Escolar Documentos
Profissional Documentos
Cultura Documentos
Abstract
Riser base gas-lift is one of several methods that have been
proven to work in subsea developments for production
enhancement. In addition, gas-lift can be used as an effective
method to suppress severe slugging that usually occurs in
flowlines with downhill inclination. In some cases, gas-lift can
be used to increase feasibility of blowdown for hydrate
prevention.
Meanwhile, the necessity of gas-lift application is not always
obvious because gas-lift effectiveness depends on reservoir
performance, fluid properties, seabed terrain, subsea
architecture, and flowline and riser specifications. In many
cases, gas-lift for production enhancement is only needed at
late life production, when oil production rates are low and
water rates might be high enough. It is clear that the necessity
of gas-lift, optimal operability and system design should be
assessed from various aspects, including flow assurance.
Whether gas-lift suitable as an artificial lift method and where
the lift-gas should be injected needs to be evaluated very early
in the project development lift cycle. Often, decisions need to
be made with a very limited analysis to screen different
development concepts, and whether to use gas-lift or not is
one such decision.
Based on the past experience of riser gas-lift applications for
different deepwater subsea projects and based the associated
multiphase flow phenomena, a generic set of guidelines was
developed. These include when gas-lift is beneficial for
production enhancement, for flow stability and for flow
assurance. Also, factors affecting the selection of a location
for lift-gas injection, and the nature of the lift-gas supply
method (dedicated vs. shared gas-lift risers, insulated vs. noninsulated gas-lift systems and gas-lift system functionalities
needed) are discussed.
Introduction
This paper discusses the riser base gas-lift used in deepwater,
subsea oil production systems. The information presented
here is drawn from currently producing subsea systems as well
as from those that are still in design stage. This paper does not
discuss downhole gas-lift used in DVA (direct vertical access)
or subsea wells, where challenges with regard to gas-lift
application may appear quite different from those that are in
the riser base gas-lift. The primary focus of this paper is to
describe how flow assurance concerns affect various
engineering decisions, in designing a gas-lift system.
Riser base gas-lift is injection of a pre-determined rate of gas
into the production flowline (or riser) on the sea floor.
Obviously, this applied to oil producing systems only. This
injected gas is provided from the host facility, through a gaslift riser. The reasons for gas-lifting can vary, but the most
important with regard to flow assurance are:
Production enhancement
Flow stabilization
Flowline depressurization
OTC 18820
OTC 18820
Uphill flowlines
In most cases severe slugging is not an issue for flowline with
uphill topography, even at high water cuts. Meanwhile
feasibility of blowdown often depends on details of uphill
flowline topography and strongly depends on water
production.
Gas-lift for blowdown assist may only become necessary at
mid to high water cuts. In such cases, it may be acceptable to
defer the installation of gas-lift system until gas-lift becomes
necessary. In some other situations (depending on flowline
geometry and GOR), blowdown may require gas-lift assist
from early life.
Other factors
Weak well start up is another factor that may impact whether
gas-lift is needed or when gas-lift is needed. Flowline
pressure can be lowered by gas-lift enabling the flow of weak
OTC 18820
Source of lift-gas
In all the cases described in this paper, the produced gas is
separated, compressed and treated at the host, before exporting
via an uninsulated gas export line. This export gas is
dehydrated, so there is no hydrate risk even when it is cooled
to the seabed temperature.
During normal production, the lift-gas is obtained downstream
of the dehydration unit. Thus, composition of lift-gas is
similar to that being exported. However, provisions should be
made to accommodate off spec gas for lift-gas. Typically, this
is achieved by injecting methanol to the gas-lift gas at the
host, to control hydrate risk.
In many cases, the gas for gas-lift is available at the outlet
pressure of the compressor in the gas export system.
Depending on the water depth, additional compression may be
needed.
When blowdown depends on gas-lift assist, there is a need for
sufficient supply of gas even under a full-field shut-in
condition. Typically, this is accomplished by buying back gas
from the gas export flowline. Since gas compression may not
be available under such conditions, gas export flowline design
should ensure the availability of a sufficient inventory of gas
in the export gas system under pressure. If the available
pressure is not adequate, then a booster compressor with a
very high availability must be used to supply gas for
blowdown with gas-lift assist. Since securing flowlines must
be done within the available cooldown time, availability of gas
during a full field shut-in may dictate the choice of hydrate
prevention strategy.
Operating Envelope
One major issue one has to face in designing a gas-lift system
is that the flowline pressure (against which the lift-gas needs
to be injected during gas-lift) varies significantly. The lowest
flowline pressure will occur when gas-lift is used during
blowdown. The highest flowline pressure against gas-lift
needs to be injected typically occurs when gas-lift needs to be
injected to a liquid filled flowline. For example, a flowline
pressure may vary from 200 psi to 2000 psi, under these
conditions. Thus, gas delivery system should to be able to
inject gas against these widely varying flowline pressures, and
may be required to maintain an acceptable gas temperature
during that process.
Insulation Requirements
Whether the lift-gas supplied to the riser base needs to be at a
high temperature or whether that lift-gas can be allowed to
cool to the ambient seabed conditions needs to be determined
as a part of the subsea flowline thermal analysis. Arrival
temperature and associated cooldown times determine the
need for insulation.
In general, shorter gas-lift risers, used in long offset subsea
systems with low temperature wells tend to have insulated
gas-lift risers. On the other hand, very long gas-lift risers,
short offset subsea systems, better flowline insulation (such as
PIP), and/or high temperature wells may result in cases where
OTC 18820
3500
3000
2500
2000
1500
1000
500
0
0
100
200
300
400
500
600
700
800
900
1000
OTC 18820
Slug Suppression
It has been observed in fields and documented that use of liftgas under some conditions may in fact promote slugging.
Also, there are cases where a relatively small change of
boarding pressure (inlet separator operating pressure) had
moved a flowline from steady flow to severe slugging.
This behavior has contributed to the skepticism, especially
among operators about the usefulness of gas-lift to suppress
severe slugging.
However, there are field observations where gradual reduction
in lift-gas rate has made the flowline to start severe slugging
and actually tripped the topside processing. This can be clearly
seen in Figure 6.
OTC 18820
Case Studies
Six cases, which use riser base gas-lift, are discussed below.
Cases 1 and 2 are currently producing assets. Case 3 through
6 are at various stages of development. Key parameters that
differentiate these cases are listed below:
Case 1 Currently producing at 6000 ft water depth, both
uphill and downhill flowlines to a FPS. No water injection or
gas re-injection.
Case 2 Currently producing at 3000 ft water depth,
predominantly uphill flowlines to a FPSO. With water
injection, but no gas re-injection.
Case 3 Under development at 3000 ft water depth, all uphill
flowlines to a FPSO. Restriction on number of risers to the
FPSO. With water injection, but no gas re-injection.
Case 4 - Under development at 3000 ft water depth, flowlines
have a major down dip to existing FPSO. With water
injection, but no gas re-injection.
Case 5 - Currently producing at 3500 ft water depth, flowlines
are all uphill to a TLP. With water injection, but no gas reinjection.
Case 6 Under development at 4500 ft water depth, with
mostly downhill flowlines to a FPS. With water injection and
gas re-injection.
Major issues related to the gas-lift system design for each of
these cases are described below.
Case 1
This is a FPS based producing deepwater subsea development
at a water depth of about 6000 ft. Subsea layout consisted of
both uphill and downhill flowlines, in the form of two oil
flowloops. Water or gas injection for reservoir support is not
used in this development [2].
Downhill flowlines in this development were expected to
show severe slugging even at a flow rate of 20,000 blpd, and
gas-lift was selected for these flowlines to prevent severe
slugging. Gas-lift assisted blowdown was not considered,
mainly due to water depth related issues. Also, the available
lift-gas injection tie in location did not favor the use of lift-gas
during blowdown.
Distances to the closest well on these two downhill flowlines
were quite different. The closest possible lift-gas tie-in
position in these flowlines was close enough to the closest
well location in one flowline, but not in the other. Thus, one
flowline was equipped with a dedicated lift-gas injection point
while the lift-gas injection to the other flowline was done at
that closest well location. This decision eliminated some
subsea hardware, but increased one gas-lift riser length by
more than 5000 ft.
The thermal considerations (available cooldown times of the
subsea system, which depends on arrival temperature while
lift-gas is used) led to the decision to insulate the shorter gaslift riser. Analysis showed was no such need for insulating the
longer gas-lift riser. Also, the available cooldown times with
cold gas injected via the uninsulated gas-lift riser was
acceptable in that flowline.
OTC 18820
OTC 18820