Escolar Documentos
Profissional Documentos
Cultura Documentos
WATER METER
DESIGN CRITERIA MANUAL &
SUPPLEMENTARY SPECIFICATONS
JANUARY 2011
City of Surrey
TABLE of CONTENTS
Engineering Department
Design Criteria Manual & Supplementary Specifications
Page i
Version, January 2011
Table of Contents
INTRODUCTION ...................................................................................................................... 1
INTENT OF THE STANDARDS ............................................................................................. 1
1.0 Water Meter Design Criteria ............................................................................................ 2
1.1 Glossary Of Terms ..............................................................................................................2
1.2 Metering Requirements ........................................................................................................2
A.
Responsibilities ...........................................................................................................2
B.
Timing ......................................................................................................................3
B.
By-pass .....................................................................................................................5
C.
Receptacles ................................................................................................................6
D.
Chambers ..................................................................................................................6
E.
Fire Hydrants..............................................................................................................6
Appendices
APPENDIX A
APPENDIX B
City of Surrey
Engineering Department
Design Criteria Manual
WATER METERS
Page 1
Version, January 2011
INTRODUCTION
This document outlines the Citys requirements for the installation of cold-water meters on
municipal water services. It is divided into two separate parts the Design Criteria and the
Supplementary Specifications.
City of Surrey
Engineering Department
Design Criteria Manual
WATER METERS
1.0
1.1
Glossary Of Terms
1.2
Page 2
Version, January 2011
Applicant
Applicants Engineer
ASTM
AWWA
City
CSA
Developer
General Manager,
Engineering
Owner
Chamber or Pit
Metering Requirements
A.
Responsibilities
The Surrey Waterworks Regulation and Charges By-law, 2007, No. 16337 (as
amended) identifies that all new service connections require water meters. For new
connections, the installation of a meter is triggered by an Application for Building
or Plumbing Permit. This requirement for a meter applies to:
City of Surrey
Engineering Department
Design Criteria Manual
WATER METERS
Page 3
Version, January 2011
For all new connections, the Applicant must supply and install all piping, fittings,
meter chamber(s) / vault(s) and equipment.
The City supplies and installs meters of sizes 19 mm (inch) for single-family and
duplex residential construction. In all other cases, the meter is supplied and
installed by the Applicant.
Backflow prevention devices although not covered within this section are to be
installed in accordance with City of Surrey Cross Connection Control Bylaw, 2007,
No. 16355 (as amended).
B.
Timing
For single family residential dwellings water meter chambers, setters and lids are to
be installed to final grade by the Applicant in advance of the Drainage, Water and
Ventilation Inspection (DWV). Water meters, installed by the City, are to be
installed after the DWV approval but in advance of the Final Plumbing Inspection.
The meter area must be kept free and accessible at all times in order to permit the
installation of the meter.
The Applicant is responsible for the protection of
installation from damage and must repair any damage that occurs to the chamber,
setter, meter, or lid.
For meters servicing other uses the meters must be installed prior to turning on the
water supply to the site.
In the case where a drawing submission is required (see Section G) installation of
the water service, chamber, or meter within private property should not begin prior
to the approval of the drawings.
1.3
City of Surrey
Engineering Department
Design Criteria Manual
WATER METERS
Page 4
Version, January 2011
For developments that are proposed to be phased, the meter chamber and piping must be
sized for the meter required for the ultimate buildout of the development. However, the
initial meter installed must be sized to accurately capture the range of flows for the first
phase.
It is expected that in most cases the water meter size will be at least 1-2 sizes smaller than
the water service connection, providing they meet the size selection criteria. The
Applicants Engineer must ensure the meter selection and installation requirements are
appropriate for the designed application.
1.4
Meter Selection
Only one domestic meter is to be supplied per property unless otherwise approved by the
General Manager, Engineering. The only exception is duplex units where two separate
domestic meters are to be provided.
Only those meters outlined in the Supplementary Specifications will be considered by the
City, unless otherwise approved by the General Manager, Engineering.
Unless otherwise approved a separate fire service line must be supplied to each property
that employs fire sprinklers or onsite fire hydrants. The fire service line must be
equipped with metering technology to detect unauthorized use of water in accordance
with AWWA standards and applicable City and Provincial codes through the use of a
double check detector valve assembly. All other uses that require service from the
potable water system (including domestic, process, and irrigation) must be serviced from
the domestic service line with tees and branches located after the water meter. The
exception to this is for single family residential homes that employ fire sprinklers. In this
case a combined service is acceptable but the meter must not be less than 38mm in size.
1.5
Meter Location
All meters 50mm and smaller must be located at the property line in a chamber in
accordance with the Supplementary Detail Drawings, unless otherwise approved by the
General Manager, Engineering.
For property line installations the meter box or vault must be located on private property
300mm from the property line and 300mm from the shut off. Where the water main is
within private property, in a right-of-way, the meter box or vault should be placed outside
the right-of-way. An area at least 1.0 m horizontal and 2.0m vertical around the meter
box or vault should be free of major landscaping or objects, including shrubs, etc., to
facilitate the future maintenance work of the meter installation. Grading of the area
around the chamber must ensure positive drainage away from the chamber.
City of Surrey
Engineering Department
Design Criteria Manual
1.6
WATER METERS
Page 5
Version, January 2011
Meter Configuration
The general configuration for meter installations has been illustrated in the
Supplementary Detail Drawings. For all non-positive displacement meters 50mm and
larger, configuration details shall be determined by the Applicants Engineer and outlined
in the design drawings.
When the meter is installed within a building the installation should be within reasonable
distance of a floor drain. The floor drain must be suitable sized to accept the high flows
associated with meter testing (25 l/s).
Under no circumstances is a meter to be installed in a bathroom or a bedroom. A space
of at least 1.0 m in front of the meter shall be free of obstruction to allow for convenient
servicing and testing of the meter at all times. No electronic, mechanical and water
sensitive equipment or machinery should be placed or installed under the meter
installation or in an area where splash or flow from the meter settings or pipes could
occur during the servicing of the meter.
For all non-positive displacement meters 50mm and greater adequate straight length pipe
should be provided upstream and downstream of the meter in order to comply with
manufacturers recommendations for maximum accuracy. Bypass tees and isolation gate
valves may be located within the straight length distance in accordance with
manufacturers recommendations. A restrained coupling must be provided on the
downstream side of the meter for flexibility in case of meter removal.
A.
Isolation Valves
Isolation valves, must be in the same chamber as the meter and are required to be
installed upstream and downstream of the meter assembly. All valves, for meters
75mm and larger, with the exception of the lockable bypass must be capable of
being operated above ground without entering the chamber through a cored hole in
the lid.
B.
By-pass
A locking bypass is required to be installed on all 50mm and larger non-positive
displacement meters. The bypass shall be 50mm with the following exceptions:
Combined fire service line meters, where approved, bypasses must be full sized;
and
Facilities with critical flow requirements with bypass sized to ensure impacts
are minimized during meter maintenance.
After testing the installation, the by-pass valve must be closed and sealed by the
installer.
City of Surrey
Engineering Department
Design Criteria Manual
WATER METERS
Page 6
Version, January 2011
By-passes must not be located above the meter in a chamber setting, however,
rotating them 45 degrees is permitted if space governs.
C.
Receptacles
For meters installed at the property line, remote register receptacles must be
mounted in the chamber lid. The remote register must be of the same manufacturer
as the meter.
For inside installations, where approved, wall mounted remote receptacles should
be located approximately 1.2 meters above grade (ground) and easily accessible for
reading. They shall not be located within locked fenced areas. Where possible
these should be located adjacent to gas or electric meters.
All receptacles shall be touch pad technology (digital readouts are not acceptable).
D.
Chambers
Meter chambers, or where specifically approved above ground enclosures, must
meet the requirements of the Supplementary Specifications, and be selected to
provide adequate space for removal and testing of all equipment within the meter.
Access lids, latches, and ladders must comply with the current requirements of the
Workers Compensation Board and provide adequate space for testing and removal
of meters and where applicable backflow prevention devices.
Thrust beams must be designed for all chambers housing equipment 75mm or
larger to ensure that the force caused by a closed valve is transferred to the full
width of the chamber. The Applicants Engineer shall ensure that the chamber
manufacturer is in agreement with the thrust bearing area on the chamber.
All chambers for non-positive displacement meters must be equipped with a sump
and drained by either a gravity connection to the storm sewer or where this is not
possible by an electric sump pump. The Owner is responsible for providing power
to the sump pump in accordance with the BC Electrical Code.
E.
1.7
Fire Hydrants
All on-site hydrants must be located after the site premise back flow prevention
device.
Submissions
Plans must be submitted by the Applicant as part of the plumbing permit application for
all meter installations. This application must be accompanied by a site plan that includes:
City of Surrey
Engineering Department
Design Criteria Manual
i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.
WATER METERS
Page 7
Version, January 2011
For all non-positive displacement meter installations 50mm and larger, the Applicants
Engineer must provide detailed sealed drawings and shop drawings of the installation and
relevant calculations, to demonstrate the appropriateness of the sizing of the meter, for
approval prior to installing the meter.
City of Surrey
Engineering Department
Supplementary Specifications
WATER METERS
Page SS-1
Version, January 2011
SUPPLEMENTARY SPECIFICATIONS
1.0
PRODUCTS
1.1
Water Meters
T-101
Elster
C-7001
Registers
City of Surrey
Engineering Department
Supplementary Specifications
WATER METERS
Page SS-2
Version, January 2011
Remote
Receptacles
City of Surrey
Engineering Department
Supplementary Specifications
1.4
Radios
WATER METERS
Page SS-3
Version, January 2011
1.5
Pipe and Fittings .1 Connections 75mm (3inches) in diameter and greater must be
restrained to the City water main.
.2 All pipe material within chambers shall be ductile iron, Schedule
80 PVC, C900 PVC, polyethylene or Type K copper. All products
must be approved for potable water application. All joints within
the chamber must be restrained (ie. Flanged, glued, welded,
threaded).
1.6
Valves
1.7
Flange Adaptors .1 Flange adapters for 38mm (1 inches) to 200mm (8 inches) sizes
must conform to AWWA C219.
City of Surrey
Engineering Department
Supplementary Specifications
WATER METERS
Page SS-4
Version, January 2011
1.8
1.9
Meter Chambers .1 Meter pits and vaults must be pre-cast chambers or where
specifically approved by the General Manager, Engineering
heated stainless steel or fibreglass enclosures on concrete pads.
.2 Lids/covers must be capable of withstanding H-20 static loading
(except where lids are located in travelling surfaces where H-20
dynamic loading applies) and be equipped with 45mm (1
inches) holes for mounting the remote receptacles. These holes
must be sealed until the installation of the receptacles. Lids for
positive displacement or residential magnetic meters must be cast
iron with hole for touch pad. Lids for non-positive displacement
meter installations must be aluminum spring assisted and divided
into multiple sections where the dimensions exceed 900mm in any
direction. Manhole access is not acceptable unless approved by
the General Manager, Engineering.
.3 Exterior of all chambers must be damp proofed by applying an
asphalt emulsion coating to all exterior surfaces. Construction
joints must be made water tight with an appropriate sealant. All
pipe entrances on the vault must be sealed and waterproof.
2.0
EXECUTION
2.1
Meter
Installation
City of Surrey
Engineering Department
Supplementary Specifications
2.2
Receptacle
Installation
WATER METERS
Page SS-5
Version, January 2011
3.0
City of Surrey
WATER METERS
Engineering Department
Design Criteria Manual & Supplementary Specifications
Appendix A
Page 1
Version, January 2011
Page 1/3
Customer Name:
Address:
PID Number:
BP Number:
Project Number:
Type of Occupancy:
Multifamily
Institutional
Commercial
Other
Industrial
Yes
No
Phase __
Buildout
Seperate calculations must be provided for both current phase and buildout
Bathtub
Bedpan Washers
Bidet
Dental Unit
Dishwasher
Drinking Fountain - Public
Hose Bibs (c/w 50 ft Wash Down)
- 1/2 inch
- 5/8 inch
- 3/4 inch
Kitchen Sink
Lavatory
Showerhead (Shower only)
Service Sink
Toilet
- Flush Valve
- Tank Type
Urinal
- Pedestal Flush Valve
-Wall Flush Valve
Wash Sink (Each Set of Faucets)
Washing Machine
Other:
No. of
Fixture
Fixtures
Value (gpm)
8
10
2
2
2
2
X
X
X
X
X
X
=
=
=
=
=
=
5
9
12
2.2
1.5
2.5
4
X
X
X
X
X
X
X
=
=
=
=
=
=
=
35
4
X
X
=
=
35
16
4
6
X
X
X
X
=
=
=
=
X
X
X
X
=
=
=
=
gpm (A)
Revised: 10-01-2013
Page 2/3
PID Number:
gpm (B)
(C)
gpm (D)
gpm (E)
Larger irrigation areas should be divided into zones with a maximum irrigation flow of 50 gpm.
If the irrigation flow is greater than 50 gpm, the Applicant's Engineer shall provide a detailed irrigation plan
with appropriately designed zones.
gpm (F)
mm (G)
mm (H)
mm
mm
Created Date:
Revised Date:
Comments:
Revised: 10-01-2013
Page 3/3
PID Number:
gpm
psi
Typical operating flows and discharge pressures shall be provided for each and every pump
for property's containing multiple buildings.
Note: The City may request pump specifications and design information for confirmation
purposes if the flow indicated above is significantly greater than the domestic demand.
B) Storage Tanks
Is there a storage tank on the property:
Yes
No
Revised: 10-01-2013
City of Surrey
WATER METERS
Engineering Department
Design Criteria Manual & Supplementary Specifications
Appendix B
Page 1
Version, January 2011
24th AVENUE
W
W
W
W
W
W
W
W
W
NOTES:
W
W
W
W
152nd STREET