Escolar Documentos
Profissional Documentos
Cultura Documentos
Rev.
Date
Description
Originator
Checker
Approver
CONTENTS:
1.0
2.0
2.1
2.2
2.3
2.4
3.0
3.1
4.0
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
5.0
6.0
OBJECTIVE................................................................................4
INTRODUCTION........................................................................4
Background.............................................................................4
Objective.................................................................................4
Project Description.................................................................4
Design Capacity......................................................................6
CONTROL PHILOSOPHY (GENERAL).......................................6
Process Control Narrative......................................................6
PROCESS DESCRIPTION & CONTROL NARRATIVE................7
Inlet manifold..........................................................................7
Inlet Separators (V6801, V-6802)...........................................8
Compressor suction header pressure controller..................11
Suction Coolers (E-6811, E-6821 & E-6831)........................12
Compressor Suction Scrubbers (V-6811, V-6821 & V-6831) 13
Booster Compressors (K-6810, K-6820 & K-6830)................15
Compressor After Coolers (E-6812, E-6822 & E-6832)........17
Condensate Separator (V-6803)............................................19
REFERENCE............................................................................23
ATTACHMENTS.......................................................................23
ABBREVATIONS
AADL
CCR
CESD
COGS
CPSD
DCS
EPC
ESD
FAR
FCS
FEED
FGS
HMI
IPS
LCP
MADL
MMSCFD
MMSCMD
PAS
PDO
PEFS
PFS
PLC
PSD
SGS
SNDC-1
SNGP
SNOS
SNS
SROS
UCP
1.0 OBJECTIVE
The objective of this document is to provide a Process Control
Narrative of the Depletion Compression Facility (Project Phase I) at
Saih Nihayda Gas Plant. It is expected that this document will be
kept up to date during FEED and detailed engineering stage.
2.0 INTRODUCTION
2.1 Background
The Saih Nihayda Deep Field is located within the cluster of nonassociated gas fields in the central Oman. The field is situated 28 km
north east of the Saih Rawl Central Processing Plant and 20 km west
of the Qarn Alam Oil station. The field has been producing via the
Saih Nihayda Gas Plant (SNGP) since Q1 2005. Based on the current
forecasts the reservoir pressure will begin to decline below the
current inlet pressure of the SNGP within the next 6 years. At this
point, the 1st Stage of Saih Nihayda Depletion Compression (SNDC1) Project will be required to deliver the gas from the wells to the
required inlet pressure of the SNGP.
2.2 Objective
The principal objective of the SNDC-1 Project is to receive about 21
MMSCMD gas and the accompanying condensate, at pressures from
70 to 38 bara, separate the condensate, compress the gas and
deliver compressed gas to the existing Gas Plant Wet gas Cooler E6212 at the conditions matching design of the existing gas plant.
The SNDC-1 involves installation of 3 nos of gas compressor units at
upstream of the existing inlet wet gas cooler E-6212. This will enable
the SNGP to continue exporting to the Central Oman Gas System
(COGS), a sustainable Maximum Annual Daily Load (MADL) of 20
MMSCMD gas. The planned on-stream date is January 2013.
Based on the 2008 Gas Business Plan, the SNGP is to produce an
Annual Average Daily Load (AADL) of 12 MMSCMD from the SN
Deep reservoirs (Barik, Miqrat & Amin), with a potential upside of
14 MMSCMD. However, in either case the compression facility must
meet MADL at 20 MMSCMD while being capable of turndown to 6
MMSCMD at high energy efficiency.
2.3
Project Description
Booster
Compressor
package
units
(A-6810/20/30)
consisting of compressors
(K-6810, K-6820 & K-6830)
Condensate Separator.(V-6803)
The overall schematic of process equipment lineup of the new
SNDC-1 facility is shown in the Figure 2.1.1 below.
Figure 2.1.1: SNDC-1 Facility Schematic
2.
3.
2.4
4.
5.
Design Capacity
The table below summarises the existing SNGP design
capacities
Existing System
Capacity
20 MM Sm3/d
10000 m3/d
1000 m3/d
20 MM Sm3/d
10000 m3/d
1000 m3/d
0.016 MM Sm3/d
II.
III.
IV.
V.
VI.
Inlet manifold
Refer the following PEFS:
1) SNG-249-PX-2365-68001-0001
2) SNG-1-6213-001
4.1.1 Process
During SNDC-1 Station commissioning and transition period, both
ends of the manifold will be active, supplying gas simultaneously to
both SNDC-1 and SNGP facilities. Since SNGP process requires inlet
pressures well in excess the upper operating limit of the SNDC-1
inlet pressure, a pressure let down valve (68PCV-0006) is provided in
the common outlet header of the inlet separators (V-6801/02.)
During the transition, the let down valve will be modulated by a
pressure controller installed on common inlet header of compressor
units.
SNDC-1 Compressors will operate at constant speed during the
transition period. The high pressure constraint controller (68PICA0003) to the well head will remain inactive during transition period.
The existing high pressure constraint controller (62PICA-103) will
protect the flow lines, manifold and inlet piping.
Past the transition period, the entire field production will feed the
SNDC-1 Facility and the pressure letdown valve (68PCV-0006) will
be bypassed. The control of SNDC-1 inlet pressure from now on will
be from the pressure controller (68PICA-0003) on the feed line to
inlet separators.
4.2
1) SNG-249-PX-2365-68002-
2) SNG-249-PX-2365-68002-0002
4.2.1 Process
Plant Inlet Separators are the first component of SNDC-1 Facility
and will operate as vertical 3-phase separators. The upstream
system consists of gas producing wells, production gathering flow
lines, and Plant Inlet Manifold.
The Plant Inlet Manifold will be extended on its top and a new
header will be installed to direct well production to SNDC-1 area.
The symmetrical inlet piping is considered for both inlet separators.
Objective
Functional Description
I. Start-up
During start-up the controller shall be in manual mode.
However opening of 68UZV-0101 will drive 68FCV-0101 in
auto mode.
II. Normal Steady-State
Level transmitter is tracking the actual value.
III. Crippled mode operation
In case of input signal failure the level cotroller will be put in
manual mode. Valve opening and closing will be done
manually.
IV. Shut down
During the PSD or ESD of the inlet separator, upstream PSD
valve
(68UZV-0101) will close and activates 68XS-0101
which will close 68FCV-0102.
V. Operator interface
DCS graphic displays will show all real time process data.
VI. Calculation
No calculations are required.
VII. Special consideration
None.
VIII. History
None.
4.2.3 Gas flow Control Logic
68LICA-0107A-Condensate level controller
68FICQA-0101-Gas flow controller
68Y-0101-Low selector
4.2.3.1
Objective
Functional Description
Start-up
During start-up the controller shall be in manual mode and
after stabilisation of operation, it will be put in the auto mode.
II.
Normal Steady-State
Flow transmitter is tracking the actual value.
III.
IV.
Shut down
During station ESD, 68FCV-0101 will be opened.
V.
Operator interface
DCS graphic displays will show all real time process data.
VI.
Calculation
No calculations are required.
VII.
Special consideration
None.
VIII.
History
None.
Objective
Functional Description
Start-up
During start-up the controller shall be in manual mode.
However opening of 68UZV-0102 will drive 68LCV-0103 in
auto mode.
II.
Normal Steady-State
Level transmitter is tracking the actual value.
III.
IV.
Shut down
During the PSD or ESD of the inlet separator , upstream PSD
valve
(68UZV-0102) will close and activates 68XS-0102
which will close 68LCV-0103.
V.
Operator interface
DCS graphic displays will show all real time process data.
VI.
Calculation
No calculations are required.
VII.
Special consideration
None.
VIII.
History
None.
4.3
Objective
During transition period, the inlet manifold pressure is 100 barg and
compressor can not be started with such a high suction pressure.
Therefore 68PICA-0006 and 68PCV-0006 will be used to control
compressor common suction header pressure in order to achieve the
required pressure at compressors suction (i.e. approximately 70
barg).
4.3.2.2
Functional Description
I. Start-up
During start-up the controller shall be at manual mode. The
pressure letdown valve 68PCV-0006 shall be opened
manually. Then the controller will be changed to AUTO mode.
II. Normal Steady-State
During normal operation, the controller shall be in auto mode
and regulates the pressure letdown valve.
III. Crippled mode operation
No special provisions are required
IV. Shut down
No special provisions are required.
V. Operator interface
DCS graphic displays will show all real time process data.
VI. Calculation
No calculations are required.
VII. Special consideration
None.
VIII. History
None.
4.4
Objective
Functional Description
I. Start-up
During start-up the low low temperature trip (68TZA-1103)
shall be overridden. The temperature controller 68TICA-1102
implemented in the DCS is configured with a default setting
with 0.0 % output and will "only" transfer to AUTO mode and
local set point on having received a request to start the fin
fans from the start-up sequence
II. Normal Steady-State
Temperature transmitter will control the variable speed
drives of the cooler fans in order to keep the outlet
temperature of the gas between 60 to 30 deg C.
III. Crippled mode operation
Temperature transmitter will be put in manual mode. Start /
stop of the cooler fans will be done manually.
IV. Shut down
No special provisions are required.
V. Operator interface
DCS graphic displays will show all real time process data.
VI. Calculation
No calculations are required.
VII. Special consideration
None.
VIII. History
None.
4.5
Process
Objective
Functional Description
4.5.2.3
I.
Start-up
During start-up, the controller shall be in manual mode.
However, opening of 68UZV-1120 will drive 68LCV-1101 to
auto mode.
II.
Normal Steady-State
Level transmitter is tracking the actual value.
III.
IV.
Shut down
During the PSD or ESD of the suction scrubber, upstream
PSD valve
(68UZV-1120) will close and activates 68XS1140 which will close 68LCV-1101.
V.
Operator interface
DCS graphic displays will show all real time process data.
VI.
Calculation
No calculations are required.
VII.
Special consideration
None.
VIII.
History
None.
4.6
6.SNG-249-PX-2365-
2. SNG-249-PX-2365-68020-0002
68020-0003
7.SNG-249-PX-2365-
3. SNG-249-PX-2365-68030-0002
68030-0003
8.SNG-249-PX-2365-
4. SNG-249-PX-2365-68003-0001
5. SNG-249-PX-2365-68004-0001
4.6.1 Process
Gas from the suction scrubber is routed to compressor. Between
start-of-run to end-of-run conditions for Phase SNDC-1, Booster
Compressor will receive from about 10.5 to 7 MMSCMD gas at
pressures ranging from 70 to 38 bara and compress it to a pressure
required at SNGP inlet for meeting its export gas target. The most
severe discharge temperature at the end-of-run is estimated to be
about 175C.
The compressor will be a single stage centrifugal type and will be
driven by a synchronous electrical motor
The suction pressure of the compressors will depend on the supply
pressure at the Plant Inlet Manifold, which will be controlled as
described in Section 4.1.1. During initial phase of operation, gas
inlet pressure will be high enough for two compressor operation,
with the third on standby, resulting in a marked improvement in
availability and production efficiency.
Compressor control will have an integrated capacity & antisurge
control. Each unit will have an independent antisurge control
integrated with overall capacity control for the entire trains. The
integration will ensure the turndown and stability.
Compressor will have a dry gas seal system, with process gas for
primary seal and instrument air as separation gas for secondary
seal. Primary seal vents will be routed to the existing SNGP AP Flare
system. Normally, seal gas for the compressor primary seal will be
provided from compressor discharge, with a cold start supply from
fuel gas line. Each compressor will have its own seal gas treatment
unit consisting of a heater, pressure letdown valves and a filter.
The control narrative for a Booster Compressor K-6810 is discussed
in this document and the same is applicable for the other booster
compressors (K-6820 and K-6830).
4.6.2 Controls
4.6.2.1
Objective
Functional Description
Start-up
During start-up the low low temperature trip (68TZA-1204)
shall be overridden. The temperature controller 68TICA-1203
implemented in the DCS is configured with a default setting
with 0.0 % output and will "only" transfer to AUTO mode and
local set point on having received a request to start the fin
fans from the start-up sequence.
II.
Normal Steady-State
Temperature transmitter will control the variable speed
drives of the cooler fans in order to keep the outlet
temperature of the gas at 100 deg C.
III.
IV.
Shut down
No special provisions are required.
V.
Operator interface
DCS graphic displays will show all real time process data.
VI.
Calculation
No calculations are required.
VII.
Special consideration
None.
VIII.
History
None.
4.8
Objective
Functional Description
Start-up
During start-up the controller shall be in manual mode.
However, opening of 68UZV-0303 will drive 68FCV-0302 in
auto mode.
II.
Normal Steady-State
Level transmitter is tracking the actual value.
III.
IV.
Shut down
During the PSD or ESD of the condensate separator ,
upstream PSD valve (68UZV-0303) will close and activates
68XS-0301 which will close 68FCV-0302.
V.
Operator interface
DCS graphic displays will show all real time process data.
VI.
Calculation
No calculations are required.
VII.
Special consideration
None.
VIII.
History
None.
Objective
Functional Description
Start-up
During start-up the controller shall be in manual mode.
However , opening of 68UZV-0303 will drive 68LCV-0301 in
auto mode.
II.
Normal Steady-State
Level transmitter is tracking the actual value.
III.
IV.
Shut down
During the PSD or ESD of the condensate separator ,
upstream PSD valve (68UZV-0304) will close and activates
68XS-0302 which will close 68LCV-0301.
V.
Operator interface
DCS graphic displays will show all real time process data.
VI.
Calculation
No calculations are required.
VII.
Special consideration
None.
VIII.
History
None.
Objective
Functional Description
Start-up
During start-up both the controllers shall be in manual mode
until the pressure will reach to normal value, then it will be
put in the auto mode.
II.
Normal Steady-State
Pressure transmitter is tracking the actual value.
III.
IV.
Shut down
Operator interface
DCS graphic displays will show all real time process data. All
control modes and parameters, except the calculation
functions of pressure controllers, will be available in standard
graphic displays and accessible to the operator.
VI.
Calculation
Calculations block is required.
VII.
Special consideration
None.
VIII.
History
None.
Objective
Functional Description
I. Start-up
During start-up pressure differential switch shall be in
manual mode and inlet valve shall be kept open. When the
pressure in the condesate separator reaches to normal value,
then it will be put in the auto mode.
II. Normal Steady-State
Pressure transmitter is tracking the actual value.
III. Crippled mode operation
In case of input signal failure, the pressure differentail switch
will be put in manual mode. Valves opening and closing will
be done manually.
IV. Shut down
No special provisions are required.
V. Operator interface
DCS graphic displays will show all real time process data.
The switch mode and other parameters, except the
calculation functions of pressure switch, will be available in
standard graphic displays and accessible to the operator.
VI. Calculation
Calculations block is required.
VII. Special consideration
None.
VIII. History
None.
5.0 REFERENCE
6.0 ATTACHMENTS
Appendix-I
Process Control Schematic Diagram
Appendix-II
Process Engineering Flow Schemes