Você está na página 1de 6

Provision of Engineering, Procurement, Construction, Activity :

Installation, Commissioning (EPCIC) of Long Term Power


Solution at Bintulu Onshore Receiving Facility (BORF) ITP No:
Seq No.
1.0

Description/ Activity

Controlling Procedure Form to


record results of compliance

Inspection & Test Plan

Contract No: PB/1302

FIBRE OPTICAL CABLE

Principal: MOC

FBSB/MOC/ITP-005

Location: BORF

Specification Acceptance Criteria


Reference

Holding Point
Contractor
(FBSB)

3rd Party
(SESCO)

Principal
(MOC)

Operation

Material Receiving Inspection

1.1

Material Received InspectionReport


Visual inspection
ITU-T Standard for fiber Optic (series
G.600-G699)

Material Deficiency Report

2.0
2.1

Check Quantity/ Condition


(Cables/Drum)
Material Verification

Visual Inspection Report

Type of material Cable size, type and


rating conform to specification, insulation
jacket
notspecification
to damaged
Correct

F-I-03

ITU-T Standard for fiber Optic (series


G.600-G699)

Material Received InspectionReport

Method Statement

On the drum test

Material Deficiency Report

Verify damage Material

Visual Inspection Report

Storage

3.1

Correct tagging number

F-I-03

ITU-T Standard for fiber Optic (series


G.600-G699)

Cleanliness

Material Received InspectionReport

Quantity

Material Deficiency Report

Refer to drawing 06001-MGP1-EG-ICDW-0060-08 "Instrument Cable


Schedule Fibre Optic".

INSTALATION AND LAY FO CABLE

4.1

Fiibre Optic Cable Type


Check Trenching size (width and depth)
and condition

W/R

W/R

W/R

Refer to drawing 06001-MGP1-EG-ICDW-0060-08 "Instrument Cable


Schedule Fibre Optic".

3.0

4.0

ITU-T Standard for fiber Optic (series


G.600-G699)
F-C-01

Prevent Bending Radius less than 15D

Refer to Drawing MOM-SK309-64-ICDW-0061-(Sheet 1 to 3) Fiber Optic


Cable Routing (Murphy BORF to SESCO
33KV Substation)

Handle with care the cable drum not to


damage the FO cable
Cable laying into trench and cable laying
by fix drum
Verify and ensure before starting under
ground placing work, all personnel shall
know the communication signal that will be
used. Personnel shall be stationed at the
reel location during cable pulling activities
to maintain proper reel rotation.
Roller shall be arranged within or on
ground surface along trench line.
Manual Cable pulling and assign
designated personnel to guide the FO
cable

Refer to Drawing MOM-SK309-64-ELDW-0085-(Sheet 1 to 3) 33kV


Underground Cable & Fiber Optic Overall Routing Plan

F-I-03

Method Statement
Refer to drawing 06001-MGP1-EG-ICDW-0060-08 "Instrument Cable
Schedule Fibre Optic".

Verify the Spacing between the HV cable


and FO as per AFC

Page 1 of 6

Comments/Remarks

Preserve both end of cable using end


cap

Page 2 of 6

Provision of Engineering, Procurement, Construction, Activity :


Installation, Commissioning (EPCIC) of Long Term Power
Solution at Bintulu Onshore Receiving Facility (BORF) ITP No:
Seq No.

Description/ Activity

5.0

BACKFILLING

5.1

Check spacing between cable

Controlling Procedure Form to


record results of compliance

Soil Compaction
Concrete slabs lining

Inspection & Test Plan

Principal: MOC

FBSB/MOC/ITP-005

Location:

Specification Acceptance Criteria


Reference

Holding Point
Contractor
(FBSB)

Refer to MOM-SK309-64-EL-DW-008601

F-C-01

Contract No: PB/1302

FIBRE OPTICAL CABLE

3rd Party
(SESCO)

Principal
(MOC)

Operation

Comments/Remarks

Cable route maker should be placed


Backfilling
6.0

FIBRE OPTIC TERMINATION

6.1

Correct tagging number.

ITU-T Standard for fiber Optic (series


G.600-G699)

F-I-03
Verify that only approved cleaving tools
and test equipment use for FO.

DEP 32.71.00.11 sec. 2.2.1

Certified personnel to Terminate the FO


FO cable is clean and dust free

Competency certificate

Refer to MOM-SK309-64-IC-DS-001900 "Instrument Datasheet for Indoor


Fiber Optic Patch Panel"

Equipment Certificate

Refer to MOM-SK309-64-IC-DS-002000 "Instrument Datasheet for High


Speed Fiber Optical Modem"

H/R

Correct Splicing and Equipment tools

Wave length test OTDR (Optical Time


Domain Reflectometer)

*Inspection and test mark-up legend: I = Inspect/Test, M=Monitor or surveillance, W = Witness, H = Hold Point, R = Document Review, A = Document Approval, SCE = Safety critical Item, 5 % V - 5 % Principal Verifi
required

Inspection and testing activities completed


3rd Party (SESCO)

Contractor (FBSB)
Signature :
Print Name :
Date :

Page 3 of 6

Operation

Contract No: PB/1302


Principal: MOC
Location: BORF

Comments/Remarks

Page 4 of 6

Page 5 of 6

Contract No: PB/1302


Principal: MOC
Location:

Comments/Remarks

ess, H = Hold Point, R = Document Review, A = Document Approval, SCE = Safety critical Item, 5 % V - 5 % Principal Verification

Principal (MOC)

Page 6 of 6

Você também pode gostar