Escolar Documentos
Profissional Documentos
Cultura Documentos
David S. Bowles
2015
2007
USA Tennessee Valley Authority (TVA) ~ 2011
Some states
Many other countries .
Structural, non-structural
measures
Regulation of US dams
Federal dams selfregulated
Hydropower dams
most regulated by
FERC (and the States)
Other dams most
regulated by the States
regulation
From standards-setting + process to goal-setting +
process e.g. NSW DSC:
Principle C.1: the DSCs approach is practicable goals-based regulation and it sets its
safety objectives accordingly
Principle E.3: safety improvements required by the DSC may be implemented
progressively
Outline
Risk assessment process
Steps in the process
Example of results format
Long dams levees
Uncertainty
Conclusions
(PFMA)
FOUNDATION
for RA
PFMA
Risk Analysis
Failure
Risk
Modes
Estimation
Identification
PFMA
Risk
Evaluation
Using
TOLERABLE
RISK
GUIDELINES
Risk Assessment
Decision Recommendation
Risk
Control
Risk Analysis
Failure
Risk
Modes
Estimation
Identification
PFMA
Risk
Evaluation
- Structural
- Recurrent
activities
- Periodic
Reassessment
1) Decisions
Existing reservoir
Scope of potential risk management actions: Investigations | Surveillance, monitoring and measurement
improvements, supervision and management | Interim/immediate risk reduction measures |Long-term risk
reduction options | Non-structural risk reduction measures
2) Decision context
Standards and good practice | Stakeholders | safety and Economic Regulators | Owner (governance,
insurance, contractual, legal, etc.) | Societal concerns | Environmental | Critical infrastructure and national
defence
5)
6)
7)
8)
9)
Accepted good practice | Tolerability of risk incldg. ALARP | Additional decision bases (owner & stakeholders)
Inductive approach
Lateral thinking
Brain storming
Uncommon, unique or odd ball failure mode
Dam-reservoir System
External
Threats
Floods
Earthquakes
System Response
Breach
Outcome
Components
(Roles & Interdependencies)
Non-Breach
Outcome
Internal
Threats
Design &
Construction
Performance
Indicators
Site
Inspection
Evidence
Condition &
Adequacy
good practice
Analyses &
Investigations
Dam-reservoir system
Hardware
Reservoir
Hillsides
Dam(s)
Abutments
Foundations
Appurtenances
Equipment
Instrumentation
Communications
Other features
relevant to safe
operation
Dam-reservoir System
Components
(Roles & Interdependencies)
Software - manuals,
logic, procedures &
software
Operations &
maintenance
Monitoring &
surveillance
Inspection
Automated or
remote control of
operations
Inflow flood
forecasts
Management
systems
Decision protocols
Resource lists
(HSE 2001)
Unacceptable
Risk Region
Tolerable Risk
Region
Broadly
Acceptable
Risk Region
Risk
Unacceptable
Risk Region
Tolerable Risk
Region
Broadly
Acceptable
Risk Region
The probability of
undesirable
consequences
Probability of an
uncontrolled release of
the contents of a
reservoir
Probability of
consequences to life,
health, property, or
the environment of
dam failure (NPP effects)
Tolerable Risk
Region
Equity
Broadly
Acceptable
Risk Region
Unacceptable
Risk Region
Tolerable Risk
Region
Broadly
Acceptable
Risk Region
(2)
Confident risks are being properly
assessed and managed (3)
Residual risks are periodically reviewed
and, if appropriate, are further reduced
to ensure that they remain as low as
reasonably practicable (ALARP) (4)
simply by a line
Determined by on-going
management not just design
considerations
ALARP
Unacceptable
Risk Region
Broadly
Acceptable
Risk Region
INFORMED
Disproportionality of
incremental cost to incremental
risk reduction benefit (BCR
goal < 1.0, e.g. 0.1 0.33, Ford
Pinto class action ~ 1.0)
Ultimately matter of judgment
Considers societal concerns
Tolerable Risk
Region
Broadly
Acceptable
Risk Region
IR = APF*Prob (Exposure|Failure)
*Prob(Life Loss|Exposure&Failure)
Unacceptable
Risk Region
Tolerable Risk
Region
Broadly
Acceptable
Risk Region
Tolerable Risk
Region
Broadly
Acceptable
Risk Region
USACE engineering
guidelines,
2) With no unconfirmed
dam safety issues, AND
3) With tolerable residual
risk (including ALARP)
RISK INFORMED
With Uncertainty
Introduction
DAMRAE
Background
Decision
Tree
Uncertainty
version
DAMRAE-U
Logic Tree
Event Tree
Fail
No-Fail
Decision tree
Consequences
Tree
Day
Night
Alt n
Decision
Alternatives
Earthquake)
effectiveness
Emergency response and factors affecting survival in
flooding
Continuously operating or standby systems e.g.
spillway gates
Flood
Event
Tree
Peak Reservoir Stage
87
85
83
81
79
77
75
73
71
69
67
65
1
0.1
0.01
0.001
0.0001
0.00001
0.000001
0.0000001
1E-08
Dam Crest
Flood
Loading
Branches
Failure
Mode
Branches
Total Probability
Number of Gates
of Failure to
Failing to Open
Open of r Gates
at a Time (r)
at a Time
0
0.932
0.056
1
2
0.001
3
0.000
5
0.010
Flood
Event
Tree
79
77
75
Flood Loading
Branches ~
different
numbers of
spillway gates
working
73
71
69
67
65
0.1
0.01
0.001
0.0001
0.00001
0.000001
0.0000001
1E-08
Dam Crest
Failure
Mode
Branches
Flood
Event
Tree
Flood Loading
Branches ~
different
numbers of
spillway gates
working
Consequences
Branches ~
Life Loss &
Economic
Losses
Exposure
Branches ~
Day/Night
Failure
Mode
Branches
1) Stillwater
elevation (E)
2) Peak annual
wind speed (Sn)
normal to the dike
2) Peak annual
wind speed (Sn)
normal to the dike
1) Stillwater
elevation (E)
Wave transformation model STWAVE and wave run-up and overwash rates
from Automated Coastal Engineering System (ACES) for E and Sn combinations
3) Average
overwash
discharge rate
5) Peak setup
elevation
Overwash FM
Secondary
Loading
Variables
4) Peak
overtopping
discharge rate
Max significant
wave height and
wave period
Overtopping FM
Earthquake Loading
Peak ground acceleration
arch/hazmaps/design/
Earthquake Loading
Most likely magnitude (mode
http://eqint.cr.usgs.gov/deaggba
nd/2002/index.php
(Ruthford et al 2011)
Modify if changes in
30
25
20
ELEVATION NAVD88
35
15
10
0.001%
0.010%
0.100%
1.000%
HISTORIC
(Bowles et al 2010)
FINAL
10.000%
0
100.000%
Fragilities
2) Reliability analysis
Deriving a distribution of interest from distributions on
other variables (e.g., Taylor series expansion or Monte
Carlo simulation)
Life-Loss Consequences
1) Semi-Empirical
LSM - BC Hydro
Tracks individuals
(year)
Percent
of Total
(-)
Annualized Economic
Consequences
Percent
of Total
($/year)
(-)
BASE RUN:
Existing Dam
Probability of
Failure (APF)
No
Individual Risk
No
Societal Risk
No
Annualized Life
Loss (ALL)
No
OT Failure
Spillway Wall OT Failure
Lq Sec Failure
1.33E-04 1 in 7,519
3.67E-04 1 in 2,725
2.99E-04 1 in 3,344
17%
46%
37%
4.43E-03
1.36E-02
4.68E-03
20%
60%
21%
1,172
3,231
2,634
17%
46%
37%
7.99E-04 1 in 1,252
100%
2.27.E-02
100%
7,037
100%
Summary Engineeirng
Assessment
NP
Flood
NP
Earthquake
P
Normal Operating
50
Risk-reduction structural
Stages
Alternatives
Alt 2.2
Cost as
Annualized
Cost
($M/year)
Failure Mode
(/year)
(year)
(-)
(-)
Percent Percent
of Total Reduction
(lives/year)
(-)
(-)
Annualized Economic
Consequences
Percent Percent
of Total Reduction
($M/year)
(-)
(-)
BASE RUN:
Existing Dam
Probability of
Failure (APF)
No
Individual Risk
No
Societal Risk
No
Annualized Life
Loss (ALL)
No
OT Failure
Spillway Wall OT Failure
Lq Sec Failure
1.33E-04 1 in 7,519
3.67E-04 1 in 2,725
2.99E-04 1 in 3,344
17%
46%
37%
4.43E-03
1.36E-02
4.68E-03
20%
60%
21%
0.001
0.003
0.003
17%
46%
37%
7.99E-04 1 in 1,252
100%
2.27.E-02
100%
100%
1.14E-05 1 in 87,719
0.00E+00 1 in 2.99E-04 1 in 3,344
4%
0%
96%
3.88E-04
0.00E+00
4.68E-03
8%
0%
92%
0.000
0.003
4%
0%
96%
##
##
##
##
1.827
1
1
1
1
4 Moderate
1
1
1
1
6
1
20
4
26 5.35382017
Plots contain:
1) Existing
Dam; 2) Alt 1.1:
Raise Dam and
Spillway Walls;
and 3) Alt 1.2
(Stage 1):
Spillway
Widening
Probability of
Failure (APF)
No
Individual Risk
No
Societal Risk
No
Annualized Life
Loss (ALL)
No
Benefit/
Cost Ratio
Disproportionality
Ratio (R)
0.002
16.66
OT Failure
Spillway Wall OT Failure
Lq Sec Failure
91%
100%
0%
91%
100%
0%
91%
100%
0%
100%
61%
5.07.E-03
100%
78%
0.003
100%
61%
Summary Engineeirng
Assessment
P
Flood
NP
Earthquake
P
Normal Operating
52
Risk-reduction structural
Stages
Alternatives
Alt 2.2
Cost as
Annualized
Cost
($M/year)
Percent Percent
of Total Reduction
Failure Mode
(/year)
(year)
(-)
(-)
Percent Percent
of Total Reduction
(lives/year)
(-)
(-)
Annualized Economic
Consequences
Percent Percent
of Total Reduction
($M/year)
(-)
(-)
##
##
##
##
1.827
1
1
1
1
4
#NAME?
1
1
1
1
6
1
20
4
## #NAME?
Probability of
Failure (APF)
No
Individual Risk
No
Societal Risk
No
Annualized Life
Loss (ALL)
No
Benefit/
Cost Ratio
Disproportionality
Ratio (R)
0.002
OT Failure
Spillway Wall OT Failure
Lq Sec Failure
1.14E-05 1 in 87,719
0.00E+00 1 in 2.99E-04 1 in 3,344
4%
0%
96%
91%
100%
0%
3.88E-04
0.00E+00
4.68E-03
8%
0%
92%
91%
100%
0%
0.000
0.003
4%
0%
96%
91%
100%
0%
16.66
3.10E-04 1 in 3,222
100%
61%
5.07.E-03
100%
78%
0.003
100%
61%
71%
0%
29%
0%
3.88E-04
0.00E+00
7.17E-05
84%
0%
16%
0%
0.000
0.000
72%
0%
28%
0%
##
##
##
##
4.6
1
1
1
1
4
#NAME?
1
1
1
1
6
1
20
4
## #NAME?
Plots contain:
1) Stage 0:
Existing Dam;
2) Stage 1 (Alt
1.2): Spillway
Widening; and
3) Stage 2:
Earthquake Fix
Probability of
Failure (APF)
YesALARP?
YesIndividual Risk
ALARP?
YesSocietal Risk
ALARP?
Annualized Life
YesLoss (ALL)
ALARP?
Benefit/
Cost Ratio
Disproportionality
Ratio (R)
0.001
159.74
OT Failure
Spillway Wall OT Failure
Lq Sec Failure
1.14E-05 1 in 87,719
0.00E+00 1 in 4.59E-06 1 in 217,865
98%
98%
98%
100%
95%
4.60.E-04
100%
91%
0.000
100%
95%
Summary Engineeirng
Assessment
P
Flood
P
Earthquake
P
Normal Operating
54
Length Effects
the issue of length effects is related to the degree of spatial correlation in these
properties rather than that the soils are classified to be the same or to have similar
properties.
correlation here refers to an expected tendency for the failure of more than
one adjacent CSR to occur during the same loading event combination and
within the same geotechnical conditions.
10
20
30
40
Length
Effects
4
10
20
40
30
50
10
20
30
40
50
10
20
30
40
50
10
20
30
40
10
20
40
30
50
10
20
30
40
50
10
20
30
40
50
10
20
30
40
10
20
40
30
50
10
20
30
40
50
10
20
30
40
50
Risk Management:
Examples of Long Dam/
Levee System Risk Profiles
Societal Risk
Probability of failure (/year)
62
Simulation Types
Deterministic Mode
Introduction
DAMRAE
Background
Uncertainty
version
DAMRAE-U
Simulation
Types
Example RA
Summary
Event
Tree
APF, ALL, etc
Uncertainty Mode
Event
Tree
APF, ALL, etc
Logic
Tree
Event
Tree
APF, ALL, etc
Logic Tree
Event
Tree
APF, ALL,64etc
Variability and
Knowledge
uncertainty in
Event Tree
80
20
0
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
1.E+00
Base Condition
Type II
simulation
100
100
95th Percentile
90
Summary
40
10
Simulation
Types
Example RA Results
50
80
70
60
50
40
30
20
10
0
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
Total Probability of Failure (/year)
100
80
60
40
20
0
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
1.E+00
95th Percentile
90
80
70
60
50
40
30
20
10
0
1.E-06
1.E+00
Percentiles of
Uncertainty in Logic
Tree
Uncertainty
version
DAMRAE-U
60
30
DAMRAE
Background
Type I
simulation
Percentiles of Uncertainty
in Logic Tree
Introduction
Percentiles
70
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
Total Probability of Failure (/year)
1.E+00
100
80
60
40
20
0
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
1.E+00
20
0
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
Base Condition
Base Condition
100
Type II
simulation
100
95th Percentile
90
80
70
60
50
40
30
20
10
0
1.E-04
1.E-03
1.E-02
1.E-01
Total Annualized Incremental Life Loss (lives/year)
60
40
20
1.E-02
1.E-01
80
70
60
50
40
30
20
10
0
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
1.E+00
80
1.E-03
95th Percentile
90
1.E+00
100
0
1.E-04
1.E+00
Summary
40
10
Simulation
Types
Example RA Results
50
1.E+00
Percentiles of
Uncertainty in Logic
Tree
Uncertainty
version
DAMRAE-U
Variability and
Knowledge
uncertainty in Event
Tree
60
30
DAMRAE
Background
Type I
simulation
Percentiles of
Uncertainty in Logic
Tree
Introduction
Percentiles
70
100
80
60
40
20
0
1.E-05
1.E-04
1.E-03
1.E-02
1.E-01
1.E+00
f- Chart
1.E-01
1.E-01
0.001 Lives/yr
1.E-02
1.E-03
i) 1.50%
APF = 1 in 10,000
(0.0001) per year
1.E-04
ii) 98.4%
1.E-05
1.E-06
iii) 0.10%
Initial Stage
1.E-07
Type I
simulation
1.E-08
Simulation
Types
0.001 Lives/yr
1.E-02
1.E-03
1.E-04
10
100
Type II
simulation
iii) 80.6%
Risk Reduction
Measure
1.E-07
80%
70%
60%
50%
40%
30%
20%
10%
0%
20
30
40
50
60
70
80
90
100
1,000 10,000
90%
10
10
100%
1.E-06
1,000 10,000
Base Condition
Summary
ii) 19.4%
1.E-05
Example RA Results
APF = 1 in 10,000
(0.0001) per year
i) 0.00%
1.E-08
1
100
Uncertainty
version
DAMRAE-U
f- Chart
Introduction
DAMRAE
Background
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
0
10
20
30
40
50
60
70
80
90
100
F-N Chart
1.E-03
95th Percentile
50th Percentile
95th Percentile
1.E-05
Limit of
Tolerability for
Existing Dams
1.E-06
Limit of
Tolerability for
Existing Dams
1.E-06
1.E-07
1.E-07
1.E-08
1.E-08
1
10
100
1,000
10,000
Simulation
Types
5th Percentile
1.E-04
1.E-05
Uncertainty
version
DAMRAE-U
10
100
1,000
10,000
Base Condition
Example RA Results
Summary
50th Percentile
1.E-04
Type II
simulation
Variability and
Knowledge
uncertainty in Event
Tree
DAMRAE
Background
Type I
simulation
Introduction
1.E-03
5th Percentile
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
10
20
30
40
50
60
70
80
90
100
at all upstream dams and intervening areas below last dam and NPP
Dam performance
full range of hazards including reliability of discharge facilities (e.g. spillway
peak elevations, time for EM, residual reservoir storage, power generation after dam
failure, time for emergency measures)
formulation
Length effects
PFHA
System response probability estimation
Reliability of discharge facilities (spillway gates)
Software designed for dam safety RA e.g. DAMRAE
Better consideration of uncertainties
Effect on Non-breach/Non-failure risk
Making the case to decision makers deliberative
process
Better integration with owners business including
71