Você está na página 1de 20

生産システム研究室 2003/12/10

Departemen Teknik Industri

TI3122 PERENCANAAN & PENGENDALIAN PRODUKSI

SISTEM PRODUKSI BERBASIS


PROYEK

Department of Industrial Engineering


Institut Teknologi Bandung
Jalan Ganesha 10, Bandung 40132

Departemen Teknik Industri

Definition

Project can usually be defined as a series of related tasks


directed toward a major output
The characteristics of a project:
ƒ It has a specific goal and deadline
ƒ It is unique or somewhat unfamiliar to the existing
work
ƒ It contains complex interrelated tasks requiring
specialized skills
ƒ It is temporary but critical to the company

TI-3131 Perencanaan dan Pengendalian Produksi 2

1
生産システム研究室 2003/12/10

Departemen Teknik Industri

A hierarchical view of the project environment

• .

Program 1 ... Program x ... Program n

Project
Project x1 Project x2 ... xm-1
Project xm

Task x21 Task x22 Task x23 ... Task x2p

Activity Activity Activity Activity


x221 x222 x223 ... x22q

TI-3131 Perencanaan dan Pengendalian Produksi 3

Departemen Teknik Industri

A hierarchical view of the project environment

• Program: the term commonly used to denote


very large and prolonged undertakings.
• Project: the term generally applied to time-
phased efforts of much smaller scope and
duration than programs. Programs are some
time viewed as consisting of a set of project
• Task: an elemental content of a project. A
project is normally composed of contiguous
arrays of tasks that all contribute to the
overall project goal
• Activity: the atom of a project. Activities are
smaller than tasks
TI-3131 Perencanaan dan Pengendalian Produksi 4

2
生産システム研究室 2003/12/10

Departemen Teknik Industri

Project management (PM)

• Project management (PM) is the process of


managing, allocating, and timing resources in
order to achieve a given objective in an
expedient manner
• The objective may be in terms of time, monetary,
or technical results
• PM is the process of achieving objectives by
utilizing the combined capabilities of available
resources
• PM represents a systematic execution of tasks
needed to achieve project objectives

TI-3131 Perencanaan dan Pengendalian Produksi 5

Departemen Teknik Industri

Planning

Organizing Scheduling

Training
Optimization

Project Contract
Risk management management management

Cost control Resource


management

Project design Software tools


Performance
control

Multidimensionality of project management


TI-3131 Perencanaan dan Pengendalian Produksi 6

3
生産システム研究室 2003/12/10

Departemen Teknik Industri

Project management (PM)

• PM covers the following basic functions: Planning,


Organizing, Scheduling and Control
• Project planning provides the basis for the initiation,
implementation, and termination of a project. It sets
guidelines for specific project objectives, project
structure, tasks, milestones, personnel, cost, equipment,
performance, and problem resolutions
• Project organization specifies how to integrate the
functions of the personnel involved in a project. Directing
(which involves guiding and supervising the project
personnel) is an important aspect of project organization

TI-3131 Perencanaan dan Pengendalian Produksi 7

Departemen Teknik Industri

Project management (PM)

• Project scheduling is the time phased arrangement of


project activities subject to precedence, time, and resource
constraints in order to accomplish project objectives. It is
often the core of project management efforts because it
involves the assignment of time periods to specific tasks
within the work schedule

TI-3131 Perencanaan dan Pengendalian Produksi 8

4
生産システム研究室 2003/12/10

Departemen Teknik Industri

Tools
Project Planning Time and cost estimates
1. Setting goals Budget, Cash flow
2. Defining the project Personnel
3. Tying needs into timed Material ability
project activities Engineering diagram
4. Orginizing the team

Project scheduling
1. Tying resources (people, money, Tools
supplies) to specific activities Gantt Chart, CPM,
2. Relating activities to each other PERT
3. Updating and revising on regular Cash flow schedules
basis

Project controlling Tools


1. Monitoring resource, costs, PERT charts
quality, budgets Reports describing
2. Revising and changing plans 1. budget by department
3. Shifting resources to meet time, 2. delayed activities
cost, and quality demands 3. slack activities
4.quality of work
completed

Before project During project

9
Start of the project
TI-3131 Perencanaan dan Pengendalian Produksi

Departemen Teknik Industri

The project of manufacturing

• In a large organization, the manufacturing system may be


configured as a multi-project endeavor
• The following figure shows the typical components of a
manufacturing enterprise organized as a project
• The project starts with a conceptualization of a product and
needs some of distinct tasks for getting the product to the
market

TI-3131 Perencanaan dan Pengendalian Produksi 10

5
生産システム研究室 2003/12/10

Departemen Teknik Industri

Systems
integration
Market
survey
Process Quality
planning specs

Feasibility
Idea study Cost Training Production

Financing Operations Schedule


planning

Facilities

Technology
assessment

TI-3131 Perencanaan dan Pengendalian Produksi 11

Departemen Teknik Industri

Project Management Technique:

1. Critical path method (CPM)


was developed in 1957 by J.E. Kelly of Remington
Rand
and M.R. Walker of duPont

2. Program Evaluation and review technique (PERT)


was developed in 1958 by the Navy with Booz, Allen
and Hamilton

TI-3131 Perencanaan dan Pengendalian Produksi 12

6
生産システム研究室 2003/12/10

Departemen Teknik Industri

The framework of CPM and PERT

Basic steps:
• Define the project and all its significant tasks or
activities
• Develop the relationship among the activities. Decide
which activities must precede and which must follow
others
• Draw the network connecting all of the activities
• Assign time and cost estimates and required resources
to each activity
• Compute the longest time path through the network.
This is called the critical path
• Use the network to help plan, schedule, monitor and
control the project
TI-3131 Perencanaan dan Pengendalian Produksi 13

Departemen Teknik Industri

The questions answered by CPM or PERT

• When will the entire project be completed?


• What are the critical activities in the project, that
is, the ones that will delay the entire project if
they are late?
• Which are the noncritical activities, that is, the
ones that can run late without delaying the whole
project’s completion?
• What is the probability that the project will be
completed by a specific date?
• At any particular date, is the project on schedule,
behind schedule, or ahead of schedule?

TI-3131 Perencanaan dan Pengendalian Produksi 14

7
生産システム研究室 2003/12/10

Departemen Teknik Industri

The questions answered by CPM or PERT

• On any given date, is the money spent equal to, less than,
or greater than the budgeted amount?
• Are there enough resources available to finish the project
on time?
• If the project is to be finished in a shorter amount of time,
what is the best way to accomplish this at the least cost?

TI-3131 Perencanaan dan Pengendalian Produksi 15

Departemen Teknik Industri

Conventions

• Activities: a task that occurs between 2 events


• Event arrows and nodes

• Activity-on-Arrow (AOA)
Arrows are used to represent activities, while
nodes represent starting and ending points of
activities

• Activity-on-Node (AON)
Nodes represent activities, while arrows
represent precedence relationships
TI-3131 Perencanaan dan Pengendalian Produksi 16

8
生産システム研究室 2003/12/10

Departemen Teknik Industri

Convention
.

Name and Symbol Description

Event A point in time, usually


a completion date or a
starting date
(node)

Activity An activity or a certain


amount of work required in
(arrow) the project

Activity A Activity B
Event 1 Event 2 Event 3

(network)
A sequence of activities
with beginning and
ending events
TI-3131 Perencanaan dan Pengendalian Produksi 17

Departemen Teknik Industri

Example 1
Activity Immediate predecessor
A -
B -
C A
D B

2
C
A

1 4

B D
3

TI-3131 Perencanaan dan Pengendalian Produksi 18

9
生産システム研究室 2003/12/10

Departemen Teknik Industri

Example 2

Beginning event Ending event Activity


1 2 1-2
1 3 1-3
2 4 2-4
3 4 3-4
3 5 3-5
4 6 4-6
5 6 5-6

TI-3131 Perencanaan dan Pengendalian Produksi 19

Departemen Teknik Industri

Example 2
.

2 4

1 6

3 5

TI-3131 Perencanaan dan Pengendalian Produksi 20

10
生産システム研究室 2003/12/10

Departemen Teknik Industri

Example 3

Activity Immediate Predecessor(s)


A -
B -
C A
D B
E C, D
F D
G E
H F

TI-3131 Perencanaan dan Pengendalian Produksi 21

Departemen Teknik Industri

Example 3
.

2 5
A C G
E

1 7
4

B D F
H
3 6

C E
2 Dummy 5
A G

Dummy activity

1 7

B
C
3 4 6
D F

TI-3131 Perencanaan dan Pengendalian Produksi 22

11
生産システム研究室 2003/12/10

Departemen Teknik Industri

Critical Path Method (CPM)

CPM is to determine the following quantities for each


activity
• ES: Earliest start time. All predecessor activities must be
completed before an activity can be started. The ending
time of the predecessor activities is the earliest time an
activity can be started
• LS: Latest start time. All successor activities must be
completed without delaying the entire project This is the
latest time an activity can be started without delaying
the entire project
• EF: Earliest finish. EF=ES+t
• LF: Latest finish. LF=LS+t

TI-3131 Perencanaan dan Pengendalian Produksi 23

Departemen Teknik Industri

Critical Path Method (CPM)

• TS: Total slack time. TS is the amount of time an


activity may be delayed from its ES without
delaying the latest completion of the project.
TS=LS-ES or TS=LF-EF
• FS: Free slack time. FS is the amount of time an
activity may be delayed from its ES without
delaying the starting time of any of its immediate
successors

⎧ ⎫
FS ( j ) = Min ⎨ ES (i ) ⎬ − EF ( j )
⎩ i∈S ( j ) ⎭
S(j): immediate successors of activity j

TI-3131 Perencanaan dan Pengendalian Produksi 24

12
生産システム研究室 2003/12/10

Departemen Teknik Industri

Critical Path Method (CPM)

• The critical path is the group of activities in the project that


have a total slack time of zero. This path is critical because
a delay in any activity along this path would delay the
entire project
• The total project completion time is calculated by adding
the time values of those activities on the critical path

TI-3131 Perencanaan dan Pengendalian Produksi 25

Departemen Teknik Industri

Example 4

Activity Duration
1-2 2
1-3 7 2
3
2
2-3 4 4
1 4
2-4 3
3-4 2 7
3
2

TI-3131 Perencanaan dan Pengendalian Produksi 26

13
生産システム研究室 2003/12/10

Departemen Teknik Industri

Example 4
.

ES, EF

2 LS, LF
3 2 6
6 3
2 2 3 2
2
1 9

0 9
1 0 4 5
4
0 9
0 9
0 6 9
7 7
7 7 2
7
7 7
3
9

TI-3131 Perencanaan dan Pengendalian Produksi 27

Departemen Teknik Industri

Example 4

Activity Duration ES EF LS LF TS
1-2 2 0 2 1 3 1
1-3 7 0 7 0 7 0
2-3 4 2 6 3 7 1
2-4 3 2 5 6 9 4
3-4 2 7 9 7 9 0

• Determine free slack times for the respective activities.

TI-3131 Perencanaan dan Pengendalian Produksi 28

14
生産システム研究室 2003/12/10

Departemen Teknik Industri

Program Evaluation and Review Technique (PERT)

One distinguishing PERT and CPM is the use of 3 activities


time estimates for each activity in the PERT technique. Only
one time factor is given for each activity in CPM. The time
estimates are:
a=optimistic time
b=pessimistic time
m=most likely time
te=expected time
v=variance of activity completion time

TI-3131 Perencanaan dan Pengendalian Produksi 29

Departemen Teknik Industri

Program Evaluation and Review Technique (PERT)

• The expected time of completion time for activity i

• The variance
a +of4completion
m+b time for activity i
te =
6

• The variance of project completion time


⎛b−a⎞
2

vi = ⎜ ⎟
⎝ 6 ⎠

V= ∑v i
i∈critical path

TI-3131 Perencanaan dan Pengendalian Produksi 30

15
生産システム研究室 2003/12/10

Departemen Teknik Industri

Program Evaluation and Review Technique (PERT)

Activity a m tb v
1-2 3 4 5 4 1/9
1-3 1 3 5 3 4/9
2-4 5 6 7 6 1/9
3-4 6 7 8 7 1/9

If the expected project completion time is 20


weeks and the project variance is 100 weeks,
what is the probability that the project will be
finished on orTI-3131
before Week 25?
Perencanaan dan Pengendalian Produksi 31

Departemen Teknik Industri

Gantt chart

• When the results of a CPM/PERT analysis are fitted to a


calendar time, the project plan becomes a schedule
• The Gantt chart showing planned (or actual) progress of
activities is one of the most widely used tools for presenting
the schedule
• The horizontal axis indicates the time scale
• The horizontal bars/lines represent activities

TI-3131 Perencanaan dan Pengendalian Produksi 32

16
生産システム研究室 2003/12/10

Departemen Teknik Industri

Gantt chart
.

Activity Duration W1 W2 W3 W4 W5 W6 W7 W8 W9

1-2 2 weeks

1-3 7 weeks

2-3 4 weeks

2-4 3 weeks

3-4 2 weeks

TI-3131 Perencanaan dan Pengendalian Produksi 33

Departemen Teknik Industri

Gantt chart

The basic Gantt chart does not show the precedence


relationships among activities but it can be modified by
linking appropriate lines

Activity Duration W1 W2 W3 W4 W5 W6 W7 W8 W9

A 2 weeks

B 7 weeks

C 4 weeks

D 3 weeks

E 2 weeks

TI-3131 Perencanaan dan Pengendalian Produksi 34

17
生産システム研究室 2003/12/10

Departemen Teknik Industri

Crashing

• Additional resources can reduce activity time for


certain activity within the project
• Although it can be expensive to shorten activity
times, doing so might be worthwhile
• The questions are:
ƒ What activities should be shortened?
ƒ How much will this action cost?
ƒ Will a reduction in the activity time in turn reduce the
time needed to complete the entire project?
• The least expensive method of shortening the
entire project should be determined

TI-3131 Perencanaan dan Pengendalian Produksi 35

Departemen Teknik Industri

Cost-time Curves

Time Cost
8 weeks $300
7 weeks $400
Cost
6 weeks $600
$600
Y-Axis

$500

$400

$300

X-Axis Time (weeks)


6 days 7 days 8 days

TI-3131 Perencanaan dan Pengendalian Produksi 36

18
生産システム研究室 2003/12/10

Departemen Teknik Industri

Cost of reducing activity time

• The objective is to reduce the entire project completion


time by a certain amount at the least cost
• If Mi = maximum reduction of time for activity i
Ci= additional cost associated with reducing activity
time for activity i
Ki= cost of reducing activity
K =
C time by one time unit
i
i

for activity i
M i

Ci
Ki =
Mi
TI-3131 Perencanaan dan Pengendalian Produksi 37

Departemen Teknik Industri

Determining the least cost


Activity Duration M C K Critical
1-2 2 1 $300 $300 No
1-3 7 4 $2000 $500 Yes Min
2-3 4 2 $2000 $1000 No
2-4 3 2 $4000 $2000 No
3-4 2 1 $2000 $2000 Yes
2
3
2

1 4 4

7 2
3

TI-3131 Perencanaan dan Pengendalian Produksi 38

19
生産システム研究室 2003/12/10

Departemen Teknik Industri

Determining the least cost

Activity 1-3 is to be shortened by 1 week in order to reduce


the project completion time to 8 weeks

Note that any further reduction in activity time along the


critical path would cause the critical path to include
activities 1-2, 2-3 and 3-4.

TI-3131 Perencanaan dan Pengendalian Produksi 39

Departemen Teknik Industri

Further Readings

• Badiru, A.B., 1996, Project management in manufacturing


and high technology operations, John Wiley and Sons, Inc.,
New York
• Heizer, J. and Render, B., 1996, Production and operations
management, Prentice Hall International Editions, New
Jersey

TI-3131 Perencanaan dan Pengendalian Produksi 40

20

Você também pode gostar