Escolar Documentos
Profissional Documentos
Cultura Documentos
Environmental Challenges
Gassim Al-Gassim
Deputy CEO for Projects
Saudi Railway Company (SAR)
Introduction
The initial studies were carried out over 15 years ago to develop
the North-South Railway.
Item
Total
2380 km
Concrete-bridges
114
Concrete-Culverts
2679
Earth work
497 million m
Sleepers
Rails
Existing Network
North-South Railway
Saudi Landbridge
Western Railway
Al Jalamid Mine
Syria
Iraq
Al Jawf
Iran
Al Basayta
Kuwait
Jordan
Ras Az Zawr
Gu
lf
Egypt
Jubail
Az Zabirah Mine
Dammam
Buraydah
Al Hufuf
Al Madinah
ea
dS
Re
Eritrea
Sudan
Hail
Bahrain
Qatar
United Arab Emirates
Kingdom of
Saudi Arabia
Oman
Yemen
Gulf of Aden
Yanbu
(Medina)
Riyadh
Haradh
Arabian Sea
Jeddah
Makkah
(Mecca)
Ethiopia
Somalia
Al-Basayta
Station
Al-Jalamid
Mines
CTW 300 750 Km from An Nafud to Al-Haditha,
HazmThree
AL Jalamid
and Al Basayta
major contracts,
7.2 Billion Saudi Riyals,
rd
Awarded
to Al-Rashid
Barclay
Mowlem
Mitsui
awarded
on 3 April
2007
for theCivil
and Track
CTW
200
440Km
from
Az
Zabirah
Junction, to
Consortium
Works In (Eastern Region , Al-Qassim , Hail , Al-Jowf
An Nafud
Awarded
JV of China
And Northern
Boarder
Region), to
asthe
following
:
th
Railway
18
Bureau
and
AlSuwaiket
Co.
Al-Jowf Station 877 Million Saudi Riyals An Nafud - 4.2-2
CTWawarded
100 576 Km from Az Zabirah Mine to Ras AzThe total
length
of
the project is approx. (2400 Km)
to Al-Khodari
Co.
Zawr Awarded to Saudi Binladen Group..
Hail Station
939 Million Saudi Riyals
An Nafud 4.2-1 awarded
Bauxite Mine/Junction
to Al-Omaier / Al Fahad Co.
CTW 400 Recently Awarder with
contract value 2.7 Billion Saudi
Al-Qassim
Station
Riyals
The total
length
of (Passenger,ganeral
freight)
460Km
from
Az Zabirah
Junction to
services
is (1418toKm)
KKIA
Awarded
Al Ayuni, Al
Omaier & CCECC.
Industrial
Station in
Sudair
Ras Az Zawr
Jubail
Majmaah
Station
Riyadh Station
GCC
NSR
SRO
Landbridge
Passenger Stations
* SAR project include six passenger stations :
Internal
view
Executive Class
Passenger Stations
External view
interior view
Headquarter
External view
Yard Facilities
* SAR project include
nine yard facilities :
Riyadh .
Sudair .
Qassim .
Hail .
jowf .
Basitah .
Ras Az Zawar .
Jubail
haditha .
-9-
Maximum Gradients:
0.5 % loaded mineral direction.
1.5 % Passenger, general freight and empty
mineral direction.
Train Speeds:
Mineral loaded:
80 km/hr
Mineral empty:
100 km/hr
General Freight:
120 km/hr
Passenger Train:
200 km/hr
Rail Type:
UIC-60-E1.
Fastening System:
Pandrol-Fast clip.
NO
permanent
Grade
Crossings
FULLY Fenced RR
Right-of-Way
(for obvious
reasons)
Environmental Challenges
1
2
3
4
5
6
Phosphate Ore
Bauxite Ore
Sulphuric Acid
Caustic Soda
General Freight
Passengers
Construction in Desert
The majority of NSR Alignment will go through remote
locations So, for the construction camps the following had to
be taken into consideration:
Accommodation for more than 1,000 Inhabitants
Supply Chain for Daily Needs of Labors
Supply of Construction Material
Supply of Construction Consumables
Sand Dunes
NSR Alignment passes through a lot of desert and sand dunes
area.
Deserts are generally characterized by the severity of sand
blowing resulting in
Contamination of the Ballast Layer (Impact on System Elasticity).
Designers can only minimize the problem associated with blowing
sand by understanding how sand moves and applying techniques
tested and found to be successful.
Construction Process
1
b.
C.
DRAINAGE
1
B.
SABKHA
Arabic term that describes a composition of Sand Deposits mixed
with Silt, Clay with the presence of salt.
Always refers to saline, puffy, crust-surfaced flat basins with the
presence of water.
Coastal Sabkha found in the eastern province of Saudi Arabia in
low-lying plains and Inland Sabkha found in northern part.
Special attention is required due to water presence.
Low load carrying capacity (Settlement).
SABKHA Mitigations
Using Geotextiles in the construction of Railway on sabkha subgrade.
Using rock fill for embankment under the sub-grade, ballast and
sub-ballast.
Pre-Loading (Additional temporary load but time consuming).
Soil Replacement.
Mechanical Compaction (e.g. Stone/Sand columns)
Operational Considerations
Sand Environment Impact on Operation:
Balises
Due to high temperature in Saudi Arabia specially during summer ,
temperature was measured and found during summer that exceed 80
C and readings from balises will be effected
For that reason Balises were equipped with covers (Shadow) to
reduce temperature and assure their functionality.
Point Machine
Because of sand problems and in order to reduce maintenance,
Point machines were designed with a special cover. This cover is
IP67 / The where no. 6 means no ingress of dust, complete
protection against contact and no. 7 means Ingress of water in
harmful quantity shall not be possible when the enclosure is
immersed in water under defined conditions of pressure and
time (up to 1 m of submersion).
-5-
-7-