AUB FARWANIYA

TIME EXTENSION REPORT

PROJECT DETAILS
Contractual Start Date

20th July 2013

Project Duration

270 Days

Contractual End Date

16th April 2014

Revised Start Date

18th November 2013

Revised End Date

14th August 2014

Project End Without Power

14th October 2014

Power On Date

30th March 2015

Substantial Completion

15th June 2015

SUMMARY

Delays Attributed to Authorities

Contractor was entitled to claim for the delay but OHA negotiated & requested Contractor not
to claim against this delay.

Delay Attributed to Site Works

Total Delay 99 Days

There was no one responsible Contractor for the Coordination resulted in Site Works delay.

Delay Attributed to Procurement Works

Total Delay 298 Days

Total Delay 30 Days

Material Procurement Delay which was out of Contractor limit

Page 1 of 3

AUB FARWANIYA

TIME EXTENSION REPORT

REASONS FOR THE DELAYS


Authorities Delay
Site Obstruction
:
Delay 121 Days
o Responsible :
MPW
o Removal of underground drainage pipes from the site resulted in project on hold.
o Project restarted on 18th November 2013.
Power Connection Delay
:
Delay 155 Days
o Responsible :
Bank, Civil Contractor & Authorities
o Power was connected to Farwaniya Branch on 30th March 2015 which was on hold

from 26th October 2014.


Civil Contractor delayed the submission of required documents to get the NOC from

KFB delayed the NOC from Municipality.


Bank has pending dues for the other locations delayed the MEW Payment for the

Project.
Electrical Room Works Delay
:
Delay 22 Days
o Responsible :
MEW
o Fifteen days delay was due to MEW Cut Out Box Installation which resulted in
delaying Civil and Electrical works inside the Electrical Room.

Contractors Delay

Basement Floor Concrete Works


:
Delay 13 Days
o Responsible :
Electrical Contractor & Joinery Contractor
o Seven days Delay in finishing the electrical conduiting inside the reinforcement by
o

Electrical Contractor.
Six Days delay was caused due to incompletion of sub frame works for doors by

Joinery Contractor
Above delays was recovered during the project.

Electrical Works
:
Delay 15 Days
o Responsible :
Electrical Contractor
o Fifteen days Delay by Electrical Contractor in submission of the LUX calculation for
o

the Project delayed the coordinated drawings which then delayed related site works.
Above delays was recovered during the project.

False Ceiling Works


:
Delay 15 Days
o Responsible :
Electrical Contractor & HVAC Contractor
o Fifteen days Delay in the fabrication, installation of the HVAC ducts by HVAC
Contractor & Electrical conduiting delayed the closing of false ceiling works in
Basement and Ground Floors.

Procurement of External Stone

:
Page 2 of 3

Delay 30 Days

AUB FARWANIYA

o
o

TIME EXTENSION REPORT

Responsible :
Out of Contractor Limit
Thirty days Delay in the procurement & installation of Stone due to the crisis
happened in Egypt delayed the installation of the same.

Snag Works before Power Connection Delay


:
Delay 15 Days
o Responsible :
All Bid Pack Contractors
o Pre- inspection was done and snag list was issued to all the Contractors to finish the
o

same by 26th October 2014.


None of the Contractors rectified the same.

Pending Works after Power Connection


:
Delay 45 Days
o Responsible :
Re-mobilization
o All the BID Pack Contractors completed their pending works by 31 st May 2015 which
o

was supposed to complete by 20th April 2015.


Since the project was on hold for more than 6 months period, Contractors were

working on different sites resulted in re-mobilization.


Carpet installation was delayed due to the delay in Final Painting by the Civil
Contractor.

Testing & Commissioning


:
Delay 7 Days
o Responsible :
Electrical Contractor & HVAC Contractor
o Electrical Contractor could not start Testing & Commissioning as scheduled due to in
o

complete site works.


HVAC T & C was rejected due to variation in the CFM readings. Rebalancing for the

machines has been done to meet the design requirement.


The above delays was recovered during the Snags Works & As Built Documents
Review period.

As Built Documents Submission & Review


:
Delay 22 Days
o Responsible :
All Bid Pack Contractors
o Fifteen days Delay by all Bid Pack Contractors in submitting As Built Documents.

Page 3 of 3