Escolar Documentos
Profissional Documentos
Cultura Documentos
Bullflex-O-Ring-Seal
Bullflex-Support Systems
Bullflex-Pillars
Bullflex-Special Products
Bullflex
Bullflex is Product and System
Textile shutter made of fabric with high tensile strength, ideal dewatering for an
optimum water-cement ratio of the grout, flat- or round woven, manufactured to
all required dimensions. We stock for quick response bigger amounts of round
woven Bullflex-Hoses in the diameters 230, 320, 400, 500, 630 und 800 mm.
Even for special dimensions we try to deliver in the shortest possible time.
Please, ask for an specified offer.
System for support, sealing, replacement and filling of cavities in tunnelling,
mining and the civil engineering even under water.
We plan and calculate for you; we deliver products and complete systemsolutions up to turn-key works to your request.
Only Bullflex is Bullflex.
Bullflex-Products
Originals made by
Bullflex-Pillars
Bullflex O-Ring-Seals
Special Applications
Bullflex-Reinforcing-Hoses
The proven Reinforcement System
for Mining and Tunnelling
immediate stress transfer
defined grout consumption
compatible to various
steel arch profiles
lagging mat
pressed to the
rock
steel arch
Gallery with rigid steel-arches and Bullflex-hoses at the colliery "Taiheiyo" in Kushiro, Japan.
3. Types of Pumps
For the filling of the Bullflex -Reinforcement-Hoses most grout pumps can be used.
The ideal pump type is a screw pump with a capacity of 2,0 to 4,0 m per hour. If a
piston pump with a capacity of more than 4,0 m/h is used the pump should be driven
at the end of the filling procedure as slow as possible to avoid damage to the hose
due to the last piston stroke.
We are at hand for questions concerning the use of the pumps our customers intend
to use.
Picture 1
Then the hose is rolled down to both sides (Picture 2).
Picture 2
Depending on the profile of the steel arches the Bullflex -Reinforcement-Hoses are
fixed on the arch by soft steel wires and/or clamps. For a channel section profile such
as the TH-profile the wires will be bound loose around the hose and the arch at approximately 1.0 m centres. These wires prevent the hose rolling off during filling. For
a GT-profile or similar reusable clamps should be used in addition to the wires (Picture 3).
After the Bullflex -Reinforcement-Hoses has been fixed onto the arch the filling nozzle is inserted into the filling valve and fixed by a clamp (Picture 3). If more than one
valve is built in to hose the filling starts at the valve which is the easiest to be
reached. When the filling pressure is approximately 4 bar or the steel arch starts to
move the filling hose should be connected to the valve at the opposite end. Normally
the hose can be filled through one valve. The additional valves are for safety to be
sure that the hose can be filled completely even if the hose is pinched by stone fall
or other reasons.
During the filling the hose should be observed because it might slide or roll from the
arch. If this happens the filling must be stopped instantly and the hose must be put
back into position.
While filling the wires are removed one by one as soon as they cause a constriction
in the expansion of the hose.
Cut Arch B
Legend
Arch B
1- Bullflex-Reinforcement-Hose
2- Bullflex-Grout-Container for Cavitity-Filling
Arch A
The pictures 2 and 3 show the Italian variant of the arch support, made of 2 light-weight IPBprofiles with joints from the same profile. This support has got the advantage of a greater
stiffness against torsion opposite to an arch made of one IPB profile with a same total weight.
Picture 4: Look in a tunnel heading with double arches and BullflexReinforcement-Hoses for pre-stressing of the support .
At use of this pipe screen method in the Maiko tunnel in Kobe, Japan, support arches were
used from an IPB 240 profile. The Bullflex Reinforcement-Hoses were there used since the
share of cohesive materials was so high in the sandy sediment that no continuous cement
screen could be built at an injection pressure of 60 bar. Clear subsidences which assumed
dubious extents moreover were already measured over the tunnel in the area built on. Measurings in front of and during the use of the Bullflex Reinforcement-Hoses showed that both
the lowering of the roof ridges at the road-head and the subsidences went back very fast after the first application to a permissible measure at the surface. In addition to these measurings voltage measurements were to the support arches during and after the filling of the
Bullflex Reinforcement-Hoses carried out. These measurings are documented on the following sides
Longitudinal
Cut
Lngsschnitt
Pipe Screen
Rohrschirm
Bullflex-Hose
Bullflex-Schlauch
BullflexBullflex-StopeFukissen
Cushion
Querschnitte
Cross Cuts
A -A
B-B
smallest Support
Arch
kleinster
Ausbauquerschnitt
grter
Ausbaubiggest Support
Arch
querschnitt
Pipe Screen
Rohrschirm
Bullflex-Hose
Bullflex-Schlauch
Bullflex-StopeBullflexCushion
Fukissen
1
2
Pipe Screen
Rohrschirm
Measurement
Levels
the Steel Profile
Meebenen
amonStahlprofil
Bullflex-Hoses
Bullflex-Schlauchsegmente
Results of theder
Measurement
Level 22
Ergebnis
Meebene
[kN/cm]
Stress
Pressure
-k
cu
rD g
n
u
n
n
a
p
-g s
u
Z
-5
A
-1
0
1
Time
Zeit[h][h]
1,0
2,0
3,0
2
3
1
Start
the fillingder
of the
StartofFllung
Bullflex-hoses
with grout
Schlauchsegmente
mit Mrtel
Positionof der
Position
the
Meelemente
measure
elements
inthe
dermeasureMein
ment
level
ebene
18
27
36
45
54
63
72
81
90
Auffahrung [m]
108 117 126 135
99
0
1
5
10
13
20
12
10
Start of Bullflex-Application
Bullflex-Einsatz
18
27
30
12 12
Setzungen an
Subsidences
der
Oberflcheon the
[mm]
Surface [mm]
Verfestigung
der Ortsbrust into the Tunnel Head
Poly-Urethane-Injections
mit Polyurthaninjektionen
berdeckung
Overburden [m]
[m]
40
30
20
10
0
9m
Pipe
Screen
Rohrschirm
0
18
27
36
45
54
63
72
81
90
99
18
27
36
45
54
63
72
81
90
99
Tunnel heading
Auffahrung
[m] [m]
108 117 126 135
0
5
10
15
20
28
30
27
34
34
35
40
43
50
Konvergenz der
Convergence
Tunnelfirste of
the
Roof [mm]
[mm]
32
Start of Bullflex-Application
Bullflex-Einsatz
Verfestigung
der Ortsbrust into the Tunnel Head
Poly-Urethane-Injections
mit Polyurthaninjektionen
Cross
Cut through
a Bullflex-Support
Querschnitt
durch einen
Bullflex-Ausbau
Monorail
Kranbahn
Diameter
of Bullflex-Hose: 230
Schlauchdurchmesser
230 mm
Reinforcement
Schalung by
aus Twinn
U 280-Profil
32 mm Profile
Shutter made of U 280-Profile
Fahrweg
ICE-Train-Rails
ICE-Bahn-Linie
Entrance
Shaft
Road
2418
Einstiegsschacht
Staatsstrae
B
approx.
20 m to
zumMainca.2
0m
the Main
Bereich
Bullflex-Ausbau
33,0mm
area
of mit
Bullflex-Support
33.0
Water Retaining
Stauerwand
Wall
Absetzbecken
Settling
Basin
Today a lively primary road, a ICE-Rail-Track and a small road are crossing the gallery rectangular. This causes the risk of intoxication of the well water. A renovation of
the front part of the gallery was necessary to protect the water against intoxication.
The renovation contained a closure of the back part of the gallery by a dam and a
stainless steel pipe led through the dam to the pump station nearby. Because no
water should be inside the front part of the gallery after the renovation the static balance was lost. A failure of the existing support has been calculated. The BullflexSupport-System was chosen to support the gallery. The system consists of the well
known Bullflex-Hoses which contain at this application an inner reinforcement. The
hoses are fixed in position inside of a shutter and then filled under pressure with
grout. The whole support reduces the clear space inside the gallery only by 0.1 m on
both side and at the top. This was very important because a stainless steel pipe of
400 mm diameter had to be installed in the gallery later.
The complete order contained the following work:
1.
the demolition and new construction of the entrance shaft
2.
the support of the gallery by the Bullflex-Support-System
3.
the installation of the monorail for the crane
4.
the erection of the water retaining wall including the inspection door and the
pipe penetrations
5.
the casting of the foundation for the sliding valve in the settling basin and
6.
the installation of the steel pipe in the gallery and in the shaft.
The work started on the 26th of January 1998.
Because it was impossible to fix the monorail for the crane at the existing roof screws
were connected to the inner reinforcement of every second Bullflex-Support. These
screws were led through the Bullflex-Fabric and protruded 50 mm out of the filled
support element. The monorail was then attached to the screws by a special hanger
system.
During the preliminary work for the construction of the water retaining wall a high
amount of water flushed in through the joints of the brickwork walls in the settling
basin. The inrush was stopped by the installation of one Bullflex-O-Ring-Seal and two
cubic Bullflex-Packers. A built-in drainage led the water coming from the roof to the
pumps behind the wall.
Picture1
For the temporary support of the bridge during the work a weight-carrying construction of Igirders with Bullflex-hoses was chosen. On both sides of the bridge one girder was fixed on
temporary abutments on the river banks. Rectangular to the streets axis 7 girders were fixed
on top of these. Welded in 100 mm centres to both sides of this 7 girders were strips of iron
which should protect the Bullflex-hoses against rolling off during the filling. The Bullflex-hoses
had the same length as the width of the bridge (Picture 2).
Picture 2
Picture 3
Picture 4
Picture 5
Picture 6 shows the temporary support before the lifting and fixing construction for
the girders had been dismantled.
Picture 6
Picture 7
Picture 8
After the dismantling of the threaded rods and the upper girders the whole load of the bridge
was led into the temporary abutments by the Bullflex-hoses and the girder-construction. Because all elements of the support were then beneath the bridge the whole surface was free
for the renovation works.
Picture 9
Bullflex-Pillars
a Support Element for Mining
for Underpinning and Support
of Buildings
fast
safe
shrinkfree
max .load
d 2 1
0,533 0.52 R 1000
4
140
h
0, 25 d
(*)
Uneven loads which can occur due to the erection of the pillar are considered in the formula.
The formula has been developed from the results of a series of load-tests done at the state's
institute MPA in Dortmund. She is valid for pillars without outside armouring. If an outside
armouring ( e.g. a steel-web ) is used the maximum load can be increased by up to 100 %.
10000
pillardiameter 0,28 m
pillardiameter 0,38 m
8000
pillardiameter 0,48 m
pillardiameter 0,528 m
6000
pillardiameter 0,68 m
pillardiameter 0,95 m
4000
2000
0
1
1,5
2,5
3,5
4,5
5,5
6,5
pillarheight [m]
(*)
The slenderness ratio may be limited by some circumstances. In DIN 1045 for
example is limited to 40 because of the maximum load-eccentricity
(**)
e.g. the German products HT33 of the Anneliese Zementwerke AG, DM1 of the
quick-mix Gruppe GmbH & Co. KG or SD1 of the Sakret Produktionsgesellschaft
Mnsterland or equal grouts.
Curing development
of the grout MS-CS
core drills taken from a
BULLFLEX-Pillar Pack
40
35
usual pack
30
25
20
15
10
0
1MIN
15MIN
1H
3H 5H
12H 1D 2D 3D 7D
Curing Time
immediate bearing
late bearing
early bearing
Filler
DES
28D
Load [kN]
Load-Deformation-Diagram
1500
1000
reinforced
not reinforced
500
0
0
30
60
90
120
150
180
Deformation [mm]
Load [kN]
Load-Deformation-Diagram
1200
1000
800
1 day curing time
600
400
200
0
0
30
60
90
120
150
180
Deformation [mm]
Load [kN]
Load-Deformation-Diagram
3000
2500
2000
10 % cement
1500
30 % cement
60 % cement
1000
500
0
0
30
60
90
120
150
Deformation [mm]
Bullflex-Pillars
Comparison of the Development of the Loadability of Roadside Packs
made of Bullflex-Pillars and usual roadside packs
with early bearing grout respective late bearing grout
Diameter of the Pillars:
Height of the Pillars:
Width of Roadside Pack:
Height of Roadside Pack:
680 mm
1800 mm
1000 mm
1800 mm
3000
2500
2000
Bullflex-Pillars
late bearing grout
1500
24
21
22
,5
19
,5
18
15
16
,5
13
,5
12
9
10
,5
7,5
4,5
0
1,5
Loadability [kN/m]
Prestress/Load [kN]
100
Load
80
60
40
20
0
0
60
120
180
240
300
360
The measurements were taken daily within 6 weeks after filling at three different BullflexPillars of the road side pack. The distance between these pillars was 5 m. The average of every
daily measurement was computed and are shown in the diagram on the next page.
Load [kN/m]
800
600
400
200
0
0
60
120
180
No visible deformation was monitored at the Bullflex-Pillars during the measurement campaign.
When the site has been visited 4 weeks after the measurement the scale of the pressure gauges
were removed. The Bullflex-Pillars had been rammed into the floor by approximately 0.3 m without
any visible deformation (see picture on the next page).
Picture 2: Two rows of Bullflex-Pillars with beams to support the roof in between.
Fig. 2: The finished dam 4 hours after beginning of the work. The dam is completely
tight and also stable against mechanical loads.
Picture 1
Picture 3
Picture 1
Picture 2
Picture 4
Documentation in Pictures
Execution of the work from November 1999 until March 2001
Picture 4: Bullflex-Pillar with 5,8 m height and a diameter of 1600 mm in the middle
of 2 overloaded basalt pillars. Span of the supported area: approx.. 10 m. Loadability
of the pillar approx. 21,300 kN.
Picture 5: Bullflex-Pillar with 5,8 m height and 960 mm in diameter as support besides a column made of mill stones. Loadability of the pillar approx. 5,250 kN
Pictures 6a and 6b: Bullflex-Pillars with 2,8 m height and a diameter of 960 mm for
the support of a destroyed shaft safety pillar.
Loadability of the pillar approx. 9,850 kN
Picture 7: Dismantling of the shutter from the Bullflex-Pillar with 6,0 m height and
960 mm diameter. Loadability of the column approx. 4,800 kN
Picture 8: The overloaded basalt pillar beside the above Bullflex-Pillar. The cracks
resulted from the overloading are to be seen clear.
Picture 13: The entrance of the chamber after installation of the filling pipes and
sealing of the dry stone wall.
The chambers were filled after the sealing by a lightweight grout up to the top.
510
505
The plan standing above corresponds to the plan from the stability evaluation of the geological national office Rheinland-Pfalz dated 21.05.2001.
In this survey it was recommended to secure the cavity 505 with a pillar of 1,500 mm diameter and the cavity 510 with a column with 960 mm in diameter. Additionally the shaft cones
within the property range should become secured against sliding by shotcreting.
The position of the Bullflex-Pillars were chosen according to the survey. One shaft cone has
been secured by shotcreting.
Picture 1: View of the entrance (height 6.0 7.0 m) to the cavities in the quarry of the company Stein with grout container
The preparation of the underground part of the site was made by the left of entrance
which can be seen in the photo above.
As grout for filling the Bullflex-Pillars and for the stabilisation of the shaft cone a cement/fly ash mixture with the trademark HT 33 of the ANNELIESE Baustoffe fr Umwelt und Tiefbau GmbH & Co. KG was used. The resistance against crushing of this
grout is 30 kN/mm in minimum.
The processing of the grout took place by means of a continuous mixer flanged to the
discharge of the grout container. The mixer discharged the grout directly into the
mortar pump.
Picture 2: The Bullflex-Pillar No. 1 during filling, seen from the eastern entrance to the
chamber
Picture 3: The Bullflex-Pillar No. 1 during filling. Filling level approx. 7.8 m
Picture 4: The finished Bullflex-Pillar No. 1 with view of the eastern entrance to the chamber
Picture 6: This illustration shows the tight contact of the Bullflex-Pillar to the roof
Picture 7: Erection of the shutter for the Bullflex-Pillar No. 2. The Bullflex-fabric is already
positioned inside the shutter.
Picture 10: The shutter has been taken off the Bullflex-Pillar No. 2. In the foreground some
elements of the reusable shutter.
Chambers
in the central area which
have to be backfilled
Minefield ERA Morsleben
Shaft Marie
Field Marie
Northern Field
Central Area
Eastern Field
Shaft Bartensleben
Western Field
Southern Field
South-East Field
Picture 1: Illustration of the Minefield of the shaft plants Bartensleben und Marie
Picture 2: Bullflex-Pillar-Wall
For the sealing of the transport raises Bullflex-Cover-Slabs or Bullflex-Packer - depending on the circumstances will be installed. If it is not possible to do preliminary
work inside the raise a Bullflex-Cover-Slab with steel reinforcement will be positioned on top of the upper mound and then inflated. For additional sealing the contact
area between the cover and the floor will be grouted.
Bullflex-Pillar-Wall
Bullflex-Packer
Bullflex-Cover-Slab
Prestress-Time-Diagram
Prestress [kN]
70
60
50
40
Prestress
30
20
10
0
0
10
15
20
25
30
35
40
45
50
55
60
65
Because of the filling pressure limit of 2.5 bar the active prestress was approximately 65 kN
directly after the filling was finished. The prestress was reduced due to the denaturing and
the shrinking of the grout during the hydratation phase to approximately 24 kN after 24 hours
and stayed constant during the whole time of measurement (4 days).
The loss of volume caused by the dewatering and the shrinking was compensated by the
radial contraction of the highly prestressed Bullflex-fabric. This also maintained the constant
prestress of 24 kN and guaranteed a proper underpinning without any loss of height.
Following 2 pages with pictures.
The "Universum-Center"
Picture 2
For transference of the load into the foundation 3 Bullflex-pillars of 2.5 m height and
950 mm diameter had to be erected in the parking deck in the 1st basement sub-
Picture 3
Only 24 hours after the filling of the pillar the bowling lanes were in use again.
After the repair of the columns on the ground floor was finished the Bullflex-pillars
were removed. The last one was broken down in July 1996.
Bullflex-O-Ring-Seals
a Seal for Shaft-sinking,
Tunnelling and Pipe-Relining
versatile in application
Prinzip einer
Principle
of a Bullflex-O-Ring-Abdichtung
Bullflex-O-Ring-Seal
Ground/Rock
Boden / Fels
Outer
Shale
Auenschale
Backfill
Hinterfllung
Special
Filling Valve
Spezialfllventil
mitCheck-Function
Rckschlagwith
funktion
Bullflex-O-RingBullflex-O-RingAbdichtung
Seal
Innenschale
Inner
Shale
Picture 1
The Bullflex-O-Ring-Seal has been applicated e.g. in London, GB, at access shafts
for the London Ring Main System, for the Sub-Way in Taipei, Taiwan, at the renovation of an old waste water collecting duct in Birmingham, GB, and for the construction
of an intake conduit for a hydro-electric power station in Valais at Sion, Switzerland.
This intake conduit connects the hydro-electric power station in the Rhonetal to the
reservoir "Grand Barrage de Dix. The 6.5 km long gallery was driven by a Full-FaceCutting--Machine in hard rock and has a diameter of 5.6 m. Bullflex-O-Ring-Seals
were used rising in an area with 30 incline as front shutters for the backfilling of the
inner shale. Other O-Ring-Seals were installed in a 750 m long, horizontal range with
a steel pipe of 5.28 m diameter installed as inner shale. The backfilling was done in
3 4
5 6 7
Picture 2
1 TBM-skin
12- Schildschwanz
Inner Shale of the
2 - Tunnelinnenausbau
Tunnel
3 - Gummilippendichtung
Rubber Seal
43- Fllventile
mit ange4 schlossenen
Filling Valve Rohren
with
5 - Dichtung
extension"A"
pipes
64- Dichtung
Seal A "B"
76- Stahlring
Seal B
7 Seal Holder (Steel)
Picture 3
Picture 5
TBM-Launch at Contract "Josephsburg Rail 1", Munich
View from the Top
Cut A A
Rail 1
Rail 2
Legend
1 - Jet-Grout-Pile
2 - TBM, Westfalia-Alpine, D = 7.4 m
3 - Bullflex-O-Ring-Seal, Excavation-Line to Liner Ring
4 - Liner Ring
5 - Bullflex-O-Ring-Seal, Excavation Line to TBM-Skin
6 - Backfill
7 - Liner Rings of Rail 2 (already completed)
8 - Pressurized Area
9 - gate
Picture 1 shows the installation of the seal inside the flat lying seal holder.
Picture 2 was taken while the seal was inspected before the Herrenknecht-TBM was installed.
Picture 1 shows the Herrenknecht-TBM in the construction phase. This TBM will drive the
western tube. On the day this picture has been taken the Bullflex-O-Ring-Seal for the eastern
TBM has been filled.
Picture 2 shows the installation of the Bullflex-O-Ring-Seal in the annulus between the seal
holder and the tunnel lining. The belt webbing with eyelets is visible which is attached to the
sides of the seal in the valves area to secure their position.
Picture 3 was taken during the filling of the Bullflex-O-Ring-Seal. Due to the special folding of
the seal no folds or torsion occur. The seal stays in position.
Picture 2
Page 2
Bullflex-O-Ring-Seal, Hose-in-Hose-System
Built-in situation
Phase 1
2 seals close the annulus between TBM skin and
the excavation line
Long section
A
2
3
A
Legend on Page 3
Cross section A - A
1
2
3
inner Bullflex-hose
outer Bullflex-hose
protection fabric, one or two layers
filling of inner hose
filling of outer hose
foam layer
belt-webbing with eyelets for fixing the seal
to the excavation line or a seal holder
TBM tail seal
TBM-skin
inner lining
Phase 2
The TBM's tail is situated under the second seal. The outer
hose of the first seal has been filled and seals the annulus
between inner lining and excavation line.
Long section
A
A
Cross section A - A
Fig.1
Fig.2 : Sketch showing the sealing in a longitudinal cut
tail end seal
TBM-skin
filling connector
eyelet strap with fixation
Fig. 2
The Bullflex-Hoses are inflated by filling connectors made of braided hoses with 50 mm in
diameter, which are led through drill holes in the segments (Fig. 3).
Fig. 3
The remaining annular space behind the liner segments is injected over similar filling ports.
This system was used with success at the construction of the Bzbergtunnel and at the
construction of the Tunnel de Mont du Russelin (both in Switzerland).
in the Westerschelde-Tunnel
With the first method a shaft with a diameter wide enough to expose the TBM is sunk
down to the invert of the TBM. The cutting head is then loosened and removed into
the shaft. After the repair the TBM will be driven forward through the shaft wall which
introduces an additional launch arrangement. Normally, the shaft will be backfilled. At
this method very high cost and a large time delay are caused by the sinking of the
shaft. In addition, the use of this method is restrictive, because of buildings on the
surface or services crossing the shaft or the TBM is at too great depth.
The Freezing of the face and a part of the tunnel requires the erection of a freezing
plant above the site of the damaged TBM with the same restricting as with the first
method or the mounting of a freezing plant in the mouth of the tunnel and the installation of bore holes for the cool lances. This also causes a large time delay particularly since a structurally sound cooling jacket must be built up. The cost of running
the power source is very high for this method.
Grouting the complete working area in front of the TBM is the easiest of the three
known methods, but high costs arise from the removal of the surplus grout by hand
excavation.
With the two the latter methods the cutting head is loosened from the TBM which can
then be pulled back to expose the damaged bearing for the repair.
When the damage occurred to the main bearing of the eastern of the two TBMs of
the Westerschelde-Tunnel project the contractor Kombinatie Middelplaat Westerschelde v.o.f. looked for a more favourable solution to safeguard the workarea during
the repair. It was decided to fill the room between cutting head and diving wall with
air filled containers and to concrete the cutting head.
TBM
Detail 1
Ground
Cutting Head
concreted area
BullflexConcretingProtective-Hood
Picture 1: Principle of the planned application
concreted area
Ground
water filled
Bullflex -O-RingSeal
Bullflex -ConcretingProtective-Hood
strap for
fixing
Bentonite
Picture 2: Detail 1
After completion of the repair the cutting head will be pulled back from the BullflexConcreting-Protective-Hood. And the hood will be removed under compressed air.
filling port
After completion of the repair the work area was put again under compressed air.
Then the mortar fill in the lower third of the backward area was extracted and the
Bullflex-Concreting-Protective-Hood was removed without problems.
After completion of the work the heading could be started again.
Bullflex-Special Applications
Anti-Foating Devices
Joint-Seals
Levelling Bags
Slope Protection
Packers
ground
Bullflex-anti-floating
device
grouted annulus
tunnel liner segments
pipe
annulus between tunnel
lining and pipe, to be
filled with grout
transport construction
for the pipe
gravel
sand
sand
ditch
cut out by under water
blasting
prepared
caisson
Bullflex -LevellingPackage
Sketch
waterlevel
Bullflex-hoses fixed into position
by divers and filled under water
quay wall
drill hole
for grout
injection
Legend
1 pipe / cut out-line of drill hole
2 Bullflex-Packer
3 filling port
4 injection pipe
Bullflex-Packer,
800 mm diameter
Gallery, filled
with mud
15
17
12
86
88
1
83
82
84
rg
Am Heerbe
88
2
96
2
81
87
96
1
85
89
2
14
90
91
114
2
92
93
94
114
1
112
shaft
security
area
27
9
11
of
mH
r de
Obe
95
111
3
113
27
10
Weg
shaft
cover plate
27
3
25
26
109
110
90
27
5
108
27
4
rt
nge
Ba
Im
2nd
3rd
4th
5th
Results
Including the core drilling, the
work was completed in only 10
working days. The concrete shaft
cover slab remained in place and
was structurally unaffected by the
works. No more earth moving or
other work were necessary.
Illustration 4: Section through a shaft stabilized by the
Bullflex-Shaft-Safeguarding-System
15
17
12
86
88
1
83
82
96
2
84
erg
Am Heerb
88
2
81
87
96
1
85
89
2
14
90
91
114
2
93
114
1
former
shaft
security
area
27
9
112
92
94
Hof
dem
r
e
Ob
11
95
111
3
113
27
10
25
26
Weg
27
3
new
shaft
security
area
109
110
90
27
5
108
27
4
rt
nge
Ba
Im
Illustration 5: extract from the land register showing the former and the new shaft security area.
Bullflex-Reinforcement-Hoses
Bullflex-Pillars
Bullflex-O-Ring-Seals
Special Applications
France
- several collieries of the Houlleries du Bassin de Lorraine
- potash mines of the Mines de Potasse d Alsace
Greece
- Smokovo, ground-outlet gallery of the Smokovo Damm Projekt
- Smokovo, Ofarna Tunnel
Great Britain
- London, Heathrow Express Project, temporary support of the tunnel
- London, Jubilee Line Project
- Peterhead/Longside, Auchlee Bridge Project
Italy
- Applications in several tunnelling projects e.g.:
- Tunnel Itinera (Autostrada Torino - Bordighera)
- Tunnel Morgex (tunnel to the Mont Blanc)
- Impresa Riunite Genova (Subway)
Japan
- Kushiro, Colliery Taiheijo
- Kobe, Maiko-Tunnel, Pipe-Umbrella-System
- Kumagai, Omaezaki-Tunnel
Korea
- Togye, Colliery DHHC
Russia
- Kemerovo, Siberia, Colliery Schwejakowa
Schwitzerland
- Applications in several tunnelling projects e.g.:
- Bzbergtunnel
- Tunnel de Mont Russellin
- Locarno, Tunnel Centovalli
Spain
-
Ukrainia
- Donezk, Colliery Skotschinski
- Podinskoje, Colliery Krasnolimanskaya
Hungary
- Applications in several collieries on yielding steel arches and on rigid steel rings
- ERA Morsleben, closures of galliers and raise chutes with Bullflex -Pillar-Walls
b) Safeguarding of Historical Cavities
- Ilmpark-Cave in Weimar, former Travertine mine, gallery support
- Kohnstein, Memorial Mittelbau-Dora, safeguarding of a T-junction
- Former iron ore mine Kahlenberg, Herbolzheim, safeguarding of several T-junctions
- Mendig, safeguarding underground cavities caused by historical basalt-mining for millstones
c) Civil Engineering
- Hattingen, underpinning of the historical City Hall
- Aachen-Schmithof, underpinning of a 2-floor building
- Wuppertal,
- Ulm, temporary underpinning of the 22-floor Universumcenter
- Tiefurt, Beercellar of a former Brewery, additional support due to construction work on the
surface above
- Gelsenkirchen, new building of the BOGESTRA, underpinning of the neighbouring buildings
- Essen, Elisabeth-Hospital, underpinning of the foundation in the area of a new building
- Freyburg, Unstruth, underpinning of the historical part of the headoffice of the champagnedresser Rotkppchen
Australia
- Calgoorlie, support in room-and-pillar gold mines
Chile
- Colliery Tamaya, road side packing
France
- Potash mine Marie-Luise, Mines de Potasse dAlsace, Safeguarding of an
extraction chamber
Italy
- Nuraxi Figus, Sardinien, Colliery Carbosulcis, seam support an safeguarding of T-junctions
Korea
- Togye, Colliery DHHC, safeguarding of T-junctions in 20 incline
Spain
- Figaredo, Colliery Minas de Figaredo, road side packing
Sdafrika
- Klerksdorp, gold mine Haartebeestfontein, seam support an safeguarding of T-junctions
USA
- Kentucky, Colliery Arch of Kentucky, gallery support
- Utah, Colliery Skyline No.1, gallery support
Hungary
- Budapest, underpinning of a building
Belgium
- Antwerpen, ASDAM-Tunnel, high speed railway connection Gent Amsterdam,
Launch seals for the TBM at both tubes
Great Britain
O-Ring-Seals in shaft-sinking e.g.:
- London, Thames Water Ring Main;
Shafts:
Ashford Common
Kempton Park
Merton
Streatham Well
Brixton
O-Ring-Seals in Tunnelling e.g.:
- Fleetwood and Blackpool, Fylde-Water-Project, launch and reception seals
for the LOVAT-TBMs
- Channel Tunnel Rail Link
Contracts (a.o.): 320, 250
- Dartford, Dartford Cable Tunnel
- Hull, 2000 UWWTD
Netherlands
- Rotterdam, Botlek-Tunnel, Launch seals for the TBM at both tubes
- Terneuzen, Westerscheldetunnel, Launch seals for the TBM at both tubes
- Rotterdam, SATURN Leidingentunnel, Launch seal for the TBM
Portugal
- Lissabon, Novaponte Ace, new Tagus-bridge, O-Ring-Seals for theannular gap between
steel foundation piles and the caissons which wioll be the foundations for the bridgdes pylons
Schwitzerland
Taiwan
- Taipei, Subway-Line Chung-Ho
Hong Kong
- Hong Kong Outfall Tunnel DC/93/18, Launch seal for the TBM
- Central, Western and Wai Chai West Trunk Sewers, Launch seal for the TBM
Thailand
- Bangkok, MRTA Initial System Project, Launch seal for the TBM
Singapore
- Project DTSS T-05, Launch seal for the TBM
- MRT North East Line Contract 704, Launch seal for the TBM
4. Special Applications
Germany
- Recklinghausen, channel harbour, sealing of joints in the quay wall partly under water
- Duisburg, harbour, sealing between quay wall and sheet pile wall
- Elsterberg, anti-floating-device fore a pipe with 600 mm diameter
- Gypsum mine Dhlau, Packer in a diameter of 1,2 m and 6 m length and in the dimensions
- 1,4 m x 1,8 m x 6 m for the sealing of the intake shafts, inflation for the surface
- Safeguarding of the blasted bunker12 nearby Schwanau/Ottenheim by covering with
Bullflex -Mattresses
- Rostock, Feste Warnowquerung, sealing and underpinning of the eastern foundation
- Conakry, Harbour, sealing of horizontal joints in the quay walls, inflation of the Bullflex Hoses in a depths of up to 12 m beneath the water surface
Japan
- Kobe, Harbour, sealing ofl joints in the quay walls which have been damaged by an
earthquake
Netherlands
Schweden
- Oscarshamn, Granite quarries of the Emmaboda AG, support of the rope-saw-cuts against
rock pressure
Spain
- Bilbao, Subway, Bullflex -Levelling-Containers for the caissons of the tunnel under the Rio
- Nevrino, inflation of the containers in a water depths of up to 20 m
Sri Lanka
- Samanalawewa Dam Project, stoppers for a temporary drain, filling in a high speed water
current
Hungary
- Budapest Castle, Budapest, safeguarding of vertical gaps beneath the castle, filling of the