Escolar Documentos
Profissional Documentos
Cultura Documentos
DATE
05.12.2014
DETAILS OF REVISION
Rev No. : 00
REV
00
Page 1 of 7
TABLE OF CONTENTS
1.0
SCOPE
2.0
PURPOSE
3.0
REFERENCE DOCUMENTS
4.0
RESPONSIBILITIES
5.0
PROCEDURE
6.0
FORMATS
7.0
DOCUMENTATION
8.0
GENERAL
9.0
SAFETY
Page 2 of 7
Rev No. : 00
Rev No. : 00
1.0 SCOPE
This Procedure describes guidelines for Installation & Testing of Dry Type Distribution Transformer included
in ELECTRICAL WORKS for VTKN CapEx up gradation Project, at Vopak, CRL Terminal Pvt. Ltd., Old
Kandla.
2.0 PURPOSE
The purpose of this procedure is to provide guidelines for Installation, Testing and Commissioning of Dry
Type Distribution Transformer at Vopak, CRL Terminal Pvt. Ltd. Old Kandla.
Approved SOR.
ii.
4.0 RESPOSIBILITIES
The responsibilities of implementation of this procedure lie with Project Manager, AFCONS A/c VTKN
CAPEX UP GRADATION PROJECT
5.0 PROCEDURE
5.1
MATERIALS
After receipt of material at site, IMIR shall be made & material shall be inspected as per approved ITP.
5.2
ii.
Check foundation its level, centrelines, anchor bolts / insert plates. In case of rail mounted type checks
centre line & level of rails. Check Transformer to be placed on foundation as per approved AFC GA drawing
for Dry Type Distribution Transformer.
iii. Check the Serial no. and Rating of Transformer as per specification / AFC drawing.
iv. Inspect for availability of all accessories.
v.
Inspect any physical damages, missing or short supplied items for insurance claim.
vi. Check completion of Civil works, get the clearance from Civil and cleanliness of area.
Page 3 of 7
Rev No. : 00
vii. Availability of Tested, Calibrated & Standard Tools & Tackles, skilled manpower for Shifting & Lifting of
equipment.
viii. Check the size of terminal box suitable for Incoming Cables.
5.3
INSTALLATION METHODOLOGY
5.3.1 INSTALLATION CHECKS OF DRY TYPE DISTRIBUTION TRANSFORMER.
i.
ii.
Check bushing cracks, chips or presence of paint or dirt. Bushing should be cleaned as per vendors
instruction.
vi. Install / Grout the anti-earthquake plate as mentioned in the specifications & approved drawings.
vii. Check healthiness of all accessories of transformer.
viii. Install all accessories of transformers as per approved GA / Installation manual.
ix. Install marshalling box as per approved GA and fix the all control cables routes to Marshalling box.
x.
Ensure cable connection at the cable & box, their colour coding & tightness (if required use of spring and flat
washers on the appropriate faces to be confirmed) and cleanliness of lapping surfaces. For multiple cable
connection, check for correctness of phasing.
xi. Check the connection of Space heaters & Thermostat in Marshalling box & Control Cabinet.
xii. Dressing of all power and control cables to be checked.
xiii. Ensure the construction of earth pits and earth grid for Transformer Body & Neutral is as per AFC drawing,
xiv. Ensure the earthing connection of Transformer body, Marshalling panel, HV Cable Box. LV terminal box,
Transformer neutral is as per AFC drawing.
xv. The equipment earthling connections tightness and earth resistance value to be checked.
xvi. If required or specified, Dry-out of Transformer to be done.
xvii. Ensure the tightness of cables at HV & LV sides and control cables in Marshalling panels.
xviii. Installation completion certificate and hand over for Testing & Commissioning.
5.3.2
i.
Measure winding resistance at each tap. Test Vector group, polarity, magnetizing current, magnetic
balancing.
ii.
Page 4 of 7
Rev No. : 00
vi. Check tightness of wire connection at NCT terminals and marshalling terminals.
vii. Simulation test for all external interface connection alarms, annunciation and trip circuits checking.
viii. Check Tap Changer Control Operation without Energizing Transformer.
ix. Check the CT Ratio & Polarity. Ensure all earthing connections.
x.
MEGGAR TEST
The Transformer & its cable shall be check for insulation resistance by using suitable rating of Meggar.
5.3.4
Equipment
Voltage (AC)
230-500V
500V
6600V
5000V
i.
ii.
HT, LT & Bus duct connections to be checked for tightness & phasing.
Page 5 of 7
Rev No. : 00
viii. Water tightness of all covers of Transformer, Bus ducts, Marshalling Panel etc.
ix. All control wires tightness to be checked.
x.
i.
ii.
Fire Alarm, Sand bucket & Fire Extinguisher shall be provided as specified near Transformer.
ii.
Sand filling shall be done in the cable trench as per the drawing. Cable trench shall be covered after the
cable laying is carried out in accordance with the specifications.
iii. Cable trays shall be covered, where ever required, as per the project specifications.
iv. Unused holes should plugged with suitable plug.
v.
After testing the J/B shall be properly closed to avoid any unauthorized changes.
vi. Proper sealing shall be provided at the cable entry into the control room, cable room.
5.3.6
6.0 FORMATS
i.
Installation / Erection & Testing of Transformer Testing & Meggar readings test Record.
Page 6 of 7
Rev No. : 00
7.0 DOCUMENTATION
i.
Documents shall be prepared in approved formats at all stages of Installation / Inspection as per approved
ITP and maintained, duly signed by AFCONS / TCE.
ii.
As Built Drawings.
8.0 GENERAL
i.
ii.
9.0 SAFETY
i.
All safety precautions shall be taken as per SHE requirements of the project.
ii.
Related JSA shall be prepared and to be approved from PMC before starting any activity.
iii. Tool box meeting shall be conducted before starting any job.
iv. Full care and precaution shall be taken by the field management for the safety and sanitation of workmen in
the field to prevent accidents during the execution of works
v.
During execution, the electrical equipment shall be placed so as to give no obstruction for traffic and proper
measures shall be taken to prevent damage due to falling bodies etc. and decrease in insulation
performance due to water penetration etc.
Page 7 of 7