Escolar Documentos
Profissional Documentos
Cultura Documentos
Ans :
There are two options constructing concrete floors they are:
1) cast in situ
2) Precast
1) CAST IN SITU
Cast-in-Place Concrete Advantages
Monolithic construction
Positive drainage is easier to achieve
Floor vibration generally negligible.
Post-tensioning forces reduces cracking in slabs
Lower maintenance costs
Higher perceived head room ceiling and more openness.
Generally no shear walls except in high seismic zones or very
tall structures
Construction can be performed by local sub contractors using
local labour.
More accommodating for unique structures with irregular
shapes, circular helix ramps
Cast-in-Place Concrete Disadvantages
Potentially higher construction cost in some regions of the
country, particularly in areas where field labor costs are high
2) Precast
Precast Concrete Advantages
Potentially lower construction cost .
Faster construction process
Shorter on-site construction schedule
More adaptable to winter construction
Economic for large scale production
Precast Concrete Disadvantages
More propensity for leaking at the joints between tee flanges
Higher maintenance cost for sealants
Lower perceived head room and less openness.
Reduced drainage slopes
More bird roosting ledges
Might not be performed by local subcontractors in many cities
Require heavy equipment.
Ans :
Pre-cast construction is cost effective and provide significant
advantages over conventional construction. Precast concrete does
not have the weather concerns that a Cast in place system has. It
has significant benefits in the schedule and cost of a project due
to its fast erection. It does not require the setting up of formwork,
pouring concrete, and then curing of the concrete because it is
produced indoors away from the site.
Factors
Access of the trucks and cranes to the site
We need to know type of cranes that can lift the beam
Delivery of the percast material to site
Sufficient place for mobility of vehicles
Procedure of pre cast beams
1. Set reference line and offset line to determine the position of
the precast elements to be installed.
Put up temporary props to support the precast beam elements
2. Provide level pads for setting the level of the elements in
position using non-ink mortar
4. Lift panel to its designed location with the use of wire ropes.
5. Secure it with diagonal props after panel is in its position.
6. For components with cast in-situ joints, place the rebars as
required.
7. Set up the formwork for the casting of the joints
8. Carry out concrete casting.
9. Remove forms after sufficient strength has been achieved by
the concrete.
Ans :
A steel-concrete composite column comprising a concrete filled
hollow section of hot-rolled steel. bare steel sections support the
initial construction loads, including the weight of structure during
construction. The light weight and high strength permit the use of
smaller and lighter foundations.
With the use of composite columns along it is possible to erect
high rise structures in an extremely efficient manner. There is
quite a vertical spread of activity working simultaneously. For
example
Sequence of work
One group of workers will be erecting the steel beams and
columns for 1st or 2nd storeys .
Another group of workers will be fixing the metal decks for
the one storey below.
Another group of workers will be concreting the floors.
Ans :
There are many options available to designers when developing
the structural of a building. The most common approaches are
cast-in-place concrete, precast concrete, or structural steel each
with this has their own advantages and disadvantages.
Cast-in-place systems
CIP system is an extremely versatile material because its shape is directed by formwork erected on site.
Considering
Material
Strength
Steel structure
R.C.C structure
Light in weight
compared with r.c.c
structure
Fire safety is low
Heavy in weight
Corrosion occurrence
is more
Periodic maintenance
is required
Life is less
Recycling of material
is possible after its
life
Seismic resistance is
less
Recycling is not
possible
Safety is high
Less maintenance
required
Life is more
Seismic resistance is
more
Construction
Cost
Failure caused is
Failure occurs
sudden
periodically
Required R.C.C
Foundation is a part
Foundation
of R.C.C structure
Shuttering and
Shuttering and
formwork is not
formwork is required
required
After constructing it is It should be in hold
ready to use
till it gains its
strength
Machinery is required Machinery is not
required
Fast in construction
Not as fast as of steel
structure
Curing is not required Curing is required
High initial cost
required
High maintenance
cost is needed