Você está na página 1de 24

GTG (MS-5001-PA)

INITIAL START-UP PROCEDURE


AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

17.1 General indication


The scope of the following instructions is to put in condition the Operators to prepare the GTG Unit
and relevant auxiliary equipment, through the commissioning activities carried out in each system
involved, at initial start-up.
The operations are developed as follows:
- Commissioning of GTG train with the auxiliary equipment installed on the same base plate (as
starting system, fuel system on base, oil system, etc.)
- Commissioning of auxiliary equipment installed outside the baseplate and installed on the different
skids.
- Initial startup procedure
- Normal startup procedure.
Therefore will be available in the plant:
- AC and DC electric power, to supply all the electric and control/protection panels of the GT and
Generator.
- The instrument air for the required uses.
- Water for cooling the oil systems.
- The fuel gas for GT operation.
- The fire fighting system of the plant to protect the auxiliary skids.
145

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

When the services before mentioned are available and the commissioning activities referred to all
systems involved in GTG operation are completed, the Operators may proceed with the initial start
activities.
17.2 PREPARATION FOR START-UP
17.2.1 General
The gas turbine MS5001PA is provided with automatic sequence for start-up and shutdown by
means of SPEEDTRONICTM Mark VI.
The aim of this paragraph is to briefly remind some of the activities involved in the initial start-up,
especially referring to all the preparation work to be carried out prior to initial operation.
Technical terms for distinguishing the different phases included inPreparation for start-up are:

Pre-commissioning:

Commissioning:

including all preparatory work


providing the start-up sequence of the units

The preparatory works includes:

Systematic conformity checks, carried out on each item of equipment or component, visual

verification of the condition of equipment, the quality of the installation, compliance with project
drawings and specifications, manufacturers instruction, safety rules, codes, standards and good
construction practice.

Completed equipment static/de-energized tests to ensure the quality of equipment installation

(cold tests concerns all disciplines):


o

Calibration of instruments
146

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

Testing and setting of pressure relief valves

Machinery alignments

Hydrostatic pressure testing of piping

Testing of cables and electric equipments (insulation resistance, continuity, etc), functional

tests on all protection relays and interlocks.

Cleaning and flushing of the unit (air blowing, oil flushing), dry all equipment.

All initial fill of lubrication oil, grease, chemicals, etc. Commissioning of the units includes:

Pre start-up activities such as:

Dynamic tests: (electrical motors uncoupled runs, instrument loops tests, electrical breakers

operation, energisation of electrical distribution net-work)


o

Mechanical preparation: (running-in and on line tests for a significant period of the utilities or

of the main process equipment in closed loop).


o

Gas-in preparation: (piping drying out, leak tests, inert).

17.2.2 Introduction
The scope of the preparatory works to get the GTG plant started is:
1)

Commissioning and put in service GTG Fire & Gas detection and protection System.

2)

Commissioning and put in service Fire & Gas Detection System for Control Cabin (at least), if

any.
3)

Commissioning and energize the MCC and all utilities needed for a normal operation of GTG,

such as:
147

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

AC & DC distribution system (MCC, UPS, etc.)


Commissioning and starting all the utilities for a gas turbine normal operation (oil systems, fuel gas,
ventilation systems, oil cooling system, GTG fire fighting system and etc.
17.3 Lube oil system
Valves position (opened/closed) for initial start-up and normal operation of lube oil system is
indicated in Schematic Piping Diagram.
The unit is equipped with one mechanical shaft-driven pump [9-P-12603X], an AC auxiliary pump
[9-P-12604X] and a DC emergency pump [9-P-12605X]. Their purpose is, to lubricate and cooling
the GT, as well as the gear box and generator, bearings during the unit operation.
The lube oil pumps are designed for continuous operation but are not operated after the gas turbine
package is shut down and the cool down timer has elapsed.
To operate the mineral lube oil pumps, the oil tank level and temperature shall be between the
operation limits; if the level (300400 mm. from tank top cover) or temperature (20C79C) is not
OK before starting, starting will be inhibited and an alarm will occur. If one of the parameters will be
not OK during operation of the unit an alarm and subsequently a shut down will occur.
Valves position (opened/closed) for initial start-up and normal operation of lube oil system is
indicated in Schematic Piping Diagram.
Prior to start the gas turbine, the operator selects:Auto control in MCC for [9-H-12601XA/B/C/D]
lube oil heaters and [9-PM-12604X] auxiliary lube oil pump, and in DCP for [9-PM-12605X]
emergency lube oil pump.
When unit start is selected the lube oil system starts automatically.

148

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

When the right pressure is restored permission to continue with starting sequence is given.
When the gas turbine reaches the OPERATING SPEED, at 95% of the rated speed, the AC
auxiliary lube oil pump will be manually stopped and the accessory gear driven main lube oil pump
guarantees the oil flow amount.
As long as the gas turbine is above the OPERATING SPEED, if the conditions LUBE OIL
HEADER PRESSURE LOW (MK VI command name 4QA) will be detected, the AC auxiliary oil
pump will be automatically started. If normal conditions are restored, the stand by pump can be
stopped manually from the HMI or from the MCC according to the duty/standby philosophy.
The lube oil header pressure low-level threshold [63QT-2A 63QT-2C]/[PT-12618-A/B/C], installed
on the Generator lube oil header, causes the DC emergency lube oil pump to start if lube oil header
pressure is lower than the shutdown level.
With such threshold, when the emergency pump comes in operation, the unit is in shutdown
condition.
Once the pump is started, it runs continuously for 15 minutes and then 30 seconds on, 3 minutes off
cycle is started for power supply batteries safeguarding until the end of cool down. The DC
emergency lube oil pump will be stopped as soon as the conditionLUBE OIL HEADER
PRESSURE NORMAL is detected [96QA-1 3]/ [PT-12618-A/B/C].
During normal GT operation, the operator is normally allowed to manually start and stop the standby
pump, unless it is prevented to run or required on by the control logic.
17.4 Hydraulic oil system
Valves position (opened/closed) for initial start-up and normal operation of the hydraulic system is
indicated in Schematic Piping Diagram.

149

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

The Gas Turbine is equipped with one mechanical shaft-driven pump installed on the Accessory gear
box. Its purpose is to operate the axial compressor IGV nozzles and the GT gas valves. [SR V-1 and
GCV-1]/[FCV-12601 & FCV-12602].
The H.P oil pump is designed for continuous operation but is not operated after the gas turbine
package is shut down.
To operate the Hydraulic oil pump, the oil pressure shall be inside the operation limit; if the pressure
value is not OK (6500 kPaG min.) an alarm will occur. The maximal pressure admitted for the
hydraulic mechanical driven pump delivery is 9000 kPaG regulated by a overpressure valve [VR21]/ [PSV-12601]; and is also protected from overpressure by a pressure regulating valve [VPR3-1]/
[PCV-12610] inside the pump body that will be regulated at 8000 kPaG.
If the pressures decrease under the minimal pressure (6500 kPaG) during the Unit operation an
alarm is generated by a pressure switch [96HQ-1]/[PT-12614]
When the hydraulic oil pump driven by accessory gear box reaches the 1500 RPM it guarantees the
oil pressure and flow amount during gas turbine operation.
17.5 Lube oil mist separator
Valves position (opened/closed) for initial start-up and normal operation of oil vapor separator is
indicated in Schematic Piping Diagram.
Prior to starting the GT operator selectsAuto control in MCC for [9-CM-12605X] lube oil vapor
separator.
One of the two lube oil vapor separator fans [9-CM-12605X] (the selected one as main) will be
started at turbine start-up and will continue to operate up to the end of cool down sequence. The
stand-by one will be started, by intervention of differential pressure transmitters, in case of oil tank
pressure increasing over the rated limit. Set: Alarm 20 mm.H2O; Trip 50 mm.H2O.
150

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

The fan will be started also in case of pressure detected in the lube oil tank after cool down end.
17.6 Fuel gas system (on base)
Prior to first gas-in, fuel gas system will be leak tested at normal operating pressure afterwards
followed by fuel gas system inerting using nitrogen (filling and purging until oxygen content at point
of supply to stop / ratio valve drops below 2%).
Required fuel gas supply pressure at point of supply to GTG must be between 1600 kPaG min. and
2400 kPaG max.
AFuel gas pressure low alarm is given in the Mark VI software by the [96FG-1]/ [PT-12602A/B/C] pressure transmitter, when gas pressure drops to 1400 kPaG.
Required fuel gas temperature for normal running at point of supply to GTG will be 28C above dew
point and in any case between 45C and 60C.
17.7 Cooling & sealing air system
The antisurge valves will be checked and will be open to be enable to start the Unit, the control of
opening of the valves will be verified by the signal transmitted by the positioning micro-switches
[33CB-1 and 33CB-2] sending a signal to the Control Panel.
Check the correct operation of the antisurge valves, before starting the turbine, using an external
source of air, to be able to open them by acting the relevant servovalve [20CB-1].

151

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

17.8 Ventilation & gas detection system


The gas turbine compartment is equipped with 2100% duty/standby ventilation fans [9-C-12608XA
and 9-C-12608XB].
Before proceeding to first start up of ventilation system operator ensures that all fire dampers for
ventilation air inlet and outlet are opened. Operation with fire dampers closed is not allowed.
The GT compartment ventilation fans are designed for continuous operation but are not operated
after the gas turbine package is shut down and cooldown timer has elapsed.
Prior to start the gas turbine, the operator selects: Main/Duty for [9-C-12608XA] turbine enclosure
ventilation fan and Standby for [9-C-12608XB] turbine enclosure ventilation fan, in Mark VI
software, and Auto control in MCC for [9-C-12608XA and 9-C-12608XB] and for [9-HH12608XA; 9-HM-12608XB] of motors space heaters.
When unit start is selected, the duty fan is started automatically.
After the activation of MASTER PROTECT IVE SIGNAL the fan is not stopped any more until
the end of cool down, unless emergency conditions such as fire dampers closed or fire detected in
the enclosure: in these cases all fans shall be immediately cut out.
Fans inhibition for fire dampers closed is not latched and once the dampers are open again the fans
are no more prevented to run.
If there are conditions asCompartment temperature high orGas detected in-side enclosure, the
stand by fan automatically starts. If normal conditions are re-stored, the duty fan can be stopped
manually from the HMI or from MCC according to the duty/standby philosophy.
During normal GT operation, the operator is never allowed to manually stop the duty fan.

152

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

The operator is normally allowed to manually start and stop the standby fan, unless it is prevented to
run or required on by the control logic.
The operator is allowed to initiate any time a duty/standby changeover: the selection is performed by
means of the MK VI <HMI> operator interface software pushbutton.
17.9 Starting system
A visual inspection of the turbine should be performed before attempting to operate the GTG.
Prior to starting the gas turbine, the operator will close the switch of [9-PD-12606X] starting motor
in MCC.
Before starting will be selected the mode of GTG operation putting the Main Selector in required
condition (CRANK, FIRE, MANUAL, AUTO, and RE-MOTE).
Will be checked the correct operation of the [33CS-1] (starting clutch limit switch).
17.10 GT Fire detection & fighting system
Valves position (opened/closed) and instruments condition for initial start-up and normal operation
of fire fighting system is indicated in Schematic Piping Diagram.
The two banks of CO2 bottles (main and spare) are operated by the Turbine Control System.
The condition ready to start will be given by the limit switches [33CP-1A/B] positioned on the
quick and slow discharge valves installed on the CO2 line to the turbine enclosure.
In case of fire the sensors installed on the accessory compartment [45FA-1/2] [45FT -14] fire
detectors; on the turbine compartment fire detectors and/or [45FT-5/6] heat detectors send fire
signals to UCP and this one generate a CO2 discharge command.

153

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

There are in the system two discharge solenoid valves operating the different groups of CO2 bottles
(for quick discharge and for slow discharge). When the fire is detected the valves [45CR-1/2] in
bank A (main bank) e energized opening the quick discharge group and consequently also the slow
discharge flow.
When is detected the fire signal are activated two alarms signal on the acoustic enclosure, through
the horns [XA-12] as acoustic signal and through the flashing lights [XL-12] as a visual signal.
The UCP fire fighting system is provided with two Fire fighting auto-inhibit switch [33CP-1A and
33CP-2Ato inhibit the discharge phase of CO2 for permission to start-up. Every inhibit signals from
the fire fighting system send an alarm to the UCP inhibiting the turbine start-up.
The start-up of the turbine will be also inhibited when the signal System fault (66XX-A/B) send
an alarm to the UCP.
The Discharge inhibition on the fire fighting system is signaled by a green lamp, lighted with the
system in AUTO mode and with an amber light when the discharge is inhibited. But the inhibition is
actuated for CO2 discharge only, while the detection modules with the relevant indications are
operating.
17.11 Generator
Valves position (opened/closed) for initial start-up and normal operation of lube oil system of
Generator is indicated in Schematic Piping Diagram.
Prior to starting the gas turbine, the operator shall check the correct oil supply pressure to the
generator bearings by the pressure indicators on the oil header, on the bearings inlet piping DE and
NDE side respectively. Will be checked also the oil flowing through the discharge oil piping flow
gauges (FG12632X; FG12633X).
The operator will check on the vibration monitor, Generator section, and the correct readings of
154

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

vibration sensors, the key-phasor values and the bearings temperature elements, to verify the correct
operation.
Will be checked also the stator winding cooling thermo elements readings for correct operation.
17.12 Load Gear Box
Valves position (opened/closed) for initial start-up and normal operation of lube oil system of Gear
Box is indicated in Schematic Piping Diagram.
Prior to starting the GTG, the operator shall check the correct oil supply pressure to the Gear Box
bearings by the pressure indicator on the oil header and the oil flowing through the bearings
discharge oil piping flow gauge (FG12631X).
Furthermore will be checked on the vibration monitor, gear box section, the correct axial positioning
of the shaft and the readings of vibration sensors and the bearings temperature elements, to verify the
correct operation.

155

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

17.13 PROCEDURE OF START-UP


Checks Prior to Start-Up
Gas Turbine checks
A visual inspection of the turbine should be performed before attempting to operate a new turbine,
with the lube oil pump operating and emphasis on the following areas:
1) Check that all piping and turbine connections are securely fastened and that all blinds have been
removed.
2) Inlet and exhaust plenums and associated ducting are clean and rid of all foreign objects. All
access doors are secure.
3) Where fuel, air or lube oil filters have been replaced check that all covers are intact and tight.
4) Verify that the lube oil tank is within the operating level and if the tank has been drained

that it

has been refilled with recommended quality and quantity of lube oil. If lube oil flushing has been
conducted verify that all filters have been replaced and any blinds if used, removed.
5) Check operation of auxiliary and emergency equipment, such as lube oil pumps, etc. Check for
obvious leakage, abnormal vibration, noise, or over-heating.
6) Check lube oil piping for obvious leakage. Also using provided oil flow sights; check visually
that oil is flowing from the bearing drains. The turbine should not be started unless flow is visible at
each flow sight.
7) Check condition of all thermocouples and/or resistance temperature detectors. Reading should be
approximately ambient temperature.
8) Device requiring manual lubrication is to be properly serviced.
9) Check the Cooling and Sealing Air Piping against the assembly drawing and piping schematic,
that all orifice plates between flanges or in orifice unions are of designated size and in designated
positions.
10) At this time all enunciated ground faults should be cleared. It is recommended that units not be
156

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

operated when a ground fault is indicated. Immediate action should be taken to locate all grounds
and correct the problems.

Generator/Gear Box checks


1)

With turbine oil pumps running check the oil flushing through the generator bearings and the

load gear box.


2)

Excitation system in operation

3)

Protection system in operation.

General checks by HMI Video Display


The most important controls to be made to verify the GTG conditions in real time, during startup or
operating sequences, should be executed by the HMI video display.
Checks during Start-Up and Initial Operation
The following checks must be done on a GTG, these checks should include: leakage test, vibration
unusual noise, overheating, and lubrication.
Listen to noise
Start turbine and stop it at around 600 rpm.
Listen for rubbing noises in the turbine compartment, load gear and genera tor.
A sound scope or some other listening type device is suggested.

157

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

Crank
1.

Listen for rubbing noises in the turbine compartment, load gear and generator.

2. A sound scope or some other listening type device is suggested. Shutdown and investigate if
unusual noise occurs.
3. Check for unusual vibration
4. Inspect for oil leakage.
Fire
1.

Check entire fuel system and the area immediately around the fuel nozzle for leaks. In

particular check for leaks at the following points:


a. Fuel oil piping/tubing to fuel nozzle
b. Fuel gas valves
c. Gas piping to the burner.
2.

Monitor the turbine control panel readings for unusual exhaust thermocouple temperature,

wheel-space temperature, lube oil drain temperature, highest to lowest exhaust temperature spreads
and hot spots, combustion chamber burning hotter than all others.
3.

Listen for unusual noises and rubbing.

4.

Monitor for excessive vibration

Manual, Automatic, Remote


1.

Continue monitoring for unusual rubbing noises and shutdown immediately

if a noise persists.
2. Monitor lube oil tank, header, white metal bearing and bearing drain temperatures continually
during the starting period.
3. At this time a thorough vibration check is recommended, using portable vibration test equipment
158

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

with filtered and unfiltered readings.


It is suggested that horizontal, vertical and axial data be recorded for the:
a) Accessory gear forward and after sides.
b) All accessible bearing covers on the turbine.
c) Turbine forward compressor casing.
d) Turbine support legs.
e) Covers on the driven Units.
4. Check and record wheel space, exhaust and control thermocouples for proper indication on the
control display.
5. Check and record electrical characteristics of generator.
6. Monitor control display data for proper operation.
17.14 Gas Turbine Start-up & Operation
Introduction
The mode of operation for GTG is:

OFF

CRANK

FIRE

MANUAL

159

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

AUTO

REMOTE

O&U-12-OM110
01
02/08/2010

General
The GT Unit Control Panel is equipped with two HMI: one (local) in the Main Sub Station Building,
for controlling purposes, and the other (remote) in the Central Control Room(CCR-I) for monitoring
purposes, as normal options.
Once the main HMI fails, the controlling functionality of the second HMI is enabled and the
operator can continue to control the unit.
Modes of operation and sequences
There are six operating modes varying from no start acceptance to full automatic start. Only one
mode can be active selecting one mode (position) of MASTER SELECTOR means disabling all the
other modes.
The mode selection can be performed at the local MKVI HMI (PC operator inter-face) and at the
operator back-up panel mounted in the front of the Mark VI panel. The back-up feature is required to
give the operator the ability to control the unit (basic function as START, STOP) in case of a failure
of the MKVI HMI or loss of customer UPS power supply.
Mode selection can be used to bring in some hold points in the start sequence and to monitor the
process at these stages.
a)

O f f Mode

When the OFF Mode is selected, the UCP does not accept the START command, and is thus not
possible to start-up the machine. All other functions remain active.
160

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.

O&U-12-OM110

Revision
Date of issuance

01
02/08/2010

Auxiliaries manual control is possible, if the relevant safeties are satisfied.


It shall not be possible to select and initiate the OFF Mode when the GTG is running or the
COOLDOWN sequence is still in progress.
b)

Crank Mode

CRANK sequence may only be selected after the gas turbine has stopped rotating.
Starting the turbine with this selection is possible if the unit start permissive is satisfied.
Starting the turbine with this selection will bring the shaft up to crank/purge speed value of 20%
(14HM).
Sequence will precede changing Master Selector position to FIRE, MANUAL, AUTO, or REMOTE
position. The shaft will continue to rotate at 20% of speed value until the operator initiates a normal
STOP, changes the Master Selector position or a shutdown occurs. Gas turbine shaft can remain at
this speed indefinitely if the operator will not select another command.
For OFF-LINE WATER WASH the selection of CRANK mode is mandatory, and as long as the
wash cycle is enabled the CRANK mode will be locked.
c)

Fire Mode

This mode of operation shall primarily be used to verify that the GT start sequence functions
properly.
Once the start permissive are valid/healthy, the operator may initiate start.
The turbine will continue to run at warm-up speed, unless the operator selects another operation
mode or initiates a normal stop or shutdown.

161

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

By subsequently selecting MANUAL, AUTO or REMOTE Mode, start-up sequence is executed to


accelerate the shaft of the turbine to the preselected speed.
d)

Standard Manual Mode

In the MANUAL Mode a start signal will result in an automatic start-up and loading to the minimum
operating speed, then the shaft speed is controlled by raise and lower commands on HMI.
e)

Auto Mode

In the AUTO Mode a start signal will result in an automatic start-up and loading to the selected
value, an external signal from DCS is taken as shaft speed set point.
f)

Remote Mode

In REMOTE Mode position, the set point of load may be varied from outside through the commands
from DCS. The increase and decrease variation speed of the turbine shaft depends on the value
imposed by the automatic ramp and can be modified through the Operator Interface.
Start-up sequence AUTO / REMOTE mode
AUTO or REMOTE Mode enables initiation of the complete start sequence, up to the pre-selected
speed of turbine shaft.
a)

Prior to start-up permissive must be confirmed; these will include:

No other modes selected and/or other sequences initiated and/or in progress (except lube oil

pump or enclosure fans post-run sequences)

Package off mode not selected

GT speed = 0 RPM
162

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

Package shutdown push buttons reset

Fuel control valves (SRV and GCV) in correct position (closed)

Fuel gas vent valve 20VG-1 in correct position (check status of output relay)

Fuel gas supply pressure above minimum

Package enclosure doors closed

Fire dampers open

Fire alarm cleared

CO2CO2 system not in fault

Battery voltage from DCP above minimum

Emergency lube oil pump Ready to start

MCC Ready to start

All parameters that are monitored for alarm and trip purposes are in the healthy state for start-

up (lube oil tank has the correct oil level and temperature, etc.)

All trip identified in P&I diagrams are cleared

Fuel gas inlet pressure not low (63FG- 1)

b)

When the Shut Down reset and Ready to start check condition as per (Control system

functional description) are satisfied, the message UNIT READY TO START will be shown on the
163

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision

O&U-12-OM110
01

Date of issuance

02/08/2010

MK VI<HMI> operator interface display.


c)

The START command can be initiated by the software pushbutton on MK VI<HMI> and the

following actions will be initiated:


d)

Start automatically the Gas Turbine Lube Oil auxiliary pump [9-PM-1 2604X]. When the lube

oil header pressure is restored, the lube oil system is considered ready for operation.
e)

Start automatically the Lube Oil main Separator fan [9-CM-12605X]

f)

Start automatically the Gas Turbine main ventilation fan [9-CM-12608XA]. The compartment

is equipped with 2100% ventilation fans. Automatic start of standby fan for the GTG is initiated by
high temperature and/or high gas concentration and/or main fan failure.
g)

UNIT READY TO START condition is achieved and if no shutdown condition is present

(theMASTER PROTECTIVE RELAY (4x) is still activated), the MK VI logic will give the
command to start the starting motor.
h)

The motor starts (4CR) is energized

i)

The turbine will accelerate up to crank speed (20% of shaft speed value 14HM).

j)

Start the turbine purge phase (approximately 2 minutes, to be configured in field) to purge the

turbine, combustion air inlet and exhaust systems, and wait for purge completion.
k)

Open the fuel gas vent valve [20VG-1] and when the fuel gas temperature reaches the set

threshold, the fuel gas vent valve [20VG- 1] will be closed.


l)

Completed the purge time, is energized the ignition (L2TVX).

m)

MKVI will check for excessive fuel flow, if that condition is detected a trip is initiated.

n)

Allow a maximum of 1 minute for light off; activate fail to ignite alarm if flame is not

detected within 2 minutes and continue to rotate at crank speed.


o)

The fuel amount is reduced and the warm-up timer is started.

p)

At the end of warm-up period (1 minute), the torque converter raises output torque unless Fire

mode is selected; in this case the turbine shaft will continue to rotate at warm-up, more than 20%
speed.
q)

The torque converter is accelerated and fuel is increased to reach the mini-mum operating
164

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

speed; during the acceleration sequence, when the turbine shaft reaches the 60% speed (14HC), the
clutch will automatically disconnected. The starting system decelerating up to minimum speed, the
starting system is stopped five minutes later (cooling time).
r)

At 90% speed of the shaft (14HSX), minimum operative speed, the lube oil auxiliary pump [9-

PM-12604X] (4QA) will receive a command to stop. The generator excitation is enabled.
s)

When the turbine shaft reaches 95% of speed (14HS-1) will be closed the axial compressor

bleed valve and the complete sequence flag will be set.


t)

After completing the Start up sequence, are enabled the speed set-point variation and the

turbine is ready to synchronize.

Activities on Generator
The following operating activities are only suggested.
Reached the complete sequence of the turbine shaft, and before synchronizing the Generator with the
network, it will be possible to perform the Generator checks, as follows:
a)
b)
c)

Short circuit checking at Generator terminals.


After exciting the Generator at required current, check the stator current measuring circuits.
Check, for each protection branch, the differential current protection, following the noting

the trip value.


d)

Check the unbalance protection increasing the stator current and noting the trip value.

e)

Check the rotor earth protection increasing the current excitation at the required value.

f)

Test of overload protection

g)

After the no load test check the Min. and Max. Voltage protections.

h)

With Generator at the rated voltage, check the frequency protection.

165

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

i)

Testing of the power protection (power return, excitation loss, etc.).

j)

Before proceeding with the synchronization check:

O&U-12-OM110
01
02/08/2010

- The synchronoscope 0,
- The differential voltage 0,
- The frequency at the coupling switches closing on an out of voltage network.
Synchronization sequences
At minimum operating speed excitation control will be enabled. The Mark VI checks the
synchronization permissive conditions and the speed reference is set at 100.3%. When 100.3% is
reached Unit ready to synchronize is displayed.
The operator has the opportunity to select in the Mark VI<HMI> Synchronization Mode Selector
the following mode: off, manual, automatic or dead bus.
a)

Off mode

Disable all the Mark VI synchronizing functions.


b)

Manual mode

The synchronization will be made in manual mode. The panel will send the raise/lower commands
signals to excitation panel for the voltage regulation. When the unit is synchronized, the operator
will close the breaker from the HMI.
c)

Auto mode

The Mark VI will adjust the speed and voltage, and will issue the command for breaker closure when
unit is synchronized.
166

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

d)

O&U-12-OM110
01
02/08/2010

Dead bus mode

For this mode, the breaker is closed before to close contactor on ECP. This will avoid high inrush
current due to energization of transformer.
As soon as the breaker is closed, the closing command to excitation contactor on ECP is given and
the generator rise on voltage and energize transformers. Once the rated voltage is reached the UCP
can start to load the machine.
Load control
Droop or isochronous control is selected on HMI.

Droop mode
When the GTG unit is connected in parallel to the main grid, the system frequency is determinate by
the grid itself and is maintained constant. The excess of fuel flow does not result in speed variation,
but in augmentation of power ex-ported to the grid.
The operator can enter a certain MW value as a load control constant. When pre-selected load is
selected the unit will automatically load or unload till the required value.
The selected mode of control (spinning reserve, preselected) will be reset to manual control when the
operator uses the raise/lower commands on HMI or when the governor control is transferred from
droop to isochronous.
The VAR control is based upon the use of voltage raise and lower signals to ECP.
Isochronous

167

GTG (MS-5001-PA)
INITIAL START-UP PROCEDURE
AND GENERAL GUIDE LINES

Document No.
Revision
Date of issuance

O&U-12-OM110
01
02/08/2010

The unit is controlled to maintain a constant speed, regardless of the grid load re-quest and
regardless of the supplier power. When the unit is in this mode, it is not possible to set a supplied
power set point.

168

Você também pode gostar