Aide Memoire

Heavy Civil Infrastructure


3 KM, 2 Lane Bridge Across River Brahmaputra, Assam
HEAVY CIVIL INFRASTRUCTURE IC
1.0

Synopsis:
4 Laning of NH-37A from KM. 0.00 (Kaliabor) to KM.17.300 (Dolabari) in Tezpur including construction of
new bridge across river Brahmaputra is issued on EPC basis by the Ministry of Road Transport and
Highways (MORT&H). This would connect Nagaon and Sonitpur districts in Central Assam with an aim to
create 4-lane connectivity to Itanagar, Arunachal Pradesh
The proposed bridge alignment is 80 m downstream parallel to the existing bridge at Tezpur.
The project is on EPC mode and the client estimate is Rs 670 Cr with bid due date Aug 21, 2014

2.0

Location:
1. Project is 150 KM from Guwahati By Road. Also, connected by Railway and Airway
2. Established Army base at Tezpur
3. PT&D Project Site, operating next to bridge location (Mr. Majumdar Cluster Head 80170008101)
& Mr. Prolay Project Manager 08876582102)
4. 215 KM from Subhanshri Project Site

3.0

About Client:
The Project is proposed to be executed by
the National Highway wing of Assam PWD
headed by Chief Engineer.

4.0

Funding Arrangement:
"Special Accelerated Road Development
Programme in North East (SARDP-NE)".
Phase A. Govt. Sanction available

5.0

2-Lane Proposed Bridge 80M


d/s to the Existing Bridge

2-Lane Existing
Bridge

Owner / Senior Management:


Mr. Sunil Kumar Verma, Chief Engineer
MoRT&H

2-Lane Existing Bridge

+91-11-23739074,
sunilkumar.verma@nic.in
6.0

Regulator: MoRT&H

7.0

Scope of Works:
1. 2 lane Bridge
= 3.01 KM (1 X
67m + 24 X 120m + 1X 67m)
2. Approaches = 14 KM

31.05.2014

Page 1

Aide Memoire
Heavy Civil Infrastructure
3 KM, 2 Lane Bridge Across River Brahmaputra, Assam
HEAVY CIVIL INFRASTRUCTURE IC
Current Status
L&T pre-qualified for Projects taken up by MoRT&H
Site visit scheduled on 2nd week of June.
Time Lines
RFP Submission Date Aug 21, 14
Prebid Meeting July 7,14

8.0

Project Status
SL
No

Item

Yes
(
)

No
(
)

3.01 KM Main bridge along with 14 KM


approach roads (including minor bridges)

Project Concept / Clear Scope

BOOT

EPC

Feasibility Report / PPR

Remarks


Available

6
7

Detailed Feasibility Report /


Detailed Project Report
Govt. Sanction
Environmental Clearance (MoEF)




Center Approved
Not required as per Govt. Mandate

Project funding Tied up

Assam PWD

9.0

Due diligence on client


SL
No

Item

Yes
(
)

No
(
)

Remarks

Project definition

Scope clarity with Client

Net worth of client

Available

Funding Source

Assam PWD

Any litigation with contractor

Nil

Clarification / delays in
payment

Final bill settlement

10.0

NA

Due diligence on Project

SL
No

Item

Yes
(
)

No
(
)

Special bridge (Span ~120m & Perennial


river)
Value > 500 Cr

Relevant Sector

Sizeable Volume

Client Relation ship

Any other reasons

31.05.2014

Remarks

Page 2

Aide Memoire
Heavy Civil Infrastructure
3 KM, 2 Lane Bridge Across River Brahmaputra, Assam
HEAVY CIVIL INFRASTRUCTURE IC

31.05.2014

Page 3