Company
:
Date:
26/8/2010
Site:
Ref:
MG 1573
The Work/Task:
The work involved is carrying out the electrical installation for a new build and part
refurbishment of a Doctors Surgery. Martin & Gerard (Electrical Contractors) Ltd has
produced this document for the work they are to carry out which is part of a larger overall
project which is under the control of the Broadstone Group.
Who will carry out the work?
Trained operatives employed by Martin & Gerard (Electrical Contractors) Ltd
What tools and equipment are required?
Employees trade tools and equipment with the addition of electrical portable tools such
as:
Dewalt DC213KB 24volt battery drill; Makita BHR200SJE 24volt battery drill; Makita
6347DWAE 18volt battery drill; Makita BDF451RFE 18volt battery drill; Makita HR2410X
110volt SDS drill; Makita 8419B 110volt drill; Makita HR3520 110volt breaker.
What materials are used?
Electrical wiring and fittings such as - twin & earth electrical wiring; plastic wall back
boxes; plastic switched socket outlet faces and light switch faces; plastic ceiling roses
and lamp holders.
Summary of hazards involved (detailed in attached risk assessments):
Manual handling; over balancing incidents; electric shocks; vibration injuries; noise
induced hearing injuries; respiratory irritations; site activities.
Summary of control measures to be used (detailed in attached risk assessment):
Training in the following:
Manual handling techniques; use of access equipment such as platform steps; use of
portable tools and equipment; wearing and use of PPE such as ear defenders, dust
masks, gloves and goggles; good house keeping procedures; awareness of others on
site.
Are any of the following specific assessments required (if YES attach to this form)
Noise
YES
NO
Vibration
YES
NO
Manual handling
YES
NO
Control of lead
YES
NO
Young persons
YES
NO
Brief outline of how the work is to be done (i.e. sequence/method):
Prior to commencement of work all Martin & Gerard (Electrical Contractors) Ltds site
operatives will be inducted by the Site Manager for Broadstone Group, on the site
procedures and safety issues applicable to the work activity and will sign the section at
the end of this form to indicate that they have read and understood the risk assessment
and method statement. All operatives will have the required PPE i.e. safety boots, hi
visibility vests, safety helmets, gloves, goggles, overalls etc. which will be worn at all
times or as dictated by the work activity.
Generally, all of our work is manual, carried out by hand with the aid of hand held
portable tools, both manually operated and electrically powered. All our operatives are
fully trained Electricians and are well aware of the need for good and safe methods of
work and we endeavour to maintain safe and tidy working areas so as not to present any
risks to others.
The new electrical installations will follow the following procedures:
1st Fixing:
The majority of the wiring will be laid over and clipped to the tops of the ceiling joists,
operatives reaching the working level from platform steps (refer to risk assessment) and
prior to the ceiling boards being fitted and plastering carried out, the cables will then be
fed down the stud walls and/or partitions drilling holes using either a battery operated
and/or a 110volt powered drill to drill the timber studs and noggins as required in order to
feed the cabling to the required position of the socket outlet and/or light switch.
Note: there maybe instances where holes need to be drilled in the brickwork and/or floor
slab to allow for cables to be passed to the outside.
2nd Fixing:
Once all the cables have been pulled in to the required positions and locations the back
boxes for the socket outlets and light switches will be fixed to the relevant timber stud
and/or noggin and the cables fed in and ends stripped and attached to the face plate of
the relevant fitting.
Once others have over boarded the ceilings and plastering works have been completed
the ceiling roses will be fixed to the ceiling with screws into the ceiling joists above, again
the cables will be fed in and ends stripped and attached to the fitting, then lighting cable
dropped from the fitting with the attached bulb holder.
Testing:
MARTIN & GERARD (ELECTRICAL CONTRACTORS) LTD
All the wiring and fitting of the relevant installations will be carried out whilst the circuits
are dead and will only be made live to carry out the required testing and
commissioning so that it conforms to the 17th Edition national standard IEE Wiring
Regulations (BS 7671).
Completion of works and waste disposal:
At completion of our works our operatives will ensure that their work activity area is left
clear by placing all waste into the appropriately marked skips provided by Broadstone
Group i.e. plastic wrappings and cardboard packaging etc.
We will remove from site all offcutts of electrical cable and any faulty fluorescent light
fittings, both of these items will be returned to the company premises and from there
taken to the appropriate waste disposal centre for recycling and in the case of the
fluorescent light fittings returned to the wholesaler for disposal.
Signed:
Name: Robert J. Carrington
Reviewing Procedures:
Should any of our standard working practices change significantly and/or new regulations
and legislation come into force then this document will be reviewed and altered
accordingly to take into account those changes.
APPENDICES:
Risk Assessments:
1. Risk Assessment - MGL/002.
2. Risk Assessment - MGL/003 (Exposure to Hand Arm Vibration).
3. Risk Assessment - MGL/004 (for Exposure to Noise).
MARTIN & GERARD (ELECTRICAL CONTRACTORS) LTD
NOTE:
The Site Operative Induction Form above must be signed by all Martin & Gerard
(Electrical Contractors) Ltds site operatives to confirm that they have read and
understood the contents of the Method Statement and Risk Assessment applicable
to this project.