Implementation of standardized, uniform project management system for all 65
subcontractors by setting up Project Control Cell responsible for 1. Time Planning and scheduling using Primavera P-6 software.
Construction Implementation
Dedicated 1,100 staff deployed to turn the Engineering Challenge into reality 1. Airside Works:
a. 4.43km of Runway along with 20km of taxiways completed in 20 months with
24.52 Lac cum of earthwork, 4.61Lac Cum of CTB ,70,651 Cum of Pavement
Quality Concrete and 5.8 Lac MT of Asphalt ,5,100 AGL lights.
b. 6.3 Lac Sqm of Apron area with 57 stands and capacity to park 115 different
types of Aircrafts involving 3 Lac Cum of Pavement Quality Concrete.
c. 11 km of Perimeter Roads, 11.2 km of precast elements Boundary Wall
d. 12.5 km of Drains and 5.5 km of Culverts
2. Terminal Building Works
i. Building Civil Structural Works
a. Structural works for 5.5 Lac Sqm area Terminal Building completed in record
18 months duration involving 5.32 Lac cum of concrete, 1.0 Lac MT steel,
10.6 Lac sqm of shuttering.
ii. Building Envelope Works
b. Terminal Building Structural roof having 16,000 MT structural steel fabricated
& erected in span of 6 months.
c. 1.92 Lac Sqm of 7 layer roof sheeting system.
d. 1.8 Lac Sqm of Faade with 3,100 MT structural steel as transoms and
mullions
iii. Building Services and Utilities
e. 2.5 Lac sqm ducting, 735 AHU installations,48 km of chilled water pipeline, 8
chillers with cumulative capacity of 20,000TR
f.
1 Lac light fixtures with 880 kms conduiting, 565 panels, 5,000 kms wiring
i.
j.
3. Airport Systems
a. 12,400 Bags per hour capacity Baggage Handling System with 6.4km
conveyor, 12 km belt, 2,100MT steel, 3,500 sensors, 41 X-ray machines.
b. 63 Nos elevators, 31 Nos escalators and 88 travelators
c. 78 Numbers PBBs capable to serve A-380
d. 40,500 Network Data points, 3,300 CCTV, 8,500 speakers, 2,500 access
control entries, 2,500 km of Optical fiber cabling,729 FIDS display screens,
168 check in counters. equipped with Common Usage Terminal Equipment
CUTE Self Check in and Boarding pass generation. IT Integrated CMS
system of MEP services to IBMS for fast and effective control.
Building Interior Finishes
e. 4.6 Lac Sqm of Flooring with 1.10 lac Sqm of Granite from Saudi and
remaining area with Vitrified, Kota, carpet and Granolithic screed flooring.
f.
3.60 Lac Sqm of false ceiling with 2.84 Lac Sqm of Metal Panels being
imported from Germany and China.
g. 1.5 Lac Sqm of Internal ACP works, 15,462 Sqm of Corian Cladding.
Mechanization of Construction
1. Mobilization of Plant and Machinery worth 150 Crore in short span of 5 months.
2. 960 Cum/hr Concrete production capacity set up.
3. 600 MT/hr production capacity Hot mix plants.
4. 8,000 MT/month capacity steel service center established at site.
5. Pre casting yards for Boundary wall and Drain and Culverts elements.
6. Establishment for Horizontal and Vertical Precast Hume pipe production at site.
7. 62 Lac Tons of High quality aggregates procured. Critical part of 10 Lac ton for
pavement works produced at L&Ts own crushing plant at Pichani.
8. 8 Lac MT of cement procured at site with cement storage capacity built up for
45,000MT.
9. 65,000 Sqm/Month duct production capacity factory set up at site for HVAC works.
10. Pipe fabrication factory with capacity of producing 88km of pipes/ month set up at
site.
11. Laser Leveling machines with racker for precision in levels upto +-3mm and
spreading capacity of 1,000 sqm in 8 hours
g. Minimum electric lighting use during daytime. Lighting Control and Monitoring
System for the whole PTB & Piers with all the associated Presence detectors,
Occupancy sensors, Daylight sensor, and Brightness sensor modules to adjust
the lighting levels as required.
h. Water-efficient landscaping using recycled water.
i.
Over 400 Nos. rainwater recharging Pit installed to conserve & replenish Ground
water
j.
STP (Sewage treatment plant) water for complete Air Conditioning system
Use of sensors in taps etc, effectively reducing the wastage of water by 20%
At Execution Stage
n. Accommodation capacity of Labour colony at site - 30, 000
o. Workmen Training Institute set up at Site itself.
p. Waste Water utilization by Sewage treatment plant at Labour colony.
q. Taking up tree plantation, dust control and zero emission provisions at HMP.
Considering energy efficient design, the Chillers installed are having very low KW/TR
(kilowatt/Tones) ratio of 0.55 at 100% load, which means reduced power consumption.
Main substation building/rooms are temperature cooled for better monitoring and
equipment operations.
State of art HVAC- CMS (Central Monitoring system) to operate, monitor and Control
HVAC system.
Electrical:
Additional levels of reliability to prevent power failure by creating multiple banks for
transformers.
Separate lighting CMS system for better monitoring and control.
Routing of 11 KV cables from Main substation to Passenger Terminal Building through
underground tunnels.
Way finding design is incorporated in the lighting design.
Fire:
Gas suppression system uses a unique gas- NOVAC 123, which is environmental friendly
having 0.0% ozone depletion effect and atmospheric lifetime of 5 days only.
All designs as per NFPA norms (National Fire Protection Association American Society)
BHS:
Sophisticated in- line Baggage Handling system, no queues to stand in to have luggage
system go through X-Ray system thereby saving time and offering comfort and
convenience to passengers
All Check in counters to use CUTE (Common user Terminal Equipment), which facilitates
airlines to use any counter during peak hours.
Foolproof security system with 5 levels of baggage screening. The baggage shall go
through level one of screening through X-ray machine. If suspicious article is found the
baggage will proceed to level 2 workstations with dual monitors. If the baggage is not
cleared, it proceeds to level 3 of screening. At level 4 screening passenger will be called
and asked to open the luggage and if there are any explosives, baggage is sent to level
5 which has designated Threat bag disposal area.
Baggage handling system running with 1,200 motors that are controlled with fully
automated Programmed Logic Controls (PLCs) that will ensure conservation and
optimum utilization of energy.
Apart from dedicated 5 carousels for domestic arrivals and another 5 for international
arrivals, another 2 inter changeable carousels are also provided which can be used
either for international or domestic arrivals during peak loads as per the requirement.
Major Software used:
Building Information Management(BIM) for 3D modeling for Design Interface and Clash
free execution.
Tekla 3D used for structural steel and Apron Interface
TERRA model for Bulk earthwork calculation
LIDAR survey for existing Fuel Farm of BPCL to create the exact 3D model of our
Aviation Fuel Connection designs.