Você está na página 1de 5

5504 Federal Register / Vol. 70, No.

21 / Wednesday, February 2, 2005 / Notices

Federal Aviation Administration, Safety and Noise Abatement Act, b. Program measures are reasonably
Northwest Mountain Region, Airports hereinafter referred to as ‘‘the Act’’) and consistent with achieving the goals of
Division, Denver Airports District 14 CFR part 150. These findings are reducing existing noncompatible land
Office, 26805 E. 68th Ave., Suite 224, made in recognition of the description uses around the airport and preventing
Denver, Colorado 80249. of Federal and nonfederal the introduction of additional
The request to release property may responsibilities in Senate Report No. noncompatible land uses;
be reviewed in person at this same 96–52 (1980). On February 19, 2004, the c. Program measures would not create
location. FAA determined that the noise exposure an undue burden on interstate or foreign
SUPPLEMENTARY INFORMATION: The FAA maps submitted by the City of Fort commerce, unjustly discriminate against
invites public comment on the request Lauderdale, Florida under part 150 were types or classes of aeronautical uses,
to release property at the Pueblo in compliance with applicable violate the terms of airport grant
Memorial Airport under the provisions requirements. On January 14, 2005, the agreements, or intrude into areas
of the AIR 21. On December 17, 2004, FAA approved the Fort Lauderdale preempted by the Federal government;
the FAA determined that the request to Executive Airport noise compatibility and
program. Most of the recommendations d. Program measures relating to the
release property at the Pueblo Memorial
of the program were approved. use of flight procedures can be
Airport submitted by the City of Pueblo
EFFECTIVE DATE: The effective date of the
implemented within the period covered
met the procedural requirements of the by the program without derogating
Federal Aviation Regulations, Part 155. FAA’s approval of the Fort Lauderdale
safety, adversely affecting the efficient
The FAA may approve the request, in Executive Airport noise compatibility
use and management of the navigable
whole or in part, no later than April 29, program is January 14, 2005.
airspace and air traffic control systems,
2005. FOR FURTHER INFORMATION CONTACT: Ms.
or adversely affecting other powers and
The following is a brief overview of Bonnie Baskin, Federal Aviation responsibilities of the Administrator
the request: Administration, Orlando Airports prescribed by law.
The Pueblo Memorial Airport requests District Office, 5950 Hazeltine National Specific limitations with respect to
the release of 6.02 acres of non- Dr., Suite 400, Orlando, Florida 32822, FAA’s approval of an airport noise
aeronautical airport property to the City (407) 812–6331, Extension 130. compatibility program are delineated in
of Pueblo, Colorado. The purpose of this Documents reflecting this FAA action FAR Part 150, Section 150.5. Approval
release is to allow the City of Pueblo to may be reviewed at this same location. is not a determination concerning the
sell the subject land that was conveyed SUPPLEMENTARY INFORMATION: This acceptability of land uses under Federal,
to the City by the United States acting notice announces that the FAA has state, or local law. Approval does not by
through the War Assets Administration given its overall approval to the noise itself constitute an FAA implementing
by Quit Claim Deed dated July 20, 1948. compatibility program for the Fort action. A request for Federal action or
The sale of this parcel will provide Lauderdale Executive Airport, effective approval to implement specific noise
funds for airport improvements. January 14, 2005. compatibility measures may be
Any person may inspect the request Under section 47504 of the Act, an required, and an FAA decision on the
by appointment at the FAA office listed airport operator who has previously request may require an environmental
above under FOR FURTHER INFORMATION submitted a noise exposure map may assessment of the proposed action.
CONTACT. submit to the FAA a noise compatibility Approval does not constitute a
In addition, any person may, inspect program which sets forth the measures commitment by the FAA to financially
the application, notice and other taken or proposed by the airport assist in the implementation of the
documents germane to the application operator for the reduction of existing program nor a determination that all
in person at Pueblo Memorial Airport noncompatible land uses and measures covered by the program are
31201 Bryan Circle, Pueblo, CO 81001. prevention of additional noncompatible eligible for grant-in-aid funding from the
Issued in Denver, Colorado, on January 12, land uses within the area covered by the FAA. Where Federal funding is sought,
2005. noise exposure maps. The Act requires requests for project grants must be
Craig Sparks, such programs to be developed in submitted to the FAA Airports District
Manager, Denver Airports District Office. consultation with interested and Office in Orlando, Florida.
[FR Doc. 05–1917 Filed 2–1–05; 8:45 am] affected parties including local The City of Fort Lauderdale, Florida
BILLING CODE 4910–13–M communities, government agencies, submitted to the FAA on February 4,
airport users, and FAA personnel. 2004, the noise exposure maps,
Each airport noise compatibility descriptions, and other documentation
DEPARTMENT OF TRANSPORTATION program developed in accordance with produced during the noise compatibility
Federal Aviation Regulations (FAR) Part planning study conducted from
Federal Aviation Administration 150 is a local program, not a Federal September 2000, through December
Program. The FAA does not substitute 2002. The Fort Lauderdale Executive
Approval of Noise Compatibility its judgment for that of the airport Airport exposure maps were determined
Program; Fort Lauderdale Executive proprietor with respect to which by FAA to be in compliance with
Airport; Fort Lauderdale, FL measures should be recommended for applicable requirements on February 19,
AGENCY: Federal Aviation action. The FAA’s approval or 2004. Notice of this determination was
Administration, DOT. disapproval of FAR Part 150 program published in the Federal Register on
ACTION: Notice. recommendations is measured February 19, 2004.
according to the standards expressed in The Fort Lauderdale Executive
SUMMARY: The Federal Aviation Part 150 and the Act, and is limited to Airport study contains a proposed noise
Administration (FAA) announces its the following determinations: compatibility program comprised of
findings on the noise compatibility a. The noise compatibility program actions designed for phased
program submitted by the City of Fort was developed in accordance with the implementation by airport management
Lauderdale, Florida under the provisions and procedures of FAR Part and adjacent jurisdictions from the date
provisions of 49 U.S.C. (the Aviation 150; of study completion, 2002, beyond the

VerDate jul<14>2003 14:19 Feb 01, 2005 Jkt 205001 PO 00000 Frm 00093 Fmt 4703 Sfmt 4703 E:\FR\FM\02FEN1.SGM 02FEN1
Federal Register / Vol. 70, No. 21 / Wednesday, February 2, 2005 / Notices 5505

year 2007. It was requested that FAA The previous part 150 study and Record decommissioning the middle marker.
evaluate and approve this material as a of Approval summarized this measure’s Therefore, the City also requests that the
noise compatibility program as benefits, when implemented as FAA continue the operation of the
described in Section 47504 of the Act. voluntary, as follows: ‘‘The elimination middle marker as an electronic
The FAA began its review of the of this measure would dramatically reference or ‘‘turn marker’’. (NCP, pages
program on July 20, 2004, and was increase direct jet overflights of the 64, 103; Figure 38)
required by a provision of the Act to close-in residential areas under the
approve or disapprove the program extended centerlines of runways at the FAA Action: Disapproved as to
within 180 days (other than the use of airport, in areas where jet operations Formalizing the Procedure;
new or modified flight procedures for currently are rare. Increased jet use Continuation of the Current Procedure
noise control). Failure to approve or would almost certainly result in a on a Voluntary Basis Is Approved, for
disapprove such program within the vigorous community reaction.’’ VFR Traffic Only, as Traffic, Weather,
180-day period shall be deemed to be an 2. Extension of Upwind Leg for Runway and Airspace Safety and Efficiency
approval of such program. 31 Departures out to the Turnpike Permit
The submitted program contained
twenty-seven (27) proposed actions for The City will continue to request that Formalizing this procedure is
noise mitigation on and off the airport. pilots delay turns to crosswind or on disapproved because there is no
The FAA completed its review and course until crossing this visual instrument approach to Runway 26, and
determined that the procedural and reference. There is no change proposed aircraft are required to fly an ILS
substantive requirements of the Act and to the measure approved by the FAA in approach to Runway 8. This opposite
FAR Part 150 have been satisfied. The 1997. (NCP, pages 64, 176) direction operation requires that
overall program, therefore, was FAA Action: Disapproved departing aircraft on Runway 26 turn as
approved by the FAA effective January The FAA objects to this measure soon as possible for safety purposes. For
14, 2005. because it may impact aircraft clarification purposes, the Runway 26
Our right approval was granted for operational safety and efficiency. VFR departure heading was changed to 315°
fifteen (15) of the twenty-seven (27) aircraft in the traffic pattern for Runway due to magnetic variation and the
specific program elements. Seven (7) 31 must be able to turn crosswind before opposite-direction departure separation
elements were disapproved for the reaching the Turnpike in order to run a requirement of 45°. The FAA does not
purposes of part 150, four (4) elements safe and efficient traffic pattern. In currently initiate a turn after crossing
were partially approved, and one (1) addition, continuation of this existing NW 31st Avenue/Runway 8 middle
required no action. The approval/ measure is disapproved due to marker. Adherence to this procedure is
disapproval action was for the following significant increase in air traffic in the voluntary on the part of the pilot. The
program measures: area from many airports. The air traffic Part 150 study approved in 1997 stated,
Operational Measures controllers need to be able to run ‘‘This measure reduces the population
aircraft as soon as possible and cannot within the 65 dB Ldn noise contour by
1. Restriction of Jet Use of Runway 13/ be required to place aircraft in a
31 631 people.’’
prescribed flight path with the
significant increase in air traffic around The FAA will not continue to use the
The City requests that the FAA amend
the existing voluntary limitation of jet FXE. middle marker as an electronic
use of Runway 13/31 to implement it as reference. As an alternative to using the
3. Voluntary Use of Turbojet Noise MM, the airport sponsor may contact
a formal preferential runway program Abatement Departure Profiles
element. This program element is the FAA to determine whether the use
appropriate because there are residential The City will continue to request that of Distance Measuring Equipment
areas closer to the ends of this runway pilots use National Business Aviation (DME) may be an appropriate substitute
than to the ends of Runway 08/26. Association (NBAA) and manufacturers’ for the electronic reference.
Formalizing the procedure is expected turbojet noise abatement departure
profiles. This program element must be 5. Evening and Night (8 p.m. to 7 a.m.)
to reduce jet use on Runways 13 and 31 Implementation of ‘‘Quiet One’’
by an additional 2 to 3 percent for both voluntary, because the pilot in
command of the aircraft has the ultimate Departure Procedure on a Formal Basis
daytime and nighttime hours. (NCP,
pages 63, 98, 123, 175, and Table 22) responsibility for safe aircraft operation.
Pilots of eastbound and southbound
No third party (including the FAA or
FAA Action: Disapproved as to the City) can dictate cockpit procedures. aircraft currently are requested to use
Formalizing the Procedure; (NCP, pages 64, 147–148, 176; Figure the ‘‘Quiet One’’ departure procedure (a
Continuation of the Current Procedure 50) climbing left 360° turn to a heading of
on a Voluntary Basis Is Approved 090°) on a voluntary basis at night (10
FAA Action: Approved as a Continuing p.m. to 7 a.m.) in visual conditions. The
The recommendation to formalize the Voluntary Measure City requests that the FAA amend this
restriction is disapproved because
Runway 13/31 would have to be 4. Runway 26 Departure Heading procedure to implement it on a formal
available for operations should Runway Pilots currently are requested to basis, and to extend the effective hours
8/26 be closed. Also, it is not clear from initiate a turn to 310° after crossing NW to run from 8 p.m. to 7 a.m. This
the NCP just how much of the noise 31st Avenue (visual conditions) or after procedure is implemented at pilot
benefit, described in Table 22 for a passing the Runway 8 middle marker request only, with ATCT approval. No
combination of three proposed formal (instrument conditions). The City change is proposed. (NCP, pages 64,
preferential procedures, is derived from requests that FAA amend this procedure 103, 176)
formalizing this measure. to implement it on a formal basis, so
This procedure may continue on a that it applies to all non-emergency
voluntary basis as traffic, weather, and operations (wind, weather, and traffic
airspace safety and efficiency permit. permitting). The FAA is

VerDate jul<14>2003 14:19 Feb 01, 2005 Jkt 205001 PO 00000 Frm 00094 Fmt 4703 Sfmt 4703 E:\FR\FM\02FEN1.SGM 02FEN1
5506 Federal Register / Vol. 70, No. 21 / Wednesday, February 2, 2005 / Notices

FAA Action: Disapproved as to good placement of facilities built on operation requires that departing aircraft
Formalizing the Procedure and airport property in a manner that would on Runway 26 turn as soon as possible
Continuation of the Current Procedure use the building as a buffer to minimize for safety purposes. Opposite direction
on a Voluntary Basis, as It Allows for airport ground-based noise on nearby operations on the same runway lower
Uncontrolled Turns in IFR Airspace in residences. Any building construction the margin of safety.
a Very Congested Area on the airport would be required to The current NCP shows that Runway
This measure was previously comply with applicable Federal 26 nighttime departures are carried out
approved as voluntary in 1997 for the requirements. about 55 percent of the time by jet
nighttime timeframe. It is being aircraft, and 35 percent of the time for
8. Restriction of Maintenance Runups 7 propeller aircraft. Runway 8 nighttime
disapproved at this time because of the p.m. Through 7 a.m. at the Runup Pad
significant increase in air traffic in the arrivals by jets occur approximately 70
area. The concern is that the controllers The existing NCP includes a percent of the time and approximately
need to be able to turn aircraft as soon restriction that is formally codified in 60 percent of the time by propeller
as possible to get them out of the way. the Aviation section of the Fort aircraft. The present nighttime
(See Measure 10, below, for a similar Lauderdale City Code. This ordinance departure rate is an improvement over
operational procedure, approved as restricts the time and location of the base case runway use reported when
voluntary.) maintenance runups. No maintenance the measure was originally
runups are allowed between 7:00 p.m. recommended in the mid-1980’s (20
6. Night (10 p.m. to 7 a.m.) and 7:00 a.m. All maintenance runups percent for all operations). The 1997
Implementation of ‘‘Quiet One’’ are limited to a location designated by NCP stated: ‘‘This measure results in a
Departure Procedure on a Formal Basis the ATCT. The designated runup pad is reduction of 31 people within the 65 dB
If the FAA disapproves the preceding at the decommissioned compass rose Ldn noise contour and operates in
formal implementation of the ‘‘Quiet located near the southeast corner of the conjunction with the noise abatement
One’’ procedure with hours extended to intersection of Runways 8/26 and 13/31. flight path for Runway 26 departures
run from 8 p.m. to 7 a.m., the City (NCP, pages 65, 151, 177) (turn to a heading of 310 degrees).’’ (See
requests that the FAA approve the Measure 4 in this Record of Approval.)
FAA Action: Approved as a Continuing
procedure on a formal basis effective Measure 10. Runway 08 Departure Heading
from 10 p.m. to 7 a.m. in visual
conditions. (NCP, pages 64, 103, 176) This measure has been approved by Presently turbojets with destinations
the FAA in past NCPs and has other than eastbound are assigned
FAA Action: Disapproved as to eliminated complaints from nearby heading 330 degrees, and non-
Formalizing the Procedure and residences about ground runup noise. eastbound propeller aircraft are assigned
Continuation of the Current Procedure Figure 53 shows that placement of the 300 degrees, with instructions to initiate
on a Voluntary Basis, as It Allows for runup area is close to land uses turns abeam of I–95. All eastbound
Uncontrolled Turns in IFR Airspace in designated as manufacturing and departures are assigned heading 090.
a Very Congested Area production. The City requests that the FAA amend
This measure was previously the existing I–95 turn as a mandatory,
9. Nighttime Preference for Runway 26 formal instrument procedure under
approved as voluntary in 1997 for the
Departures and Runway 08 Arrivals, for FAA radar control, applicable to all
nighttime timeframe. It is being
All Aircraft aircraft, wind, weather, and traffic
disapproved at this time because of the
significant increase in air traffic in the This measure maximizes operations permitting. A 90 degree heading would
area. The concern is that the controllers over the less developed areas west of the be assigned when required to avoid
need to be able to turn aircraft as soon airport. This bi-directional runway use potentially unsafe traffic conflicts.
as possible to get them out of the way. is feasible at night because winds are (NCP, pages 64, 103, 111, 117–118, 178;
(See Measure 10, below, for a similar calmer, operations levels are lower at Figure 43; and Tables 18, and 33)
operational procedure, approved as night, and the ATCT is open all night,
ensuring the safe and optimal use of the FAA Action: Disapproved as a
voluntary.) Formalizing the turn could Mandatory, Formal Instrument
place a large number of VFR flights into procedure. The city makes an annual
payment out of airport funds to staff the Procedure; Approved as a Continuation
congested IFR airspace. of an Existing Voluntary Measure When
ATCT at night to permit implementation
7. Support of Airport Perimeter of this measure and to maximize the Traffic, Weather, and Airspace Safety
Development as a Noise Barrier effectiveness of other nighttime and Efficiency Permit Between the
This measure is a continuation of a measures. The City requests that the Hours of 11 p.m. and 7 a.m.
measure approved by the FAA in 1997. FAA amend this measure to implement This measure is disapproved as a
It calls for the City to continue to work it as a formal preferential runway mandatory, formal instrument
with airport tenants to implement this program element. (NCP, pages 63, 98, procedure. Air traffic has significantly
measure as part of any proposed 122, 178; and Table 22) increased in this corridor since the 1997
development on the airport perimeter. approval of the voluntary procedure.
FAA Action: Disapproved as a Formalizing this departure procedure by
The structures would be placed in such
Mandatory Formalized Procedure; turning all turbojet aircraft on this
a manner that they can act as noise
Continuing This Measure on a heading creates a safety issue due to the
barriers addressing aircraft taxi
Voluntary Basis, When Wind Weather, air traffic congestion in the south
operations for neighboring residences.
and Airspace Safety and Efficiency Florida area when traffic is other than
(NCP, pages 65, 148, 177)
permit Is Approved light.
FAA Action: Approved as a Continuing Formal implementation of this The Letter of Agreement between the
Measure procedure is disapproved. The noise Miami ATCT and FXE ATCT was
The airport sponsor has included this abatement flight path is infrequently revised August 1, 2004, to require that
recommendation in past NCP studies. used, and initiated only upon pilot ATCT assign a heading of 330° to all
The intent of the measure is to promote request. This opposite direction turbojet aircraft departing Runway 8

VerDate jul<14>2003 14:19 Feb 01, 2005 Jkt 205001 PO 00000 Frm 00095 Fmt 4703 Sfmt 4703 E:\FR\FM\02FEN1.SGM 02FEN1
Federal Register / Vol. 70, No. 21 / Wednesday, February 2, 2005 / Notices 5507

between the hours of 11 p.m. and 7 a.m. 13. Future Use Restriction if no new land use measures are
(this excludes emergency Lifeguard Implementation of Operational recommended. It is recommended that
flights). The measure may be extended Measures Does Not Meet Objectives the revised NCP continue to include the
at the discretion of ATCT to 8 a.m. if The City will monitor the jet fleet existing compatible land use measures
traffic, weather, and airspace safety and mix, and implementation and to prevent development of new
efficiency permit. The 1997 NCP stated: effectiveness of noise abatement noncompatible uses to the extent
‘‘The elimination of this procedure measures, to determine whether the feasible. (NCP, page 167).
would approximately double the projected retirement of non-Stage 3 jets, 1. Rezoning Noncompatible Property as
population within the 65 dB Ldn combined with operational measures, Opportunity Arises
contour.’’ The FAA approved the accomplishes two objectives: (1)
measure in 1997 as voluntary. This NCP City staff members continue to
Eliminating residential and other
states that without the existing measure monitor areas within existing and
potentially non-compatible land uses
in place, ‘‘the population within the forecast NEM to identify opportunities
within the 65 DNL contour, and (2)
contours more than doubles from 730 to for rezoning. The very limited
eliminating all Runway 08 straight-out
1801, clearly indicating the noncompatible areas of land within the
(090° heading) jet departures, with the
effectiveness of this existing measure.’’ contours and the highly developed
exception of those required by
The VFR turn abeam I–95 is voluntary nature of those areas limit
emergency or safety conditions. If these
on the part of the pilot and ATCT does opportunities. (NCP, pages 65, 167).
objectives are not met, the City will
not issue turns abeam I–95. initiate the analysis of use restriction FAA Action: Approved as a Continuing
11. Restriction of Night, Weekend, and options that might provide similar noise Measure
Holiday Touch-and-Go Operations and benefit. The scope of the study will
2. Local Jurisdictions To Incorporate
Practice Approaches on a Voluntary include, but not be limited to: (1)
Noise Requirements Into Development
Basis Restriction of Stage 1, or Stage 1 and 2
Control
operations; (2) single event noise level
Expand the existing voluntary night
limits; (3) night operating restrictions; The City has requested that local
(10 p.m. to 7 a.m.) touch-and-go
and (4) feasible enforcement jurisdictions adopt the noise
restriction to encompass touch-and-go
mechanisms and penalties for requirements on a case-by-case basis
and practice-approach training
violations. (NCP, pages 143–147; Figure (NCP, pages 65, 167, 180)
operations at night, and on a 24-hour
49; and Tables 30, 31, and 33).
basis on weekends and City holidays. FAA Action: Approved as a Continuing
This measure is predicted to reduce the FAA Action: Approved for Further Measure
number of people within the 65 DNL Study
3. Voluntary Fair Disclosure by Real
noise contour from 730 to 700. (NCP, Recommendations in this NCP for Estate Agents
pages 65, 127–131, 178; Figure 46; formalizing measures have not been
Tables 25, 26, and Table 33) This measure is an informal
approved due to potential impacts on
educational effort. Information is
FAA Action: Approved as a voluntary efficient use and management of the
disseminated through newsletters and
measure navigable airspace and potential
presentations to all the local
reduction in the level of aviation safety
12. Raise the Approach Slope on All governments in the ares as well as
presently provided. Predicted
Runway Ends to 3.5° realtors, other businessmen and
reductions of impacts on the noise
residents. The community Advisory
This measure calls for raising the contour by formalizing these measures
Committee also serves as an ongoing
Runway 8 approach slope to 3.5°. It also will, therefore, not be fully realized.
conduit of revised noise-related
requires the City to raise the PAPI There is no forecast year NEM without
information. (NCP, pages 65, 167, 180)
angles to 3.5 degrees on all runway these formalized measures in place, so
ends, with FAA approval. The city the population within the 2007 noise FAA Action: Approved as a Continuing
would publicize these changes. It contour is not known (the forecast case Measure
should be noted that a glide slope angle 2007 noise contours include the noise
4. Monitor Noise To Determine Exact
above 3 degrees on a runway with an abatement elements of the ‘‘operational
Extent of Contour Into Residential Area
ILS such as Runway 8, is considered composite case’’). Implementing the
exceptional and requires special FAA approved measures within this ROA The City installed permanent noise
approval. Figure 48 presents the appears to provide a benefit by monitor number 6 in Village Park
resulting contours, which show contour removing the DNL 65 dB noise contour Mobile Home Park (NCP, pages 66, 167,
shrinkage immediately under the from about 30 to 70 people (see Table 180; Figure 54)
extended runway centerlines. The 33, page 157). The 2002 base case shows
FAA Action: No Action Required
population within the contours falls by that a total of 730 people reside within
an estimated 74 residents. (NCP, pages the DNL 65 dB noise contour. It should This measure was approved by the
139, 179; Figure 48, and Tables 28, 29, be noted that FAA will not accept as FAA in the 1997 NCP, and the City has
and 33) justification for an airport noise or implemented the action.
access restriction new noncompatible 5. Noise Abatement Advisory Committee
FAA Action: Disapproved for Purposes
development that occurs within the
of FAR Part 150 The City will continue to implement
airport’s published NEM contours.
FAA has not raised the approach this program element through the
slope for other than safety reasons, to Land Use Measures monthly meetings of the Aviation
maintain cockpit proficiency. Further, at Based on the projection that there will Advisory Board (AAB). The AAB;
FXE, if the approach minimums were be no noncompatible land uses within receives a report on the NCP
raised it would prohibit access to the the DNL 65 dB noise contour in 2007, implementation and status and statistics
aircraft by Category D aircraft due to the with implementation of the noise on compliance with noise abatement
airport’s runway length. abatement elements of this revised NCP, measures. (NCP, page 66, 169, 180)

VerDate jul<14>2003 14:19 Feb 01, 2005 Jkt 205001 PO 00000 Frm 00096 Fmt 4703 Sfmt 4703 E:\FR\FM\02FEN1.SGM 02FEN1
5508 Federal Register / Vol. 70, No. 21 / Wednesday, February 2, 2005 / Notices

FAA Action: Approved as a Continuing FAA Action: Approved as a Continuing operations, or if the NCP requires a
Measure Measure revision). (NCP, pages 67, 172, 182)
6. Noise Abatement Officer 9. Airfield Noise Abatement Advisory FAA Action: Approved
Signs
Supplement part-time responsibilities 12. ATIS Noise Abatement Advisory
The City has installed noise
of the FXE Airports Program Manager The City will continue to request
abatement signage at key locations on
and Airports Programs Aide with the airfield, notifying pilots of major incorporation of noise abatement
addition of a dedicated ‘‘Noise noise abatement concerns. No advisory information on the ATIS
Abatement Technician’’, to focus on additional or modified signage is recording. (NCP, pages 67, 173, 182)
day-to-day and month-to-month required at this time. However, any such
responsibilities, and assist the more FAA Action: Disapproved
new or modified signage would be
senior staff on specialized program eligible for up to 90 percent FAA and Revised Order 7110.65, Air Traffic
requirements. This is a dedicated staff 5 percent FDOT grants. (NCP, pages 67, Control, no longer provides for noise
position for which the city will be 172, 182) abatement advisories. Noise abatement
responsible for the cost. (NCP pages 66, advisories may be published in the
161, 181) FAA Action: Disapproved
Airport Facilities Directory and pilot
The NCP states that no additional or handouts.
FAA Action: Approved modified signs are required at this time,
7. Permanent Noise and Operations so this measure is not a necessary 13. Achievements in Community
Monitoring System element of this NCP. Signs must not be Excellence (ACE) Awards
construed as mandatory air traffic
The City proposes to implement procedures. The content and location of The City will continue to provide
enhancements to the existing ANOMS airfield signs are subject to specific Achievement in Community Excellence
installation to ensure the system approval by appropriate FAA officials (ACE) awards program to encourage
outside of the FAR Part 150 process and aircraft operators, through a program of
continues to provide appropriate
are not approved in advance by this positive recognition, to comply with the
monitoring coverage in a state-of-the-art
determination. NCP noise abatement elements to the
fashion. The enhancements will include
maximum feasible extent. The city has
five additional permanent noise 10. Pilot Manual Noise Abatement Insert provided ACE awards to ten different
monitors, upgraded central computer companies since 1998. (NCP, pages 67,
The City prepares and distributes a
hardware and software, and 173, 183)
revised pilot noise abatement handout
enhancements to the flight tracking and
in a format that is compatible with a FAA Action: Approved as a Continuing
identification system to provide more Jeppessen-sanderson manual. Following
specific aircraft identification through Measure
the FAA’s review and approval of this
monitoring of Mode C transponder NCP, the City should revise the existing 14. Pilot Noise Abatement Workshops
transmissions. The expanded insert to reflect program changes and
geographic coverage and age of the redistribute it to pilots, FBOs, and other The City will continue to hold these
system installation also justify an operators. (NCP, pages 67, 172, 182) sessions, as another mechanism for
upgrade to the central ANOMS publicizing noise abatement measures,
hardware and software. The current FAA Action: Approved as a Continuing goals, and implementation status, and
system is based on UNIX operating Measure for educating pilots. The city has
platform; modern systems are Windows- Language in revised inserts should organized and conducted several
based. (NCP, page 66, 171, 181) accurately reflect FAA actions on this workshops, two or three times a year.
revised NCP. Inserts must not be (NCP, pages 67, 173, 183)
FAA Action: Disapproved Pending construed as mandatory air traffic
Submission of Additional Information FAA Action: Approved as a Continuing
procedures. The content of the inserts Measure
are subject to specific approval by
Other than the location of one of the
appropriate FAA officials outside of the These determination are set forth in
five proposed new monitors (under the
FAR Part 150 process and are not detail in a Record of Approval signed by
Runway 13/31 extended centerline and approved in advance by this the FAA on January 14, 2005. The
identified as ‘‘B’’ in the 2002 NEM determination. Record of Approval, as well as other
Figure 53), the documentation does not evaluation materials and the documents
show where these new monitors will be 11. NEM/NCP Review and Revision
comprising the submittal, are available
located within the official NEM noise The City will continue existing NEM for review at the FAA office listed above
contours. Measures submitted in a NCP and NCP review and revision practices, and at the administrative office of the
for approval must be located within the as necessary. The City will also update City of Fort Lauderdale, Florida. The
sponsor’s NEM contour (14 CFR part the NCP, if made necessary by NEM Record of Approval also will be
150, section 150.23(e), and 49 U.S.C. revision. The city utilizes information available on-line at http://www.faa.gov/
47504(a)(2)) and must otherwise be from a variety of sources to monitor the arp/environmental/14cfr150/
shown to satisfy part 150 approval accuracy of the NEMs and the index14.cfm.
requirements. effectiveness of the NCP, including:
Issued in Orlando, Florida, on January 5,
ANOMS monitoring, citizen reports,
8. Public Information Program 2005.
FAA ATCT traffic counts. The city uses
these sources to determine if operations Bart Vernace,
The FXE staff and other City staff Acting Manager, Orlando Airports District
have changed sufficiently to require an
provide regular reports to the AAB, and Office.
NEM update (e.g., difference of more
ad hoc reports to other interested groups [FR Doc. 05–1921 Filed 2–1–05; 8:45 am]
than 15 percent in operations, or if new
as requested. (NCP, pages 66, 172, 181) noncompatible uses due to changes in BILLING CODE 4910–13–M

VerDate jul<14>2003 14:19 Feb 01, 2005 Jkt 205001 PO 00000 Frm 00097 Fmt 4703 Sfmt 4703 E:\FR\FM\02FEN1.SGM 02FEN1

Você também pode gostar