The suitable site for this practical had been located infront of BengkeL
Ukur in Kuching Sarawak Polytechnique by my group and I (Group 2).
During fieldwork, the total station was set up at each point in the control
network in turn and used to locate detail from them. Below is the step by
step procedure to survey the details.
2.1
Traversing
2.2
Pickup details
Traditionally, two people have been required to locate detail using
total station : one operating the Leica Total station and the other
recorded
The details were roads, parking lots, trees and so on
Leica Total station was used to measure and record the details but
the operator is needed to be alerted and always pressed the All
2.3
Downloading data
file
The CDS stadia file was checked if the recorded data in good shape
or not
Stadia file for the job have been created
2.4
calculated
Topography details was shown graphically
The details graphic in CDS was exported in AutoCAD
Engineering plan or topography plan for practical 1 was produced.
Summary Steps:
1. Set the instrument up over the station required
2. Use the Automation Survey concept; Instrument height, Reflector
3.
4.
5.
6.
completed
7. Select the detail points in a clockwise
8. Download the data to computer via USB or cable
9. Process the data by using Civil Design & Survey (CDS)
10. Edit the data bu using AutoCAD to produce Engineering Plan