12250 Federal Register / Vol. 72, No.

50 / Thursday, March 15, 2007 / Notices

per day. The relocation of the north- of Decision will be provided through FRA completed a Program EIR/EIS for
south mainline will require the direct mail, the Federal Register and the California HST System in 2005 as
construction of a new corridor other media. Notification also will be the first-phase of a tiered environmental
approximately 10 to 13 miles in length sent to Federal, State, local agencies, review process for the proposed
depending on the alignment alternative. persons, and organizations that submit California HST System. The Authority
The east-west corridor may be comments or questions. Precise certified the Final Program EIR and
approximately 8 to 9 miles in length. schedules and locations for public issued a decision, and FRA issued a
The relocation of the railroad corridors meetings will be announced in the local Record of Decision in November 2005
would eliminate at least 47 grade news media. Interested individuals and on the Final Program EIS, selecting the
crossings. The relocated rail corridors organizations may request to be HST Alternative for further project level
would be entirely grade separated. included on the mailing list for the environmental review and selecting
The numerous grade crossings with distribution of meeting announcements corridor alignments and potential
high vehicle traffic volumes within the and associated information. station locations, including a corridor
city limits require the CSXT trains to between Los Angeles and Orange
(Catalog of Federal Domestic Assistance
reduce speed as they pass through Program No. 20.205, Highway Planning and County. The preparation of this project
Vincennes. Two CSXT mainlines cross Construction. The regulations implementing level Los Angeles-Orange County HST
in the middle of the city, and trains that Executive Order 12372 regarding EIR/EIS will involve development of
switch between mainlines move slowly, intergovernmental consultation on Federal preliminary engineering designs and
creating traffic backups, emergency programs and activities apply to the assessment of environmental effects
vehicle delays, and delays in rail program). associated with the construction,
operations. Frequently, train movements Authority: 23 U.S.C. 315; 23 CFR 771.123; operation, and maintenance of the HST
literally cut the city in half. In addition, 49 CFR 1.48. system, including track, ancillary
the large volumes of trains and facilities and stations, along the
Issued on: March 9, 2007.
vehicular traffic crossing the railroad previously selected Los Angeles-Orange
corridor increase the probability of Robert F. Tally, P.E.,
Division Administrator, Indianapolis,
County corridor.
collisions at the crossings.
Cooperating Agencies: The Federal Indiana. DATES: Written comments on the scope
Railroad Administration has agreed to [FR Doc. E7–4725 Filed 3–14–07; 8:45 am] of the Los Angeles-Orange County HST
serve as a cooperating agency. No others BILLING CODE 4910–22–P EIR/EIS should be provided to the
have been yet identified for this project. Authority by April 24, 2007. Public
Environmental Issues: Possible scoping meetings are scheduled from
environmental impacts include DEPARTMENT OF TRANSPORTATION April 5–April 12, 2007, as noted below.
displacement of commercial and ADDRESSES: Written comments on the
residential properties, increased noise Federal Railroad Administration
scope should be sent to Mr. Dan Leavitt,
in some areas, decreased noise in other Deputy Director, ATTN. Los Angeles—
Environmental Impact Statement for
areas, effects to historical properties or Orange County, California High-Speed
the California High Speed Train
archaeological sites, viewshed impacts, Rail Authority, 925 L Street, Suite 1425,
System From Los Angeles to Orange
impacts to water resources, wetlands, Sacramento, CA 95814, or via e-mail
County, CA
farmed wetlands, prime farmland, with the subject line ‘‘Los Angeles-
sensitive biological species and habitat, AGENCY: Federal Railroad Orange County HST’’ to:
land use compatibility impacts, and Administration (FRA) Department of comments@hsr.ca.gov. Comments may
impacts to agricultural lands. Transportation (DOT). also be provided orally or in writing at
Alternatives: The EIS will consider ACTION: Notice of Intent to Prepare an the scoping meetings scheduled at the
alternatives that include: (1) Taking no Environmental Impact Statement. following locations:
action; (2) rail relocation and • Union Station/METRO (Los
reconstruction of railroad line(s) and SUMMARY: FRA is issuing this notice to
Angeles), METRO Board Room, One
grade separations on new location. advise the public that FRA and the Gateway Plaza, Los Angeles, CA 90012,
Scoping and Comment: FHWA California High Speed Rail Authority on April 5, 2007, from 3 p.m. to 5 p.m.
encourages broad participation in the (Authority) will jointly prepare a project and from 6 p.m. to 8 p.m.
EIS process and review of the resulting level Environmental Impact Statement
environmental documents. A scoping • Anaheim, Gordon Hoyt Conference
(EIS) and project level Environmental
meeting will be conducted in the City of Room, City Hall West, 201 S. Anaheim
Impact Report (EIR) for the section of
Vincennes area at a date and place, Boulevard, Anaheim, CA on April 11,
the Authority’s proposed California
which will be widely publicized well in 2007, from 3 p.m. to 5 p.m. and from 6
High-Speed Train (HST) System from
advance of the meeting. Comments, p.m. to 8 p.m..
the City of Los Angeles (Union Station)
questions, and suggestions related to the to Orange County (Anaheim) in • Norwalk, Arts & Sports Complex
project and potential environmental compliance with relevant State and Community Meeting Center (Sproul
concerns are invited from all interested federal laws, in particular the California Room), 13000 Clarkdale Avenue,
agencies and the public at large to Environmental Quality Act (CEQA) and Norwalk, CA 90651 on April 12, 2007,
ensure that the full range of issues the National Environmental Policy Act from 3 p.m. to 5 p.m. and from 6 p.m.
related to the proposed action and all (NEPA). to 8 p.m..
reasonable alternatives are considered FRA is issuing this notice to solicit FOR FURTHER INFORMATION CONTACT: Mr.
and all significant issues are identified. public and agency input into the David Valenstein, Environmental
These comments, questions, and development of the scope of the EIS and Program Manager, Office of Railroad
rmajette on PROD1PC67 with NOTICES

suggestions should be forwarded to the to advise the public that outreach Development, Federal Railroad
address listed above. The public is activities conducted by the Authority Administration, 1120 Vermont Avenue
invited to participate in the scoping and its representatives will be (Mail Stop 20), Washington, DC 20590;
process as well. Notices of availability considered in the preparation of the Telephone (202) 493–6368, or Mr.
for the Draft EIS, Final EIS, and Record combined EIR/EIS. The Authority and Leavitt at the above noted address.

VerDate Aug<31>2005 14:20 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00087 Fmt 4703 Sfmt 4703 E:\FR\FM\15MRN1.SGM 15MRN1
Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Notices 12251

SUPPLEMENTARY INFORMATION: The (CEQ) regulations (40 CFR 1508.28) and California’s metropolitan areas from a
California High-Speed Rail Authority State CEQA Guidelines (14 C.C.R. transportation system that will become
(Authority) was established in 1996 and § 15168[b]). Tiering will ensure that the less reliable as travel demand increases.
is authorized and directed by statute to Los Angeles-Orange County HST EIR/ The intercity highway system,
undertake the planning for the EIS builds upon all previous work commercial airports, and conventional
development of a proposed statewide prepared for and incorporated in the passenger rail serving the intercity
HST network that is fully coordinated statewide program EIR/EIS. The EIR/EIS travel market are currently operating at
with other public transportation will be carried out in accordance with or near capacity, and will require large
services. The Legislature has granted the FRA’s Procedures for Considering public investments for maintenance and
Authority the powers necessary to Environmental Impacts (64 FR 28545 expansion to meet existing demand and
oversee the construction and operation [May 26, 1999]) and will address not future growth. The purpose of the
of a statewide HST network once only NEPA and CEQA, but other proposed HST system is to provide a
financing is secured. As part of the applicable statutes, regulations and new mode of high-speed intercity travel
Authority’s efforts to implement a high- executive orders, including the 1990 that would link the major metropolitan
speed train system, the Authority Clean Air Act Amendments, Section 404 areas of the state; interface with
adopted a Final Business Plan in June of the Clean Water Act, the National international airports, mass transit, and
2000, which reviewed the economic Historic Preservation Act of 1966, highways; and provide added capacity
feasibility of a 700-mile long HST Section 4(f) of the Department of to meet increases in intercity travel
system capable of speeds in excess of Transportation Act, the Endangered demand in California in a manner
200 miles per hour on a dedicated, fully Species Act, and Executive Order 12898 sensitive to and protective of
grade-separated state-of-the art track. on Environmental Justice. This EIR/EIS California’s unique natural resources.
The FRA has responsibility for process will also continue the NEPA/ Alternatives: The Los Angeles-Orange
oversight of the safety of railroad Clean Water Act Section 404 merger County HST EIR/EIS will consider a No
operations, including the safety of any process established through the Action or No Project Alternative and
proposed high-speed ground statewide program EIR/EIS process. HST Alternatives for the Los Angeles to
transportation system. For the proposed The Los Angeles-Orange County HST Orange County corridor.
HST, it is anticipated that FRA would EIR/EIS and other project level EIR/EISs No Action Alternative: The take no
need to take certain regulatory actions will examine a range of project action (No Project or No Build)
prior to operation. alternatives for portions of the proposed alternative is defined to serve as the
In 2005, the Authority and FRA HST system within corridors selected in baseline for assessment of the HST
completed a Final Program EIR/EIS for the statewide program EIR/EIS, as well Alternative. The No Build Alternative
the Proposed California High-Speed as a no action alternative. This and represents the region’s transportation
Train System (statewide program EIR/ other project level EIR/EISs will fully system (highway, air, and conventional
EIS), as the first-phase of a tiered describe site-specific environmental rail) as it existed in 2006, and as it
environmental review process. The impacts and will identify specific would exist after completion of
Authority certified the Final Program mitigation measures to address those programs or projects currently planned
EIR under CEQA and approved the impacts and will incorporate design for funding and implementation by
proposed HST System, and FRA issued practices to avoid and minimize 2030. The No Build Alternative defines
a Record of Decision under NEPA on the potential adverse environmental the existing and future intercity
Final Program EIS. This statewide impacts. The FRA and the Authority transportation system for the Los
program EIR/EIS established the will assess the site characteristics, size, Angeles to Orange County corridor
purpose and need for the HST system, nature, and timing of proposed site- based on programmed and funded
analyzed a HST alternative, and specific projects to determine whether improvements to the intercity
compared it with a No Project/No the impacts are potentially significant transportation system through 2030,
Action Alternative and a Modal and whether impacts can be avoided or according to the following sources of
Alternative. In approving the statewide mitigated. This and other project EIR/ information: State Transportation
program EIR/EIS, the Authority and EISs will identify and evaluate Improvement Program (STIP), Regional
FRA selected the HST Alternative and reasonable and feasible site-specific Transportation Plans (RTPs) for all
selected certain corridors/general alignment alternatives, evaluate the modes of travel, airport plans, and
alignments and general station impacts from construction, operation, intercity passenger rail plans.
locations, incorporated mitigation and maintenance of the HST system, HST Alternative: The Authority
strategies and design practices, and and identify mitigation measures. proposes to construct, operate and
specified further measures to guide the Information and documents regarding maintain an electric-powered steel-
development of the HST System at the the HST environmental review process wheel-on-steel-rail HST system, over
site-specific project level of will be made available through the 700-mile long (1,126-kilometer long),
environmental review to avoid and Authority’s Internet site: http:// capable of speeds in excess of 200 miles
minimize potential adverse www.cahighspeedrail.gov/. per hour (mph) (320 kilometers per hour
environmental impacts. Purpose and Need: The need for a [km/h]) on dedicated, fully grade-
The Los Angeles-Orange County HST HST system is directly related to the separated tracks, with state-of-the-art
EIR/EIS will be developed as a second- expected growth in population, and safety, signaling, and automated train
tier, site-specific environmental increases in intercity travel demand in control systems. The Los Angeles to
document. It is one of a number of California over the next twenty years Orange County corridor that was
second-tier environmental reviews for and beyond. With growth in travel selected by the Authority and FRA with
sections of the HST system that FRA demand, there will be an increase in the statewide program EIR/EIS follows
rmajette on PROD1PC67 with NOTICES

and the Authority intend to undertake. travel delays arising from the growing the existing BNSF/Metrolink rail
It will be tiered from and incorporate by congestion on California’s highways and corridor (also known as the LOSSAN
reference the certified statewide at airports. In addition, there will be Corridor) from Los Angeles Union
program EIR/EIS in accordance with negative effects on the economy, quality Station as far south as Irvine. The Los
Council on Environmental Quality of life, and air quality in and around Angeles-Orange County HST EIR/EIS

VerDate Aug<31>2005 14:20 Mar 14, 2007 Jkt 211001 PO 00000 Frm 00088 Fmt 4703 Sfmt 4703 E:\FR\FM\15MRN1.SGM 15MRN1
12252 Federal Register / Vol. 72, No. 50 / Thursday, March 15, 2007 / Notices

will consider HST service from Los turnback/layover train storage facilities and included in additional public
Angeles to Anaheim. The HST system and a main HST repair and heavy notification.
can provide service to Orange County maintenance facility will be evaluated Issued in Washington, DC, on March 9,
with a terminus in Anaheim. Beyond in the Los Angeles-Orange County HST 2007.
Anaheim right-of-way is constrained EIR/EIS. Mark E. Yachmetz,
and environmental conditions are Probable Effects: The purpose of the Associate Administrator for Railroad
different. HST service beyond Anaheim EIR/EIS process is to explore in a public Development.
to Irvine may be considered separately setting the effects of the proposed [FR Doc. E7–4710 Filed 3–14–07; 8:45 am]
in the future. project on the physical, human, and BILLING CODE 4910–06–P
Further engineering studies to be natural environment. The FRA and the
undertaken as a part of this EIR/EIS Authority will continue the tiered
process will examine and refine evaluation of all significant DEPARTMENT OF TRANSPORTATION
alignments in the selected corridor, environmental, social, and economic
including the alignment option impacts of the construction and Federal Railroad Administration
identified in the statewide program EIR/ operation of the HST system. Impact
EIS that shares tracks with other areas to be addressed include: Environmental Impact Statement for
passenger services separated from Transportation impacts; safety and the California High Speed Train
freight trains with 4 total tracks (2 for security; land use and zoning; System from Palmdale to Los Angeles,
passenger rail service and 2 for freight secondary development; land CA
service) between Los Angeles and acquisition, displacements, and
Fullerton and 2 total tracks with AGENCY: Federal Railroad
relocations; cultural resource impacts, Administration (FRA) U.S. Department
additional passing tracks South of including impacts on historical and
Fullerton. With this alignment option, of Transportation (DOT) .
archaeological resources and parklands/
the electrified HST would share tracks ACTION: Notice of intent to prepare an
recreation areas; neighborhood
(at reduced speeds) with non-electric Environmental Impact Statement.
compatibility and environmental
Metrolink commuter rail, Amtrak justice; natural resource impacts SUMMARY: FRA is issuing this notice to
Surfliner intercity services and including air quality, wetlands, water
occasional freight trains (there are fewer advise the public that FRA and the
resources, noise, vibration, energy, California High Speed Rail Authority
freight operations south of Fullerton). wildlife and ecosystems, including
This alignment option is based on the (Authority) will jointly prepare a project
endangered species. Measures to avoid, level Environmental Impact Statement
premise that the capacity and
minimize, and mitigate all adverse (EIS) and project level Environmental
compatibility issues associated with the
impacts will be identified and Impact Report (EIR) for the section of
shared operations with existing non-
evaluated. the Authority’s proposed California
electric service (Surfliners, Metrolink,
and freight) can be resolved. Additional Scoping and Comments: FRA High-Speed Train (HST) System from
alignment options will be considered encourages broad participation in the the City of Palmdale to the City of Los
that involve dedicated HST tracks that EIS process during scoping and review Angeles in compliance with relevant
may be exclusive to HST service or that of the resulting environmental State and federal laws, in particular the
may also accommodate Metrolink documents. Comments and suggestions California Environmental Quality Act
express services. are invited from all interested agencies (CEQA) and the National Environmental
Station location options were selected and the public at large to insure the full Policy Act (NEPA).
by the Authority and FRA with the range of issues related to the proposed FRA is issuing this notice to solicit
statewide program EIR/EIS considering action and all reasonable alternatives public and agency input into the
travel time, train speed, cost, local are addressed and all significant issues development of the scope of the EIS and
access times, potential connections with are identified. In particular, FRA is to advise the public that outreach
other modes of transportation, ridership interested in determining whether there activities conducted by the Authority
potential, and the distribution of are areas of environmental concern and its representatives will be
population and major destinations along where there might be a potential for considered in the preparation of the
the route, and local planning significant impacts identifiable at a combined EIR/EIS. The Authority and
constraints/conditions. Alternative project level. Public agencies with FRA completed a Program EIR/EIS for
station sites at the selected general jurisdiction are requested to advise FRA the California HST System in 2005 as
station locations will be identified and and the Authority of the applicable the first-phase of a tiered environmental
evaluated in this project level EIR/EIS. permit and environmental review review process for the proposed
Station area development policies to requirements of each agency, and the California HST System. The Authority
encourage transit-friendly development scope and content of the environmental certified the Final Program EIR and
near and around HST stations that information that is germane to the issued a decision, and FRA issued a
would have the potential to promote agency’s statutory responsibilities in Record of Decision in November 2005
higher density, mixed-use, pedestrian- connection with the proposed project. on the Final Program EIS, selecting the
oriented development will be prepared Public agencies are requested to advise HST Alternative for further project level
in coordination with local and regional FRA if they anticipate taking a major environmental review and selecting
planning agencies. Potential station action in connection with the proposed corridor alignments and potential
locations to be evaluated in the Los project and if they wish to cooperate in station locations, including a corridor
Angeles-Orange County HST EIR/EIS the preparation of the project level EIR/ between Palmdale and Los Angeles. The
include: City of Los Angeles-Union EIS. Public scoping meetings have been preparation of this project level
rmajette on PROD1PC67 with NOTICES

Station; City of Norwalk-Norwalk scheduled as an important component Palmdale-Los Angeles HST EIR/EIS will
Transportation Center; and City of of the scoping process for both the State involve development of preliminary
Anaheim-Anaheim Regional and Federal environmental review. The engineering designs and assessment of
Transportation Intermodal Center scoping meetings described in this environmental effects associated with
(ARTIC). In addition, potential sites for Notice will also be advertised locally the construction, operation and