Which of the following cannot be identified after performing a forward and backward pass?
A. Dummy activities
B. Slack time
C. Critical path activities
D. How much overtime is planned
The shortest time necessary to complete all of the activities in a network is called the:
A. Activity duration length
B. Maximum slack path
C. Critical path
D. Compression path
3.
The major disadvantage of using bar charts to manage a project is that bar charts:
A. Are ineffective for projects under one year in length
B. Are ineffective for projects under $1 million in size
C. Do not identify start and end dates of a schedule
D. Do not show dependencies between activities
4.
5.
Optimistic, pessimistic, and most likely activity times are associated with:
A. GERT
B. PDM
C. ADM
D. PERT
6.
20
7.
8.
You have an activity where the early start is week 6, the early finish is wee 10, the latest start is week
14, and the latest finish is week 18. The slack in this activity is:
A. 4 weeks
B. 6 weeks
C. 8 weeks
D. 18 weeks
9.
If a worker earn $30 per hour in salary but the project is charged $75 per hour for each hour the
individual works, then the overhead rate is:
A. 100%
B. 250%
C. None of the above
D. 150%
10.
If BCWS = 1000, BCWP = 1200, and ACWP = 1300, the project is:
A. Ahead schedule and under budget
B. Behind schedule and over budget
C. Ahead of schedule and over budget
D. Behind schedule and under budget
11.
If BAC = $20,000 and the project is 40 percent complete, then the earned value is:
A. $5000
B. $20,000
C. Cannot be determined
D. $8000
12.
In BAC = $12,000 and CPI = 1.2, then the variance at completion is:
A. -$2000
B. -$3000
C. +$2000
D. +$3000
13.
If BAC for a work package is $10,000 and BCWP = $4,000, then the work package is:
A. 80 percent complete
B. 100 percent complete
C. 120 percent complete
D. 40 percent complete
14.
If CPI = 1.1 and SPI = 0.95, then the trend for the project is:
A. Running over budget but ahead of schedule
B. Running over budget but behind schedule
C. Running under budget but behind schedule
D. Running under budget but ahead of schedule
15.
If BAC = $24,000, BCWP = 12,000, ACWP = $10,000, and CPI = 1.2, then the cost that remains to
finish the project is:
A. $12,000
B. $14,000
C. Cannot be determined
D. $10,000
16.
17.
A project was originally scheduled for 20 months. If CPI is 1.25, then the new schedule date is:
A. 16 months
B. 20 months
C. 25 months
D. Cannot be determined
18.
19.
20.
21.
The person responsible for assigning the resources to a project is most often:
A. The project management
B. The Human Resources Department
C. The executive sponsor
D. The line manager
22.
Projects that remain almost entirely within one functional area are best managed by the:
A. Project manager
B. Project sponsor
C. Functional manager
D. Assigned functional employees
23.
24.
The most difficult decision for an executive sponsor to make at the end-of-phase review meeting is to:
A. Allow the project to proceed to the next phase based upon the original objective
B. Allow the project to proceed to the next phase based upon a revised objective
C. Cancel the project
D. Postpone making a decision until more information is processed
25.
26.
In which organizational form would the project manager possess the greatest amount of authority?
A. Classical/traditional
B. Strong matrix
C. Projectized
D. Weak matrix
27.
Most people believe that the best way to train someone in project management is through:
A. University seminars
B. Graduate degrees in project management
C. Professional seminars and meeting
D. On-the-job training
28.
29.
Which form of power do project managers that have a command of technology and are leading R&D
projects most frequently use?
A. Reward power
B. Legitimate power
C. Referent power
D. Expert power
30.
Most project managers are motivated by which level of Maslows hierarchy of human needs?
A. Safety
B. Socialization
C. Self-actualization
D. Self-esteem
Part B
Q1
10
The questions given can be answered by one and only one of the terms in the choices given
below. Fill in the blank with correct term.
i) What is the revised estimate for the final cost at the completion of the project? __EAC__
ii)
iii)
How much physical work was actually accomplished thus far? __EV (BCWP)___
v)
From where we are today, how much money is needed to complete the work? _ETC___
vi)
By how much have we deviated from the schedule baseline, favourably of unfavourably?
vii) By whom much have we deviated from the cost baseline, favourably or unfavourably?
CV__
SV__
viii) What is the planned cost or value of the work accomplished thus far? _PV (BCWS)__
Options are: BCWS, ACWP, BAC, SV, CV, ETC, BCWP, EAC
Q2
BCWS
100
110
BCWP
100
200
ACWP
150
SV
CV
00
-50
90
-100
100
350
400
175
250
300
200
150
350
-100
-50
200
150
25
50
1135
1050
1,000
-85
50
10
Q3
Activity
Immediate
predecessor
A
B
C
D
E
F
G
H
I
A
A
B
C
D, F
G
E, H
Optimistic
time
A
4
1
2
3
7
1
1
6
1
Most
Likely
time m
5
3
2
4
8
2
1
6
2
Pessimistic
time
b
6*
5
2*
5
15
3*
1*
12*
3*
4/36
0
4/36
0
36/36
4/36
10