PROJECT DETAILS
Contractual Start Date
Project Duration
270 Days
Power On Date
Substantial Completion
SUMMARY
Contractor was entitled to claim for the delay but OHA negotiated & requested Contractor not
to claim against this delay.
There was no one responsible Contractor for the Coordination resulted in Site Works delay.
Page 1 of 3
AUB FARWANIYA
Project.
Electrical Room Works Delay
:
Delay 22 Days
o Responsible :
MEW
o Fifteen days delay was due to MEW Cut Out Box Installation which resulted in
delaying Civil and Electrical works inside the Electrical Room.
Contractors Delay
Electrical Contractor.
Six Days delay was caused due to incompletion of sub frame works for doors by
Joinery Contractor
Above delays was recovered during the project.
Electrical Works
:
Delay 15 Days
o Responsible :
Electrical Contractor
o Fifteen days Delay by Electrical Contractor in submission of the LUX calculation for
o
the Project delayed the coordinated drawings which then delayed related site works.
Above delays was recovered during the project.
:
Page 2 of 3
Delay 30 Days
AUB FARWANIYA
o
o
Responsible :
Out of Contractor Limit
Thirty days Delay in the procurement & installation of Stone due to the crisis
happened in Egypt delayed the installation of the same.
Page 3 of 3