distribution licensees as
required under section 59(1)
of the Electricity Act, 2003
for the financial year 2014-15
WEST
BENGAL
ELECTRICITY
REGULATORY COMMISSION
Reports submitted by the distribution licensees as required under section 59(1) of the
Electricity Act, 2003 and the Regulations on Standard of Performances of the Licensees
framed and published by West Bengal Electricity Regulatory Commission as required in
terms of Section 59 (2) of the Electricity Act, 2003.
CONTENTS
Sl. No.
Description
Pages
1.
Index
2.
3.
4.
5.
6.
ANNUAL REPORT UNDER SUB SECTION (1) OF SECTION 59 OF THE ELECTRICITY ACT, 2003
Name of the Distribution licensee
Types of complaints
1.
9.
II
1.
Interruptions in power supply: No. of instances of interruptions in power supply (01.04.2014 to 31.03.2015)
2.
2.
3.
4.
5.
6.
7.
8.
Number of
complaints
received
Whether
attended
2240
2149
291
266
30886
29384
2351
04
78
96005
2220
04
61
89027
12
09
44291
43798
Number of
cases where
compensation
was payable
Number of cases
where
compensation
was paid
Total amount
(in Rs.) of the
compensation paid
81
01
88500
LT Network11 KV
HT Network33 KV
LT Network 11 KV
HT Network 33 KV
524394
33438
49518.97
5069.97
ANNUAL REPORT UNDER SUB SECTION (1) OF SECTION 59 OF THE ELECTRICITY ACT, 2003
Name of the Distribution Licencee
Full Office address (HQ) of the Licencee
:
:
CESC Ltd.
CESC House, 1, Chowringhee Square, Kolkata 700 001
ANNUAL REPORT FOR THE FINANCIAL YEAR 2014-15 ENDING ON 31.03.2015 (01.04.2014 TO 31.03.2015)
I. Number and Type of the consumer complaints received , attended and compensation paid: Sl.
Types of complaints
Number of
Number of cases
Total amount
Number of
Whether
No
cases where
where
(in Rs.) of the
complaints
attended
compensation
compensation
was
compensation
received
was payable
1.
2.
3.
4.
paid
paid
414
Yes
__
__
__
59
Yes
__
__
__
10
Yes
__
__
__
58
Yes
__
__
__
__
__
__
__
__
__
__
__
5.
Unplanned interruptions
(approx)
3790
Yes
6.
765
Yes
7.
523
Yes
8.
57
Yes
__
__
9.
Others
737
Yes
__
__
__
__
II. Planned interruptions in power supply: 1. No. of instances of planned interruptions in power supply in 2. Total duration in hours of planned interruptions in power supply in -
__
LT network 52780
HT network - 786
LT network 105560
HT network 915
EXPLANATORY NOTE
1. LT Network In 182 areas of Licensed Area overhead maintenance work was taken up. In the interest of our consumers the work was phased
out over 290 days so as to cause minimum inconvenience to them. The average interruption time was 2 hours per day. The total duration of
planned interruption was 105560 hours.
2. HT Network There were 786 instances of planned interruption and the total duration of such interruption was 915 hours.
3. In addition to the figures in item 5, there are LT fuse cases, which are generally caused by drawal of loads higher than applied for.
Sd/-
(Amitava Shome)
ANNUAL REPORT UNDER SUB SECTION (1) OF SECTION 59 OF THE ELECTRICITY ACT, 2003
Name of the Distribution Licencee
Full Office address (HQ) of the Licencee
:
:
ANNUAL REPORT FOR THE FINANCIAL YEAR 2014-15 ENDING ON 31.03.2015 (01.04.2014 TO 31.03.2015)
I. Number and Type of the consumer complaints received, attended and compensation paid (if any)
Sl.
No
Types of complaints
1.
2.
3.
4.
5.
7.
8.
II
1.
2.
Whether attended
Number of cases
where
compensation
was payable
Number of
cases where
compensation
was paid
Total amount
(in Rs.)
of the
compensation paid
05
05
Nil
Nil
Nil
06
06
Nil
Nil
Nil
17
17
Nil
Nil
Nil
06
06
Nil
Nil
Nil
03
03
Nil
Nil
Nil
05
05
Nil
Nil
Nil
1015
811
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Unplanned interruptions
6.
9.
Number of complaints
received
Nil
LT network
HT network
Total duration in hours of planned interruptions in power supply in LT network
HT network
386 Nos.
359 Nos.
551.19 hrs.
491.49 hrs.
ANNUAL REPORT UNDER SUB SECTION (1) OF SECTION 59 OF THE ELECTRICITY ACT, 2003
:
:
DPSC Ltd
"Centre for Excellence" Plot No. X-1, 2 & 3, Block EP,
Sector - V, Salt Lake City, Kolkata - 700 091
ANNUAL REPORT FOR THE FINANCIAL YEAR 2014-15 ENDING ON 31.03.2015 (01.04.2014 TO 31.03.2015)
I. Number and Type of the consumer complaints received, attended and compensation paid (if any)
Sl.
No.
Types of complaints
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Number of
complaints
received
Whether
attended
Number of cases
where
compensation was
payable
Number of cases
where
compensation
was paid
Nil
NA
Nil
NA
Nil
NA
Nil
Nil
NA
NA
Nil
02
Total amount
(in Rs.)
of the compensation
paid
NA
YES
NIL
NIL
Nil
NA
Nil
Nil
NA
NA
II Planned interruptions in power supply: 1. No. of instances of planned interruptions in power supply in
LT networkHT network2. Total duration in hours of planned interruptions in power supply in
LT NetworkHT network-
NIL
Nil
2427
Nil
1657.26 hrs.
Sd/
Debasis Sarkar, Vice President (Technical)
5
ANNUAL REPORT UNDER SUB SECTION (1) OF SECTION 59 OF THE ELECTRICITY ACT, 2003
Name of the Distribution Licensee
Full Office address (HQ) of the Licensee
:
:
ANNUAL REPORT FOR THE FINANCIAL YEAR 2014-15 ENDING ON 31.03.2015 (01.04.2014 TO 31.03.2015)
I. Number and Type of the consumer complaints received , attended and compensation paid (if any): Sl.
Types of complaints
Number of
Number of cases
Total amount
Number of
Whether
No
cases where
where
(in Rs.) of the
complaints
attended
compensation
compensation
was
compensation
received
was payable
1.
2.
3.
4.
5.
6.
7.
8.
9.
paid
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
** Unplanned interruptions
NIL
15
Yes
NIL
NIL
01
Yes
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL
Others
NIL
NIL
NIL
II. Planned interruptions in power supply: 1. No. of instances of planned interruptions in power supply in 2. Total duration in hours of planned interruptions in power supply in
paid
LT network
HT network (33 KV and above) LT network
HT network - (33 KV and above) -
NIL
NIL
NA
657 (131-OFF-TAKE Points)
NA
2505(131-OFF-TAKE Points)
NOTE
* Excludes extension/enhancement of load been held up due to augmentation of present transformer / line capacity at some S/s.
** Meant for interruption (excludes load-shedding) due to break-down in the Lines, switch-gears etc.
Sd/Chief Engineer (Comml.) Comml. Dept, DVC, Kolkata 700 054
ANNUAL REPORT UNDER SUB SECTION (1) OF SECTION 59 OF THE ELECTRICITY ACT, 2003