Escolar Documentos
Profissional Documentos
Cultura Documentos
Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct
Department of Civil Engineering, Castilla-La Mancha University, Avda. Camilo Jos Cela s/n, 13071 Ciudad Real, Spain
Instituto de Ciencia y Tecnologa del Hormign (ICITECH), Departamento de Ingeniera de la Construccin y Proyectos de Ingeniera Civil, Universidad Politcnica de Valencia, Camino
de Vera s/n, 46023 Valencia, Spain
c
Department of Bridge Engineering, Tongji University, 1239, Siping Road, 200092 Shanghai, China
d
Department of Construction Engineering, Universitat Politcnica de Catalunya, BarcelonaTech, c/Jordi Girona 1-3, C1, 08034 Barcelona, Spain
b
a r t i c l e
i n f o
Article history:
Received 26 April 2011
Revised 2 December 2011
Accepted 5 February 2012
Available online 28 March 2012
Keywords:
Cable-stayed bridges
Construction process
Temporary supports erection method
Backward modeling
a b s t r a c t
The temporary supports erection method is a fast and economical way of building cable-stayed bridges.
In this method the bridge deck is rst erected on a set of temporary and permanent supports and then,
the stays are successively placed and tensioned according to a predened tensioning sequence. A proper
denition and analysis of this sequence is very complex as the structure is highly statically indeterminate, exhibits a non linear behavior and has a changing static scheme.
Despite its importance, no specic research referring to the modeling of the temporary support erection method has been found as most of the modeling procedures are proposed for the alternative erection
technique, the cantilever erection method. The modeling carried out by most of these methods is based
on the opposite construction sequence followed on site, this is to say, the structure is disassembled from
the desired nal stage (Objective Completion Stage, OCS).
A procedure, the Backward Algorithm (BA), is formally presented in this paper for calculation of the
erection of cable-stayed bridges built on temporary supports. Because of its simplicity the BA can be
reproduced by any structural code that enables the modeling of the prestresses of the stays by means
of imposed strains or imposed temperature increments. Another advantage is that no separate models
are needed to calculate the evolution of stresses in the strands when the strand by strand tensioning
technique is used. Furthermore, the stay elongations when prestressed can be easily obtained when
the stays are prestressed in a single operation or strand by strand. This information is important to control the correct and safe prestressing of the stay on site. In addition, it also help the designer to control if
the anchor wedge bites the strand in the same position several times during the prestressing process.
2012 Elsevier Ltd. All rights reserved.
1. Introduction
One of the most important causes of the rapid progress of
cable-stayed bridges in recent decades is the development of the
construction techniques that made its erection possible [15].
Wherever it is possible, the temporary support method is the fastest way of building cable-stayed bridges because conventional
construction techniques may be used. This fact simplies the erection task and leads to lower costs [6]. This technique has been
employed in many cable-stayed bridges such as the Val-Benoit
Bridge [7] or the Sanhao Bridge [8]. When environmental factors
or the requirements of the foundations prevent the placement of
the temporary supports during construction, the cantilever erection method [9] is used. This technique has been employed in
the construction of the longest cable-stayed bridges such as Sutong
Bridge [10] with a main span of 1088 m. The cantilever erection
method consists on the placement of deck segments in cantilever
either in both sides of the pylon or in one side only and balanced
by backstays located on the opposite side of the deck.
The structural behavior of these structures has been studied by
many authors [1116]. Nevertheless, the erection procedures of
the cable-stayed bridges are not so studied. Many works [1724],
have been presented in order to either optimize or simulate the
construction process of cable-stayed bridges using the cantilever
method. Nevertheless, no specic works based on the temporary
supports erection method have been found. This paper aims to ll
this gap by providing a new procedure that models the construction process of cable-stayed bridges built on temporary supports.
Fig. 1 presents the temporary support erection method for an
N = 6 six stay cable-stayed bridge built on K construction stages.
96
Nomenclature
BA
Auxiliary
Cn
Cn,1
Cn,2
CPm
FEM
[FM]
[IM]
K
L
N
k
NBA
Cn
Softwarek
NCn
NOCS
Cn
Nk;i
Cn
NkTM
eU
NCCnm
{NTL}
{NOCS}
OCS
OSS
P
RTL
Tt
RTL
C n;2
Backward Algorithm
Modelk,i ith local iteration of the kth auxiliary model
nth stay
Connection between the pylon and the nth stay
Connection between the deck and the nth stay
mth Comparison Parameter
Finite Element Method
Force Matrix
Inuence Matrix
number of construction stages
length of the stay
number of stays
axial force in the nth stay in the kth construction stage
obtained by the BA
axial force in the nth stay in the kth construction stage
obtained by the commercial software
axial force in the nth stay in the OCS
axial force in the nth stay in the kth construction stage
in the ith local iteration
axial force dened for the kth row of the [TM]
axial force in the nth stay produced by an imposed unitary strain in the mth stay
vector of axial forces in the stays produced by the TL
vector of axial forces in the stays in the OCS
Objective Completion Stage
Objective Service Stage
number of permanent supports
vertical reaction in the tth temporary support when TL
is applied
vertical reaction in a ctitious temporary support located at the connection between the nth stay and the
bridge girder when TL is applied
In the initial stage (Stage k = 0), the self weight of the structure, g1,
is counterbalanced by a set of T = 2 temporary supports and P = 3
permanent supports (Fig. 1a). This way, vertical reactions in both
the temporary supports, R0T t , and in the permanent supports, R0Pp ,
are found. Then, during the tensioning process, the stays are successively placed and tensioned by the jacks and the deck is raised
from the temporary supports (Fig. 1b). In these stages, the load g1 is
counterbalanced by the non-raised supports, RkT t , and by the tensile
forces introduced into the placed stays, N kC n . When the tensioning
process is completed after K tensioning stages (Fig. 1c), the nal
desired stage, known as the Objective Completion Stage (OCS), is
achieved. This stage can be easily calculated from the Objective
Service Stage (OSS), which satises the stress distribution pursued
by the designer in such a way that under a certain load hypothesis,
target load, TL, the stays present a given vector of forces {NOSS}
(Fig. 1d). This stage will only be achieved when TL is applied into
the structure.
Calculation of the construction process of cable-stayed bridges,
this is to say, the tensioning process that has to be followed during
construction, is very complicated as the structure is statically
highly redundant, non linear and is continuously changing its static
scheme during its construction. The forward simulation of the actual construction sequence on site is associated with a number of
computational difculties. For example, each time that any stay
is being prestressed the axial forces of the rest of stays are changed
(see Fig. 8 in Section 5.2). Because of these difculties the backward simulation is commonly used, as it is much simpler. In fact,
this technique has been employed by many authors for the
Rk;i
Tt
RkPp
Stagek
Stagek1
T
TL
[TM]
i
k
p
t
uTL
C n;1
wk;i
Tt
acn
DNk;i
Cn
DL
DW k;i
Tt
eUCm
{eCP}
ek;i
CP
cantilever method: Behin in [17,18] proposed a substructure-frontal technique that started the calculation in the reference conguration of the completed bridge. In this technique, nonlinearities for
P-Delta effects were included by a continuous updating of the geometric conguration and nonlinearities from cables were included
by using catenary equations. Fan et al. in [25] proposed a method
to dene the optimum stay forces from a backward analysis that
included the creep effect. Mao et al. in [26] proposed a backward-analysis based on the creep aging theory for erection of concrete cable-stayed bridges. Reddy et al. in [20] proposed a
nonlinear nite-element methodology for the stage by stage construction. The results of this method were compared with eld
measurements of a long-span cable-stayed bridge. Wang et al. in
[23] proposed a method for nding the initial shape of bridge
structures during the cantilever erection procedure. In the backward approach the structure is disassembled from the OCS. The sequence of events in the disassembly analysis is the opposite of that
which occurs during erection. The tensioning process that has to be
followed during construction can be dened by a Tensioning Matrix [TM], like the one shown in Fig. 2. As the backward approach
is used, this matrix is calculated from the bottom up. Nevertheless,
the erection direction is the opposite. With K being the number of
construction stages and N the number of stays, this matrix is
formed of K rows and two columns; the rst column describes
the stay that is prestressed at each stage and the second describes
the axial force to be introduced by the jack. Usually each stay is
tensioned several times through the tensioning process. For a K
stage construction process, the last K N + 1 axial forces of [TM]
Fig. 1. Temporary supports erection method: (a) Stagek=0, (b) Stagek=k, (c) Stagek=K or
Objective Completion Stage (OCS), (d) Objective Service Stage (OSS).
can be directly dened by the designer. Nevertheless, the remaining N 1 axial forces, highlighted in bold in Fig. 2, are unknown
due to innate evolutionary nature of the construction process of
the cable-stayed bridges. For this reason, it can be said that the
[TM] is incomplete or not fully known. The calculation of these unknown forces is indirect and must take into account all the preceding and subsequent tensioning operations. In fact, the axial force
that has to be introduced into each stay when placed must be calculated in such a way that the achievement of the OCS is assured
after completion. [TM] can be enlarged into the Force Matrix,
[FM], which describes the axial forces of all placed stays
97
98
Fig. 2. Example of Tensioning Matrix, [TM], and Force Matrix, [FM], for a N = 6 stay bridge with K = 12 tensioning stages modeled backwards. The unknown forces are bold
and the prestressed stays in each stage are framed. The modeling direction is showed by the continuous arrow and the erection direction by the dotted one.
Nevertheless, without any lack of generality any of the other described criteria could have been used. The Rigidly Continuous Supported Beam criterion is based on the assumption that the cablestayed bridge deck behaves, in a long-term, like a rigidly continuous beam borne on ctitious rigid supports at cable anchor points.
In order to dene the axial forces in the stays in the OSS, N OSS
C n , the
following procedure is followed: rst of all, the vertical reaction,
RTL
C n;2 , obtained in the equivalent beam model in each temporary
support, Cn,2, under the TL is obtained, as presented in Fig. 3a. Then,
as is shown in Fig. 3b, the axial forces of the stays, N OSS
C n , are obtained considering that RTL
C n;2 is its vertical projection. Mathematically, the value of N OSS
can be deduced from Eq. (1), where
Cn
tensile forces and upward reactions are considered positive.
NOSS
Cn
RTL
C n;2
SinaC n
99
3. Commercial software
Fig. 3. Rigidly continuous beam criterion: (a) Continuous beam reactions. (b)
Projection of the reaction in the stays direction. The second subindex shows the stay
extremity, 1 is for the pylon and 2 for the deck.
the passive nth stay produced by the TL in the model without temporary supports, N TL
C n , and the effect on the nth stay of the prestress
of all N stays, as presented in Eq. (2).
TL
NOSS
Cn NCn
N
P
eU
NCCnm eC m
m1
eU
The term NCCnm represents the axial force produced in the nth stay by
a unitary strain introduced in mth stay of the structure, eUCm . This
relation can be expressed more compactly in a matrix form.
feg IM1 fNOSS g fN TL g
Nowadays, the modeling of the construction process of cablestayed bridges built on temporary supports can be carried out by
advanced commercial programs which are usually based on the
backward approach. In this approach, the structure is successively
disassembled from the OCS (according to the opposite construction
sequence) until the initial stage, where the bridge deck is supported by the set of temporary and permanent supports, is
achieved. An intuitive interface is available to dene the planned
construction schedule exactly, including all changes in the structural behavior of the bridge. This tool allows the users to activate
or deactivate loads, elements and boundary groups throughout
the modeling of the construction process. The superposition of
stages principle is used. The temporary supports are usually modeled by means of special elements that are only able to counterbalance compressive axial forces. Hence, if tensile stresses are
obtained in any temporary support during the modeling of the construction process, the element is deactivated from the structure by
means of a local iterative process, affecting only this precise construction stage, where its force is redistributed to the rest of the
structure. These programs also include several advanced features
such as powerful solver modules to analyze the optimum forces
of the stays during construction. Another sophisticated feature is
that the stay prestress is introduced by means of imposed forces.
This way of modeling the tensile forces in the stays, although correct, does not provide too much information to the designer. In
fact, it is necessary to develop separate models to dene the stresses in the strands when the strand by strand tensioning procedure
is used. Furthermore, the vast majority of the ordinary calculation
programs do not include such rened features and therefore, the
modeling of the construction process of cable-stayed bridges is
more complex. In the next section a procedure developed by the
authors that solves all these problems, the Backward Algorithm
(BA), is described.
4. Backward Algorithm
A nite element computation procedure that models the construction process of cable-stayed bridges built on temporary supports, the Backward Algorithm (BA), in formally presented in this
section. Its application is limited for an initial design of the construction process. If differences between the predicted and the actual behavior on site are observed, a forward approach [34] is
suggested. The BA, as most of the advanced commercial programs,
is based on the backward approach from which the algorithm receives its name. In the backward approach, the conguration of
any partial structure is determined by disassembling the bridge
from the OCS. The sequence of events in a disassembly analysis is
the opposite of that which occurs during erection. Thus, every
kth stage, Stagek, can be calculated by subtracting an auxiliary
model to the following construction stage as shown in Fig. 4 or
by subtracting Kk auxiliary models from the OCS as presented in
Eq. (5)
k
OCS
K
P
Auxiliary Model
kk
Each of these K Auxiliary Modelsk represents the effect of the tensile force introduced by the jack in each of the rows of the Tensioning Matrix [TM].
The BA models the tensile forces in the stays by means of imposed strains instead of imposed forces, as in the case of the most
advanced commercial software. This way of modeling the tensile
forces in the stays has two advantages. First of all, it is not
100
a way that the axial force dened in the kth row of the [TM] is
achieved. The analysis of each auxiliary model produces some
increments of vertical deections in the bridge deck at the location
of the temporary support T; Dwk;i
T t , and axial forces in the stays,
DN k;i
C n . Once the effect of the tensile force has been subtracted from
Stagek+1, the ith iteration of the local iterative process is nished
and the Stagek,i is obtained. If, in this stage, positive deections in
temporary supports, wk;i
T t , are obtained, the structural system of
the auxiliary model is changed adding additional temporary supports in the next iteration of the local iterative process as shown
in Fig. 4b. The requirement to evaluate if any temporary support
has been borne is presented in Eq. (6).
k;i
k1
wk;i
T t wT t DwT t P 0
Fig. 4. Superposition of stages in the BA and modeling of temporary supports bearing: (a) ith local iteration, (b) i + 1th local iteration. The active stays are presented by a lled
arrow and the passive stays by unlled arrows.
101
ferent elements of the structure. Among all these matrices, they are
remarkable the two ones that show the evolution of the raising of
the temporary supports. One of these matrices presents the compressive force of each temporary support when borne and the
other one their vertical deection when raised. Finally, compared
with advanced commercial programs, an additional output is provided. This is a vector of strains in the stay that has to be introduced by the jack along the Construction Process, {eCP}. A
summary of the input and output data can be found in Table 1.
The ow chart presented in Fig. 5 summarizes the procedure
followed by the BA. Once the input data has been introduced into
the program, the OSS is stored. Then, auxiliary models that include
the effect of each tensioning stage by means of imposed strains, ek;i
CP ,
are successively subtracted in order to obtain the preceding construction stage. This strain ek;i
CP is calculated in such a way that
the axial force dened in the kth row of the [TM] is achieved. A local iterative process is used to model the nonlinear behavior of the
temporary supports bearing. At the beginning of this iterative process, the Auxiliary Modelk,i has the same number of temporary supports and stays that the Stagek+1. After subtracting Auxiliary Modelk,i
from Stagek+1, the Stagek,i is obtained. In this stage, if positive
deections, wk;i
T t in any temporary support T are measured, Auxiliary
Modelk,i is changed into Auxiliary Modelk,i+1 activating the borne
temporary supports. In addition to this, if tensile reactions, Rk;i
Tt ,
are found in any active temporary support, this is deactivated in
the following auxiliary model (Auxiliary Modelk,i+1). If no positive
k;i
deections, wk;i
T t , nor tensile reactions, RT t are found, the next construction stage, k 1, is calculated. The process stops when the initial stage (k = 0), in which the deck is supported by the set of the
temporary and permanent supports, is achieved. The main advantage of this procedure is that it can be easily reproduced by any
structural software that is able to include either imposed temperature increments or strains in the stays.
In the following section the results of the modeling of the construction process of a simplied cable-stayed bridge obtained by
several advanced commercial programs and those obtained by
the BA are presented.
5. Application of the algorithm
The construction process of a cable-stayed bridge analyzed by
the Backward Algorithm is described in this section. The main
characteristics of this structure and its modeled tensioning process
are rst described. It is to point out that this structure is erected on
a set of temporary supports placed below every stay. Nevertheless,
and without any lack of generality, the algorithm could have been
applied for any other distribution of the temporary supports. Then,
the results obtained by several advanced commercial programs are
presented. Next, these results are compared with those obtained
by the BA. Finally, the BA is applied to obtain the stresses in the rst
strand when using the strand by strand tensioning technique as
well as the stay elongations when prestressed.
5.1. Description of the model
In order to evaluate the efciency of the developed algorithm,
the cable-stayed bridge shown in Fig. 6, is analyzed. This structure
is a simplied model of a project for the city of Wuxi in China. The
bridge has one 54 m high concrete pylon, a 180 m length steel box
girder deck and 18 stayed cables arranged in a semi-harp symmetrical form. The self weight of the bridge deck, g1, and the target
load, TL, are 135 kN/m and 202.5 kN/m respectively. The anchorage
of the two central stays in the bridge deck is separated 15 m from
the pylon. The anchorage of these elements in the pylon is separated 28.8 m from bridge deck. The rest of the stays are uniformly
Table 1
Input and Output data of the BA.
Input data
Output data
anchored every 9 m along the bridge deck and every 1.8 m along
the pylon.
The structural Finite Element Model (FEM) of the whole bridge
consists of 20 beam elements for the girder and 12 beam elements
for the pylon and 18 special elements for the stays. These last elements have no bending stiffness. The values of the Elasticity Modulus, Inertia and Area of the different elements used in the model
are listed in Table 2.
The cable-stayed bridge is built by means of the temporary supports erection method. The tensioning process has K = 35 stages
and its OSS has been dened by means of the Rigidly Continuous
Beam Criterion [29,30]. It has been assumed that non evolutionary
construction process has been needed to reach this initial stage.
The initial stage on site consists of the bridge deck supported by
a set of T = 18 temporary supports. Then, in the next N 1 stages
the rst 17 stays are placed and prestressed by the jack. The axial
forces to be introduced by the jack in these stages are unknown as
presented in Fig. 2. Those forces correspond with the rst N 1
stages of the Tensioning Matrix, [TM]. During the modeling of the
evolutionary process, once a temporary support has been raised
it is removed from the structure. In the Nth stage the 18th stay is
placed. Afterwards, in the nal N 1 stages the axial forces of all
the rest of stays are successively modied. It is worth noting that
there are innity tensioning strategies that can be applied to the
structure in order to assure the achievement of a certain stage after
completion. This strategy can be characterized by the denition of
the N known axial forces of [TM]. In this example, these forces were
chosen to assure that any bending moments, shear forces, axial
forces and nor deection of the structure exceeded safety ranges
during construction.
102
c1 c2 c3 c4 c5 c6 c7 c8 c9
103
Table 2
Properties of the elements of the FEM.
Girder
Pylon
Cable
Inertia (m )
Area (m )
206,000
33,500
195,000
4.2
14.4
0.0
1.7200
8.5400
0.0072
CP1 Maximum
Softwarek
jNC n k N Cn
!
j
BA
NCn k
n : 1N;
k : 1K
BA
The term NC n k represents the axial force in the nth stay calculated by
Softwarek
the BA in the kth construction stage while NC n
represents the
same force calculated by the commercial software. The second comparison parameter, CP2, is based on the differences of axial forces in
all placed stays for a certain construction stage k in absolute value.
As this parameter is different for each construction stage, the maximum value is used. Eq. (8) shows the denition of this parameter
for the quadratic comparison between the BA and the commercial
software.
PN
!
BAk
Softwarek
n1 N N
k : 1K
CP2 Maximum 1 PN C n BA Cn BA
N k N k
n1
Cn
Cn
104
Fig. 7. Tensioning Matrix, [TM], and Force Matrix, [FM], and strain vector feCP g obtained by the BA. The stays that are being prestressed in each stage are framed. Axial forces
in kN and strains dimensionless.
Table 3
Maximum differences in the comparison parameters referring to a percentage of the
results obtained by the BA.
CP1
CP2
Midas (%)
Wiseplus (%)
0.0014
0.0001
0.0025
0.0002
This structural system remains constant throughout the restressing stage. When all the strands have been re-stressed, the
stress of the rst strand is reduced 1.70 MPa respect to its value
when re-stressed. The increment of axial force along the restressed stage is 12.5 kN, which is the 5.2% of that axial force intro34
duced by the jack, that is, N 35
C 9 N C 9 . The comparison of the reduction percentages of the stress in the rst strand obtained in the 1st
and the 35th construction stages showed that lower reductions of
stress were calculated when the stay is re-stressed. This can be explained by the fact that in the re-stressing stage the axial force
introduced by the jack is lower as well the structural system of
the bridge is stiffer as all the stays were placed in the preceding
stages.
DLC n ekCP LC n
105
3500
3400
3300
3200
3100
3000
2900
2800
2700
2600
2500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
CONSTRUCTION STAGE
Fig. 8. Axial forces (kN) of the 9th stay along the construction stages (kN). Stages 1 and 35, where the stay is prestressed, are dotted.
Fig. 9. Stresses in the rst strand of the 9th stay and structural system of the bridge throughout the local tensioning process (MPa): (a) rst construction stage, (b) last
construction stage, which is 35th.
Table 4
DLC 9 (mm) in the Stage1 and Stage35 obtained by different tensioning
processes.
Stay 9
Stage1
Stage35
80.48
5.84
jeopardize the integrity of the strand along the time due to fatigue
problems.
6. Conclusions and future work
When the environmental factors or the requirement of the
foundations do not prevent the placement of the temporary supports during construction, the temporary supports erection method uses to be the most economic way of building cable-stayed
bridges. Unlike its alternative construction method, the cantilever
erection method, no specic research based on the modeling of
the construction process of cable-stayed bridges built on temporary supports has been found by the authors. This paper aims to ll
this gap by providing a computation procedure, the Backward
Algorithm (BA).
The modeling proposed by the BA consists of disassembling the
cable-stayed bridge from the Objective Completion Stage (OCS)
according to the opposite sequence of events which occurs during
erection on site. The BA presents several advantages compared
with the rest of modeling proposed procedures: (1) Unlike the advanced commercial programs, the BA models the prestress of the
stays by means of imposed strains instead of forces. Therefore, it
is not necessary to develop separate models to calculate the stress
variation in the rst strand of a stay when the strand by strand tensioning technique is used. Knowing these stresses is highly recommended because a more efcient control of the construction
process can be carried out on site thus increasing safety during
construction. (2) The stay elongation when prestressed can be easily calculated when the stay is prestressed. This information is not
only important to control the correct and safe prestressing of the
stay on site. It also help the designer to control if the anchor wedge
bites the strand in the same position several times during the prestressing process. (3) Finally, the main advantage of this process is
its simplicity as its results can be easily reproduced by any structural software. This way, faster calculation can be carried out and
the procedure can be efciently used to initially design the construction process of cable-stayed bridges.
The numerical analysis of the cable-stayed bridge studied in
this paper showed that non-representative differences were found
between the results obtained by two studied commercial programs, and those obtained by the BA. Nevertheless, the BA can only
approximate the effects of the time-dependent phenomena, unless
a global iterative process or a backward-forward analysis is performed. To take into account these phenomena, the more complex
but more suitable procedure presented in [34] is proposed. In future works this algorithm will be adapted to take into account
the evolutionary construction of the bridge superstructure.
106
Acknowledgments
The authors wish to thank the support provided by the Ministerio de Ciencia e Innovacin and by Junta de Comunidades de Castilla-La Mancha (Spain) through the research Projects BIA200913056 and PII2I09-0129-4085 (Optimization of the construction
process of cable-stayed bridges built on temporary supports), directed by Jos Turmo.
Part of this work was done through a collaborative agreement
between University of Castilla-La Mancha (Spain) and Tongji University (China). This included an exchange of faculty and scholars.
The nancial support from Kwang-Hua Foundation from College of
Civil Engineering of Tongji University and from the International
Relation Ofce of University of Castilla-La Mancha is greatly
appreciated.
Finally, the authors also want to thank the support provided by
J.A. LLombart and J. Fernndez from Eipsa (Spain), R. Snchez-de
Len and C. Bernal from AIA (Spain), E.W. Vieira from University
of Castilla-La Mancha and by Y. Zhao from Tongji University.
References
[1] Fleming JF. Non linear static analysis of cable-stayed bridge structures. Comput
Struct 1979;10:62135.
[2] Billington D, Namzy A. History and aesthetics of cable-stayed bridges. Struct
Eng 1990:310134.
[3] Virlogeux M. Recent evolution of cable-stayed bridges. Eng Struct
1999;21:73755.
[4] Gimsing NJ. Cable supported bridges; concept and design. Chichester: John
Wiley & Sons; 1997.
[5] Gimsing NJ. The modern cable-stayed bridge-50 years of development from
1955 to 2005. Innovat Sustain Struct 2005;13:4764.
[6] Menn C. Prestressed concrete bridges. Zurich: Springer-Verlag; 1986.
[7] Cremer JM. The val-benoit cable-stayed bridge. In: IABSE symposium
proceedings cable-stayed bridges, past, present and future, Malmo (Sweden);
1999.
[8] XU D, Chen B, Liu L. Tensioning process of Sanhao arch pylon cable-stayed
bridge. In: IABSE symposium, Bangkok; 2009.
[9] Mathivat J. The cantilever construction of prestressed concrete bridges. John
Wiley and Sons Ltd.; 1983.
[10] Feng M. Chinas major bridges. IABSE workshop Shanghai: ETH Honggerberg;
2009. p. 124.
[11] Mozos CM, Aparicio AC. Parametric study on the dynamic response of cable
stayed bridges to the sudden failure of a stay, part I: bending moment acting
on the deck. Eng Struct 2010;32(10):3288300.
[12] Mozos CM, Aparicio AC. Parametric study on the dynamic response of cable
stayed bridges to the sudden failure of a stay, part II: bending moment acting
on the pylons and stress on the stays. Eng Struct 2010;32(10):330112.