as per rate list available at
any Field or external Laboratory specified by the Engineer.
The Quality Control tests to be carried out from an external laboratory defined in are
recommended to be carried out at laboratories mentioned below or as directed by the
Engineer. The cost of transportation and testing charges shall be the Contractors
responsibility. Following or any laboratory specified by the Engineer shall be used for
external testing;
Material
Test
Designation
Testing Frequency
SOIL
Grain Size Analysis
ASTM D-422
Liquid Limit
ASTM D-4318
Plastic Limit
ASTM D-4318
Shrinkage Limit
ASTM D-427
Moisture
Relationship
Moisture
Relationship
Field
Density
Embankment
for
ASTM D-1556
ASTM D-1556
Moisture Content
Specific Gravity
ASTM D-854
CBR
AASHTO T193
As required
Sieve Analysis
ASTM C-136
ASTM C-117
Unit Weight
ASTM C-29
Moisture Content
ASTM C-566
Soundness
ASTM C-88
COARSE AGGREGATE
Specific
Gravity
Absorption
and
ASTM C-131
ASTM C-142
Petrographic Analysis
ASTM C-295
Lightweight Particles
ASTM C-123
BS 1377
ASTM C-136
ASTM C-117
ASTM C-29
ASTM C-128
Moisture Content
ASTM C-566
Soundness
ASTM C-88
Clay Lumps
Particles
&
Friable
FINE AGGREGATE
Sieve Analysis
Material
Sieve
Passing
#200
Unit Weight
Specific
Gravity
Absorption
Material
and
Test
Designation
Testing Frequency
ASTM C-142
Sand Equivalent
ASTM C-2419
Organic Impurities
ASTM C-40
Lightweight Particles
ASTM C-123
Petrographic Analysis
ASTM C-295
Water Soluble at
ASTM C-1812, or BS
812
Clay Lumps
Particles
&
Friable
BS 1377
CEMENT
Setting Time
ASTM C-191
Mortar Strength
ASTM C-109
ASTM C-114
As required
ASTM 615
As required
Elongation
ASTM 615
As required
Bending
ASTM 615
As required
Tensile Strength
ASTM 615
As required
ASTM 615
As required
Complete
Analysis
Chemical
REINFORCEMENT
Complete
Analysis
Chemical
Complete
Analysis
Chemical
WATER
CONCRET
E
Making
and
concrete specimen
curing
Once
month/Source
ASTM C-31
As required
Compressive Strength
ASTM C-39
Slump
ASTM C-143
Air Content
ASTM C-231
Temperature
Fresh Density
Air Entraining
ASTM C-260
As required by the
Engr.
ASTM C-494
As required by the
Engr.
Curing Compound
ASTM C-309
As required by the
Engr.
ADMIXTURES
OTHERS
Joint Filler
ASTM D 1752-84
As required by the
Engr.
Joint Sealant
ASTM C 920-98
As required by the
Engr.
Waterstop
US Federal Test
As required by the
Engr.
Method
No.601
3.7.7
Standard
QC Test Results
All QC tests results shall be submitted to the Engineer for his review and acceptance. The
test results must show full compliance with the Specifications, in order for the works to be
approved.
3.8
a)
Soil reports showing locations, material source, material type, density, moisture
content, density-moisture content relationship, degree of compaction (RC) and
relative density where applicable.
b)
c)
Aggregates reports for filters, base course, showing source of material, test
results showing compliance with the specification and placing location.
d)
Purpose
To provide a system for identification, collection, indexing, filing, storage, maintenance
and disposition of quality records at Site.
Scope
Documents consist of recording formats, which furnish objective evidence of the extent
of the fulfillment of the requirements for quality. Quality Records to be used at Site
consist of Consultant / Client specified or site specified formats.
Responsibilities
QA/QC team at site is responsible to ensure that quality records are distributed,
maintained and controlled at each owner department/section through the project
execution. QA/QC team is responsible to generate the filled formats of quality records.
They will ensure their maintenance and distribution.
Procedure
Identification
Records are to be dated, and signed by the person who establishes the record.
Retention of Records
The retention period of records is to be established for the periods during which the
record may be required for study or verification in accordance with the contract.
Storage
Records are to be stored in files that are to be properly numbered and indexed for easy
retrieval and to avoid damage. Cabinets containing records are properly labeled to
display their contents.
Document No.
Document Description
SOIL
LR-01
LR-02
LR-03
LR-04
LR-05
LR-06
LR-07
LR-08
LR-09
LR-10
LR-11
LR-12
LR-13
LR-14
LR-15
LR-16
LR-17
LR-18
LR-19
LR-20
LR-21
LR-22
LR-23
LR-24
LR-25
LR-26
LR-27
LR-28
Sand Equivalent
LR-29
Sulphate Soundness
LR-30
LR-31
LR-32
LR-33
LR-34
LR-35
LR-36
LR-37
LR-38
LR-39
Misc.
LR-40
Weather Record
LR-41
LR-42
Stone Pitching
LR-43
LR-44
LR-45
LR-46
LR-47
LR-48
LR-49
LS-01
BB-01
FR-01
Check Request
FR-02
Field Note
Note: FR = Field Record, LS = Level Sheet, BB = Bar Bending Schedule
Note: All above listed documents are given in ANNEXURE B.
3.9
TRAINING
3.9.1 PURPOSE
To establish a system for determining the need of staffs training, providing training and
maintain training records at site.
3.9.2 SCOPE
This procedure applies to all training programs provided by SINOHYDRO-NEL JOINT
VENTURE at site.
3.9.3 RESPONSIBILITIES
PM and SM are responsible for identifying and recommending employees after
assessing the training needs of their staff.
Manager Admin is responsible for the following:
Arrange orientation on quality assurance and maintaining relevant record for the
site.
Arrange orientation and maintain record at Site for new appointees/transferred
personnel.
Maintaining the record for internal/external training of Project Site personnel.
3.9.4 PROCEDURE
Orientation
Arrangements for orientation of new appointees/transferees are to be made by the
Manager Admin at site in the following areas;
Project Orientation.
TRAINING RECORD
Internal
Based on the training course attended by the employee training record is to be updated.
External
After successful completion of external training the employee is to submit a copy of the
training certificate to Manager Admin for record in his personal file.
3.10 INTERNAL QUALITY AUDITS
3.10.1 Purpose
To provide a system for conducting Internal Quality Audits and determine whether quality
of activities and related results are complying with planned arrangements and whether
these arrangements are implemented effectively.
3.10.2 Scope
This procedure is applicable to all Site activities falling within the quality system.
3.10.3 Responsibility
Project Manager & Site Manager at Site are responsible for establishing the team, to
perform Internal Quality Audit. P.M. will be the head of the audit team. Site Manager,
Planning Engineer and Construction Managers shall be the members of Audit Team.
3.10.4 Procedure
To provide a procedure for conducting Internal Quality Audits and to determine whether
the site Quality Assurance activities are conforming to the system, giving the desired
results and complies with plans, quality audit process is as follows.
3.10.5 Quality audit process
Audit Program
The Audit Team Leader shall do the following:
Prepare an Audit Program listing the Manpower and its individual responsibilities
Period of Audit
Working Files of Previous Audits, if any, for clearance of the outstanding matters.
Have an opening conference with the QC Team and those involved in explaining
the scope, duration and need for documents etc. and providing explanations as
necessary
Visiting the site of the project, obtaining a brieng and getting the feel of the
works, site conditions, progress, materials, etc.
Clarify and obtain explanations and remedy where necessary with verbal or
written responses.
ANNEXURE A
(Organogram)
ANNEXURE B
QA/QC Reporting Documents