Escolar Documentos
Profissional Documentos
Cultura Documentos
TES-P-104.03, Rev. 0
TABLE OF CONTENTS
1.0
2.0
3.0
SCOPE
GENERAL
POWER CABLE TYPES AND APPLICATION
3.1
3.2
3.3
4.0
5.0
6.0
General
IEC STANDARDS
TESP10403R0/YM
PAGE NO. 2 OF 16
1.0
TES-P-104.03, Rev. 0
SCOPE
This standard covers the selection of a specific type and size of power cable based on
particular applications and conditions in the system of Saudi Electricity Co. (SEC)
Saudi Arabia..
2.0
GENERAL
2.1
2.2
The selection of the specific type and size of power cable will be based on the
following:
a)
b)
c)
d)
TESP10403R0/YM
Operating Conditions:
a.
b.
c.
d.
e.
System frequency.
f.
g.
PAGE NO. 3 OF 16
2.3
TES-P-104.03, Rev. 0
h.
i.
j.
k.
l.
m.
The process used in selecting and sizing a power cable shall be as follows:
a)
b)
c)
d)
e)
2.3.1
Installation Data:
2.3.1A
a.
b.
Underground Cables
a)
TESP10403R0/YM
PAGE NO. 4 OF 16
2.3.1B
2.3.1C
TES-P-104.03, Rev. 0
b)
Depth of laying.
c)
d)
e)
f)
g)
h)
i)
j)
Cables in Air
a)
b)
c)
Cables in Water
Individual installations require special consideration.
2.4
3.0
TESP10403R0/YM
Single conductor cables are easy to handle, splice, terminate and are
supplied in longer lengths than three conductor cables.
Date of Approval: December 16, 2006
PAGE NO. 5 OF 16
TES-P-104.03, Rev. 0
Their reactance is higher than three conductor cables and the use of a
metallic sheath for mechanical protection would be more expensive
and result in higher losses than with a three conductor cable.
3.1.2
3.2
In general, the ampacity and voltage drop will be higher for three
single conductor cables when compared with a similar size of three
conductor cable.
U-
Selection of Uo and U:
The selection of Uo depends on the type of system and on the system
earthing arrangements. For this purpose, systems have been divided
into followinf categories:
TESP10403R0/YM
PAGE NO. 6 OF 16
TES-P-104.03, Rev. 0
Category A:
Where earth faults are cleared as rapidly as possible but in any case
with in 1 min.
Category B:
This category comprises those systems, which, under fault conditions,
are operated for a short time only with one phase earthed. This
period should, in general, not exceed one hour, but a longer period
can be tolerated for radial-feed cables, and in special circumstances.
Under no circumstances, however, shall the period exceed eight
hours.
NOTE:
Category C:
This category comprises all systems which do not fall into Category
A&B.
For both categories, U should not be less than 0.85 Um.
NOTE:
3.2.2
Selection of Up
The value of Up to be adopted should be one of the values associated
with the selected highest voltage (Um) and is divided in to following
3 levels
Notes
TESP10403R0/YM
PAGE NO. 7 OF 16
TES-P-104.03, Rev. 0
Exposure to Over-Voltages
Installations can be classified as follows:
3.3
a.
b.
Ampacity
b)
c)
3.3.2
3.3.3
TESP10403R0/YM
PAGE NO. 8 OF 16
4.0
TES-P-104.03, Rev. 0
3.3.4
3.3.5
4.1.b
It is mandatory that the Design Engineer have full knowledge of the system
route limitations, circuitry and environment temperatures of the application
under consideration. He should consider the worst conditions of operation plus
future growth requirements of the circuit.
4.2
Since most applications of cable installation on the SEC system involve direct
buried cable, additional replacement cost for undersized cables must be
considered. Duct installed cables can be replaced within the limitations of the
duct size.
4.2.1
4.3
Load - MVA.
Load Factor (LF).
Thermal Resistivity of the Soil (RHO).
Ambient Temperature - mean temperature of the soil or riser
temperature at above ground (in air) terminals.
Short circuit values with finite information on time duration
(affects sizing of copper in cable shield).
Derating factors for circuity (multiplicity of circuits and tie
formations).
Route location that might affect placement of splice bays/
manholes and terminations.
Ampacity Derating
4.3.1
TESP10403R0/YM
PAGE NO. 9 OF 16
4.4
TES-P-104.03, Rev. 0
For other factors, temperature with resistivity (RHO), number of circuits,, the
following conversions should be utilized:
4.4.1
Tc Ta
Tc - Ta
Where
4.5
T
Ta
Ta
Tc
=
=
=
=
4.6
Load Factor
All ampacities shall be calculated on the basis of 100% load factor.
4.7
Circuitry
4.7.1
For the calculation of desired ampacity for the load required, it may
be necessary to consider additional circuits also (installed in the same
trench or in parallal).
4.7.2
TESP10403R0/YM
PAGE NO. 10 OF 16
TES-P-104.03, Rev. 0
TABLE 04-1
STANDARD SEC CABLE SIZES
SIZE
mm
35
70
120
185
300
400
500
630
800
1000
1200
1600
2000
2500
4.8
7.7
10.7
14.2
17.6
22.5
25.6
28.8
32.7
37.0
41.6
45.0
48.1
54.3
62.7
2
2/0
4/0
350
600
750
1000
1250
1750
2000
-
Ampacity
4.8.1
4.9
DIAMETER
mm
Cable Calculation
This is for guidance on how to select an adequate cable for a particular
application and should not be considered as a standard method to solve all
problems.
4.9.1
TESP10403R0/YM
Information Required
a)
b)
c)
d)
e)
PAGE NO. 11 OF 16
4.9.2
TES-P-104.03, Rev. 0
Voltage to be used.
Required reliability of the power supply.
Cost of material, installation and mintenance.
Type of Installation
The system requirements and area conditions will determine the type
of installation to be used, which could be:
a)
b)
c)
4.9.4.a
TESP10403R0/YM
PAGE NO. 12 OF 16
4.9.4.b
TES-P-104.03, Rev. 0
4.9.4.c
4.9.5
Q.S
K.R.t
Ln
where
T2
T1
t
TESP10403R0/YM
1/K - 20 + T2
l/K - 20 + T1
PAGE NO. 13 OF 16
TES-P-104.03, Rev. 0
: I =
where,
where,
Capacitance (C)
______ _____
18 Ln (Di/dc)
(F/km)
TESP10403R0/YM
PAGE NO. 14 OF 16
c)
TES-P-104.03, Rev. 0
where,
: 3.1416
f
: Frequency (Hz)
VOLTAGE REGULATION
5.1
General
While the heat generated in a cable conductor determines the maximum current
it can carry without deterioration, it is often necessary to limit the current to an
even lower value because of excessive voltage drop. This problem is usually
confined to the high current, low voltage secondary of distribution circuits. For
this reason, it is advantageous to carry the primary circuit as close to the load
as possible before transforming so the secondary runs, where most of voltage
drop occurs, will be small. The voltage drop of a cable may be calculated with
the following formula:
U = 100 (VS-VL)
VL
Where:
Vs
voltage at source
VL
voltage at load
Vs
(VLcos+RI) +(VLsin+XI)
Where:
load current
Cos
TESP10403R0/YM
PAGE NO. 15 OF 16
TES-P-104.03, Rev. 0
For 3-phase circuits, use the voltage resistance and reactance to neutral.
6.0
IEC STANDARDS
i
ii
iii
iv
TESP10403R0/YM
PAGE NO. 16 OF 16