QUALITY CONTROL & QUALITY

ASSURANCE PROCEDURES
2011 EDITION

QUALITY CONTROL &


QUALITY ASSURANCE
PROCEDURES
GUIDELINES AND SUPPORTING
DOCUMENTS FOR IMPLEMENTATION
OF POLICIES AND PROCEDURES TO
ENSURE THAT ALL ROAD, BRIDGE
AND UTILITY DESIGN SUBMITTALS
TO THE DESIGN SECTION MEET
MUNICIPALITY OF ABU DHABI CITY
QUALITY STANDARDS.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Content

1 Quality Assurance Plan

Form 2

33

1.1

Introduction

Design Completion Certificates

33

1.2

Quality Assurance Form

Form 3

34

1.3

Design Completion Certificates

10

Consultant Evaluation Form

34

1.4

Design Review Checklists

12

Checklists

36

1.5

Submittals for Roads, Structures & Utilities

14

Checklist No. 1 Plans to be submitted at Each Stage

36

Checklist No.2 - CIVIL (Conceptual Design Stage)

38

Checklist No.3 CIVIL (Preliminary Design Stage)

40

Checklist No.4 CIVIL (For all stages)

41

Checklist No.5 CIVIL (for all stages)

42

Checklist No.6 Structures (Concept Design Stage)

50

Checklist No.7 Structures (Approval in Principle Report)

54

Checklist No.8 Structures (Preliminary Design Stage)

61

Checklist No.9 Structures (Detailed Design/Final Design Stage)

62

Checklist No.10 Structural Drawings for all Stages

63

Checklist No.11 Utilities (For Concept Design Stage)

66

Checklist No.12 Utilities (Preliminary Design Stage)

67

Checklist No.13 Utilities (For all stages)

68

2 Quality Control Plan

16

3 Consultant Evaluation

20

3.1

Introduction

22

3.2

Design Submittal Evaluation

24

3.3

Rating Definitions

26

3.4

How the ADM Reviewers Evaluate the Submittal

28

Appendix

30

Form 1

32

Quality Assurance Form

32

1. QUALITY
ASSURANCE
PLAN

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

1.1

Introduction
The purpose of these
procedures is to
enable consultants to
demonstrate to the
Municipality of Abu
Dhabi City (ADM) that
they are incorporating
effective quality control
measures into the
design process.

The increased awareness and


documentation from following
these procedures will provide ADM
with heightened confidence in the
quality of design submittals and
promote uniformity, consistency,
and reduced review time, resulting
in quicker turnaround times for
design submittals.
These procedures are not intended
to replace the quality control
measures that are currently in use,
but rather to promote awareness
regarding the importance of
quality control throughout the
design process. Computation
sheets and drawings must still be
initialled by the designer and the
checker, as per current practice,
and the review of items should still
be carried out independently by
qualified assessors.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

1.2

Quality Assurance Form


The project manager must
complete the Quality Assurance
Form (Form 1) and include it
with each submittal stage. The
consultants reviewer must sign
the form and type his name below
the signature line. The item blank
will generally correspond to the
appropriate checklist in Appendix,
which must be completed by the
reviewer. If any numbered items
are not applicable for a specific
project, they should be marked
with a N/A (Not Applicable) in
the reviewer space. When items to
be reviewed do not correspond to
a number in the checklist, a short
description should be included in
the item space.
The Quality Assurance Form must
be signed by the designer and the
consultants reviewer, and then
approved by a professional or
qualified engineer. Prior to each
submittal, the project manager
must review the plans to ensure
consistency between sheets,
completeness and overall content.

This will include verifying that


the proper number of plans and
items, such as construction cost
estimates, are included with the
submittal. The project manager
should submit a design review log
sheet that includes all comments,
which will confirm that all
requested revisions from previous
submittals have been made or
communicated.
Providing the name and the
contact details of the consultants
project manager is important for
future communication between
him and the ADM project manager.
Telephone conversations are
encouraged to clarify items or
answer questions during the review
process. The remarks section can
also be used to list any requested
revisions that were not made with
an acceptable reason; however, the
project manager is encouraged to
discuss these items with the ADM
reviewer prior to the submittal.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

1.3

Design Completion Certificates


Similar to the Quality Assurance
Form, the Design Completion
Certificates Form must be
completed and signed by the
project manager, the designer
and the verifier to certify that
the consultant has used his
professional skill and care to
produce the submittal.

10

This form is to be submitted at


each design stage. Refer to Form 2
of the appendices for the form and
the certificate.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

1.4

Design Review Checklists


The Municipality of Abu Dhabi
City Roads Design Section has
prepared these checklists to serve
as guidelines for design consultants
during the design review process
and to submit to ADM as part
of each design submittal. ADM
expects consultants to use design
review checklists for all design
submittals. Care must be taken to
ensure that the checklists cover
the most critical aspects and
considerations of a design. The
consultants reviewer must sign the
applicable checklists and type his
name at the bottom.
For design review checking to be
effective, the reviewer must be an
individual with in-depth knowledge
of the relevant discipline. It is also
important that he not be the creator
of the calculation or drawing being
checked. This enables the ADM
reviewer to bring an impartial
perspective to the review, helping
to ensure that the intentions of the
designer are accurately conveyed
to the calculations and drawings.
The size of the project will dictate
how much information is contained
on each drawing. More than one
drawing checklist may have to be
applied to check a single drawing,
if it contains more than one design
discipline. For example, under

12

certain circumstances, a single


drawing may contain utilities,
existing conditions and proposed
plans. In this case, each of the
three relevant checklists would be
applied to the drawing. In other
cases, a single checklist may have
to be applied to several drawings.
In order to ensure the accuracy of
calculations, calculation checking
should be a two-step process.
The first step is to verify the
validity of all assumptions, given
parameters, and formulation.
The second step is checking the
numerical values for accuracy.
The purpose of checking is to
ensure that everything is accurate
and consistent, and that each
drawing properly and adequately
relates to the others in the set,
reflects the design analysis,
uses the current standards of
presentation, and provides all
details needed for construction.
All design review checklists for
common design elements can be
found in the appendices. It should
be noted that these samples are
not comprehensive, and ADM
expects consultants reviews,
prior to submittal, to be more
thorough and exacting, when and
where required.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

1.5

Submittals for Roads, Structures & Utilities


Roads
All checklist forms can be found
in the appendices. Checklist No.1
details the plans to be submitted
at each stage. It should be
seen as a guide for consultants,
although the ADM project
manager or reviewer may request
additional drawings at any stage.
Consultants are not required to
submit a complete set of drawings
at every stage, but rather only to
submit those required by ADM for
the particular design stage.
Design Review Checklists should
be used for all stages of the design
process, as follows:

14

1. Pre-Study Stage (10%)


2. Conceptual Design Stage
(30%); Checklist No.1,
Checklist No.2 (Design
Concept Report)
3. Preliminary Design Stage
(60%); Checklist No.1,
Checklist No.3 (Preliminary
Design Report), Checklist
No.4 and Checklist No.5
(All Drawings)
4. Detailed Design/Final Design
(100%); Checklist No.1,
Checklist No.4 and Checklist
No.5

Bridges and Highway


Structures
5. Conceptual Design Stage
(10%); Checklist No.1
and Checklist No.10
(Design Drawings), the
conceptualisation of
solutions and development
of alternative concepts is
outlined in Checklist No.6
(Concept Design Report)
6. Preliminary Design Stage
(60%); Consultant will use
the Approval in Principle
(AIP) document for selected
alternative based on ADMs
structural design guidelines
and criterion mentioned in
Checklist No.7 (Approval
in Principle) for ADMs
approval. Checklist No.1,
Checklist No.10 (Design
Drawings) and Checklist
No.8 (Preliminary Design)
7. Detailed Design/Final
Design (100%); Checklist
No.1 and Checklist No.10
(Design Drawings), Checklist
No.7 (Updated Approval in
Principle), Checklist No.9
(Detailed Design/Final Design)

Utilities
8. Conceptual Design Stage
(20%); Checklist No.1 and
Checklist No.11 (Design
Concept Report)
9. Preliminary Design Stage
(30%); Complete Design
Checklist No.1, Checklist
No.12 (Preliminary Design
Report) and Checklist No.13
(Drawings)
10. Detailed Design/Final Design
(50%); Complete Design
Checklist No.1, Checklist
No.12 and Checklist No.13

These checklists are meant to


be used as guides and are not
all-inclusive. Their purpose is to
provide a minimum acceptable
list of items that are to be
independently reviewed prior to
submittal; the consultant may
propose additional items to be
checked in the development of
the design for approval. With the
completion of each design stage,
the consultant is required to make
a formal presentation to ADM,
describing the work completed and
the details of the design itself.

15

2. QUALITY
CONTROL
PLAN

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

2.0

Quality Control Plan


Consultants bear full responsibility
for the accuracy, completeness,
consistency and uniformity of their
plans, calculations, and related
documents furnished under the
scope of services. To help ensure
that accuracy and completeness,
ADM requires consultants to
implement and follow a quality
control plan.
A meaningful quality control plan
must be in place before design
work begins, and must remain in
effect throughout the duration of
the design contract. At a minimum,
a functional quality control plan
establishes processes to ensure
the following:
All final plans and calculations
are checked, back-checked,
verified and approved.
Checking should be done
independently by a second
party. The assessor must be
an experienced engineer who
has not participated in the
production of the design plans.
Check prints of all drawings and
calculations are to be maintained
for a minimum of seven years
from the completion of a design
contract.

18

All related correspondence


and memoranda are received
by authorised persons and
maintained in the project files
within an established document
control system.
Cross-checking has been carried
out to avoid any mismatch
and/or discrepancy between
the documents (e.g. profiles
match plans, drawings match
specifications and BOQ, etc.).
Overall appearance, format
and content of the deliverables
correspond to the expectations
of ADM.
The consultant is expected to
perform an internal quality control
review of deliverables at all stages
of design completion. These reviews
are to be carried out by experienced
engineers in the relevant disciplines.
The purpose of these reviews
is to satisfy the consultant that
deliverables are of a quality that
is acceptable to ADM and to the
consultant itself. ADM may request
that the consultant update its quality
control plan at any stage of the
design process, in order to enhance
its functionality.

3. CONSULTANT
EVALUATION

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

3.1

Introduction
To monitor the quality of
deliverables prepared by
consulting firms and to
evaluate the performance
of consultants at each
design stage, ADM project
managers must complete
consultant evaluation
forms, and provide a
copy of each evaluation
to the consultant for their
records and necessary
corrective actions.

22

The consultant has the right to


question any or all of the ratings.
The results of evaluations will be
referenced by ADM when selecting
consultants for future projects.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

3.2

Design Submittal Evaluation


The blank Consultant Evaluation
Form (Form 3) must be attached
to all submittals of plans and/or
reports to be reviewed.
ADM project managers use this
form when a consultant makes a
submittal. He must complete the
general project information and the
coordination team rating items. On
the middle left of the evaluation
form, the project manager indicates
the type of plans and/or reports that
have been submitted. Items to be
rated are located on the right of the
evaluation form. The ADM reviewer
rates the items found in the middle
right, under ADM Reviewers
Rating Items.

24

The rating to be used is found at


the lower right of the evaluation
form. At the very bottom of
the form is the final area to be
completed by the reviewer. In this
area, the reviewer can indicate
what plans and/or reports are to be
submitted next. The last line on the
form is for the reviewer to sign and
date the completed evaluation.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

3.3

Rating Definitions
The review of each submittal will
be performed by ADM, providing
the consultant with a clear
understanding of how the quality
of work is being perceived by ADM
as the project progresses. The
review of completed evaluations
is extremely important to the
consultants project manager
because the evaluation reflects
the comments within the reviewed
plans and/or reports. If the
consultant has any questions
regarding the given rating, the
ADM reviewer must answer these
questions.
The ratings range from a high
of 5 to a low of 1. A rating of
3, 2, or 1 indicates that the
reviewer assessed the item under
consideration as not satisfactory.
The general interpretations of the
ratings are as follows:

26

5. Excellent: Consultant performed


beyond expectations; submittal
approved with very minor
comments.
4. Good: Several revisions required;
submittal approved with
comments to be incorporated in
next stage.
3. Average: Many revisions
required, mostly minor but
several major comments;
submittal returned for revision
and resubmittal.
2. Poor: Many major comments;
submittal not accepted.
1. Unsatisfactory: Full of mistakes
and major comments, poor
document quality; submittal
not accepted and returned to
consultant with notice of concern
from ADM.

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

3.4

How ADM Reviewers Evaluate Submittals


Assurance Program, how
well the computations were
executed will not be examined
as thoroughly as in the past.
However, spot-checking will
occur and the rating of this item
will reflect the spot-checking.
The scoring will be as follows:

Form 3 illustrates the items to be


evaluated at each project stage.
The following briefly describes
each item:
1. Design Concept: The
consultants submittal will be
evaluated on the completeness
of the proposed design concept.
The term completeness
encompasses how well the
consultant has thought through
all of the necessary factors that
result in the best possible design.
If certain items omitted from the
design concept are detrimental to
the design, a lower rating will be
issued. The evaluation will also
consider how well the consultant
addressed any encountered
obstacle that was not foreseen
at the time of completion of the
Engineers Report.
2. Critical Design Elements:
Failure to satisfactorily address
all applicable design criteria will
result in a rating no higher than 3.
3. Calculations: The operations
of mathematical computations
and deletions and/or additions
to the computations are
areas of scrutiny. With the
implementation of the Quality

28

a. A major error is defined as


an error originating from the
computations that would result
in a significant design change.
b. A minor error is one that would
pose no significant change to
any element of the design. If
computations are not submitted
because of the nature of the
submittal or because they are not
warranted, this item will not be
rated. If the reviewer believes that
some computations were needed
but failed to be submitted, the
reviewer will not rate this category
on this basis alone; this would be
addressed in the Documentation
of Work item, thereby avoiding
double penalties.

4. Plan/Report Quality: All


material submitted at each
stage of development, such as
plans, Design Summary Report
(DSR), design computations,
special provisions, and any
other supporting material, will
be evaluated. Ratings will be
based on presentation, legibility,
structure and print quality.
5. Engineering Judgement: The
rating of this item is subjective
to the evaluator. If it is felt that
good or poor judgement was
used, this will be reflected in
the given rating. Engineering
Judgement will be evaluated
for areas such as value
engineering, rehabilitation
options, project constructability,
selection of construction
materials, and maintenance of
traffic scheme.
6. Documentation of Work:
This item will be rated based
on how well each design
decision is documented, or if
the decisions were documented
at all. The majority of the
documentation will be found in
the Design Summary Report,
but documentation may also be
found elsewhere.

7. Procedure/Standard
Compliance: This category
will evaluate how well the
consultant is familiar with local
policies, and will consider
how well the consultant uses
the available standards and
guidelines, as well as whether
the standards and guidelines
were effectively implemented
in the design. This category
will also evaluate how well the
consultant follows established
procedures for specific
items, including foundation
reviews, final plans submittal
memorandum to the Contract
Section, etc.

9. Cooperation: This rating


is based on how well the
consultant cooperates with
the ADM reviewer when
changes are required and
requested. Willingness to attend
meetings, timely response
to ADMs queries, and ease
of participation for project
development will also be
reflected in this category.

8. Quality Assurance: The ADM


reviewer will rate this category
based upon the consultants
compliance with the Quality
Assurance Guidelines. Design
computations should be
initialled by both the design
engineer and a second
engineer, who has reviewed
the design engineers work.
This item rating is intended to
monitor how well the consultant
has performed the evaluation of
checks and balances required
for quality assurance, including
the submittal of the Quality
Assurance Evaluation Form.

29

APPENDIX

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Form 1

Form 2

Quality Assurance Form

Design Completion Certificates

ADM Quality Assurance Form

Design Certificate

(Consultant to complete this section)

Form of Certificate to be used by the Designer for certifying the design of the Works in accordance with the
Clients requirements.

Consultant:
Project No.:
Project Description:
Submittal Stage:
This submittal has been reviewed with regard to consistency, completeness, and overall content prior to
submittal by
, Project Manager, on
_ , 2011, telephone number __________

(Reviewer to complete this section)

WE CERTIFY THAT -

1. We have used reasonable professional skill and care in preparation of the Design Data for .
Design listed below which:
(a) Satisfy the Employers Requirements, the Contractors Proposals, and the following:
(List, if any, the changes covered by any Change Certificate received and countersigned
by the Employers Agent); and
(b) Comply with the design requirements of the Contract; and

The submittal described above has been reviewed for quality in accordance with ADM Quality Control and
Quality Assurance Procedures
The consultant is responsible for checking all of their work as outlined in ADM Quality Control and Quality
Assurance Procedures. The table shown below indicates which of the reviewers personnel has reviewed
which checklist.

Checklist No.

Designer

Reviewer

Approved By

Date

2. We have used reasonable professional skill and care in translating the Design Data into safe
design and drawings whose unique numbers is listed below.
3. The Design Data where used as part of the Temporary Works will have no adverse effect on the
Permanent Works; and
4. Where required a Safety Audit Certificate for Stage *[2] *[3] is attached.
LIST OF DESIGN DATA
Designer
Name: ....................................
Signed: .................................. Date: ...................................
Verifier
Name: ....................................
Signed: .................................. Date: ....................................
Project Manager/ Approver
Name: ....................................
Signed: .................................. Date: ...................................

Please insert the following as part of the submission:


Design Revision Log
NOCs Status

32

33

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Form 3
Consultant Evaluation Form
Project No.:

Contract:

Location:

Work Type:
Consultant:
Consultant Project Manager:
Description:
Submittal Stage:

Reviewers Rating Items

Score

Design Concept

__

Critical Design Elements

__

Calculations

__

Plan/Report Quality

__

Value Engineering / Engineering Judgment

__

Documentation of Work

__

Procedure Compliance

__

Quality Assurance

__

Scheduling / Cooperation

__

Included With This Submittals Are:


Markups of:
Computations:

__

Cost Estimate:

__

Quantities:

__

Q.A. Form:

__

Other: Remarks
ADM Reviewers Signature:

Date:

ADM Reviewers Printed Name and Phone Number

5 = Excellent

34

4 = Good

3 = Marginal 2 = Poor

1 = unsatisfactory

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No. 1 Plans to be submitted at Each Stage

Item
No
1.0

CIVIL

1.1

G1- Location Plan

Conceptual
Design Stage

Preliminary
Design Stage

Detailed/ Final
Design Stage

1.2

G2 List of Drawings

1.3

C1 Typical Cross Sections

1.4

C2 - Existing Conditions

1.5

C3 General Plan and Profiles

1.6

C4 Design Detail Plans

1.7

C5 Grading Plans

1.8

C6 Proposed Plans

1.9

1.10

1.11

1.12

1.13

36

Drawings to be submitted

C7 Survey Control and Alignment


Plans

C8 Ramp Terminal Details


C9 Maintenance of Traffic and
Construction Staging
C10 Traffic Control Devices Signs
and Pavement Markings
C11 Miscellaneous Details

2.0

STRUCTURAL

2.1

S0 List of Drawings

2.2

S1 General and Design Notes

2.3

S2 Site Location and Bore Holes Location Plans

2.4

S3 General Arrangement Drawings

2.5

S4 Dimensional Details

2.6

S5 Bearings and Expansion Joints Details

2.7

S6 Reinforcement and Post Tensioning Details

2.8

S7 Miscellaneous Details

3.0

UTILITIES

3.1

X
X

U1 Existing Condition

3.2

U2 Utility Plans

3.3

U3 Service Reservations and Duct Plans

3.4

U4 Miscellaneous Utilities Details, Compliance with ADM and


other stakeholders(i.e. UPC, DOT, PRFD, etc.) guidelines and
criteria are specified

3.1

ELECTRICAL

3..1.1

E1 - Electrical, Lighting, / CCTV Plan , Scada System and


Lightning Protection if it is required.

3.1.2

E2 - Decorative Lighting or not decorative Plan

3.1.2

E3 - Lighting Plan for Miscellaneous Roadway Structures

3.1.3

E4 - Lighting Plan for Miscellaneous Other Facilities

3.2

MECHANICAL

3.2.1

M1 - Mechanical Services for Pedestrian Underpass, Bridges

3.2.2

M2 - Mechanical Services for Stormwater, Fountains and Fire


Protection

3.2.3

M3 - Mechanical Services for Miscellaneous Facilities and


Scada System

37

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.2 - CIVIL (Conceptual Design Stage)

Item No

Document Type:

Item to be Checked

38

Design Concept Report


(DCR) and Alternative Design
Concepts
Y

N/A

Item No

Remarks

Document Type:

Item to be Checked

The scope of work is clearly defined

10

Vertical grades, K values, vertical clearance are specified

All applicable codes and standards are specified

11

DOTs circular for parking demand rates

Compliance with ADM and other stakeholders(i.e. UPC, DOT,


PRFD, etc.) guidelines and criteria are specified

12

Kerb/barrier parameters and clear zone are specified

Survey and geotechnical investigation requirements and


methods are defined (i.e. coordinate system, datum,
benchmarks, soil investigation requirements for compaction
and structures)

13

Bus/taxi stop requirements, geometric details and proposed


locations

Existing site data

14

Tram routes and dimensions (if applicable)

Roadway classifications, design vehicle, design/posted speed


are specified.

15

Roundabout geometric details (if applicable)

Horizontal curve radius, normal cross slope, maximum super


elevation (SE), SE transition, curve widening requirements are
specified

16

Interchange alternatives (if applicable); pros and cons of each


alternative, interchange spacing, ramp terminal computation,
etc.

Typical cross section details; lane width, number of lanes,


shoulder width, sidewalk and median widths, landscape zone
and bikeway dimensions (if applicable), parking dimensions

17

Pavement design parameters and formula

Horizontal and vertical sight distance computation

Design Concept Report


(DCR) and Alternative Design
Concepts
Y

N/A

Remarks

39

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists

Checklists

Checklist No.3 CIVIL (Preliminary Design Stage)

Checklist No.4 CIVIL (For all stages)

Item
No

Document Type:
Item to be Checked

NOIs (Notice of Intent) sent to consultants and authorities

Liaison with the other stakeholders; minutes of coordination meetings held, design review
log, critical issues, etc.

Detailed Site Data; survey and investigation results, and information received from
consultants and agencies. In depth analysis of the data.

Item
No

Document Type:
Item to be Checked

N N/A Remarks

Correctness of line weights, lettering sizes, and style

Correctness spelling, punctuation, and grammar

Details are clear and easy to read

Title block has correct formats; project name and number, Department name, consultant
name, signature boxes (design/review/approve), drawing title and number

Traffic Impact Study (TIS) report and findings; average daily traffic (ADT), existing and
proposed traffic circulation, parking demand/supply, existing and proposed pedestrian and
bike paths, access/egress details, weaving analysis, etc.

Drawing title and number is consistent with the List of Drawings

Detailed cross sections (including existing and proposed service corridors)

Consistency of project title and identification with specifications, the Bill of Quantities,
and other Contract Documents

Design progress report on the selected alternative by the Department

North arrow, street names, sector names, plot numbers, directions are shown

Location map (if needed) is accurate and proper area is highlighted

Approval of ADM and/or other stakeholders for the design items departing from standards
9

Legend is included (if needed) and representing the elements on the drawing (i.e. no
unnecessary legend)

10

Notes referring to standards and/or other drawings are accurate

11

Match lines are consistent with referenced drawings

40

Preliminary Design
Report (PDR)

Feasibility Study (FS) - Preliminary engineering calculations according to FS IRI ADM


requirements.

Value Engineering (VE) proposals including MEP Services

10

Constructability issues and solutions (i.e. excavation limits for tunnels, availability of
detour areas, existing utility constraints, etc.) based on IRI ADM Sustainability Guideline

12

Drawing is on accurate coordinate system; Northing and Easting gridlines are accurate

11

Proposed location of critical utilities and structures (i.e. substations, pump stationsetc),
and coordination with relevant agencies

13

Limit of construction (LOC) is shown

14

Symbols and abbreviations are matching with the typical details

12

Proposed guide sign locations and destination names (if applicable)

13

Cost Estimate

All Drawings
Y

N N/A Remarks

41

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.5 CIVIL (for all stages)

Item
No

Document Type:

Item to be Checked

42

Drawings Specific to Each


Discipline
Y

N/A

Item
No

Remarks

Document Type:

Item to be Checked

1.0

G1 Location Plan

3.3

Pavement section is designed as per the pavement calculation


which is reviewed and approved by the Department

1.1

Scale is correct (as per ADM Consultant Procedure Manual)

3.4

Kerbs, barriers, pavement type, geometric details, cross slope/


SE, definitions (i.e.lane, aux. Lane, median, shoulder, sidewalk,
landscape, SR,etc.), centerline are properly shown.

1.2

Existing and future developments in the vicinity of the project is


shown

3.5

The limits (from/to station) should represent the correct typical


section, any transition section should be shown seperately; check
the stationing against the proposed plans

1.3

Traffic directions and destinations are shown

3.6

Side slopes, toe/top of slope are shown

2.0

G2 List of Drawings

3.7

Limit of construction, plot/building lines are shown

2.1

Drawing sequence, numbering and titles are as per ADM


Consultant Procedure Manual

3.8

The section contains the proposed improvement and removal of


existing features; identifies all payment items

2.2

Drawing number and title shown in the list is consistent with the
information on the drawings

4.0

C2 Existing Conditions

2.3

Amendments are shown (i.e. addendum, revision, deletion)

4.1

Existing centreline and road names are shown

3.0

C1 Typical Cross Sections

4.2

Existing service reservation and surface utility features are shown

3.1

All typical sections in the project are shown; check the cross
section against the plan view

4.3

Existing buildings/plots, trees, and other structures (i.e. seawall,


bridge, etc.) are shown

3.2

Typical section is as per the approved design criteria

4.4

Existing traffic directions/circulation and destinations are shown

Drawings Specific to Each


Discipline
Y

N/A

Remarks

43

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.5 CIVIL (for all stages)

Item
No

Document Type:

Item to be Checked

44

Drawings Specific to Each


Discipline
Y

N/A

Item
No

Remarks

Document Type:

Item to be Checked

5.0

C3 General Plan and Profiles

5.11

Structures (i.e. bridges, tunnels, walls) and major utilities (i.e.


pipelines, power lines) are shown on profile with the vertical
clearance information

5.1

All roadway paving types are hatched on the plan

5.12

Locations of crossing and intersecting roads shown on the


profile and proposed elevations are matching with crossing and
intersecting roads elevations

5.2

Paving types are matching with the typical cross sections

6.0

C4 Design Detail Plans

5.3

Service reservation (existing to remain and proposed) is shown on


the plan

6.1

Project specific details as required by the Department

5.4

Kerb/barrier types are shown on the plan

7.0

C5 Grading Plans

5.5

Existing and proposed structures (i.e. bridges, wingwalls, outfall


structure, lifting station, etc.) are shown on the plan

7.1

Grading plans prepared for all intersections and merging/diverging


roads; i.e. roundabouts, signalized/unsignalized intersections,
T-junctions, ramp terminals, etc.

5.6

Cross section locations to be shown on the plan and shall be


consistent with C1 series drawings

7.2

Grading plan is matching with the profile(s) and typical section

5.7

All removals are shown on the plan, and materials to be salvaged


are covered by notes or specifications

7.3

Roadway drainage is properly maintained with the proposed


grading plan

5.8

Check existing ground elevations against the survey data

7.4

Finish-grade elevations are specified at 10 -meter intervals at the


roadway centerline, curb lines, and at geometric break points. The
intervals shall be reduced as needed.

5.9

Vertical alignment calculations are as per the approved design


criteria; i.e. minimum grade for proper drainage, K values, cross
slope and superelevation, vertical sight distance, etc.

7.5

Grading plans for roundabouts are as per AASHTO and other


international desing guidelines for roundabouts

5.10

Compare vertical alignment data against calculations and design


software output

8.0

C6 Proposed Plans

Drawings Specific to Each


Discipline
Y

N/A

Remarks

45

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.5 CIVIL (for all stages)

Item
No

46

Document Type:

Drawings Specific to
Each Discipline

Item to be Checked

N/A

Item
No

Remarks

Document Type:

Drawings Specific to
Each Discipline

Item to be Checked

8.1

Centerline / reference line information is shown (i.e. centerline name,


stationing every 100m, POB/POE, CT/TC/CTC, any stationing equation)

9.3

Horizontal alignment calculations and data are as per the approved design
criteria by the Department

8.2

All dimensions are shown; widths, radius, tapers, transitions, island nose
locations (Station/Offset), begin/end kerbs and barriers, etc.

9.4

Alignment calculations and design software output is matching with the


alignment data on the drawings

8.3

All geometric details are as per the approved design criteria by the
Department

9.5

Alignment data and curve data information is matching with the geometry
on the plan

8.4

Traffic circulation/directions are shown

9.6

Horizontal sight distance is checked

8.5

Service reservation corridor is shown

9.7

Numbering for alignment points and curves to sequential and not repeated

8.6

Location of structures (i.e. bridges, tunnels, walls) and major utilities (i.e.
pipelines, power lines) are shown

10.0

C8 Ramp Terminal Details

8.7

Work to be done by others is properly annotated

10.1

Exit and entrance ramp terminal details (acceleration/deceleration length,


auxiliary lane, taper lengths, weaving distance) are as per the approved design
criteria by the Department and other international standards (i.e.AASHTO)

8.8

Limits of construction cover entire area of construction

10.2

Ramp terminal geometry is matching with the horizontal alignment data (i.e.
no kinks or mismatch coordinates)

9.0

C7 Survey Control and Alignment Plans

11.0

C9 Maintenance of Traffic and Construction Staging

9.1

All control points are approved by ADM/TPD, and checked/verified by the


Consultant by setting up traverse

11.1

Check constructability of the project with the proposed detour

9.2

Coordinate system and datum are as per the approved design criteria by
the Department

11.2

Maintenance of traffic and construction staging has been reviewed and


coordinated with the other stakeholders (AD Traffic Police, DOT, utility agencies),
and verify any necessary permits and licenses have been obtained

N/A

Remarks

47

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.5 CIVIL (for all stages)

Item
No

Document Type:

Item to be Checked

48

Drawings Specific to
Each Discipline
Y

Item
No

N/A Remarks

Document Type:

Item to be Checked

11.3

Access to sectors, plots, pedestrian paths have been maintained at all times
during construction

12.2

Existing structures and utilities are considered while locating the proposed
signs in order to avoid any obstruction to signs.

11.4

Alternative routes proposed for the drivers with adequate signage

12.3

Pedestrian walkways and bikeways are not interrupted by the signs

11.5

Transition between construction stages is adequately addressed

12.4

Proposed pavement marking is tieing in with the existing pavement marking


properly (i.e. no kinks, no sudden change in width and type)

11.6

All temporary works are properly labelled as such and that descriptions match
the pay items

12.5

Signs and pavement markings has been reviewed and coordinated with the
other stakeholders (AD Traffic Police, DOT)

11.7

Safety has been considered by all means; i.e. proper lane drops, proper
signage and marking, additional traffic control devices such as crush cushions
and portable VMS (variable message signs) have been proposed

12.6

Safety has been considered by all means; i.e. proper lane drops, proper
signage and marking, additional traffic control devices such as crush cushions,
etc.

12.0

C10 Traffic Control Devices Signs and Pavement Markings

13.0

C11 Miscellaneous Details

12.1

Traffic signs and pavement markings are as per ADMs Traffic Control Devices
Manual and approved design criteria by the Department (i.e. all signs and
markings are as per the approved design speeds and roadway classifications)

13.1

Project specific details as required by the Department

Drawings Specific to
Each Discipline
Y

N/A Remarks

49

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.6 Structures (Concept Design Stage)

Item
No

Document Type:

Item to be Checked

50

Concept Design Stage

N/A

Item
No

Remarks

Document Type:

Item to be Checked

1.0

General

4.2

Typical Cross Section

1.1

ADM Structural Design Guidelines Adopted

4.3

Initial Dimensions

1.2

Applicable Codes and Standards Adopted

4.4

Type of Hand/ Traffic Railing

1.3

Purpose/Function of the Structure Identified

4.5

Type of Superstructure

1.4

ADM IRI Sustainability Guideline

4.6

Articulation Arrangement /Type of Bearings/Type of Expansion Joints

2.0

Roadway Design Features

4.7

Type of Abutment, Pier, Foundation

2.1

Horizontal Clearances, Vertical Clearances. Existing Restrictions, Typical


Cross Sections etc. considered

4.8

Type of Retaining wall

3.0

Geotechnical Investigation

4.9

Signage Structures

3.1

Available Information and Recommendations

4.10

Protection Structures

4.0

Selection of Structural Elements

4.11

Other Structures

4.1

Span Arrangement

5.0

Selection of Materials

Concept Design Stage

N/A

Remarks

51

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.6 Structures (Concept Design Stage)

Item
No

Document Type:

Item to be Checked

5.1

6.0

52

Concept Design Stage

N/A

6.10

Deflection/Camber (Vertical/Incremental/Lateral)

7.0

Other Considerations

7.1

Structure Drainage and Stormwater Systems

7.2

Lighting System over and under Structure Compliance with ADM and
other stakeholders(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are
specified

7.3

Existing Site Condition/ Constructability and IRI ADM Sustainability


Guideline

7.4

Proposed Arrangements for Maintenance and Inspection

7.5

Utilities Carried through or Affected by the Structure

7.6

Environmental & IRI ADM Sustainability Guideline & Environmental


&Considerations

7.7

Risk and Hazards Considerations

7.8

Execution of Work, Traffic Management and Utilities Diversion

7.9

Coordination with all Concerned Authorities and Any Special Conditions

Remarks

Concrete, Reinforcement Steel, Pre stressing Steel, Structural Steel

Design Considerations

6.1

Design Specifications

6.2

Service Life

6.3

Durability Considerations

6.4

Analysis and Design Methodology

6.5

Construction Sequence

6.6

Operational Considerations Crack Sensitivity (Gas Tightness/Liquid


Retaining) Vibration, Wind and Fire Sensitivity

6.7

Permanent Loads

6.8

Live Loads

7.10

Time (Design, Coordination and Execution)

6.9

Other Loads

7.11

Cost (Initial, Final and Maintenance)

53

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.7 Structures (Approval in Principle Report)

Item
No

Item to be Checked

54

Approval in
Principle (AIP)

Document Type:

Item
No

N/A Remarks

Approval in
Principle (AIP)

Document Type:

Item to be Checked

1.0

General

4.1

Available Information

1.1

ADM Structural Design Guidelines

4.2

Acceptance of Recommendations of the Geotechnical Report

1.2

Applicable Codes and Standards and Other References

5.0

Description of Structure

1.3

Design Verification Process

5.1

Pedestrian/ Traffic Railing

2.0

Architectural/ Aesthetics

5.2

Superstructure

2.1

Overall Scheme

5.3

Sub Structure

2.2

Pedestrian/ Traffic Railing, Pier, Abutment, Retaining Wall, Movement Joints,


Drainage System etc.

5.4

Articulation Arrangement

3.0

Roadway Design Features

5.5

Foundation

3.1

Proposed Horizontal and Vertical Clearances and Existing Restrictions

5.6

Others

3.2

Proposed Geometric Design


(Typical Cross Sections, Type of Road, Permitted Speed etc.)

6.0

Materials

4.0

Geotechnical Information

6.1

Concrete

N/A Remarks

55

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.7 Structures (Approval in Principle Report)

Item
No

Item to be Checked

56

Approval in
Principle (AIP)

Document Type:

Item
No

N/A Remarks

Approval in
Principle (AIP)

Document Type:

Item to be Checked

6.2

Reinforcement

8.0

Structural Design

6.3

Pre-stressing Strands

8.1

Design Specifications

6.4

Structural Steel

8.2

Service Life

7.0

Durability Considerations

8.3

Structural Analysis and design Methodology

7.1

Concrete Strength/ Steel grade

8.4

Construction Methodology

7.2

Minimum Concrete Cover

8.5

Operational Considerations Crack Sensitivity (Gas tightness/Liquid and


retaining) Vibration, Wind and Fire Sensitivity

7.3

Concrete Crack Control

8.6

Load Modifier, Load Factor , Resistance Factors etc.

7.4

Concrete and Steel work protection

8.7

Permanent Loads

7.5

Concrete Surface Finish

8.8

Dead Load

7.6

Waterproofing

8.9

Superimposed Load

7.7

Other Durability Considerations

8.10

Utilities Load

N/A Remarks

57

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.7 Structures (Approval in Principle Report)

Item
No

Item to be Checked

58

Approval in
Principle (AIP)

Document Type:

Item
No

N/A Remarks

Approval in
Principle (AIP)

Document Type:

Item to be Checked

8.11

Live Loads

8.22

Temperature, Shrinkage, Settlement

8.12

Pedestrian Live Load

8.23

Friction Force

8.13

Vehicular Live Load including Dynamic, Centrifugal and Braking Effects

8.24

Vessel Collision Load

8.14

Exceptional Abnormal Load

8.25

Other Loads

8.15

Rail Transit Load

8.26

Wind load

8.16

Live Load Surcharge

8.27

Earthquake load

8.17

Vehicular Collision Load

8.28

Fatigue

8.18

Earth Load

8.29

Plant and equipment load

8.19

Earth Fill

8.30

Construction Load

8.20

Earth Pressure (Earth pressure coefficients)

8.31

Any Special loading not covered above

8.21

Water Load/ Uplift Load

8.32

Deflection/ Camber (Vertical/incremental/Lateral)

N/A Remarks

59

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists

Checklists

Checklist No.7 Structures (Approval in Principle Report)

Checklist No.8 Structures (Preliminary Design Stage)

Item
No

Item to be Checked

60

Approval in
Principle (AIP)

Document Type:

Item
No

N/A Remarks

Document Type:

Preliminary Design
Stage

Item to be Checked

9.0

Other Considerations

Updated Approval in Principle (AIP) Report

9.1

Structure Drainage System Compliance with ADM and other stakeholders


(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

Compliance of AIP to the Preliminary Design

9.2

Lighting system on and under structure Compliance with ADM and other
stakeholders(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are specified

Architectural Plans

9.3

Farthing and Stray Currents requirements

Applicable Roadway/ Utilities Design Plans

9.4

Existing Site Condition

Structural Design Drawings

9.5

Proposed arrangements for Maintenance and Inspection

Structural Design Calculations

9.6

Utilities Carried Through or Affected by the Structure Compliance with ADM


and other stakeholders(i.e. UPC, DOT, PRFD, etc.) guidelines and criteria are
specified

Geotechnical Report

9.7

Environmental & IRI ADM Sustainability Guideline considerations

Bill of Quantities

9.8

Risk and Hazards considerations

Construction Specifications

9.9

Execution of work, Traffic Management and Utilities Diversion

10

Design Verification Report

9.10

Coordination with all Concerned Authorities and any Special Conditions

N/A Remarks

61

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists

Checklists

Checklist No.9 Structures (Detailed Design/Final Design Stage)

Checklist No.10 Structural Drawings for all Stages

Item
No

Item to be Checked
1

Final Approval in Principle (AIP) Report

Durability Report

Compliance of AIP to the Final Design

Final Applicable Roadway/ Utilities Design Plans

Final Structural Design Drawings

Final Structural Design Calculations

Final Geotechnical Report

Bill of Quantities

11
12

62

Item
No

N/A Remarks

Document Type:

Item to be Checked

1.0

S0 List of Drawings

2.0

S1 General and Design Notes

2.1

Design criteria, necessary information and assumptions to develop design


drawings.

2.2

Notes common to all structures such as design code, basic loading values,
surface finish etc.

2.3

Notes specific to a particular structure e.g. bridges, underpass, concrete


structures, steel structures etc. as applicable.

2.4

Unless otherwise covered above, each drawing may have specific notes
related to that particular drawing.

3.0

S2 Site Location and Bore Holes Location Plans

3.1

Project location, existing and future developments in the vicinity of the project.

3.2

Project location Plan

3.3

Existing site conditions and bore holes location Plans.

3.4

Proposed Structure location with project key plan highlighting structure


location including.

Drawings Specific to
Each Discipline
Y

N/A Remarks

Final Architectural Plans

10

Detailed/ Final
Design Stage

Document Type:

Construction Specifications
Design Verification Report
Any Other Relevant Details not Stated Above

63

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists

Checklists

Checklist No.10 Structural Drawings for all Stages

Checklist No.10 Structural Drawings for all Stages

Item
No

Document Type:

Item to be Checked

Item
No

N/A Remarks

Document Type:

Item to be Checked

4.0

S3 General Arrangement Drawings

7.0

S6 Reinforcement and Post tensioning Details*

4.1

Architectural drawings

7.1

Foundation including footing and pile caps

4.2

Structure plan, elevation and typical cross sections showing Span


arrangement and types of structural elements.

7.2

Substructure elements

7.3

Superstructure elements

4.3

Setting out details, key levels, Clearance envelope, and radius of curves*

7.4

Box structures

4.4

Bore holes location and bore log details.*

7.5

Retaining walls

4.5

Existing/ proposed utilities crossing or affecting structures, deck drainage,


lightings and other necessary features.

7.6

Other Structures

4.6

Construction sequence

7.7

Bar cutting and bending schedules

5.0

S4 Dimensional Details*

8.0

S7 Miscellaneous Details

5.1

Foundation including footing and pile caps

8.1

Waterproofing.

5.2

Substructure elements

8.2

Joints.

8.3

Drainage and structure lightings.

8.4

Wearing course. Curbs, Sidewalks, and pedestrian and traffic railings.

8.5

Surface protection.

8.6

Other necessary details.

5.3

64

Drawings Specific to
Each Discipline

Superstructure elements

5.4

Box structures

5.5

Retaining walls

5.6

Other Structures

6.0

S5 Bearings & Expansion joints Details*

Drawings Specific to
Each Discipline
Y

N/A Remarks

*Not required for submission of Concept Design stage.


*Except S6, all above drawings are required for submission of Preliminary Design Stage. However
approximate quantities of steel with bar diameter is required for pricing purposes.
* Detailed drawings of S0, S1 to S7 are required for submission of detailed design/ Final Design Stage.

65

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists

Checklists

Checklist No.11 Utilities (For Concept Design Stage)

Checklist No.12 Utilities (Preliminary Design Stage)

Item
No

Document Type:

Item to be Checked

Sustainability Strategy: to follow Estidama requirement for 2 Pearl rating for


the Building Areas and will implement accordingly in our Design IRI ADM
Sustainability Guideline for mentioned areas but not limited because the
proposed HVAC (A/C) shall be VRF (VRV) System or equivalent

The Parking Garage: to coordinate with CD the Induction Fan system

Plumbing: design according to the last version of ADM implemented standard


for materials.

All temporary works are properly labelled as such and that descriptions match
the pay items

Electrical Systems based on :


a- Electrical Power: A breakdown (calculations) required for Total Load of
the project such as electrical power and LED Lighting or equivalent using
ADM Specification and Standard.
b- CCTV and Security ( control access)Systems will be provided
4

c- Elevators (Elec. Or Hyd.)

All Drawings

Item
No

Document Type:

Item to be Checked

N/A Remarks
1

Submittal form filled, stamped & singed

Letter from consultant stamped & singed

Key plan (show the location of project).

Proposed roads layout

Existing roads layout

Existing roads lighting services.

Existing roads lighting poles with mention height and luminaries.

Watts and type as per standard legend

Existing cable with size and circuits

10

Existing feeder pillar location

11

Existing roads lighting ducts

12

Estimated cost

13

Total proposed roads length.

14

Existing substations location

15

Height of poles (Columns)

16

Pole spacing.

All Drawings

N N/A Remarks

d- Fire Alarm System


e- Scada System
f- Lightning Protection if it is required.
More over, study the possibility to provide gas line .

66

67

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES 2011 EDITION | MUNICIPALITY OF ABU DHABI CITY

Checklists
Checklist No.13 Utilities (For all stages)

Item
No

Document Type:

Item to be Checked

68

Submittal form filled, stamped & singed.

Key plan (show the location of project).

Four set of color drawing

CD digital copy as drawing index layout.

Bill of Quantities

Existing & proposed substation with location & number

DEWA overhead lines (Proposed).

Details for DEWA overhead with lighting poles section & profile

Single line diagram with each circuit load & total load for FP. Voltage drop on each circuit
maximum 4% to be show.

10

Under bridge lighting & design calculation

11

Tunnel lighting drawing & design calculation

12

Roads lighting design calculation

13

Prepare a schedule of work.

14

Copy of Updates/new standards from the Consultant implemented for the design

All Drawings

N/A Remarks

QUALITY CONTROL & QUALITY ASSURANCE PROCEDURES


2011 EDITION

Municipality of Abu Dhabi City