Você está na página 1de 213
| ead Acceptance Testing Specifications for Electric Power Distribution Equipment and Systems These spocifications have been developed e InterNational Electrical Testing Assoviation for use ‘electrical power distribution system engineers. ‘Copy InterNational Electrical Testing Association PO Box 687 * 106 Stone Street + Morrison, CO 80465 303.697.8441 + Fax: 303.697.8431 E-mail; neta@netaworld.org » Web site: www.netaworld.org —_ Wtlious Mblnote NETA Standards Review Council These specifications were submitted for public comment and reviewed by the NETA Standards Review Council. Charles K. Blizard Diane W. Johnson Mark Lautenschlager Roderic L, Hageman Mary R. Jordan Alan D. Peterson NOTICE In no evant shall the IntérNational Electrical Testing Association be liable to anyone for special, collateral, incidental, or consequential damages in connection with or arising out of the use of these. materials, This document is subject to periodic review, and users are cautioned to obtain the latest edition. Comments and suggestions are invited from all users for consideration by the Association in connection wi ‘such review. Any such suggestions will be fully reviewed by the Association after giving the commenter, upon request, 3 reasonable opportunity to be heard. ‘This document should not be confused with federal, state, or municipal specifications or regulations, insurance requirements, or national safety codes, While the Association racommends reference to or use ¢ this document by government agencies and others, use of this document is purely voluntary and not bindin oth tte, G i a interNational Electrical Testing Association PO Box 687 + 106 Stone Street + Morrison, CO 80465 303.697.8441 FAX:303.697.8431 E-mail, neta@netaworid.org + Web Site: www.netaworld.org Mary R. Jordan, EdD - Executive Director PREFACE The purpose of these specifications is to assure that all tested electrical equipment and systems supplied by either contractor or owner are operational and within applicable standards and manufacturer's tolerances and that equipment and systems are installed in accordance with design specifications. The need for acceptance testing of electrical power systems is very clear to those with extensive startup and/or operating experience. Shipping and installation damage, field and factory wiring errors, manufacturing defects, and systems and components nat in accordance with drawings and specifications are some of the many problems that can be detected by appropriate testing. When these defects are found before startup they can be corrected under warranty and without the safety hazards and possible equipment and consequential damages of Joss of use/production that can occur if discovered after startup or energizing. In addition, test results obtained during acceptance testing are invaluable as base reference data for the periodic testing that is an essential element of an effective maintenance program. It is the intent of this document to list a majority of the field tests availabie for assessing the ‘Suitability for service and reliability of the power distribution system. Certain tests have been assigned an “optional” classification. The following considerations were used in determining the use of the “optional” classification: 1. Did another test listed provide similar information? 2. How did the cost of the test compare to the cost of other tests providing similar information? 3. Haw commonplace was the test procedure? Is it new technology? While acknowledging the above, it is still necessary to make an informed judgment for each Particular system regarding How extensive the testing should be. The approach taken in these specifications is to present a comprehensive series of tests that is applicable to most industrial and larger commercial systems. The guidance of an experienced testing professional should be sought when making decisions such as how extensive testing should be. In smaller systems some of the tests can be deleted. In other cases, a number of the tests indicated as optional should be performed. As a further note, it is important to follaw the recommendations contained in the manufacturer's instruction manuals. Many of the details of a compiete and effective acceptance testing procedure can only be obtained from that source. ‘The Association encourages comment fram users of this document. Please contact the NETA office at 303.697.8441 or your local NETA member firm. Alan D. Peterson NETA Technical Chair CONTENTS ELECTRICAL ACCEPTANCE TESTS: ; 4. GENERAL SCOPE, ACCEPTANCE TESTING SPECIFICATIONS. ; 2. APPLICABLE REFERENCES... 3. QUALIFICATIONS OF TESTING ORGANIZATION AND PERSONNE! 4. DIVISION OF RESPONSIBILITY... 5, GENERAL.. 5.1. Safety and Precautions .. 52 Suitability of Test Equipment 5.3 Test {instrument Cafibration 6.1 Short-Circuit and Coordination Studies 6.2 Load Flow Studies - Reserved 6.3 Stability Studies - Reserved 6.4 Switching Transients Studies - Motor Starting Studies - Reserved (187 kVA Single-Phase, 500 kVA Three-Phase, and Smaller). 2. Alr-Cooled, All Above 600 Volt and 600 Volt and Below - Large (Greater than 187 kVA Single-Phase and 500 kVA Three-Phase). 2. Liquid-Filed. 7.3 Cables..... 1, Low-Voltage, Low-Energy - Reserved 2. Low-Voltage, 600 Volt Maximum 3. Medium-Voltage, 69 kV Maximur 4. High-Voltage 7.4 Metal-Enclosed Busways 2 Medium-Voltage, 3. High- and Medium-Voltage, Open 2. Oil Switches: Medium-Voltage ..... 3. Vacuum Switches: Medium Voltage. 4. SF Switches: Medium-Voltage - Reserved es 7 de 5. Cutouts - Reserved. 7.6 Circuit Breakers. 1. Low-Voltage. Insulated Case/Molded Case .. 7.7 Circuit ‘Switchers. 7.8 Network Protectors, 600 Volt Class. 7.9 Protective Relays... 7.10 Instrument Transformers 7.11 Metering 7.12 Regulating 1. Voltage.. 1. Step-Voltage Regulators 2. Induction Regulator 2, Current - Reserved 7.13 Grounding Systems. 7.14 Ground-Fault Protection Sys! 7.16 Rotating Machinery. ral a 7.17 Adjustable Speed Drive Systems. 7.18 Direct-Current System: 3 Rectifiers - Reserved 7.19 Surge Arresters 1. Low-Voltage Surge Protection Devices. 2. Medium- and High-Voltage Surge Prote: 7.20 Capacitors and Reactors.. 4. Capacitors... 2. Capacitor Control Devices - Reserved 3. Reactors (Shunt & Current Limiting) 7.21 Outdoor Bus Structures 7.22. Emergency Systems. 1, Engine Generato 3, Automatic Transfer Switches 7.23 Telemetry/Pilot Wire/Scada - Reserved. 7.24 Automatic Circuit Reclosers and Line Sectionalizers 1. Automatic Circuit Reclosers, OilVacuum 2. Automatic Line Sectionalizers, Oi 7.25 Fiber-Optic Cables .... 7.26 Electrostatic/Electromagnetic Field Testing - Reserved 7.27 Special Systems - Reserved 8. SYSTEM FUNCTION TESTS 9. THERMOGRAPHIC SURVEY . : @*% 10. 10.4 10.2 10.3 10.4 10.5 10.6 10.7 10.8 10.9 10.10 10.14 10.12 10.13 10.14 10.15 10.16 10.17 10.18 TABLES Insulation Resistance Tests, Electrical Apparatus and System: ‘Switchgear Withstand Test Voltages. Recommended Dissipation Factor/Power Factor of Liquid-Filled Transformers, Regulators, and Reactors. Suggested Limits for New Insulating Liquids ‘Test Limits for New Insulating Oil Received in New Equipment. Test Limits for Silicone Insulating Liquid in New Transformers Typical Values for Less-Flammable Hydrocarbon Insulating Liquid Transformer insulation-Resistance, Acceptance Test Voltage and Minimum Results... Medium-Voltage Cables, Maximum Field Acceptance Test Voltages (kV, dc) Malded-Case Circuit Breakers, Inverse Time Trip Test... Instantaneous Trip Tolerances for Field Testing of Circuit Breakers. Instrument Transformer Dielectric Tests, Acceptance.. Maximum Allowable Vibration Amplitude ... Overpotential Test Voltages for Elactrical Apparatus Other than Inductive Equipment. Bolt Torques for Bus Connection: US Standard, Heat-Treated ~ Cadmium or Silicon Bronze Fasteners, Torque {Foot Pounds) ‘Aluminum Alloy Fasteners, Torque (Foot Pounds) .. Stainless Steel Fasteners, Torque (Foot Pounds: Reserved Insulation Resistance Conversion Factors for Conversion of Test Temperature to 20°C.. AC High-Potential Test Voltage for Automatic Circuit losers. AC High-Potential Test Voltage for Automatic Line Sectionalizers. Metal Enclosed Bus Dielectric Withstand Test Voltages . ‘Thermographic Survey, Suggested Actions Based on Temperature Rise STANDARD SPECIFICATION FORM Electrical Acceptance Tests GENERAL SCOPE, ACCEPTANCE TESTING SPECIFICATIONS 41 1.2 This standard covers the suggested field tests and inspections that are available to assess the suitability for initial energization of electrical power distribution equipment and systems. The purpose of these specifications is to assure that all tested electrical equipment and systems are operational and within applicable standards and manufacturer's tolerances and that the equipment and systems are installed in accordance with design specifications. The work specified in these specifications may involve hazardous voltages, materials, operations, and equipment. These specifications do not purport to address all of the safety problems associated with their use. It is the responsibility of the user to review all applicable regutatory limitations prior to the use of these specifications. @ ATS -1999 1 2. APPLICABLE REFERENCES 2.1 Alll inspections and field tests shall be in accordance with the latest edition of tt following codes, standards, and specifications except as provided otherwise herein. 1. 2. American Society for Testing and Materials - ASTM American National Standards Institute - ANSI ASTM D 92-90. Test Method for Flash and Fire Points by Cleveland Op Cup ASTM D 445-88. Test Method for Kinematic Viscosity of Transparent an Opaque Liquids ASTM D 664.95 Test Method for Acid Number of Petroleum Products b Potentiometric Titration ASTM D 877-87. Test Method for Dielectric Breakdown Voltage of Insulating Liquids using Disk Electrodes ASTM D 923-91. Test Method for Sampling Electrical insulating Liquids ASTM D 924-98 (1990). Test Method for A-C Loss Characteristics and Relative Permittivity (Dielectric Constant) of Electrical Insulating Liquids ASTM D 971-91. Test Method for Interfacial Tension of Oil against Wate by the Ring Method ASTM D 974-95, Test Method for Acid and Base Number by Color-Indic: Titration ASTM D 1298-85 (1990). Test Method for Density, Relative Density (Specific Gravity), or AP! Gravity of Crude Petroleum and Liquid Petrole Products by Hydrometer Method ASTM D 1500-91. Test Method for ASTM Color of Petroleum Products (ASTM Color Scale) ASTM D 1524-94 (1990). Test Method for Visual Examination of Used Electrical Insulating Oils of Petroleum Origin in the Field ASTM D 1533-88. Test Methods for Water in insulating Liquids (Kart Fischer Reaction Method) APPLICABLE REFERENCES (cont.) ASTM D 1816-84a (1990). Test Method for Dielectric Breakdown Vottage of Insulating Oils of Petroleum Origin Using VDE Electrodes ASTM 0 2029-92, Test Methods for Water Vapor Content of Electrical Insulating cases by Measurement of Dew Point ASTM D 2129-90. Test Method for Color of Chiorinated Aromatic Hydrocarbons (Askareis) ASTM D 2284-95, Test Method of Acidity of Sulfur Hexafluoride ASTM D 2285-85 (R1990). Test Method for Interfacial Tension of Electrical Insulating Oils of Petroleum Origin Against Water by the Drop-Weight Method ASTM D 2477-84 (R1990). Test Method for Dielectric Breakdown Voltage and Dielectric Strength of Insulating Gases at Commercial Power Frequencies ASTM D 2685-95. Test Method for Air and Carbon Tetrafluoride in Sulfur Hexafluoride by Gas Chromatography ASTM D 2759-94. Method for Sampling Gas from a Transformer under Positive Pressure ASTM D 3284-90a (R1994). Test Method for combustible Gases in Electrical Apparatus in the Field ASTM D 3612-95. Test Method of Analysis of Gases Dissolved in Electrical Insulating Oil by Gas Chromatography ASTM D 3613-92, Methods of Sampling Electrical insulating Oils for Gas Analysis and Determination of Water Content Association of Edison Illuminating Companies - AEIC Canadian Standards Association - CSA Institute of Electrical and Electronic Engineers - IEEE ANSI/IEEE C2-1997, National Electrical Safety Code ANSI/IEEE C37-1995, Guides and Standards for Circuit Breakers, Switchgear, Relays, Substations, and Fuses ANSI/EEE C57-1995, Distribution, Power, and Regulating Transformers APPLICABLE REFERENCES (cont.) ANSI/IEEE C62-1995, Surge Protection ANSI/EEE Std. 43-1974 (R1991). EEE Recommended Practice for Testing Insulation Resistance of Rotating Machinery ANSI/EEE Std. 48-1996. Standard Test Procedures and Requirements Alternating-Current Cable Terminations 2.5 kV through 765 kV. IEEE Std, 81-1983. IEEE Guide for Measuring Earth Resistivity, Ground impedance, and Earth Surface Potentials of a Ground System (Part |) ANSI/EEE Std. 81.2-1991. /EEE Guide for Measurement of Impedance and Safety Characteristics of Large, Extended or Interconnected Groun Systems (Part 2) ANSI/IEEE Std, 95-1977 (R191). IEEE Recommended Practice for Insulation Testing of Large AC Rotating Machinery with High Direct Volt IEEE Std. 100-1996. The JEEE Standard Dictionary of Electrical and Electronics Terms ANSI/EEE Std. 141-1993. /EEE Recommended Practice for Electricat Power Distribution for Industrial Plants (IEEE Red Book.) ANSI/EEE Std. 142-1991. EEE Recommended Practice for Grounding Industrial and Commercial Power Systems (IEEE Green Book) ANSIIEEE Std. 241-1990 (R1997). IEEE Recommended Practice for Electric Power Systems in Commercial Buildings (Gray Book) ANSI/IEEE Std. 242-1986 (R1981). IEEE Recommended Practice for Protection and Coordination of industrial and Commercial Power Systen (Buff Book) IEEE 386-1995. f/EEE Standard for Separable insulated Connectors System for Power Distribution Systems above 600 V. ANSI/IEEE Std, 399-1990. IEEE Recommended Practice for Industrial a Commercial Power Systems Analysis (Brown Book) ANSI/IEEE Std. 400-1991. IEEE Guide for Making High-Direct-Voltage Tests on Power Cable Systems in the Field ANSI/EEE Std. 421B-1979. /EEE Standard for High-Potential-Test Requirements for Excitation Systems for Synchronous Machines @ , | APPLICABLE REFERENCES (cont.) ANSWIEEE Std. 446-1995, IEEE Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications (Orange Book) ANSIIEEE Std. 450-1995 EEE Recommended Practice for Maintenance, Testing, and Replacement of Vented Lead-Acid Batteries for Stationary Applications ANSIIEEE Std. 493-1990. fEEE Recommended Practice for the Design of Reliable industrial and Commercial Power Systems (Gold Book) ANSI/IEEE Std. 602-1996. IEEE Recommended Practice for Electric ‘Systems in Health Care Facilities (White Book) ANSI/EEE Std. 637-1985 (R1992). IEEE Guide for the Reclamation of Insulating Oi} and Criteria for ts Use ANSI/IEEE Std. 739-1995. EEE Recommended Practice for Energy Management in Commercial and Industria! Facilities (Bronze Book) ANSI/IEEE Std. 1100-1992. IEEE Recommended Practice for Powering and Grounding Sensitive Electronic Equipment (Emerald Book) ANSI/EEE Std. 1106-1995. EEE Recommended Practice for Maintenance, Testing, and Replacement of Nickel-Cadmium Storage Batteries for Generating Stations and Substations ANSVIEEE Std. 1159-1995 - Recommended Practice for Monitoring Electric Power Quality ANSI/IEEE Std, 1188-1996. Recommended Practice for Maintenance, Testing, and Replacement of Velve-Regulated Lead-Acid (VRLA) Batteries for Stationary Applications Insulated Cable Engineers Association - CEA InterNational Electrical Testing Association - NETA. NETA MTS-97. NETA Maintenance Testing Specifications for Electrical Power Distribution Equipment and Systems National Electrical Manufacturer's Association - NEMA NEMA Standard for Publication No. AB4-1991. Guidelines for Inspection and Preventive Maintenance of Molded-Case Circuit Breakers Used in Commercial and industrial Applications NEMA Publication MG1-1993. Motors and Generators @ ATS-1999 5 CNN Mica cheikh PSE EG AMAA Soot Os 2. APPLIGABLE REFERENCES (cont.) 9. National Fire Protection Association - NFPA ANSI/NFPA 70-1996. Nationa! Electrical Code ANSI/NFPA 708-1994, Recommended Practice for Electric Equipment Maintenance ANSI/NFPA 70E-1996. Electrical Safety Requirements for Employee Workplaces ANSI/NFPA 99-1993. Standard for Healthcare Facilities ANSIINFPA 101-1894. Life Safety Code ANSI/NFPA 110-1993, Emergency and Standby Power Systems ANSI/NFPA 780-1995. Installation of Lightning Protection Systems 10. Occupational Safety and Health Administration - OSHA 11. Scaffold Industry Association - SIA ANSI/SIA A92.2-1990. Vehicle Mounted Elevating and Rotating Aerial Devices 12. State and local codes and ordinances 13, Underwriters Laboratories, Inc. - UL 2.2 Other Publications Paul Gill, Electrical Power Equipment Maintenance and Testing, New York: M: Dekker, Inc., 1998 6 ATS-—1999 & 9 | 3 QUALIFICATIONS OF TESTING ORGANIZATION AND PERSONNEL 34 32 3.3 ‘The testing organization shall submit appropriate documentation to demonstrate that it satisfactorily complies with the following, An organization having a "Full Membership” classification issued by the InterNational Electrical Testing Association meets this criteria. 1. The testing organization shall be an independent, third party, testing organization which can function as an unbiased testing authority, professionally independent of the manufacturers, suppliers, and installers of equipment or systems evaluated by the testing organization. 2. The testing organization shall be regulary engaged in the testing of electrical equipment devices, installations, and systems. The testing organization shall utilize technicians who are regularly employed for testing services. Each on-site crew leader shall hold a current ragistered certification in electrical testing applicable to each type of apparatus to be inspected or tested. The certification in electrical testing shall be issued by an independent, nationally- recognized, technician certification agency. The following entities shall qualify as independent, nationally-recognized, technician certification agencies: 1, InterNational Electrical Testing Association (NETA) Accepted cettifications: Certified Technician/Level Ill Certified Senior Technician/Leve! IV 2. National institute of Certification in Engineering Technologies (NICET) certifications specifically in Electrical Testing Engineering Technology: Engineering Technician/Level Ill Senior Engineering Technician/Level !V @ ATS -—1999 7 4 DIVISION OF RESPONSIBILITY 4.1 The owner's representative shall provide the testing organization with the following: 1. A short-circuit analysis and coordination study and a protective device setting sheet as described in Section 6. A complete set of electrical plans and specifications along with any pertinent change orders. An itemized description of equipment to be inspected and tested. A determination of who shall provide a suitable and stable source of electrical power to each test site, Notification of when equipment becomes available for acceptance tests. ‘Work shall be coordinated to expedite project scheduling. 4.2 — The installing contractor or testing firm shall perform certain preliminary iow- voltage insulation-resistance, continuity, and/or rotation tests prior to and in addition to tests specified herein. 4.3 The testing organization shall provide the following: 1. All field technical services, tooling, equipment, instrumentation, and technical supervision to perform such tests and inspections. Specific power requirements for test equipment. Notification to the owner's representative prior to commencement of any testing. A timely notification of any system, material, or workmanship which is fou deficient on the basis of acceptance tests. Avwritten record of all tests and a final report. & ATS—1999 ” GENERAL 5.1 Safety and Precautions This document does not include any procedures, including specific safety procedures, it is recognized that an overwhelming majority of the tests and inspections recommended in these specifications are potentially hazardous. Inherent in this determination is the prerequisite that individuals performing these tests be capable of conducting the tests in a safe manner and with complete knowledge of the hazards involved. 4, Safety practices shail include, but are not limited to, the following requirements: 1, Occupational Safety and Health Act. 2. Accident Prevention Manual for industrial Operations, National Safety Council. 3. Applicable state and local safety operating procedures. 4. Owner's safety practices. 5. ANSI/NFPA 70E, Electrical Safety Requirements for Employee Workplaces. 2. Alltests shall be performed with apparatus de-energized except where otherwise specifically required. 3. The testing organization shall have a designated safety representative on the project to supervise operations with respect to safety. 5.2 Suitability of Test Equipment 4. All test equipment shall be in good mechanical and electrical condition. 2. Split-core current transformers and clamp-on or tong-type ammeters require consideration of the following in regard to accuracy: 4. 2. Position of the conductor within the core Clean, tight fit of the core pole faces 6 ATS- 1999 9 5. GENERAL (cont) 3. Presence of external magnetic fields 4, Accuracy of the current transformer ratio in addition to the accurat of the secondary meter. Selection of metering equipment shall be based on a knowledge of the waveform of the variable being measured. Digital multimeters may be average or RMS sensing and may include or exclude the de component. When the variable contains harmonics or dc offset and, in general, any deviation from a pure sine wave, average sensing, RMS scaied meters n be misleading. Field test metering used to check power system meter calibration must have an accuracy higher than that of the instrument being checked. Accuracy of metering in test equipment shall be appropriate for the test being performed but not in excess of two percent of the scale used. Waveshape and frequency of test equipment output waveforms shall be appropriate for the test and tested equipment. 5.3 Test Instrument Calibration 4. ‘The testing firm shall have a calibration program which assures that all applicable test instruments are maintained within rated accuracy. The accuracy shall be directly traceable to the National Institute of Standards and Technology (NIST). Instruments shall be calibrated in accordance with the following frequenc schedule: 4. Field instruments: Analog, 6 months maximum; Digital, 12 months maximum 2. Laboratory instruments: 12 months 3. Leased specialty equipment: 12 months where accuracy is guaranteed by lessor. ‘Dated calibration \abels shall be visible on all test equipment. Records, which show date and results of instruments calibrated or tested shall be kept up-to-date, 10 ATS—1999 6. Up-to-date instrument calibration instructions and procedures shall be maintained for each test instrument, Calibrating standard shail be of higher accuracy than that of the instrument tested. 5.4 Test Report 1. | 5. GENERAL (cont) t \ i t i ' i The test report shall include the following: 1. ‘Summary of project. 2. Description of equipment tested. 3. Description of test. 4. Test data. 5. Analysis and recommendations, Test data records shall include the following minimum requirements: 1. Identification of the testing organization. 2. Equipment identification. 3. Humidity, temperature, and other atmospheric conditions that may affect the results of the tests/calibrations. 4. Date of inspections, tests, maintenance, and/or calibrations. 5. Identification of the testing technician. 6. Indication of inspections, tests, maintenance, and/or calibrations to be performed and recorded. 7. Indication of expected results when calibrations are to be performed. 8. Indication of “as-found” and “as-left” results. 9. ‘Sufficient spaces to allow all results and comments to be indicated. The testing firm shall fumish a copy or capies of the complete report to the ‘owner as required in the acceptance contract. & ATS—1999 11 6. POWER SYSTEM STUDIES 6.1 Short-Ci 1. it and Coordination Studies Scope of Services 4. Provide a current and complete short-circuit study, equipment- interrupting or withstand evaluation, and a protective-device coordination study for the electrical distribution system. The studies shall include all portions of the electrical distribution system from the normal and altemate sources of power throughou the low-voltage distribution system. Normal system operating method, alternate operation, and operations which could result in maximum-fautt conditions shall be thoroughly covered in the study Short-Circuit Study 1. 2. 3. The study shall be in accordance with applicable ANS! and IEEE standards. The study input data shall include the utility company's short-circu single- and three-phase contribution, with the X/R ratio, the resistance and reactance components of each branch impedance, motor and generator contributions, base quantities selected, and 2 other applicable circuit parameters. Short-cireuit momentary duties and interrupting duties shal! be calculated on the basis of maximum available fault current at each switchgear bus, switchboard, motor control center, distribution panelboard, pertinent branch circuit panelboards, and other significant locations through the system. Equipment Evaluation Study An equipment evaluation study shall be performed to determine the adequacy of circuit breakers, controllers, surge arresters, busways, switches, and fuses by tabulating and comparing the short-circuit ratings these devices with the maximum short-circuit momentary and interrupting duties. The evaluation study should be submitted prior to final approval ot equipment submittals. 12 ATS— 1999 oy L | POWER SYSTEM STUDIES (cont.) 6.1 Short-Circuit and Coordination Studies (cont.) 4 Protective-Device Coordination Study 1. A protective-device coordination study shail be performed to select or to verify the selection of power fuse ratings, protective-relay characteristics and settings, ratios and characteristics of associated voltage and current transformers, and low-voltage breaker trip characteristics and settings. The coordination study shail include all voltage classes of equipment from the utility's incoming Jine protective device down to and including each motor control center and/or panelboard. The phase and ground overcurrent protection shall be included as well as settings for all other adjustable protective devices. Coordination shall be in accordance with requirements of the National Electrical Code and the recommendations af ANSIIEEE. ‘Standard 399, as applicable. Protective device selection and settings shail be in accordance with requirements of the National Electrical Code and the recommendations of ANS{/IEEE Standard 399, as applicable. 5. Study Report 1. Discrepancies, problem areas, or inadequacies shall be promptly brought to the owner's attention. The results of the power-system studies shall be summarized in a final report. The report shall include the following sections: 1. Description, purpose, basis, and scope of the study and a single-line diagram of the partion of the pawer system which és inciuded within the scope of study. 2. Tabulations of circuit breaker, fuse, and other equipment ratings versus calculated short-circuit duties and commentary regarding same. 3. Protective device coordination curves, with commentary. G ATS —1999 13 6. POWER SYSTEM STUDIES (cont.) 6.4 Short-Circuit and Coordination Studies (cont.) 4. The selection and settings of the protective devices shall be provided separately in a tabulated form listing circuit identification, IEEE device number, current transformer ratios manufacturer, type, range of adjustment, and recommended settings. A tabulation of the recommended power fuse selection shall be provided for alt fuses in the system. 5. Fault-current tabulations including a definition of terms and a guide for interpretation. 6. Implementation The owner shali engage an independent testing organization for the purpose of inspecting, setting, testing, and calibrating the protective relays. circuit breakers, fuses, and other applicable devices as recommended in the power-system study report. 6.2 Load Flow Studies - Reserved 6.3 Stability Studies - Reserved 6.4 Switching Transients Studies - Reserved 6.5 Motor Starting Studies - Reserved 6.6 Harmonic Analysis - Reserved 6.7 Ground Mat Studies - Reserved 6.8 Cable Ampacity Studies - Reserved 6.9 Reliability Studies - Reserved 14 aTS-1999 & t 7 t TA INSPECTION AND TEST PROCEDURES Switchgear and Switchboard Assemblies 1. Visual and Mechanical Inspection 1. (~ Compare equipment nameplate data with drawings and specifications inspect physical and mechanical condition. Verify appropriate anchorage, required area clearances, physical damage, and cortect alignment. inspect all doors, panels, and sections for corrosion, dents, ‘Scratches, fit, and missing hardware. Verify that fuse and/or circuit breaker sizes and types correspond to drawings and coordination study as well as to the circuit breaker’s address for microprocessor-cormmunication packages. Inspect all bolted electrical connections for high resistance using one of the following methods: 4 Use af low-resistance ohmmeter in accordance with Section 7.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by Calibrated torque-wrench method in accordance with manwfacturer’s published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Verify that current and potential transformer ratios correspond to drawings. Compare equipment nameplate data with latest one-line diagram when available. Confirm correct operation and sequencing of electrical and mechanicat intertack systems. “Optional ATS-1999 15 7. INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies (cont.) 10. 11. 1. Attempt closure on locked-open devices. Attempt to open locked-closed devices. 2. Make key exchange with devices operated in off-normal positions. Thoroughly clean switchgear prior to testing. Lubrication 1. Verify appropriate contact lubricant on moving current- carrying parts. 2. Verify appropriate lubrication on moving and sliding surfac Inspect insulators for evidence of physical damage or contaminat surfaces. Verify correct barrier and shutter installation and operation. Exercise all active components. Inspect all mechanical indicating devices for correct operation. Verify that filters are in place and/or vents are clear. Perform visual and mechanical inspection on all instrument transformers in accordance with Section 7.10.1 (Visual and Mechanical Inspection). Inspect control power transformers. 4. Inspect physical damage, cracked insulation, broken leads tightness of connections, defective wiring, and overall gen condition. 2. Verify that primary and secondary fuse ratings or circuit breakers match drawings. 3. Verify correct functioning of drawout disconnecting and grounding contacts and interlocks *Optional 46 ATS—1999 ® Oo t INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assembiies (cont.) 2. Electrical Tests 1. Perform tests on ail instrument transformers in accordance with Section 7.10.2 (Electrical Tests). Perform ground-resistance tests in accordance with Section 7.13. Perform resistance tests through all bus joints with a low-resistance ohmmeter, if applicable, in accordance with Section 7.1.1 (Visual and Mechanical inspection). Perform insulation-resistance tests on each bus section, phase-to- phase and phase-to-ground, for one minute in accordance with Table 10.1. Perform an overpotentiai test on each bus section, each phase to ground with phases not under test grounded, in accordance with manufacturer's published data. If manufacturer has no recommendation for this test, it shall be in accordance with Table 10.2. The test voltage shall be applied for one minute. Refer to Section 7.1.3.4 before performing test. Perform insulation-resistance tests at 1000 volts de on all contro! wiring. For units with solid-state components, follow manufacturer's recommendations. Perform contro} wiring performatice test in accordance with Section 8. Perform current injection tests on the entire current circuit in each section of switchgear. 1. Perform current tests by primary injection, where possible, with magnitudes such that a minimum of 1.0 ampere flows in the secondary circuit. 2. Where primary injection is impractical, utilize secondary injection with a minimum current of 1.0 ampere. 3. Test current at each device, Determine accuracy of all meters and calibrate watthour meters in accordance with Section 7.11. Verify multipliers. “Optional o ATS - 1999 17 7 INSPECTION AND TEST PROCEDURES 7.1 Switchgear and Switchboard Assemblies (cont) Perform phasing check on double-ended switchgear to insure cor bus phasing from each source. 10. 11. 13. Control Power Transformers 1. Perform insulation-resistance tests. Perform measuremen from winding-to-winding and each winding-to-ground. Tes voltages shail be in accordance with Table 10.1 uniess, otherwise specified by manufacturer. Perform secondary wiring integrity test. Disconnect transformer at secondary terminals and connect secondar wiring to correct secondary voltage. Confirm potential at a devices. Verify correct secondary voltage by energizing primary winding with system voltage. Measure secondary voltage the secondary wiring disconnected. Verify correct function of control transfer relays located in switchgear with multiple power sources. Voltage Transformers 1. 3. Perform insulation-resistance tests. Perform measuremen from winding-to-winding and each winding-to-ground. Tes voltages shall be in accordance with Table 10.1 unless otherwise specified by manufacturer. Perform secondary wiring integrity test. Confirm correct potential at all devices. Verify secondary voltages. Verify operation of switchgear/switchboard heaters. “Optional 18 ATS-1999 o INSPECTION AND TEST PROCEDURES 1. a. | 7.4 Switchgear and Switchboard Assemblies (cont.) 3. Test Values } § : i Compare bus connection resistances to values of similar connections. Bolt-torque levels shall be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivalt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. if manufacturer's data is not available, investigate any values which deviate from similar bus by more than 50 percent of the lowest value. Insulation-resistance values for bus, control witing, and contro! power transformers shail be in accordance with manufacturer's published data. In the absence of manufacturer's published data, use Table 10.1. Values of insufation resistance tess than this table or manufacturer's minimum shall be investigated. Overpotential tests should not proceed until insulation-resistance levels are raised above minimum values. The insulation shail withstand the overpotential test voltage applied. > “Optional & ATS- 1999 19 oT SN aries a INSPECTION AND TEST PROCEDURES 7.2. Transformers 4. Dry Type 4, Air-Cooled, 600 Voit and Below - Small (467 kVA Single-Phase, 500 KVA Three-Phase, and Smaller) 1. Visual and Mechanical Inspections 1. Compare equipment nameplate data with drawings and specifications. 2, Inspect physical and mechanical condition, 3. Verify that resilient mounts are free and that any Shipping brackets have been removed. 4, Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordan with Section 7.2.1.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrica connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. *Optional @ 20 ATS- 1999 7. INSPECTION AND TEST PROCEDURES: 7.2 Transformers (cont) 4. Dry-Type (cont) 1 Air-Cooted, 600 Volt and Below — Small i 500 KVA Three-Phase, and Smaiter) 2 Electrical Tests an Perform resistance measurements through al bolted connections with a low-resistance ohmmeter, if applicable, in accordance with Section 7.2.1.1.1 (Visual and Mechanical Inspection). 2, Perform insulation-resistance tests winding-to-winding and each winding-to-ground with test voltage in accordance with Table 10.5. 3. Calulate polarization index. “4, Perform tums ratio tests at all tap positions. *5. Verity that as-left tap connections are as specified, “Optional 6 ATS — 1899 24 ne . REIT Ty | 7 INSPECTION AND TEST PROCEDURES 7.2 Transformers (Continued) 1. Dry-Type (cont.) 1. Air-Cooled, 600 Voit and Balow ~ Small (167 kVA Single-Phase, 500 kVA Three-Phase, and Smailer) (cont) 3. Test Values 1. Compare bolted connection resistances to values o similar connections. Bolt-torque levels should be in accardance with Tat 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed th high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's da is not available, investigate any values which deviat from similar connections by more than 50 percent a the lowest value. Insulation-resistance test values at one minute shai not be less than the values calculated in accordance with the formula in Table 10.5, Results shall be temperature corrected in accordance with Table 10 The polarization index shall be greater than 1.0 anc shall be tecorded for future reference, ‘Tums-ratio test results should not deviate more tha one-half percent from either the adjacent coils or th calculated ratio. “Optional 22 ATS- 1999 pn a a Pe 7 INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) “Optional 4, Dry-Type (cont) 2. Alt-Cooled, All Above 600 Volt and 600 Volt and Below ~ Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phase) 4. Visual and Mechanical inspection 4. Compare equipment namepiate data with drawings and specifications, Inspect physical, electrical, and mechanical condition. Verify that control and alarm settings on temperature indicators are as specified. Verify that cooling fans operate and that fan motors have correct overcurrent protection. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of fow-resistance ohmmeter in accordance with Section 7,2.1.2.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Perform specific inspections and mechanical tests as recommended by manufacturer. Verify that resilient mounts are free and that any shipping brackets have been removed. Verify that the core, frame, and enclosure groundings are correct. Verify the presence of transformer surge arresters. Verify that as-left tap connections are as specified. ATS— 1999 23 t INSPECTION AND TEST PROCEDURES 7.2. Transformers (cont.) 4. Dey Type {cont} Air-Cooled, All Above 600 Volt and 600 Volt and Below - Large (Greater than 167 kVA Single-Phase and 500 kVA Throe-Phas (cont) 2. Electrical Tests 1. “7. 10. Perform insulation-resistance tests winding-to-windir and each winding-to-ground with test voltage in accordance with Table 10.5. Calculate polarization index. Perform resistance measurements through all bolted connections with low-sesistance ohmmeter, if applicable, in accordance with Section 7.2.1.2.1 (Vis and Mechanical inspection). Perform power-factor or dissipation-factor tests in accordance with the test equipment manufacturer's published data. Perform a tums-ratio test on all tap connections. Ver that winding polarities are in accordance with nameplate. Perform an excitation-current test on each phase. Measure the resistance of each winding at each tap connection. Measure core insulation resistance at 500 volts de if core i insulated and if the core ground strap is removable. Perform an overpotential test on all high- and low- voltage windings-to-ground. Verify correct secondary voltage phase-to-phase and phase-to-neutral after energization and prior to loadin *Optional 24 ATS—1999 @ 7. INSPECTION AND TEST PROCEDURES: 7.2 Transformers (cont.) ‘Dry Type (cont) Air-Cooled, All Above 600 Volt and 600 Volt and Below ~ Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phase) (cont.) 3. Test Values 1. Compare bolted connection resistances to values of similar connections. 2 Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. 3. Microhm or miliivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. {f manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. 4, Insulation-resistance test values at one minute should Rot be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14, 5. The polarization index shall be greater than 1.0 and shall be recorded for future reference, 6. Tums-ratio test results shall not deviate more than ‘one-half percent from either the adjacent coils or the calculated ratio. 7. Cy and C, dissipation-factor/power-factor values will vary due to support insulators and bus work utilized on dry transformers. The following is expected on Cia, power factors: Power Transformers: one percent or less Distribution Transformers: three percent or less ‘Consult transformer manufacturer's or test equipment manufacturer's data for additional information. “Optional @ ATS- 1989 25 7. INSPECTION AND TEST PROCEDURES 7.2. Transformers (cont.) 4. Dry Type (cont) 2 Air-Cooled, All Above 600 Volt and 600 Volt and Below - Large (Greater than 167 kVA Single-Phase and 500 kVA Three-Phas (cont.) 8. 10. 11. Winding resistance test results, after factoring in temperature corrections, should compare within on percent of factory obtained results except in instan¢ of extremely low resistance values. Typical excitation current test data pattem for a thre legged core transformer is two similar current readi and one lower current reading. Core insulation resistance values should be comparable to factory obtained results but not less t ‘one megohm at 800 volts de. AC overpotential test shall not exceed 75 percent of factory test voltage for one minute duration. DC overpotential test shall nat exceed 100 percent of th factory RMS test voltage for one minute duration. Tk insulation shall withstand the overpotential test volta applied. “Optional 26 ATS—1999 eer t INSPECTION AND TEST PROCEOURES ‘ 12 Transformers (Cont,) 2. Liguid-Fittled 1. Visual and Mechanical Inspection 1 16. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Verify removal of any shipping bracing after final placement. Inspect impact recorder prior to unloading, if applicable, Verify settings and operation of afl temperature devices, if applicable. Verify that cooling fans and pumps operate correctly and that fan and pump motors have correct overcurrent protection, if applicable. Verify operation of all alarm, control, and trip circuits from temperature and level Indicators, pressure relief device, and fauit pressure refay, if applicable. Inspect all bolted electrical connections for high resistance using one of the following methods: 4. Use of Jow-resistance ohmmeter in accordance with Section 7.2.2.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10,12. 3. Perform thermographic survey in accordance with Section 9, Verify correct liquid tevel in alt tanks and bushings. Verify that positive pressure is maintained on nitrogen- blanketed transformers. *Optionat @ ATS-1999 27 (gee 7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont,) Liquid-Filled (cont.) 2. 11. 12. 13. Perform specific inspections and mechanical tests as recommended by manufacturer. Verify correct equipment grounding. Verify the presence of transformer surge arresters. 2. Electrical Tests 1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, i accordance with Section 7.2.2.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests, winding-to-winding an each winding-to-ground in accordance with Table 10.5. Calculate polarization index. Perform turns-ratio tests at all tap positions. Test load tap-changer in accordance with Section 7.12, if applicable. Perform insulation power-factor/dissipation-factor tests on windings in accordance with test equipment manufacturer published data. Perform power-factor/dissipation-factor tests or hot collar watts-loss tests on bushings in accordance with test equipment manufacturer's published data. Perform excitation-current tests in accordance with test equipment manufacturer's published data. Measure resistance of each high-voltage winding in each load tap-changer position. Measure resistance of each lo. voltage winding in each load tap-changer position, if applicable. “Optional 28 ATS—1999 @ 7 {NSPECTION AND TEST PROCEDURES 7.2. Transformers (cont.) 2, Liquid-Filled (cont) 10. tt. 12. 413. 14. If core ground strap is accessible, measure core insulation resistance at 500 voits de. Measure the percentage of oxygen in the nitrogen gas blanket, if applicable. Remove a sample of insulating liquid in accordance with ASTM D-923, Sample shall be tested for the following: 4. Dielectric breakdown voltage: ASTM D-877 and/or ASTM D-1816.. 2, Acid neutralization number: ANSI/ASTM D-974. *3, Specific gravity: ANSVASTM 0-1298. 4, interfacial tension: ANSI/ASTM D-971 or ANSYVASTM D-2285. 5. Color; ANSI/ASTM D-1500. Visual Condition: ASTM D-1524. “7. Water in insulating liquids: ASTM D-1593, (Required ‘on 25 kV or higher voltages and on alll silicone-filled units.) *8. Measure dissipation factor or power factor in accordance with ASTM 0-924. Remove a sample of insulating liquid in accordance with ASTM 03613 and perform dissolved gas analysis (GA) in accordance with ANSVIEEE C57.104 or ASTM D-3612, Perform tests on all instrument transformers in accordance with Section 7.10, *Optional @ ATS— 1999 29 on ee ee 7. INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont) 2. Liquid-Filled (cont) 3. Test Values 1. 10. Compare bolted connection resistance to values of similar connections. Balt-torque levels should be in accordance with Table 10.1 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacture published data. If manufacturer's data is not available, investigate any values which deviate from similar connecti by more than 50 percent of the lowest value. Insulation-resistance test values at one minute should not fess than the values calculated in accordance with the forr in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14. The polarization index shall be greater than 1.0 and shall | recorded for future reference. Tums-ratio test results shall not deviate more than one-ha percent from either the adjacent coils or the calculated rat Maximum power factor of liquid-filled transformers shall be accordance with manufacturer's published data. Representative values are indicated in Table 10.3. investigate bushing power factors and capacitances that \ from nameplate values by mote than ten percent, investig any bushing hot collar watts-loss results that exceed the t equipment manufacturer's published data. Typical excitation-current test data pattem for threetegge core transformer is two similar current readings and one I current reading. Winding-rasistance test results, after factoring in tempera’ correction, should compare within one percent of factory obtained results except in instances of extremely low resistance values. “Optional 30 ATS - 1999 @ w INSPECTION AND TEST PROCEDURES 7.2 Transformers (cont.) 2 Liquid-Filled (cont.) 11. Consult manufacturer if core insulation is tess than one megohm at 500 volts de, : 12. Investigate presence of oxygen in the gas nitragen blanket, 13. Insulating liquid test results shai! be in accordance with Table 10.4. 14. Evaluate results of dissolved-gas analysis in accordance with ANSI/IEEE Standard (57,104. Use results as baseline for future tests, fre eters “Optional 6 ATS~ 1999 31 fe tara eR MNT a pe oe 7. _ INSPECTION AND TEST PROCEDURES 7.3 Cables 4. Low-Voltage, Low-Energy - Reserved 2. Low-Voitage, 600 Volt Maximum 1 ‘Visual and Mechanical Inspection 1. Compare cable data with drawings and specifications. 2. Inspect exposed sections of cables for physical damage correct connection in accordance with single-line diagrar 3. Inspect all bolted electrical connections for high resistan: using one of the following methods: 4. Use of low-resistance ohmmeter in accordance wi Section 7.3.2.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method i accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. 4. Inspect compression-applied connectors for correct cable match and indentation. 5. Verify cable color coding with applicable specifications ar the Nationai Electrical Code. *Optional 7) 32 ATS- 1999 —_—>s_C og 7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.) Low-Voltage, 600 Volt Maximum (cont.) 2. Electrical Tests 1 3. Perform insulation-resistance test on each conductor with respect to ground and adjacent conductors. Applied potential shall be 500 volts de for 300 voit rated cable and 1000 volts dc for 600 voit rated cabfe. Test duration shall be one minute. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.3.2.1 (Visual and Mechanical Inspection). Perform continuity test to insure correct cable connection. 3. Test Values 1. Compare bolted connection resistance to values of similar cons Bolt-torque levels shautd be in accordance with Table 10.12 unless otherwise specified by the manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normat range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than §0 percent of the lowest value. Minimum insulation-resistance values should not be less than 50 megohms. Investigate deviations between adjacent phases. *Optional @ ATS—1999 33 7 INSPECTION AND TEST PROCEDURES. 7.3 Cables (cont) 3. Medium-Voltage, 69 KV Maximum 1. Visual and Mechanical Inspection 1. 2. Compare cable data with drawings and specifications. Inspect exposed sections of cables for physical damage Inspect all bolted electrical connections for high resistan: using one of the following methods: 1. Use of low-resistance ohmmeter in accordance w Section 7.3.3.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method i accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9, Inspect compression-applied connectors for correct cable match and indention. Inspect for shield grounding, cable support, and terminati Verify that visible cable bends meet or exceed ICEA and/ manufacturer's minimum allowable bending radius. Inspect fireproofing in common cable areas, if specified. If cables are terminated through window-type current transformers, make an inspection to verify that neutral ani ground conductors are correctly placed and that shields a correctly terminated for operation of protective devices. ‘Visually inspect jacket and insulation condition. Inspect for correct identification and arrangements. “Optional 34 ATS - 1999 ® ee ——-———————__ a... 7. INSPECTION AND TEST PROCEDURES 7.3 *Optionat Cables (cont) 3. Medium-Voltage, 69 kV Maximum (cont.) 2. Electrical Tests t. Perform a shieid-continuity test on each power cable by ohmmeter method. Perform an insulation-resistance test utilizing a megohmmeter with a voltage output of at least 2500 volts. Individually test each conductor with all ther conductors and shields grounded. Test duration shall be one minute. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.3.3.1 (Visual and Mechanical Inspection). Perform a de high-potential test on afl cables, Adhere to all precautions and limits as specified in the applicable NEMAVJICEA Standard for the specific cable. Perform tests in accordance with ANSI/IEEE Standard 400. Test procedure shall be as follows, and the results for each cable test shall be recorded as specified herein. Test voltages shall nat exceed 80 percent of cable manufacturer's factory test value or the maximum test voltage in Table 10.6. 4. Insure that the input voltage to the test set is regulated. 2. Current-sensing circuits in test equipment shall measure only the leakage current associated with the cable under test and shall not include internal teakage of the test equipment. 3. Record wet- and dry-bulb temperatures or relative humidity and temperature. 4. Test each section of cable individually. 5. Individually test each conductor with all other conductors grounded. Ground alll shields. 6. ‘Terminations shali be adequately corona-suppressed by guard ring, field reduction sphere, or other suitable methods as necessary. @ ATS-1999 35 7. INSPECTION AND TEST PROCEDURES 7.3 Cables (cont.) Medium-Voltage, 69 kV Maximum (cont.) 3. 7 10. Insure that the maximum test voltage does not exc the limits for terminators specified in ANSVIEEE Standard 48, IEEE 386, or manufacturer's specifications, Apply a dc high-potential test in at Jeast five equal increments until maximum test voltage is reached. increment shall exceed the voltage rating of the ca Record dc leakage current at each step after a constant stabilization time consistent with system charging current. Raise the conductor to the specified maximum tes! voltage and hold for 15 minutes on shielded cable five minutes on nonshielded cable. Record reading leakage current at 30 seconds and one minute anc ‘one minute intervals thereafter. Reduce the conductor test potential to zero and measure residual voltage at discrete intervals. Apply grounds for a time period adequate to drain insulation stored charge. When new cables are spliced into existing cables, dc high-potential test shail be performed on the ne cable prior to splicing in accordance with Section 7 After test results are approved for new cable and tl splice is completed, an insulation-resistance test a shield-continuity test shall be performed on the len of new and existing cable including the splice. Afte satisfactory insulation-resistance test, a de high- potential test shalt be performed on the cable utilizi test voltage acceptable to owner and nat exceedin: percent of factory test value. *Optional 36 ATS - 1999 @ 7. INSPECTION AND TEST PROCEDURES 7.3 Gables (cant) 3. Medium-Voltage, 68 kV Maximum (cont.) 3. Teast Values. 1. | é e | “8. ‘Compare bolted connection resistance to values of similar con Boit-torque fevels should ba in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. if manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Shielding shall exhibit continuity. Investigate resistance values in excass of ten ahms per 1000 feet of cable. Graphic plots may be made of leakage cutrent versus step voltage at each increment and leakage current versus time at final test voltages. 1. The step voltage slope should be reasonably linear. 2. Capacitive and absorption current should decrease continually until steady state leakage is approached. “Optional FE ne ee a & ATS~1999 37 7 INSPECTION AND TEST PROCEDURES. 7.3 Cables (cont) 4. High-Voltage 1. Visual and Mechanical Inspection 1. 2 10. Compare cable data with drawings and specifications. Inspect exposed sections of cables for physical damag Inspect alt bolted electrical connections for high resista using one of the following methods: 1. Use of low-resistance ohmmeter in accordance Section 7.3.4.2 (Electricai Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench metho: accordance with manufacturer's published data Table 10.12. 3. Perform thermographie survey in accordance wi Section 9. Inspect compression-applied connectors for correct cal match and indention. Inspect for shield grounding, cable support, and termin Verify that visible cable bends meet or exceed ICEA at manufacturer's minimum allowable bending radius. Inspect fireproofing in common cable areas, if specifiec If cables are terminated through window-type current transformers, make an inspection to verity that neutral ground conductors are correctly placed and that shield correctly terminated for operation of protective devices Visually inspect jacket and insulation condition, Inspect for correct identification and arrangements. “Optional 38 ATS —1999 & =) 7. INSPECTION AND TEST PROCEDURES, 7.3 Cables (cont) 4. High-Voltage (cont,) 2, Electrical Tests 1. Perform a shieid-continuity test on each power cable by ohmmeter method. Perform an insulation-resistance test utilizing a megohmmeter with a voltage output of at least 2500 volts, individually test each conductor with all other conductors and shields grounded, Test duration shall be one minute. Perform resistance measurements through all bolted connections with jow-resistance ohmmeter, if applicable, in accordance with Section 7.3.4.1 (Visual and Mechanical Inspection). Perform a dc high-potential test on all cables. Adhere to ai! precautions and limits as specified in the applicable NEMAJICEA Standard for the specific cable, Perform tests in accordance with ANSI/IEEE Standard 400. Test procedure shall be as follows, and the results for each cable test shail be recorded as specified herein. Test voltages shall not exceed 80 percent of cable manufacturer's factory test value or the Maximum test voltage in Table 10.6. 1. Insure that the input voltage to the test set is regulated. 2. Current-sensing circuits in test equipment shall measure only the leakage current associated with the cable under test and shail not inciude internal leakage of the test equipment. 3. Record wet- and dry-bulb temperatures or relative humidity and temperature. 4. Test each section of cable individually. 5. Individually test each conductor with all other conductors grounded. Ground all shields. 6. Terminations shail be adequately corona-suppressed by guard ring, field reduction sphere, or other suitable methods as necessary. “Optional & ATS-1999 39 7. INSPECTION AND TEST PROCEDURES: 7.3 Cables (cont) High-Voltage (cont) 4 7. 10. 11. 12. Insure that the maximum test voltage does not exces the limits for terminators specified in ANSIIEEE Standard 48 or manufacturer's specifications. Apply a de high-potential test in at least five equal increments until maximum fest voltage is reached. N increment shal! exceed the voltage rating of the cabl Record de leakage current at each step after a constant stabilization time consistent with system charging current. Raise the conductor to the specified maximum test voitage and hold for 16 minutes on shielded cable an five minutes on nonshielded cable. Record readings : leakage current at 30 seconds and one minute and a ‘one minute intervals thereafter. Reduce the conductor test potential to zero and measure residual voitage at discrete intervals. Apply grounds for a time period adequate to drain ail insulation stored charge. When new cables are spliced into existing cables, the dc high-potential test shall be performed on the new cable prior to splicing in accordance with Section 7.3.2 After test results are approved for new cable and the splice is completed, an insulation-resistance test and « shield-continuity test shall be performed on the tength of new and existing cable including the spice. After a satisfactory insulation-resistance test, a dc high- potential test shall be performed on the cable utilizing : test voltage acceptable to awner and not exceeding 6¢ percent of factory test value. *Optional 40 ATS- 1999 @ High-Voltage (cont,) 3. Test Values 1. 2 “5. 7. _ INSPECTION AND TEST PROCEDURES 7.3 Gables (cont) 4 ‘Compare bolted connection resistance to values of similar connections. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or miliivolt drop vaiues shall not exceed the high fevels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Shielding shall exhibit continuity. Investigate resistance values in excess of ten ofims per 1000 feet of cable. Graphic plots may be made of leakage current versus step voltage at each increment and leakage current versus time at final test voltages. 4. ‘The step voltage slope should be reasonably linear. 2. Capacitive and absorption current should decrease continually until steady state leakage is approached. 6 ATS—1999 41 7. INSPECTION AND TEST PROCEDURES 7.4 Metal-Enclosed Busways 1. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications, Inspect busway for physical damage and correct connection in accordance with single-line diagram. Inspect for appropriate bracing, suspension, alignment, and enclosure ground. Inspect all bolted electrical connections for high resistance using o! of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.4.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections t calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9 Confitm physical orientation in accordance with manufacturer's labels to insure adequate cooling. Examine outdoor busway for removal of ‘weep-hole” plugs, if applicable, and the correct installation of joint shield. Electrical Tests. 41. Measure insulation resistance of each busway, phase-to-phase anc phase-to-ground for one minute, in accordance with Table 10.1. Perform an averpotential test on each busway, phase-to-ground wit phases not under test grounded, in accordance with manufacturer's published data. If manufacturer has no recommendation for this tes it shall be in accordance with Table 10.17. Where no dc test value i shown in Table 10.17, ac value shall be used. The test voltage shal be applied for one minute. “Optional 42 ATS—1999 & [" | ae pe INSPECTION AND TEST PROCEDURES 7.4 Metal-Enclosed Busways (cont) 3. Perform contact-fesistance test on each connection point of noninsulated busway. On insulated busway, measure resistance of assembled busway sections and compare values with adjacent phases, Perform phasing test on each busway tie section energized by ‘separate sources, Tests must be performed from their permanent sources, 3. Test Values 1. Campare bolted connection resistances and bus joint resistances to values of similar connections. Bus boit-torque feveis should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data, if manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. insuiation-resistance test voltages and resistance vatues shail be in accordance with manufacturer's published data or Table 10.1. Minimum resistance values are for a nominal 1000 foot busway run. Use the following formula ta convert the measured resistance value to the 1000-foot nominal value: ngth of Rui con “Measured Resistance x “S087 °Run Converted values of insulation resistance less than those in Table 10.1 or manufacturer's minimum shail be investigated. Overpotential tests shall not proceed until insulation-resistance levels are raised above minimum values, The insulation shail withstand the overpotential test voltage applied. *Optional ES) ATS~1999 43 7. INSPECTION AND TEST PROCEDURES 7.6 Switches 1. Air Switches: 1. Low-Voltage 1. Visual and Mechanical Inspection 1 10. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended lubricants. Verify appropriate anchorage and required area clearances. Verify appropriate equipment grounding. Verify correct blade alignment, blade penetration, travel stops, and mechanical operation. Verify that fuse sizes and types are in accordance with drawings and short-circuit and coordination studies. Verify that each fuse holder has adequate mechanical ‘support. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.5.1.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's, published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Test all interlocking systems for correct operation and sequencing. *Optionai 44 ATS ~ 1999 @ See 7. INSPECTION AND TEST PROCEDURES. 7.8 Switches (cont) 1. Air Switches (cant) 4. Low-Voltage (cont.) tt 12. Verify correct phase barrier materials and installation. Inspect all indicating and control devices for correct operation. 2 Electrical Tests 4. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer's published data or Table 10.1. Measure contact-resistance across each switchblade and fuse holder. Measure fuse resistance. Perform resistance measurements through all bolted connections with low-resistance chmmeter, if applicable, in accordance with Section 7.5.1.1.1 (Visual and Mechanical Inspection). Verify heater operation. "Optional fe) ATS-1999 45 a INSPECTION AND TEST PROCEDURES 7.6 Switches (cont.) t Air Switches (cont) Low-Voltage (cont.) 1 3. Test Values 4. Compare bolted connection resistance to values of similar connections. Bolt-torque levels should be in accordance with Tab 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's dat is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Minimum insulation resistance shall be in accordanc with manufacturer's published data or Tabie 10.1. Investigate any contact resistance values which deviate from adjacent poles or similar switches by more than 25 percent. Investigate fuse-resistance values that deviate from each other by more than 15 percent. “Optional 46 ATS—1999 INSPECTION AND TEST PROCEDURES 7.6 Switches (cont) 1. Air Switches (cont) 2 Medium-Voltage, Metal-Enciosed 14, Visual and Mechanical inspection 4. Compare equipment nameplate data with drawings and specifications. 2. Inspect physical and mechanical condition. 3. Confirm correct application of manufacturer's recommended lubricants. 4. Verify appropriate anchorage and required area clearances. 5. Verify appropriate equipment grounding. travel stops, and mechanical operation. 7. Verify that fuse sizes and types are in accordance with drawings and short-circuit and coordination studies. 8. Verify that expulsion-limiting devices are in place on all holders having expulsion-type elements. 9. Verify that each fuse holder has adequate mechanical support, 10. — Inspect ail bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.5.1.2.2 (Electrical Tests). | 7. i i | { 6. Verify correct blade alignment, blade penetration, 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. *Optional @ ATS- 1999 47 3 t INSPECTION AND TEST PROCEDURES 7.5 Switches (cont) Air Switches (cont.) 2. Medium-Voltage, Motal-Enclesed (cont) 4 11, 12. 13. 14, Test all interlocking systems for correct operation and sequencing. Verify correct phase-barrier materials and installation. Compare switchblade clearances with industry standards. Inspect all indicating and control devices for correct operation, 2 Electrical Tests 1. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Te voltage shail be in accordance with manufacturer's published data or Table 10.1. Perform an overpotential test on each pole with switch closed. Test each pole-to-ground with all other poles grounded, Test voltage shall be in accordance with manufacturer's published data or Table 10.2. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.5.1.2.1 (Visui and Mechanical Inspection). Measure contact resistance across each switchblade and fuse holder. Measure fuse resistance. Verify heater operation. “Optional 48 ATS ~ 1999 @ 7 INSPECTION AND TEST PROCEDURES 75 Switches (cont) 4, Air Switches (cont.) 2. Medium-Voltage, Metal-Enclosed (cont.) 3. Test Values 1. Compare bolted connection resistances to values of similar connections. Bolt-torque levels should be in accordance with Table 10,12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high fevels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. The insulation should withstand the overpotential test voltage applied. Minimum insulation resistance shall be in accordance with manufacturer's published data or Table 10.1. Investigate fuse resistance values that deviate from each other by more than 15 percent. “Optional @ ATS-1999 49 7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont) 4. Air Switches (cont.) 3. High- and Medium-Voltage, Open 4. Visual and Mechanical inspection 4. Compare equipment nameplate data with drawings and specifications. 2. Inspect physical and mechanical condition. 3. Confirm correct application of manufacturer's. recommended lubricants. 4. Verify that grounding is in accordance with industry standards and project specifications. 5, Inspect all bolted electrical connections for high resistance using one of the following methods: 1, Use of low-resistance ohmmeter in accordanc: with Section 7,5.1.3.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10. 12. 3. Perform thermographic survey in accordance with Section 9. 6. Perform mechanical operator tests in accordance with manufacturer's published data. 7. Verify correct operation and adjustment of motor operator limit-switches and mechanical interlocks, if applicable, 8. Verify correct blade alignment, blade penetration, travel stops, arc interrupter operation, and mechanical operation, if applicable. “Optional @ §0 ATS-1999 = “Optional Switches (cont) 1. Air Switches (cont) 3. High- and Medium-Voltage, Open (cont) 2. Electrical Tests 7. INSPECTION AND TEST PROCEDURES 75 | 1. 1 t j Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with switch closed and across each open pole for one minute. Test voltage shall be in accordance with manufacturer's published data or Table 10.1. Perform an overpatential test on each pole with switch closed, Test each pole-to-ground with all other poles grounded. Test voltage shall be in accordance with manufacturer's published data or Table 10.11. Perform contact-resistance test across each switchblade and fuse holder. 3. Test Values 1. Compare bolted connection resistances to values of similar connections, Boit-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivalt drop vaiues shall not exceed the high levels of the normal tange as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Insulation resistance values shall be in accordance with manufacturer's data or Table 10.1. The insulation shall withstand the overpotential test voltage applied. Contact resistance shalll be determined in microhms. Investigate any value exceeding 500 microhms or any values which deviate from adjacent poles or similar switches by more than 25 percent. & ATS~1999 64 i (INSPECTION AND TEST PROCEDURES 7.8 Switches (cont.) 2 Oil Switches: Medium-Voltage 1. ‘Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Inspect anchorage, alignment, and grounding. Perform all mechanical operation and contact alignment tes ‘on both the switch and its operating mechanism. Check each fuse holder for adequate support and contact. Verity that fuse sizes and types correspond to drawings. ‘Test all electrical and mechanical interlock systems for corre operation and sequencing, Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.5.2.2 (Electrical Tests). 2. Verity tightness of accessible boited electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.72. 3. Perform thermographic survey in accordance with Section 9. Verify that insulating oil level is correct. *Optional 52 ATS - 1999 & 7. _ INSPECTION AND TEST PROCEDURES 78 ‘Switches (cont.) 3. Vacuum Switches: Medium-Voltage 1. Visual and Mechanical inspection 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanicai condition. inspect anchorage, alignment, and grounding. Perform all mechanical operation and contact alignment tests ‘on both the switch and its operating mechanism. Check each fuse holder for adequate support and contact, Verify that fuse sizes and types correspond to drawings, Test all electrical and mechanical interlock systems for correct operation and sequencing, Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.5.3.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Verify that insulating oil level is correct, if appiicable. “Optional & ATS-1989 55 7. INSPECTION AND TEST PROCEDURES 7.5 Switches (cont.) 3. Vacuum Switches: Medium-Voltage (cont.) 2. Electrical Tests 4. *8. Perform resistance measurements through all bolted electrica connections with a low-resistance ohmmeter, if applicable. See Section 7.5.3.1 (Visual and Mechanica! inspection). Perform a contact-resistance test. Verify open and close operation from control devices, if applicable. Perform insulation-resistance tests pole-to-pole, pole-to- ground, and across open poles at 2500 volts minimum. Perform vacuum bottle integrity (overpotential) test across each vacuum bottle with the switch in the open position in strict accordance with manufacturer's published data. Do not exceed maximum voitage stipulated for this test. Provide adequate barriers and protection against x-radiation during this test. Do not perform this test unless the contact displacement of each interrupter is within manufacturer's tolerance. (Be aware that some dc high-potential test sets are half-wave sectified and may produce peak voltages in excess of the switch manufacturer's recommended maximum.) Remove a sample of insulating liquid, if applicable, in accordance with ASTM D-923. Sample shail be tested in accordance with the referenced standard. 4 Dielectric breakdown voltage: ASTM D-877 2. Calor: ASTM D-1500 3. Visual condition: ASTM D-1524 Perform insulation-resistance tests on all control wiring at 4009 volts de. For units with solid-state components, follow manufacturer's recommendations. Perform an overpotential test in accordance with manufacturer's published data. *Optional 86 ATS— 1999 & 75 ical Switches (cont) 7 INSPECTION AND TEST PROCEDURES: Vacuum Switches: Medium-Voltage (cont) 3. Test Values 1. Compare bolted connection resistances to values of similar connections. Bolt-torque levels should be in accordance with Table 10.12 untess otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from adjacent poles or similar switches by more than 50 percent of the lowest value, Contact displacement shall be in accordance with factory recorded data marked on the nameplate of each vacuum ‘switch or bottle. ‘The vacuum bottles shall withstand the overpotential voltage applied. ‘Control wiring insulation resistance should be a minimum of two megohms. The insulation shail withstand the overpotential test voltage applied, Insulating liquid test results shall be in accordance with Table 10.4. 4. SF, Switches: Medium-Voltage - Reserved 5. Cutouts - Reserved *Optional & ATS-1999 57 1. INSPECTION AND TEST PROCEDURES 7.6 — Circuit Breakers (cont.} Low-Voltage (cont.) 1. Insulated Case/Molded Case (cont) 3. Test Values 1. Compare bolted connection resistance to values of similar connections. Bott-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer Microhm or millivolt drop values shail not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Circuit breaker insulation resistance should be in accordance with Table 10.1, Control wiring insulation resistance should be a minimum of two megohms. Trip characteristic of breakers shall fall within manufacturer's published time-current characteristic tolerance band, including adjustment factors. If manufacturer's curves are Not available trip times shall be equal to or less than the values shown in Table 10.7. Circuit breakers exceeding specified trip time at 300 percent of pickup shall be tagged defective. Instantaneous pickup vaiues of moided-case circuit breakers shail be within the tolerances shown in Table 10.8. *Optional 60 ATS-1999 & 7 INSPECTION AND TEST PROCEDURES, 76 *Optional Circuit Breakers (cont) 1. Low-Voltage (cont) 2. Power 1. Visual and Mechanical Inspection t. 10. Compare nameplate data with drawings and specifications, Inspect physical and mechanical condition. Confirm correct application of manufacturer's tecommended lubricants. Inspect anchorage, alignment, and grounding. Inspect arc chutes. inspect moving and stationary contacts for condition, wear, and alignment. Verify that all maintenance devices are available for servicing and operating the breaker. Verify that primary and secondary contact wipe and other dimensions vital to satisfactory operation of the breaker are correct. Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism. Inspect all bolted electrical connections for high tesistance using one of the following methods: 4 Use of iow-resistance ohmmeter in accordance with Section 7.6.1.2.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrencht method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Verify cell fit and element alignment. Verify racking mechanism. ATS—1999 61 7. INSPECTION AND TEST PROCEDURES. 7.6 Circuit Breakers (cont) 4 Low-Voltage (cont.) 2. Power (cont) 2. Electrical Tests 1. 2 “4. 10. “11. Perform a contact-resistance test. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.1.2.1 (Visual and Mechanical inspection). Perform an insuiation-resistance test at 1000 volts de from pole-to-pole and from each pole-to-ground with breaker closed and across open contacts of each phase. Perform insulation-resistance tests at 1000 volts de on all control wiring. Do not perform the test on wiring connected to solid state components. Make adjustments for the final settings in accordance with the coordination study supplied by owner, Determine minimum pickup current by primary current Injection. Determine long-time delay by primary current injection. Determine short-time pickup and delay by primary current injection. Determine ground-fault pickup and delay by primary current injection. Determine instantaneous pickup value by primary current injection. Verity the calibration of all functions of the trip unit by means of secondaty injection. “Optional 62 ATS-1999 @ oo en ee r INSPECTION AND TEST PROCEDURES: 7.6 Circuit Breakers (cont) 1. Low-Voltage (cont) 2, Power (cont) 12. Activate auxiliary protective devices, such as ground- fault or undervoltage relays, to insure operation of shunt trip devices. Check the operation of electrically- operated breakers in their cubicles. 13. Verify correct operation of any auxiliary features such as trip and pickup indicators, zone interlocking, electrical close and trip operation, trip-free, and antipump function and verify trip unit battery condition. 14. Verify operation of charging mechanism. 3. Test Values 1. Compare bolted connection resistance to values of ‘similar connections. 2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. 3. Microhm or millivolt drop values shail not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. 4 Circuit breaker insulation resistance should be in accordance with Table 10.1. 5. Central wiring insulation resistance should be a minimum of two megohms. 6. Trip characteristics of breakers shall fall within manufacturer's published time-current tolerance bands. *Optional & ATS-1999 63 7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont) 4 Air 1. Visual and Mechanical Inspection 1. Compare nameplate data with drawings and specifications. inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended I Inspect anchorage, alignment, and grounding. Inspect are chutes. Inspect moving and stationary contacts for condition, wear, and alignment. Verify that all maintenance devices are available for servicing and operating the breaker. Verify that primary and secondary contact wipe and other dimensions vital to satisfactory operation of the breaker are correct. Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism. inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.6.2.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3, Perform thermographic survey in accordance with Section 9. Check cell fit and element alignment. “Optional 64 ATS~1999 ® cto gree 7 INSPECTION AND TEST PROCEDURES 76 *Optional Circuit Breakers (cont.) 2 Medium-Voltage (cont) 1 Air (cont) 10. 11. “412. 13, ‘Check racking mechanism. Inspect puffer operation. Perform circuit breaker timing tests. Record as-found and as-left operation-counter readings. 2. Electrical Tests 41. 2. *4, 6. Perform a contact resistance test. Measure insulation resistance pole-to-pole, pole-to- ground, and across open poles. Use a minimum test voltage of 2500 volts. Perform resistance measurements through alll bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.2.1.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests at 1000 volts dc on all contro{ wiring. Do not perform the test on wiring connected to solid-state components. With breaker in the test position, make the following tests: 1. Trip and close breaker with the control switch. 2. Trip breaker by operating each of its protective relays. 3. Vetify trip-free and antipump function. *4. Test trip and close circuit at reduced control voltages, if applicable. Perform dissipation-factor/power-factor test with breaker in both open and closed positions. & ATS-—1999 65 7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2. Medium-Voltage (cont) 1. Air(cont,) “7. Perform an overpotentiat test in accordance with manufacturer's published data. 8. Measure blow-out coil circuit resistance. 3. Test Values 1. Compare bolted connection resistance to values of similar connections. 2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. 3. Microhm or millivolt drop values shall not exceed the high fevels of the normal range as indicated in the manufacturer's published data. [f manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. 4. Circuit breaker insulation resistance should be in accordance with Table 10.1. 6. Control wiring insulation resistance should be a minimum of two megohms. 6. _Dissipation-factor/power-factor test results shall be compared with previous tests of similar breakers or manufacturer's published data. 7. The insulation shall withstand the overpotential test voltage applied. 8. Minimum pickup for trip and close coils shall conform to manufacturer's published data. *Optional a) 66 ATS—1999 7 INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont) 2. Medium-Voltage {cont) 2 oi 1. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. 2. inspect physical and mechanical condition. 3. Confirm correct application of manufacturer's recommended fubricants. 4, Inspect anchorage, alignment, and grounding. 5. Verify that breather vents are clear, 6. Perform ail mechanical operation and contact alignment tests on both the circuit breaker and its operating mechanism in accordance with manufacturer's published data. 4 7. Jf performing internal inspection: 4. Remove oil. Lower tanks or remove manhole covers as necessary. Inspect bottom of tank for broken parts and debris. 2. Inspect lift rod and toggle assemblies. contacts, interrupters, bumpers, dashpots, bushing current transformers, tank liners, and gaskets. 3. ‘Slow-close breaker and check for binding, friction, contact alignment, penetration, and overtravel, Verify that all phases make contact simultaneously. 4, Refill tank(s) with filtered oil to correct levels. “Optional @ ATS—1999 67 7. _ INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) Medium-Voltage (cont.) 2, Oif (cont) 8. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.6.2.2.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9, 9. Test alarms and lockouts for pneumatic and/or hydraulic operators as recommended by the manufacturer. 10. — Perform circuit breaker time-travel analysis. 11. Record as-found and as-left operation counter readings. 2. Electrical Tests 1. Perform a contact resistance test. 2. Remove a sample of insulating liquid in accordance with ASTM D-923. Sample shall be tested for the following: 1 Dielectric breakdown voltage: ASTM D-877. 2. Color: ANSI/ASTM B-1500. 3. Power factor: ASTM D-924. “4. Interfacial tension: ANSI/ASTM D-971 or ANSI/ASTM D-2285. 5. Visual condition: ASTM D-1524. *Optional @ 68 ATS ~1999 : Pe 7.6 Circuit Breakers (cont) - 7. INSPECTION AND TEST PROCEDURES. 2, Madium-Voltage (cont) 2 Oil(cont) 3. *10. “11. Trip circuit breaker by operation of each protective device. Perform insulation-resistance tests pole-to-pole, pole- to-ground, and across open poles at 2500 voits minimum. : Perform resistance measurements through ail bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.8.2.2.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests on all control wiring at 1000 volts de. Do not perform this test on wiring connected to solid-state relays. Perform dissipation factor/power factor tests on each Pole with breaker open and each phase with breaker closed. Determine tank loss index. Perform dissipation-factor/power-factor tests on ¢ach bushing. Use conductive straps and hot collar Procedures if bushings are not equipped with a power- factor tap. Verify trip, close, trip-free, and antipump functions. Perform minimum pickup voltage tests on trip and close coils. Perform an overpotential test in accordance with manufacturer's instructions, *Optional & ATS -—1999 69 7 INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 2, Medium-Voltage {cont) 2 Oil (cont) 3. Test Values 4. 11. *Optional 70 ATS - 1999 Compare bolted connection resistance to values of similar connections. Boit-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Compare circuit breaker travel and velocity values to manufacturer's acceptable limits. Insulating-liquid test results should comply with Table 10.4. Circuit breaker insulation resistance should be in accordance with Table 10.1. Control wiring insulation resistance should be a minimum of two megohms. Dissipation-factor/power-factor test results and tank loss index shall be compared to manufacturer's published data. In the absence of manufacturer's published data, the comparison shall be made to similar breakers. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings. The insulation shall withstand the overpotential test voltage applied. Minimum pickup for trip and close coils shail conform to manufacturer's published data. & vine 7.5 vee _ , ! | Circuit Breakers (cont) 7. INSPECTION AND TEST PROCEOURES 2 Medium-Voltage {cont} 3. Vacuum 1. Visual and Mechanical inspection 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Confirm correct appiication of manufacturer's secommended lubricants. Inspect anchorage, alignment, and grounding. Perform ait mechanical operational tests on both the circuit breaker and its operating mechanism. Measure critical distances such as contact gap as recommended by manufacturer. Inspect all boited electrical connections for high resistance using one of the following methods: 1. Use of iow-resistance ohmmeter in accordance with Section 7.6.2.3.2 (Electrical Tests). 2 Verity tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Perform timing tests. Record as-found and as-left operation counter readings. > ? “Optional & ATS~1999 71 7. INSPECTION AND TEST PROCEQURES 7.6 Clreuit Breakers (cont) 2. Medium-Voltage (cont) 3. Vacuum {cont.) 2. Electrical Tests 1. *2. “10. “411. Perform a contact-resistance test. Perform minimum pickup voltage tests on trip and cl coils, Verify trip, close, trip-free, and antipump function. Trip circuit breaker by operation of each protective device. Perform resistance measurements through all boltec connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.2.3.1 (Vis and Mechanical Inspection). Perform insulation-resistance tests pole-to-pole, pole to-ground, and across open poles at 2500 volts minimum Perform vacuum bottle integrity (overpotential) test across each vacuum bottle with the breaker in the open position in strict accordance with manufacturer’: instructions, Perform insulation-resistance tests at 1000 volts on all control wiring de. For units with solid-state component: follow manufacturer's recommendations. Perform dissipation-factor/power-factor tests on each pote with the breaker open and each phase with the breaker closed. Perform dissipation-factor/power-factor tests on each bushing. Use conductive straps and hot collar procedures if bushings are not equipped with a power factor tap. Perform an overpotential test in accordance with manufacturer's instructions. *Optional 72 ATS-1999 @ conn en 7. 7.8 ose ual \ ’ INSPECTION AND TEST PROCEDURES Circuit Breakers (cont) 2. Medium-Voltage (cont) 3. Vacuum (cont,) 3. Test Values 1. Compare bolted connection resistance to values of similar connections. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. if manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percant of the lowest value. Circuit breaker insulation resistance should be in accordance with Table 10.1. Contact displacement shall be in accordance with factory recorded data marked on the namepiate of each vacuum breaker or bottle. The interrupter shall withstand the overpotential voltage applied. Compare circuit breaker timing values to manufacturer's published data. Control wiring insulation resistance should be a minimum of two megohms. Dissipation-factor/power-factor test results shall be compared to manufacturer's published data. In the absence of manufacturer's published data the comparison shall be made to similar breakers. "Optional 7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont) 2 Medium-Voltage (cont) 3. Vacuum (cont) 10, Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings. The insulation shail withstand the overpotential test voltage applied. “Optional 74 ATS—1999 7% INSPECTION AND TEST PROCEDURES 78 Circuit Breakers (cont) Medium-Voltage {cont} 4. ‘SF, 1. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications, Inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended lubricants. Inspect anchorage and grounding. Inspect and verify adjustments of mechanism in accordance with manufacturer's published data. Inspect air compressor in accordance with manufacturer's published data. Inspect hydraulic system in accordance with manufacturer's published data. Test for gas leaks. Verify correct operation of all air and SF, gas pressure alarms and cutouts. Siow close/open breaker and check for binding. Perform time-travel analysis. Test SF, gas for moisture and nitrogen content. *Optional @ ATS~1999 76 7 INSPECTION AND TEST PROCEDURES: 7.6 Circuit Breakers (cont.) 2. Medium-Voltage {cont.) 4, SF (cont) 13. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of law-resistance ohmmeter in accordance with Section 7.6.2.4.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3, Perform thermographic survey in accordance with Section 9. 14. Record as-found and as-left counter aperations. 15. Verify aperation of alf heaters. “Optional 6 76 ATS- 1999 - 7. INSPECTION AND TEST PROCEDURES: 76 Sireuit kers (cont.) Medium-Voltage (cont) 4. SFe(cont) 2. Electrical Tests 1. Perform a contact resistance test. 2. Perform resistance measurements through all bolted “4. connections with fow-resistance ohmmeter, if applicable, in accordance with Section 7.8.2.4.1 (Visus and Mechanical inspection). Perform insulation-resistance tests pole-to-pole, pole- ta-ground, and across open poles at 2500 volts ‘minimum. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer's recommendations. Perform dissipation-factor/power-factor tests on breake and bushings. Perform overpotentiat test in accordance with manufacturer's instructions. Perform minimum pick-up voltage test on trip and close coils, Verify trip, close, trip-free, and antipump functions. Trip circuit breaker by operation of each pratective device, *Optionai @ ATS- 1999 77 7. INSPECTION AND TEST PROCEDURES 78 gireult Breakers (cont) Medium-Voitage (cont.) 4, SF {cont.) 3. Test Values. 4. Compare bolted connection resistance to values of similar connections, Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivott drop values shall not exceed the high levels of the normal range as indicated inthe ‘manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 58 percent of the lowest value. Compare time-travel data with manufacturer's published data. Control wiring insulation resistance should be a minimum of two megohms. Circuit breaker insulation resistance should be in accordance with Table 10.1. Dissipation-factor/power-factor test results shall be ‘compared to manufacturer's published data. In the absence of manufacturer's published data, the comparison shail be made to similar breakers. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings. The insulation shail withstand the overpotential test voltage applied, Minimum pickup for trip and close coils shall conform to manufacturer's published data. “Optional 78 ATS-1999 & t INSPECTION AND TEST PRUGEDURES 7.6 Circuit Breakers (cont.) 3, High-Voltage 1. (Ol 1. Visual and Mechanical inspection 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition, Confirm correct apptication of manufacturer's recommended ‘ubricants. Inspect anchorage, alignment, and grounding. Verify that breather vents are clear. Perform all mechanical operation and contact alignment tests on both the circuit breaker and its operating mechanism. If performing intemal inspection: 1. Remove oil, Lower tanks or remove manhole covers as necessary. Inspect bottom of tank for broken parts and debris. 2 Inspect lift rod and toggle assemblies, contacts, interrupters, bumpers, dashpots, bushing current transformers, tank liners, and gaskets. 3. Slow-close breaker and check for binding, friction, contact alignment, penetration, and overtravel. Check that all phases make contact simultanecusly. 4, Refill tank(s) with filtered oii to correct levels. “Optional @ ATS - 1999 7£ 7 INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 3. “Optional 80 ATS-1999 Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.6.3.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Test alarms and fockouts for pneumatic and/or hydraulic operators as recommended by the manufacturer. Perform circuit breaker time-travel analysis. High-Voltage (cont) 4. Oil (cont) 8 9. 10. it. Record as-found and as-left operation counter readings. 2. Electrical Tests Perform a contact resistance test. Remove a sample of insulating liquid in accordance with ASTM D-923, Sample shall be tested for the following: 41. Dielectric breakdown voltage: ASTM D-877 2. Color: ANSVASTM D-1500. *3. Power factor: ASTM D-924 *4, Interfacial tension: ANSVASTM D-971 or ANSVASTM 0-2285 6. Visual condition: ASTM D-1524 7 INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont) 3. High-Voltage (cont.) 4. Oil (cont) 3. “7, “10. “11. Trip circuit breaker by operation of each protective device. Verify trip, close, trip-free, and antipump function, Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accardance with Section 7.6.3.1.1 (Visua and Mechanical Inspection). Perform insulation-resistance tests pole-to-pole, pole- to-ground, and across open poles at 15,000 volts minimum. Perform insulation-resistance tests on all control wiring at 1000 volts de. For units with solid-state components, follow manufacturer's recommendations. Perform power-factor tests on each pole with breaker open and each phase with breaker closed. Determine tank loss index. Perform power-factor tests on each bushing. Use conductive straps and hot collar procedures if bushings are not equipped with a power-factor tap. Perform minimum pickup voltage tests on trip and close coils, Perform an overpotential test in accordance with manufacturer's published data. 3. Test Vaiues 4. 2. Compare boited connection resistance ta values of similar connections. Bolt-torque levels should be in accordance with Tabie 10.12 uniess otherwise specified by manufacturer. *Optionat @ ATS-—1989 81 a INSPECTION AND TEST PROCEDURES: 7.8 Cireuit Breakers (cont.j 3. High Voltage (cont) 4. Oil (cont) 3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value, 4. Compare circuit breaker travel and velocity values to manufacturer's published data. 5. Insulating liquid test results should be in accordance with Table 10.4. 6. Circuit breaker insulation resistance should comply with Table 10.1. 7. Controf wiring insulation resistance should be a minimum of two megohms, 8. Dissipation-factor/power-factor test results and tank Joss index shall be compared to manufacturer's published data. In the absence of manufacturer's published data, the comparison shal! be made to similar breakers. 9. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating far bushings. 10. The insulation shail withstand the overpotential test voltage applied. 14. Minimum pickup for trip and close coils shall conform to manufactures’s published data. *Optional @ 82 ATS~1999 , 4 y 7. INSPECTION AND TEST PROCEDURES 7é Circuit Breakers (cont) 3. High-Voltage (cont) SFs 2 1. ‘Visual and Mechanical Inspection 1. Cornpare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended fubricants. inspect anchorage and grounding. inspect and verify adjustments of mechanism in accordance with manufacturer's published data. Inspect air compressor in accordance with manufacturer's published data. Inspect hydraulic system in accordance with manufacturer's published data. Test for gas leaks, Verify correct operation of all air and SF, gas pressure alarms and cutouts. ‘Slow close/open breaker and check for binding. Perform time-travel analysis. Test SF, das for moisture and nitrogen content. *Optional 6 ATS- 1999 8 7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont) 3, High-Voltage (cont.) 2. SFa(cont) 13, Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.6.3,2.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. 14, Record as-found and as-left counter operations. 415. Check spring charging motor starts counter and compare with operations counter, i applicable, 16. Verify operation of all heaters. *Optional co) 84 ATS-1999 7 INSPECTION AND TEST PROCEDURES: 7.6 Circuit Breakers (cont) Q 3. High-Voltage (cont.) 2. SF¢ (cont) i Electrical Tests 1. 2. “4. "5. Perform a contact resistance test. Perform resistance measurements through ail bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.6.3.2.1 (Visue and Mechanical Inspection). Perform insulation-resistance tests pole-to-pole, pole- to-ground, and across open poles at 15,000 volts minimum. Perform insulation-resistance tests on ail control wiring at 1000 volts de, For units with solid-state components, follow manufacturer's recommendations. Perform dissipation-factor/power-factor tests on breake and bushings. Perform overpotential test in accordance with manufacturer's instructions. Perform minimum pick-up voltage test on trip and close coils. Verify trip, close, trip-free, and antioump functions. Trip circuit breaker by operation of each protective device. "Optional @ ATS -~ 1998 BE 7. INSPECTION AND TEST PROCEDURES: 7.6 Circuit Breakers (cont.) 3 High-Voltage (cont.) 2 SFs (cont.) 3. Test Vaiues. 4, 10. Compare bolted cannection resistance to values of simitar connections, Boit-torque levels should be in accordance with Tabie 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any vatues which deviate fram similar connections by more than 50 percent of the lowest value. Compare time-travel data with manufacturer's published data. Contrat wiring insulation resistance should be a minimum of two megohms. Circuit breaker insulation resistance should be in accordance with Table 10.1. Dissipatian-factor/power-factor test results shall be compared to manufacturer's published data. In the absence of manufacturer's published data, the comparison shall be made to similar breakers. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings. The insulation shall withstand the overpotential test voltage applied Minimum pickup far trip and close coils shall conform to manufacturer's published data. *Optional 86 ATS—1999 6 6% % INSPECTION AND TEST PROCEDURES 76 Circuit Breakers (cont) 4. Extra-High-Voitage 1. ‘Ss 1. Visual and Mechanical Inspection 1. 10. 44. Compase equipment nameplate data with drawings and specifications. inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended lubricants. Inspect anchorage and grounding. Inspect and verify adjustments of mechanism in accordance with manufacturer's published data. Inspect air compressor in accordance with manufacturer's published data. Inspect and service hydraulic system in accordance with manufacturer's published data. Test for gas leaks. Verify correct operation of ail air and SF, gas pressure alarms and cutouts. ‘Stow close/open breaker and check for binding. Perform time-travel analysis. Test SF gas for moisture and nitrogen content. “Optional & ATS - 1999 87 7. INSPECTION AND TEST PROCEDURES: 7.6 Circuit Breakers (cont) 4, Extra-High-Voltaye (cont) 4. SFe (cont) 13. — tnspect ail bolted electricat connections for high resistance using one of the following methods: 1. Use of Jow-resistance ohmmeter in accordance with Section 7,6.4.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perfarm thermographic survey in accordance with Section 9. 14, Record as-found and as-left counter operations. 45. Check spring charging motor starts counter and compare with operations counter, if applicabie. *Optional @ 8B ATS —1999 (') , ’ 7. INSPECTION AND TEST PROCEDURES 7 *Optional Circuit Breakers (cont.) 4 Extra-High-Voltage (cont) 4. SFe (cont) 2. Electrical Tests 1. 2. “5. Perform a contact resistance test. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.8.4.1.1 (Visu and Mechanical Inspection). Perform insulation-resistance tests pole-to-pole, pole- to-ground, and across open poles at 15,000 volts minimum. Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with solid-state components, follow manufacturer's recommendations. Perform dissipation-factor/power-factor tests on breake and bushings. Perform averpotential test in accordance with manufacturer's instructions Perform minimum pick-up voltage test on trip and close coils. Verify trip, close, trip-free, and antipump functions. Trip circuit breaker by operation of each protective device. @ ATS—1999 89 7. INSPECTION AND TEST PROCEDURES 7.6 Circuit Breakers (cont.) 4 Extra-High-Voltage (cont.) 1. SF¢ (cont) 3. Test Values. 1. 2. 10. Compare bolted connection resistance to values of similar connections. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Compare time-travel data with manufacturer's published data. Control wiring insulation resistance should be a Minimum of fvo megohms. Circuit breaker insulation resistance should be in accordance with Table 10.1. Dissipation-factor/power-factor test results shail be compared to manufacturer's published data. In the absence of manufacturer's published data, the comparison shalt be made to similar breakers. Dissipation-factor/power-factor and capacitance test results should be within ten percent of nameplate rating for bushings. The insulation shall withstand the overpotential test voltage applied Minimum pickup for trip and close coils shall conform t manufacturer's published data. “Optional 90 ATS- 1999 & 4 7. INSPECTION AND TEST PROCEDURES: 7.7 Circuit Switchers 1. 2. 3. 4. 5. ¢,.0 9. 10. 7 9 1. Visual and Mechanical Inspection Inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended lubricants. Inspect anchorage, alignment, and grounding, Perform all mechanical operational tests on both the circuit switcher and its operating mechanism. Inspect all bolted electrical connections for high resistance using on of the following methods: 1. Use of low-resistance ohmmeter. See Section 7.7.2 (Electrice Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.72. 3. Perform thermographic survey in accordance with Section 9. Verify correct operation of SF, interrupters. Verify correct SF, pressure. Verify correct operation of isolating switch. Perform timing tests. Record as-found and as-left operation counter readings. 2. Electrical Tests 1. Perform resistance measurements through all connections with a low-resistance ohmmeter, if applicable, in accordance with Section 7.7.1 (Visual and Mechanical Inspection). Perform contact-resistance test of interrupters and isolating *Optional | ’ ‘switches. @ ATS — 1999 94 7 INSPECTION AND TEST PROCEDURES 7.7 Circuit Switches (cont.) “Optional 92 ATS-—1999 3. Perform minimum pickup voltage tests on trip and close coils. 4 Trip circuit switcher by operation of each protective device. 5. Verify correct operation of electrical shunt trip of interrupters. *6. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at 15,006 volts minimum, *7. Perform insulation-resistance tests on al) conirol wiring at 1000 voits de, For units with solid-state components, follow manufacturer's recommendations, 8. Perform an overpotential test in accordance with manufacturer's published data. Test Values 41. Compare bolted connection resistances to values of similar connections. 2 Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. 3 Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from adjacent poles or similar switchers by more than 50 percent of the lowest value. 4. Minimum pickup for trip and close coils shall conform to manufacturer's published data. 5. Circuit switcher insulation resistance should be in accordance with Table 10.1. 6. Controt wiring insulation resistance should be a minimum of two megohms. 7. The insulation shall withstand the overpotential test voitage applied. 8. Timing tests shall be in accordance with manufacturer's published data. & By 9 6} > t INSPECTION AND TEST PROCEDURES 7.8 Network Protectors, 600 Volt Class *Optional 1, Visual and Mechanical inspection 1. 10. 12, 13. ‘Open the protector and rack it out of the enclosure. Note that the network bus and transformer generally will be energized. Exercise extreme caution. Observe clearances and check for smoothness of operation when racking. Compare equipment nameplate data with drawings and specifications. inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended lubricants. Inspect the enclosure door gasket and sight glass for damage. Inspect the interior of the enclosure for debris or damaged components, inspect insulating components, current carrying parts, and secondary disconnecting devices. Exercise extreme caution when working around the network bus conductors. Check for missing parts on the protector. Verify tightness of electrical and mechanical connections. Tighten as necessary according to manufacturer's published data, Inspect insulating barriers for damage and costect mounting. Inspect network protector fuse covers, fuses, and blown fuse indicators for damage. taspect closing motor brushes and commutator surface for damage. Inspect motor brake mechanism, if applicable. Remove and inspect arc chutes for damage. Verify sequence of main and arcing contacts by slow-closing the protector. Adjust as necessary according to manufacturer's published ata. Manually open and close the protector and verify that the mechanism latches correctly in each position. Verify correct operation of the position indicator. 6 ATS-1999 93 7. INSPECTION AND TEST PROCEDURES 7.8 Network Protectors, 600 Volt Class {cont.) 14. _ Verify electrical connections to network and auxiliary refays. inspect -electromechanical relays for freedom of movement of internal parts. 15. Verify electrical connections to auxiliary switches, secondary disconnects, current transformers, voltage transformers, control power transformers, closing motors, contactors, trip coils, loading resistors, and any other auxiliary devices. 16. Record the as-found and as-left operations counter reading. 17. Perform a leak test on submersible enciosure in accordance with manufacturer's published data. Electrical Tests 1. Perform insulation-resistance tests at 1000 volts dc for ane minute across the contacts of each poie with the protector open and from pole-to-pole and each pole-to-ground with the protector closed. *2. Perform insulation-resistance tests at 1000 volts de for one minute o all contro! wiring and electromechanical components. For units with solid-state components, follow manufacturer's recommendations. *3. Verify current transformer ratios in accordance with Section 7.10. 4. Perform a contact resistance test. *5. Measure the resistance of each protector power fuse. 6. Measure minimum pickup voltage of motor control relay. *7. Verify that the motor can charge the closing mechanism at the minimum voltage specified by the manufacturer. 8. Measure minimum pickup voltage of the trip actuator. Verify that th: actuator resets correctly. 9. Calibrate the network protector relays in accordance with Section 79. *Optionai 94 ATS - 1999 6 @o é 7 INSPECTION AND TEST PROCEDURES 7.8 Network Protectors, 600 Volt Class {cont.} 10. Perform operational tests. 1, Verify correct operation of alt mechanical and electrical interlocks. 2. Verify trip-free operation. 3 ‘Verity correct operation of the auto-open-ciose control handle. 4. Verify the protector will close with voltage on the transformer side only. 5. Verify the protector will open when the source feeder breaker is opened. Test Values 1. Insulation resistance of the protector components should be in accordance with Table 10.1. Control wiring insulation resistance should be a minimum of two. megohms. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Resistance of power fuses shall be evaluated on a comparative basis. Minimum voltage to operate the trip actuator shail be in accordance with manufacturer's published data. Minimum acceptable motor closing voltage shall be in accordance with manufacturer's published data. Network protector shall automatically close upon closing the feeder breaker with normai load demand and shall automaticaily trip when source feeder breaker is opened. “Optional & ATS -1999 95 7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays 1, Visual and Mechanical Inspection 1. 5. Compare equipment nameplate data with drawings and specifications. Inspect relays and cases for physical damage. Remove shipping restraint material. Tighten case connections. Inspect cover for correct gasket seal. Clean cover glass. Inspect shorting hardware, connection paddles, and/or knife switches. Remove any foreign material from the case. Verify target reset. Inspect relay for foreign material, particufarly in disk slots of the damping and electromagnets. Verify disk clearance. Verify contact clearance and spring bias. Inspect spiral spring convolutions, Inspect disk and contacts for freedom of movement and correct travel. Verify tightness of mounting hardware and connections. Bumish contacts. Inspect bearings and/or pivots. Set refays in accordance with coordination study supplied by owner. Electrical Tests 1. Perform insulation-resistance test on each circuit-to-frame. Determine from the manufacturer's instructions the allowable procedures for this test for solid-state and microprocessor-based relays. Inspect targets and indicators. 1. Determine pickup and dropout of electromechanical targets. 2. Verify operation of all light-emitting diode indicators. 3. Set contrast for liquid-crystal display readouts. *Optional 96 ATS- 1999 @ 6) 9 7. INSPECTION AND TEST PROCEDURES 7a Protective Relays {cont} 3. Functional Operation t. 2/62. Timing Relay 1. Determine time delay. 2. Determine instantaneous contacts. 21 Distance Relay 1. Determine maximum reach. 2. Determine maximum torque angle. 3. Determine offset. “4. Plot impedance circle. 24 Volts/Hertz Relay 1. Determine pickup frequency at rated voltage. 2. Determine pickup frequency at 4 second voltage level. 3. Determine time delay. 25 Sync Check Relay 1. Determine closing zone at rated voltage. 2 Determine maximum voltage differential that permits closing at zero degrees. 3. Determine live line, live bus, dead line, and dead bus set points. 4, Determine time delay. 5. Verify dead bus/live line, dead lineflive bus and dead bus/dead line controt functions. *Optional & ATS—1999 87 v. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.) 5. 27 Undervoltage Relay 1. Determine dropout voltage. 2. Determine time delay. 3. Determine the time delay at a second point on the timing curve for inverse time refays. 32 Directional Power Relay 4. Determine minimum pickup at maximum torque angie. 2. Determine closing zone. 3. Determine maximum torque angle. 4. Determine time delay. 5. Verify the time defay at a second point on the timing curve for inverse time relays. *6. Plot the operating characteristic. 40. Loss of Field (Impedance) Relay 1. Determine maximum reach. 2 Determine maximum torque angle. 3. Determine offset. *4. Plot impedance circle. 468 Current Balance Relay 1. Determine pickup of each unit, 2. Determine percent slope. 3. Determine time delay. “Optional 98 ATS~ 1999 @ 7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont) 46N Negative Sequence Current Relay 1, Determine negative sequence alarm level and trip. 2. Determine negative sequence minimum trip level. 3. Determine maximum time delay. 4. Verify two points on the (1,)*t curve. 47. Phase Sequetce or Phase Balance Voltage Relay 1. Determine positive sequence voltage to close the nomalty open contact. 2. Determine positive sequence voltage to open the normally closed contact (undervoltage trip). 3. Verify negative sequence trip. 4. Determine time delay to close the normally open contact with sudden application of 120 percent of pickup. 5. Determine time delay to clase the normally closed contact upon removal of voltage when previously set to rated system voltage. 49R_ Thermal Replica Relay 1. Determine time delay at 300 percent of setting. 2. Determine a second point on the operating curve. *3. Determine pickup. 49T Temperature (RTD) Relay 1. Determine trip resistance. 2. Determine reset resistance. 9. 10. ’ 11. 12. (,% *Optional @ ATS - 1999 99 7 INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont) 413. 14, 16. 50 4. 2 *3. 55 1. 2. 59 4. 2. 60 “2. Instantaneous Overcurrent Relay Determine pickup. Determine dropout. Determine time defay. Time Overcurrent Determine minimum pickup, Determine time delays at two points on the time current curve. Power Factor Relay Determine tripping angle. Determine time delay. Overvoltage Relay Determine overvoltage pickup. Determine time delay to close the contact with sudden application of 120 percent of pickup. Voltage Balance Relay Determine voltage difference to close the contacts with one sauree at rated voltage. Piot the operating curve for the relay. *Optional 100 ATS — 1999 & 7. INSPECTION AND TEST PROCEDURES 7.9 Protective Relays (cont.) bie 48. 20. ¢3 63 Transformer Sudden Pressure Relay 1. 2. 3. Determine rate-of-rise or the pickup level of suddenly applied pressure in accordance with manufacturer's specifications. Verify operation of the 63 FPX seal-in circuit. Verify trip circuit to remote breaker. 64 Ground Detector Relay 41. Determine maximum impedance to ground causing Telay pickup. 67 Directional Overcurrent Relay 1. *3. "4. Determine directional unit minimum pickup at maximum torque angle. Determine closing zone. Determine maximum torque angle. Plot operating characteristics. Determine overcurrent unit pickup. Determine overcurrent unit time delay at two points on the time current curve. *Optional & ATS~1999 101 7. INSPECTION AND TEST PROCEDURES 7.8 Protective Relays (cont.) 21. 22. 23. 24, 79 Reciosing Relay 1. Determine time delay for each programmed reclosing interval. 2. Verify lockout for unsuccessful reclosing. 3. Determine reset time. *4. Determine close pulse duration. 5. Verify instantaneous overcurrent lockout. 81 Frequency Relay 14. Verify frequency set paints. 2. Determine time delay. 3. Determine undervoltage cutoff. 85 Pilot Wire Monitor 1. Determine overcurrent pickup. 2. Determine undercurrent pickup. 3. Determine pilot wire ground pickup level. 87 Differential 1. Determine operating unit pickup. 2. Determine the operation of each restraint unit. 3. Determine slope. 4, Determine harmonic restraint. 5. Determine instantaneous pickup. *6. Plot operating characteristics for each restraint. *Optional 102 ATS ~ 1999 7. _ INSPECTION AND TEST PROCEDURES ' 7.9 Protective Relays (cont) Bl 6 3. Control Verification Verify that each of the relay contacts performs its intended function in the control scheme including breaker trip tests, close inhibit tests, 86 lockout tests, and alarm functions. 4. System Tests After the equipment is initially energized, measure magnitude and phase angle of all inputs and compare to expected values. 5. Test Values 4. Use manufacturer's recommended tolerances when other tolerances are not specified. 2. ‘When critical test points are specified, the relay shall be calibrated to those points even though other test points may be out of tolerance. *Optional @ ATS—1999 103 7. INSPECTION AND TEST PROCEDURES 7.10 Instrument Transformers 1. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Verify correct connection of transformers with system requirements. Verify that adequate clearances exist between primary and secondary circuit wiring. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.10.2 and 7.10.3 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Verify that all required grounding and shorting connections provide contact. Verify correct operation of transformer withdrawal mechanism and grounding operation, Verify correct primary and secondary fuse sizes for potential transformers. Electrical Tests - Current Transformers 1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.10.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests of the current transformer and wiring-to-ground at 1000 volts dc. For units with solid-state components, follow manufacturer's recommendations. “Optional 104 ATS - 1999 @ as INSPECTION AND TEST PROCEDURES 7.10 Instrument Transformers (cont.) 3. 4. Perform a polarity test of each current transformer. Perform a ratio-verification test using the voltage or current methox in accordance with ANS! C57.13.1 (IEEE Guide for Field Testing o Relaying Current Transformers). Perform an excitation test on transformers used for relaying applications in accordance with ANS! C57.13.1, (IEEE Guide for Figid Testing of Relaying Current Transformers). Measure current circuit burdens at transformer terminals and determine the total burden. When applicable, perform insulation-resistance and dielectric withstand tests on the primary winding with secondary grounded. ‘Test voltages shall be in accordance with Tables 10.13 and 10.9 respectively, 3. Electrical Tests - Voltage Transformers. 1. Perform resistance measurements through all bolted connections with Jow-resistance ahmmeter, if applicable, in accordance with Section 7.10.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests winding-to-winding and each winding-to-ground with test voltage in accordance with Tabie 10.5. Test voltages shail be applied for one minute. For units with solid- ‘state components, follow manufacturer's recommendations. Perform a polarity test on each transformer to verify the polarity marks or H1-X1 relationship as applicable, Perform a tums ratio test on all tap positions, if applicable. Measure potential circuit burdens at transformer terminals and determine the total burden. Perform a dielectric withstand test on the primary windings with the secondary windings connected to ground. The dielectric voltage she be in accordance with Table 10.9. The test voltage shail be applied for ane minute. | “Optional © : ATS ~ 1999 1€ 7 INSPECTION AND TEST PROCEDURES 7.10 Instrument Transformers (cont.) Electrical Tests - Coupling-Capacitance Voltage Transformers 4 rs 2. Measure capacitance of capacitor sections. 3. Measure power factor/dissipation factor in accordance with test equipment manufacturer's published data. Test Values 1. Compare bolted connection resistance to values of similar connections. 2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. 3. Microhm or millivolt drop vaiues shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. 4 Insulation-resistance measurement on any instrument transformer should be not less than that shown in Table 12. t. 5. Polarity results shail agree with system drawings. 6. Compare measured burdens to calculated burdens supplied by ‘owner. 7. Ratio accuracies shall be in accordance with manufacturer's published data. 8. The insulation shall withstand the overpotential test voltage applied. 9. Capacitance of capicator sections of coupling-capacitance voltage transformers shall be in accordance with manufacturer's published data. 10. Power factor/dissipation factor shail be in accordance with test Perform ail tests from 7.10.3 Voltage Transformers. equipment manufacturer's published data. “Optional 106 ATS ~ 1999 & 7. INSPECTION AND TEST PROCEDURES 7.11 Metering 2. Calibrate watthour meters according to manufacturer’s published | 4 9 1. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and 2. Inspect physical and mechanical condition. 3. Verify tightness of electrical connections. 4, Inspect cover gasket, cover glass, condition of spiral spring, disk clearance, contacts, and case-shorting contacts, as applicable. 5. Verify freedom of movement, end play, and alignment of rotating disk(s). 2. Electrical Tests 4. Verify accuracy of meters at all cardinal points. d data. 3. Verify all instrument muttiptiers, ¢ 4. Verify that current transformer and voltage transformer secondary circuits are intact. ) “Optional @ ATS-1999 10 1a INSPECTION AND TEST PROCEDURES “Optional 108 ATS- 1999 7.12 Regulating Apparatus 1. Volta; AL Step-Voltage Regulators 1. Visual and Mechanical Inspection 1. 10. 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Inspect impact recorder prior to unloading regulator, if applicable. Verify removal of any shipping bracing and vent plugs after final placement. Verify auxiliary device operation. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.12.1.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. Verify motor and drive train for correct operation and automatic motor cut-off at maximum lower and maximum raise. Verify correct liquid level in atl tanks and bushings. Perform specific inspections and mechanical tests as. recommended by the manufacturer. Verity equipment grounding. Verify operation of heaters. © 7 INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont.) 4. Voltage (cont) 4. Stop-Voltage Regulators (cont) Electrical Tests 2. 1. *8. 10. 11. Perform resistance measurements through all boited connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.12.1.1.1 (Visual and Mechanical inspection). Perform insulation-resistance tests on each winding-tc ground in the neutral position with the test voltage in accordance with Table 10.5. Calculate polarization index. Perform insulation power-factor/dissipation-factor test: on windings and in accordance with test equipment manufacturer's published data. Perform power-factor/dissipation-factor tests (or hot colfar watts-loss test) on bushings and in accordance with test equipment manufacturer's published data. Measure winding-resistance of source windings in the neutral position, Measure resistance of all taps on loa¢ windings, Perform special tests and adjustments as recommended by manufacturer. ff the regulator has a separate tap~changer compartment, measure the percentage of oxygen in the nitrogen gas blanket in the main tank. Perform tums ratio test on each voltage step position. Verify that the indicator correctly identifies all tap positions. Perform insulation-resistance test on each winding at each tap position, Verify accurate operation of voltage range limiter. *Optional @ ATS~1989 10! 7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont) 1. Voltage (cont) 1. ‘Step-Voltage Regulators (cont) 12. “13. Verify functioning and accuracy of bandwidth, time delay, voltage and line-drop compensation adjustments. If regulator has a separate tap-changer compartment, sample insulating liquid in the main tank in accordance with ASTM D3613 and perform dissolved gas analysis in accordance with ANSIMEEE 57.104 or ASTM D3612. Remove a sample of insulating liquid from the main tank or common tank in accordance with ASTM D923. ‘Sample shall be tested in accordance with the referenced standard. 41 Dielectric breakdown voltage: ASTM D877 and/or ASTM D1816. 2. Acid neutralization number: ANSI/ASTM D-974. 3. Specific gravity: ANSVASTM D-1298. 4. Interfacial tension: ANSVASTM D971 or ASTM 02285, 5. Color: ANSI/ASTM D1500. 6. Visual condition: ASTM D1524. “7, Power factor: ASTM D924. Required when the regulator voltage is 46 kV or higher. *8, Water in insulating liquids: ASTM D1533. Required on 25 kV or higher voltages and on all silicone-filled units. *Optional 110 ATS—1999 @ 7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont) 4. Voltage (cont) 1. Step-Voltage Regulators (cont) 15. Remove a sample of insulating jiquid in the tap-chang tank in accordance with ASTM D923. Sample shall be tested for the following: 1. Dielectric breakdown voltage: ASTM D877. 2 Color: ANSI/ASTM D-1500. 3. Visual condition: ASTM D1524. 3. ‘Test Values 1. ‘Compare bolted connection resistance to values of similar connections. 2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by the manufacturer : 3. Microhm or millivolt drop values shall not exceed the f a ’ high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by mare than 50 percent of the lowest value. 4, Insulation-resistance values at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperatur corrected in accordance with Table 10.14, 5. The polarization index shall be compared to manufacturer's factory test results. If manufacturer's data is not available, the acceptance test results will serve as baseline data. py *Optional @ ATS-1989 11° % INSPECTION AND TEST PROCEDURES. 7.12 Regulating Apparatus (cont) Voltage (cont) 1. Step-Valtage Regulators (cont) 6. Maximum power factor/dissipation factor of liquid-filled regulators shall be in accordance with manufacturer's published data. In the absence of manufacturer's data compare to test equipment manufacturer's published data. Representative va(ues are indicated in Table 10.3. Investigate bushing power factor/dissipation factor and capacitances that vary from namepfate values by more than ten percent. Investigate any bushing hot collar watts-loss results that exceed the test equipment manufacturer's published data. Consult manufactures if winding-resistance test results vary more than one percent from test results of adjacent windings. Tums-ratio test results should maintain a normal deviation between each voltage step and should not deviate mare than one-half percent from the calculated voltage ratio. There should be no indication of oxygen present in gas bianket. Insulating liquid test results shall be in accordance with Table 10.4. *Optional 112 ATS— 1999 7, INSPECTION AND TEST PROCEDURES 7.12. Regulating Apparatus (cont) 4. Voltage (cont.) 2 induction Regulators (cont,) Electrical Tests 2. 1. Perform resistance measurements through ail bolted connections with (ow-resistance ohmmeter, if applicable, in accordance with Section 7.12.1.2.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests winding-to-winding and each winding-to-ground with test voltage in accordance with Table 10.5. Calculate polasization index. Perform winding insulation power-factor/dissipation- factor tests on windings and in accordance with test ‘equipment manufacturer's instructions. Perform power-factor/dissipation-factor or hot collar watts-loss tests on bushings and in accordance with test equipment manufacturer's publishers data. Verify that regulation corresponds to nameplate utilizing the voltage comparison method. Verify that the indicator correctly identifies neutral position. Perform winding resistance tests on each winding at neutral position. *Optional 114 ATS-1999 @ 7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont) 1. Voltage (cont) 2. Induction Regulators (cont.) 9. ‘Sample insulating liquid, if applicable, in accordance with ASTM D923. Sample shall be tested in accordance with the referenced standard. 1. Dielectric breakdown voltage: ASTM D877 and/or ASTM 01816, 2. Acid neutralization number: ASTM D974. *3. Specific gravity: ANSVASTM D1298. 4. Interfacial tension: ANSVASTM D971 or ASTM 2285. 5. Color: ANSI/ASTM D1500. 6. Visual condition: ASTM D1524, *7. Power factor: ASTM D924 required when the regulator voltage is 46 kV or higher. . *8, Water in insulating liquids: ASTM 01533. Required when the regulator voltage is 25 kV or higher. 3. Test Values 1. Compare bolted connection resistance to values of ‘similar connections, Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Insulation-resistance value at one minute should not be less than the values calculated in accordance with the formuia in Table 10.5. Results shall be temperature Corrected in accordance with Table 10.14. “Optional @ ATS = 1999 115 7. INSPECTION AND TEST PROCEDURES 7.12 Regulating Apparatus (cont) 4. Voltage (cont,) 2 Induction Regulators {cont} 4. The polarization index shall be compared to manufacturer's factory test results. If manufacturer's data is not available, this information will serve as baseline data. 5, Maximum power factor of liquid-filled regulators shall be in accordance with manufacturer's specifications. In the absence of manufacturer's data compare to test equipment manufacturer's published data. Representative values are indicated in Table 10.3 6. Bushing power factors and capacitances should not vary by mare than ten percent of nameplate values. Any hot collar watts-loss results that exceed the test equipment manufacturer's recommendations should be investigated. 7. The regulation should be a linear ratio throughout the range between the maximum raise and the maximum lower positions. 8. Insulating liquid test results shall be in accordance with Table 10.4. 9. If winding-resistance measurements vary by more than ‘one percent from adjacent windings, consult manufacturer. 2. . Current - Reserved “Optional re) 116 ATS- 1999 ~ 7. INSPECTION AND TEST PROCEDURES: 7.12 Regulating Apparatus (cont) e) ‘9 3. Load Tap-Changers 4. Visual and Mechanical Inspection 4. Compare equipment nameplate data with drawings and specifications. 2. inspect physical and mechanical condition. 3. Inspect impact recorder, if applicable. 4, Verify removal of any shipping bracing and vent plugs. 5. Inspect all bolted electrical connections for high resistance using one of the following methods: 41. Use of low-resistance ohmmeter in accordance with Section 7.12.3.2. 2 Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in ‘ ” accordance with manufacturer's published data on Table 10.12. t 3. Perform thermographic survey in accordance with Section 9. 6. Verify correct auxiliary device operation. 7. Verify motor and drive train for correct operation and automatic motor cut-off at maximum lower and maximum raise. 8. Verify correct liquid level in all tanks. 9. Perform specific inspections and mechanical tests as recommended by the manufacturer. 10. Verify correct equipment grounding. a *Optional & ATS - 1999 117 7. INSPECTION AND TEST PROCEDURES. 7.42. Regulating Apparatus (cont.) 3. Load Tap-Changers (cont.) 2. Electrical Tests 1. 4. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.12.3.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests in accordance with Section 7.2. Perform insulation power-factor/dissipation-factor tests in accordance with Section 7.2. Perform winding-resistance tests in accordance with Section 72. Perform special tests and adjustments as recommended by the manufacturer. Perform tumns-ratio test in accordance with Section 7.2. Remove a sample of insulating liquid in accordance with ASTM D923. The sample shail be tested for the foliowing: 4. Dielectric breakdown voitage: ASTM D877. 2. Color: ANSI/ASTM D1500. 3. Visual condition: ASTM D1524. *Optional 118 ATS — 1999 @ 7. INSPECTION AND TEST PROCEDURES 7.42. Regulating Apparatus (cont.) 3. Load Tap-Changers (cont) 3. Test Values 1. o}0 Compare bolted connection resistance to values of similar connections. {nsulation-resistance test values at one minute should not be less than the values calculated in accordance with the formula in Table 10.5. Results shall be temperature corrected in accordance with Table 10.14. The polarization index shall be compared to manufacturer's factory test results. If manufacturer's data is not available, the acceptance test results will serve as baseline data. Tums ratio test results should maintain a normal deviation between each voltage step and should not deviate more than one-half percent from the caiculated voltage ratio Maximum winding insulation power factor/dissipation factor of liquid-filled transformers shall be in accordance with manufacturer's specifications. Representative values are indicated in Table 10.3. Also, compare with test equipment manufacturer's published data. Consult manufacturer if winding-resistance test results vary more than one percent from test results of adjacent windings. Insulating liquid test results shall be in accordance with Table 10.4. 9 “Optional @ ATS-1999 119 7. _ INSPECTION AND TEST PROCEDURES 7.43 Grounding Systems 4. Visual and Mechanical Inspection 4. Verify ground system is in compliance with drawings and specifications. 2. Electrical Tests ca Perform fali-of-potential test or alternative in accordance with IEEE ‘Standard 81 on the main grounding electrode or system. 2. Perform point-to-point tests to determine the resistance between the main grounding system and all major electrical equipment frames, system neutral, and/or derived neutral points. 3. Test Values 1. The resistance between the main grounding electrode and ground should be no greater than five ohms for commercia! or industrial systems and one ohm or less for generating or transmission station grounds unless otherwise specified by the owner. (Reference: ANSIIEEE Standard 142.) 2. Investigate point-to-point resistance values which exceed 0.5 ohm. *Optionat o 120 ATS - 1999 > 7. INSPECTION AND TEST PROCEDURES 7.44 Ground-Fault Protection Systems: 1. Visual and Mechanical inspection 1 ‘Compare equipment nameplate data with drawings and specifications. Visually inspect the components for damage and errors in polarity or conductor routing. 1. 5. Verify that ground connection Is made ahead of neutral disconnect link and on the line side of any ground fault sensor. Vetify that neutral sensors are connected with correct polarity on both primary and secondary. Verify that all phase conductors and the neutral pass through the sensor in the same direction for zero sequence systems. Verify that grounding conductors do not pass through zero sequence sensors. Verify that the grounded conductor is solidly grounded. inspect aif bolted electrical connections for high resistance using one of the follawing methods: 1. 3. Use of low-resistance ohmmeter in accordance with Section 7.14.2 (Electrical Tests). Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. Perform thermographic survey in accordance with Section 9. Verify correct operation of all functions of the self-test panel. Verify that the control power transformer has adequate capacity for the system. *Optional & ATS ~1999 421 7. INSPECTION AND TEST PROCEDURES 714 Ground-Fault Protection Systems (cont) 6. Set pickup and time-delay settings in accordance with the settings provided in the owner's specifications. Record appropriate operation and test sequences as required by NEC Article 230-95. Electrical Tests 1. *3. Measure the system neutral-to-ground ingulation resistance with the neutral disconnect tink temporarily removed. Replace neutral disconnect fink after testing. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.14.1 (Visual and Mechanical Inspection), Perform insulation resistance tests at 1000 volts de on all contro! wiring, For units with solid state components, follow manufacturer's recommendations. Perform the following pickup tests using primary injection: 4. Verify that the relay does not operate at 90 percent of the pickup setting. 2. Verify pickup is less than 125 percent of setting or 1200 amperes, whichever is smaller. For summation type systems utilizing phase and neutral current transformers, verify correct polarities by applying current to each phase-neutral current transformer pair. This test also applies to molded-case breakers utilizing an external neutral current transformer. 4. The relay shall operate when current direction is the same relative to polarity marks in the two current transformers. 2 The relay shail not operate when current direction is opposite relative to polarity marks in the two cusrent transformers. Measure time delay of the relay at 150 percent or greater of pickup. *Optional 122 ATS- 1999 @ 7. INSPECTION AND TEST PROCEDURES 7.14 Ground-Fault Protection Systems (cont) 8. 7 Verify raduced control voltage tripping capability: 55 percent for ac systems and 80 percent for de systems. Verify blocking capability of zone interlock systems. 3. Test Values 1. Compare bolted connection resistance to values of similar connections. Bolt-torque leveis should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivoit drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the Jowest value. ‘System neutral-to-ground insulation resistance shall be a minimum of one megohm. Control wiring insulation resistance values shall be in accordance with Table 10.1. Relay timing shall be in accordance with manufacturer's specifications but shall not exceed one second at 3000 amperes. “Optional @ ATS -1999 123 7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery Motors 1. AC Motors 4. Visual and Mechanical inspection 4. ‘Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Confirm correct application of manufacturer's: recommended lubricants. Inspect anchorage, and grounding. Inspect ail bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.16.1.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. When applicable, perform special tests such as air gay spacing and pedestal alignment. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run. 2, Electrical Tests - Induction Motors 1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15.1.1.1 {Visual and Mechanical Inspection). “Optional 124 ATS—1999 & 6) 9 eo 7 INSPECTION AND TEST PROCEDURES 7.18 Rotating Machinery (cont) 4. Motors (cont) 4. AC Motors (cont.) 2. "3, “4, *5. 11. 12. Perform insulation-resistance tests in accordance with ANSI/EEE Standard 43, 1. Motors larger than 200 horsepower: Test duration shall be for ten minutes. Calculat polarization index. 2. Motors 200 horsepower and Jess: Test duration shall be for one minute. Calculate the dielectric-absorption ratio. Perform de overpotential tests on motors in accordane with ANSIMEEE Standard 95. Perform insulation power-factor or dissipation-factor tests. Perform surge comparison tests. Perform insulation-resistance test on pedestal in accordance with manufacturer's published data. Test surge protection devices in accordance with Section 7.19. Test mator starter in accordance with Section 7.16. Verify that resistance temperature detector (RTD) circuits conform to drawings. Verify that metering or relaying devices using the RTD's have the correct rating. Verify that the motor space heater is functional. Perform a rotation test to insure correct shaft direction. Measure running current and evaluate relative to load conditions and nameplate fullioad amperes. “Optional @ ATS — 1999 12! 7. INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont,) 1. Motors (cont) AL AC Motors (cont.) 3. Electrical Tests - Synchronous Motors 1. “2. 3. “4. “6. Perform all tests as indicated In Section 7.15.1.1.2 for induction motors. Perform a voltage-drop test on ail salient poles. Perfarm insulation-resistance tests on the main rotating field winding, the exciter-field winding, and the exciter- armature winding in accordance with ANSI/IEEE Standard 43. Perform a high-potential test on the excitation system in accordance with ANSVIEEE Standard 421B. Measure and record resistance of motor field winding, exciter-stator winding, exciter-rotor windings, and field discharge resistors. Perform front-to-back resistance tests on diodes and gating tests of silicon controlled rectifiers for field application semiconductors. Prior to initial start, apply voltage to the exciter supply and adjust exciter-field current to nameplate value. Verify that the field application timer and the enable timer for the power-factor relay have been tested and set to the motor drive manufacturer's recommended values. “Optional 126 ATS- 1999 e- 7. INSPECTION AND TEST PROCEDURES 7.48 Rotating Machinery (cont) ) 0 4. Motors (cont) 4. AC Motors (cont) “9. Record stator current, stator voltage, and field current by strig chart recorder for the complete acceleration period including stabilization time for a normally loaded starting condition. Fro the recording determine the following information: 1. Bus voltage prior to start. 2. Voltage drop at start. 3. Bus voltage at motor full-load. 4. Locked-rotar current. 6. Current after synchronization but before loading. 6. Current at maximum loading. 7. Acceleration time to near synchronous speed. 0 ° 8 RPMjust prior to synchronization. 9 Fieid application time. 10. Time to reach stable synchronous operation. "10, Plot a V-curve of stator current versus excitation current at approximately 50 percent load to check correct exciter operation. "11. If the range of exciter adjustment and motor loading permit reduce excitation to cause power factor to fall below the trip value of the power-factor relay. Verify relay operation. *Optional & ATS—1999 123 7. INSPECTION AND TEST PROCEDURES 7.A8 Rotating Machinery (cont) 1. Motors (cont) 4. ‘AC Motors (cont) 4 Test Values 1. Compare bolted connection resistance to values of similar connections, Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shail not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Insulation-resistance test results shail be in accordance with Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation. NOTE: Overpotential, and surge comparison tests ‘shall not be made on motors having values lower than those indicated above. Stator winding de overpotential test voltage shall be in accordance with NEMA publication MG 4, paragraph 3.01. Test results are dependent on ambient conditions, and evaluation is on a withstand basis. If phase windings can be separately tested, values of leakage current may be compared for similar windings. Vibration amplitudes shall not exceed values shown in Table 10.10. ‘Optional 128 ATS-1999 e 7. INSPECTION AND TEST PROCEDURES 7.18 Rotating Machinery (cont) ito 4. Motors (cont.) 4. AC Motors (cont) 7. Salient pole voltage drop shall be equal for each pole NOTE: For dc tests each pole (or pair of poles) shall not vary more than two percent fram the average. An ac test is more sensitive than a dc test in determining shorted turns, A pole with shorted turns will have a substantially lower voitage than sound coils. Coils adjacent to coils with shorted turns will exhibit slightly Jower voltage. 8. The measured resistance values of motor-field windings, exciter-stator windings, exciter-rotor windings, and field-discharge resistors shall be compared to manufacturer's recommended values. py Optional 6 ATS— 1999. 128 7. INSPECTION AND TEST PROCEDURES 715 Rotating Machinery (cont) Motors (cont) 2 DC Motors 4. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Confirm correct application of manufacturer's recommended lubricants. Inspect anchorage and grounding. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.15.1.2.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3, Perform thermagraphic survey in accordance with Section 9. When applicable, perform special tests such as air gap ‘spacing and pedestal alignment. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run. *Optional 130 ATS ~ 1999 7. INSPECTION AND TEST PROCEDURES 7.48 Rotating Machinery (cont) 6} 6 4. Motors (cont.) 2. DC Motors (cont) 2. Electrical Tests 1. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15.1.2.1 (Visual and Mechanical Inspection). 2. Perform insuiation-resistance tests on all windings in accordance with ANSIIEEE Standard 43. 1. Motors larger than 200 horsepower: Test duration shall be for ten minutes. Calculate polarization index. 2. Motors 200 horsepower and less: Test duration shall be for one minute. Calculate the dielectric absorption ratio. 3. Perform high-potential test in accordance with NEMA (| 9 publication MG 1, paragraph 3.01. “4. Perform a voltage-drop test on all field poles. *5. Perform insulation power-factor or dissipation-factor tests. voltage. Compare to nameplate. 7. Perform vibration baseline tests. 8. Verify that ail protective devices are in accordance with 6, Measure armature running current and field current or Section 7.16. i i | | *Optional @ ATS~1999 131 7 INSPECTION AND TEST PROCEDURES 7.48 Rotating Machinery (cont.) Motors {cont.) 2, DC Motors (cont) 1. 3. Test Values 1. Compare bolted connection resistance to values of similar connections. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Insulation-resistance test values shall be in accordance with those listed in Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation. NOTE: Overpatential, and surge comparison tests shall not be made on motors having values Jower than those indicated above, Overpotential test evaluation shall be on a withstand basis. Vibration amplitudes shail not exceed vaiues shown in Table 10.10. “Optional 132. ATS - 1999 6 Bw INSPECTION AND TEST PROCEDURES 7.46 Rotating Machinery (cont.) 2 Generators 41. AC Generators 1. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. Inspect physical and mechanical condition. Confirm correct application of manufacturer's lubricants. Inspect anchorage and grounding. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.15.2.1.2 (Electrical Tests), 2. Verify tightness of accessible batted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. When applicable, perform specia! tests such as air gap spacing and pedestal alignment. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run “Optional @ ATS- 1999 133 7 INSPECTION AND TEST PROCEDURES 7.45 Rotating Machinery (cont,} Generators (cont.) 1. AC Generators (cont,) 2. 2 Electrical Tests - Induction Generators 1. *3. "4, Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15.2.1.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests in accordance with ANSIMEEE Standard 43. 4. Allgenerators: Record insulation-resistance value at one minute, test voltage, and winding temperature. 2. Generators rated above 600 volts: Test duration shall be for 10 minutes. Calculate polarization index. 3. Generators rated 600 volts and less: Test duration shall be for one minute. Calculate the dielectric-absorption ratio. Perform de overpotential tests on generators in accordance with ANSW/IEEE Standard 95. Perform insulation power-factor or dissipation-factor tests. Perform surge comparison tests. Verify operation of overspeed protection on prime mover. Verify that resistance temperature detector (RTD) circuits conform to drawings. Verify that metering or relay devices using the RTD's have the correct rating Verify that the generator space heater(s) is functional. “Optional 134 ATS ~ 1999 & 7 INSPECTION AND TEST PROCEDURES: 7.15 Rotating Machinery (cont) 2. Generators (cont,) 4. AC Generators (cont.) 9. Perform load test in accordance with manufacturer's recommendations, “10. Perform vibration baseline test. 3. Electrical Tests - Synchronous Generators NOTE: _ If generator is in a health care facility, also perform tests in accordance with NFPA 110. 1. Perform ail tests as indicated in 7.15.2.1.2 for induction generators. s Perform an ac voltage-drop test on all salient poles. 3. Perform insulation-resistance tests on the main field winding, the exciter-field winding, and the exciter- armature winding in accordance with ANSI/IEEE Standard 43. *4. Perform a high-potential test on the excitation system in accordance with NEMA publication MG 1, paragraph 3.01. 5. Measure and record resistance of generator field winding, exciter-stator winding, and exciter-rotor windings. “6. Perform front-to-back resistance tests on diodes and gating test of silicon controlled rectifiers for field application semiconductors. Perform resistance test on any MOV or surge suppression devices. “7. Simulate the following transient conditions to verify generator operation in accordance with manufacturer's specifications. Load to be maximum attainable, up to full load, 1, Drop out of generator under load. y 2. Reconnection of generator with load. “Optional @ ATS- 1999 135 t INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont.) Generators (cont) 4. AC Generators (cont. 3. Transfer load to utility power system and back to generator. 4. Generator output voltage deviation from no load to 25 percent [oad and return, and 60 percent to 100 percent and return. 4 Test Values 4. Compare boited connection resistance to values of similar connections. Bolt-torque levels should be in accordance with Table 10,12 unless otherwise specified by the manufacturer Microhm or millivolt drop values shall nat exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. Insulation-resistance test resuits shail be in accordance with values listed in Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation. NOTE: Overpotential and surge comparison tests shall not be made on generators having insulation-resistance test values lower than those indicated above. Stator winding de overpotential test voltage shall be in accordance with NEMA publication MG 1, paragraph 3,01. Test results are dependent on ambient conditions, and evaluaticn is on a withstand basis. {f phase windings can be separately tested, values of teakage current may be compared for similar windings. *Optional 136 ATS ~1999 @ 7 INSPECTION AND TEST PROCEDURES 7.48 Rotating Machinery (cont.) €) 4 2. Generators (cont.) 4. AC Generators (cont) | 6. Salient pole voltage drop shall be equal for each pole. Investigate values that differ by more than ten percent. 7. The measured resistance values of generator-field winding, exciter-stator winding, and exciter-rotor | windings shall be compared to manufacturer's recommended values. “Optional & ATS-1999 137 7. INSPECTION AND TEST PROCEDURES 7.18 Rotating Machinery (cont) 2, Generators (cont.) 2. DC Generators 4. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. lospect physical and mechanicat condition. Confirm correct application of manufacturer's lubricants. Inspect anchorage and grounding. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.15.2.2.2 (Etectrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. When applicable, perform special tests such as air gap spacing and pedestal alignment. Verify the absence of unusual mechanical or electrical noise or signs of overheating during initial test run. Inspect brushes and brush rigging. “Optional 438 ATS — 1999 @ 7. INSPECTION AND TEST PROCEDURES 7.48 Rotating Machi ry (cont) 2. Generaers (cont.) 2. DC Generators (cant.) 2. Electrical Tests 1. *3. “4. Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable, in accordance with Section 7.15,2.2.1 (Visual and Mechanical Inspection). Perform insulation-resistance tests on all windings in accordance with ANSI/IEEE Standard 43. 1. Alllgenerators: Record insulation-resistance value of armature and fields at 1 minute, test voltage, and winding temperature. 2. Generator armatures larger than 150 kilowatts: Test duration shall be for 10 minutes. Calculate polarization index. 3. Generator armatures rated 150 kilowatts and less: Test duration shall be for 1 minute. Calculate ‘the dielectric-absorption ratio. Perform overpotential test in accordance with NEMA. publication MG 1, paragraph 3.01. Perform an ac voltage-drop test on all field poles. Measure armature running current and field current or voltage. Compare to nameplate. Perform vibration baseline test. “Optional & ATS -1999 139 7 INSPECTION AND TEST PROCEDURES 7.15 Rotating Machinery (cont) 2. Generators (cont) DC Generators (cont) 2. 3. Test Values 1. Compare bolted connection resistance to values of similar connections. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by the manufacturer. Microhm or milivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the lowest value. insulation-resistance test results shall comply with values listed in Table 10.1. Investigate dielectric absorption ratios less than 1.4 and polarization index ratios less than 2.0 for Class B insulation and Class F insulation. NOTE: — Overpotential tests shall not be made on generators having insulation-resistance test values lower than those indicated above. Overpotential test evaluation shall be on a withstand basis. “Optional 140 ATS ~ 1999 @ 7. INSPECTION AND TEST PROCEDURES: 7.16 Motor Control pe $9 4. Motor Starters 1. Low-Voltage | 1. Visual and Mechanical Inspection 1. Compare equipment nameplate data with drawings and specifications. 2. Inspect physical and mechanical condition. 3. Inspect and adjust contact gap, wipe, alignment, and pressure in accordance with manufacturer's published data. *4. — Motor-Running Protection 1. Compare overload element rating with motor full-load current rating to verify correct sizing. 2. If power-factor correction capacitors are connected on the load side of the overload i Protection, include the effect of the capacitive a) reactance in determining appropriate overload element size. 3. If motor-running protection is provided by fuses, verify correct rating considering motor characteristics and power-factor correction capacitors, 5. Inspect all bolted electrical connections for high resistance using one of the following methods: 1. Use of low-resistance ohmmeter in accordance with Section 7.16.1.1.2 (Electrical Tests). 2. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method in accordance with manufacturer's published data or Table 10.12. 3. Perform thermographic survey in accordance with Section 9. *Optionai @ ATS— 1999 141 7. INSPECTION AND TEST PROCEDURES 7.16 Motor Control (cont) 1. *Optional 142 ATS - 1999 Motor Starters (cont.) 1. Low-Voitage (cont) 2. Electrical Tests 1 Insulation Tests 1. “4. Perform resistance measurements through all bolted connections with (ow-resistance ohmmeter, if applicable, in accordance with Section 7.16.1.1.1 (Visual and Mechanical Inspection). Measure insulation resistance of each combination starter, phase-to-phase and phase- to-ground, with the starter contacts closed and the protective device open. Test voltage shall be in accordance with Table 10.1. Refer to manufacturer's instructions for devices with solid-state components. Measure insulation resistance of each control circuit-to-ground. Perform an insulation resistance test at 1000 volts de on ail control wiring. For units with solid- state components, follow manufacturer's recommendations. 2. Test the motor overload relay elements by injecting primary current through the overload circuit and monitoring trip time of the overload element. NOTE: Test times for thermal trip units will, in general, be longer than manufacturer's curve if single-pole testing is performed. Optionally test with all poles in series for time test and each pole separately for comparison. (Refer to ANSI/NEMA ICS 2, Part 4.) 3. Test circuit breakers, including motor circuit protectors, in accordance with Section 7.6.1.1. 4. Perform operational tests by initiating control devices. @ | w INSPECTION AND TEST PROCEDURES 7.46 Motor Control (cont) 1. Motor Starters (cont.) 1. Low-Voltage (cont) 3 Test Values 1. Compare bolted connection resistance to values of similar connections. 2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by manufacturer. 3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated in the manufacturer's published data. If manufacturer's data is not available, investigate any values which deviate from similar connections by more than 50 percent of the iowest vaiue. 4. Insulation-resistance values shall be in accordance with Table 10.1. 5. Control wiring insulation test resistance should be a minimum of two megohms. 6. Overload trip times shall be in accordance with manufacturer's published data. “Optional @ ATS —1999 14:

Você também pode gostar