Você está na página 1de 103

UNIVERSITAS INDONESIA

RENEWABLE BIODIESEL FROM


CRUDE PALM OIL, JATROPHA OIL, NYAMPLUNG OIL
REPORT ASSIGNMENT 2

GROUP 21
GROUP PERSONNEL:
DANAR ADITYA S.

(1206263401)

DENNY SETYADARMA

(1206263351)

HASANNUDIN

(1206230725)

MUHAMMAD HAFIZ AL RASYID

(1206219161)

TITEN PINASTI

(1306482054)

CHEMICAL ENGINEERING DEPARTMENT


FACULTY OF ENGINEERING
UNIVERSITAS INDONESIA
DEPOK
2015

EXECUTIVE SUMMARY

In order to design renewable diesel plant, we have to make Piping and


Instrumentation Diagram and Equipment Sizing. Piping and Instrumentation
Diagram known as P&ID is one of some objectives in this assignment. It is the
completion of Process Flow Diagram made in first assignment. It makes P&ID is
more detail than PFD. P&ID is used in manufacturing the renewable biodiesel
plant. Valves and some controllers also connected to the P&ID. P&ID is a used by
process engineer in communicating with other engineer from another discipline.
With this P&ID, we expect the other engineer can understand the whole plant
system easily. In this P&ID we separate it to some pages based on process to
make easy in attaching the valves and controller. There are 4 pages containing of
Degumming, Bleaching, Steam Methane Reforming, Hydrothreating.
After designing P&ID, We need to calculate the specification of the
process equipment being used in a plant known as equipment sizing. This is
another objective of this assignment There are equipment specifications,
equipment sizing, equipment calculations used in making renewable biodiesel
plant in this second assignment. Equipment needed in this plant are 5 tanks, 4
pumps, heat exchanger, reactor, three phase separator. These data is used for
manufacturing in plant design. Sizing of equipment based on rule of thumbs of the
equipment and industrial calculation method by using manual calculation and
software.

ii

Universitas Indonesia

TABLE OF CONTENTS

EXECUTIVE SUMMARY .................................................................................... ii


TABLE OF CONTENTS ....................................................................................... iii
LIST OF FIGURES ................................................................................................ v
LIST OF TABLES ................................................................................................. vi
CHAPTER 1 ........................................................................................................... 1
CONTROL AND INSTRUMENT DESIGN .......................................................... 1
1.1.

Plant Control Tabulation .......................................................................... 1

1.2.

Piping and Instrument Diagram .............. Error! Bookmark not defined.

1.3.

Start up, Normal and Shutdown Procedure ............................................ 12

1.3.1.

Start Up Procedure .......................................................................... 12

1.3.1.1.
1.3.2.

Start Up Procedures for Each Section ..................................... 13

Shut Down Procedure ..................................................................... 14

CHAPTER 2 ......................................................................................................... 15
EQUIPMENT SIZING ......................................................................................... 15
2.1.

Main Equiment ....................................................................................... 15

2.1.1.

Storage Tank ................................................................................... 15

Crude Palm Oil Storage Tank T-101 ................................................................ 15


Jatropha Oil Storage Tank T-101 ...................................................................... 16
Nyamplung Oil Storage Tank T-101 ................................................................ 17
Renewable Biodiesel Storage Tank T-102........................................................ 18
Degumming Tank V-101 .................................................................................. 19
Shift Converter Reactor R-102 ......................................................................... 20
Absorber Column V-103................................................................................... 21
2.2.

Supporting Equipment............................................................................ 24

Heat Exchanger E-101 ...................................................................................... 24


Heat Exchanger E-102 ...................................................................................... 25
Heat Exchanger E-103 ...................................................................................... 26
Cooler E-104 ..................................................................................................... 29
CONCLUSION ..................................................................................................... 38
iii

Universitas Indonesia

REFERENCES ..................................................................................................... 39
APPENDIX ........................................................................................................... 40
Storage Tank ..................................................................................................... 40
Crude Palm Oil Storage Tank ........................................................................... 41
Jatropha Oil Storage Tank ................................................................................ 41
Nyamplung Oil Storage Tank ........................................................................... 42
Renewable Biodiesel Storage Tank .................................................................. 42
Degumming Tank ............................................................................................. 48
Hydrotreating Reactor Sizing ........................................................................... 52
Shift Converter Reactor R-102 ......................................................................... 60
Absorber Calculation ........................................................................................ 62
Heat Exchanger Design Procedure ................................................................... 70
Heat Exchanger E-101 ...................................................................................... 75

iv

Universitas Indonesia

LIST OF FIGURES
Figure A.1. Types of head of storage tank ............................................................ 44
Figure A.1. Power Number ................................................................................... 51
Figure B.1. Fixed Bed Reactor ............................................................................. 53
Figure B.2. Polymath Programming ..................................................................... 55
Figure B.3. Polymath Programming Result .......................................................... 56
Figure B.4. Polymath Programming Graph .......................................................... 56
Figure B.5. Equation used for the design or sizing of fixed bed reactor .............. 61
Figure B.6. Design for Various Packing ............................................................... 64
Figure B.7. Flooding Line Graph .......................................................................... 65
Figure C.1. Shell and Tube Overall Coefficient ................................................... 71
Figure C.2. Air Cooled Exchangers and Immersed Oil Overall Coefficient ........ 71
Figure C.3. Coomon Tube Layouts....................................................................... 72
Figure C.4. Heat exchangers tube-layouts ............................................................ 72
Figure C.5. Type of Heat Exchanger Baffles ........................................................ 73
Figure C.6. Temperature Correction Factor : two shell passes ; four or multiple
passes .................................................................................................................... 76
Figure C.7. Tube Sheet Layouts (square pitch) .................................................... 77
Figure C.8. HE Layouts ........................................................................................ 78
Figure C.9 jH Factor ............................................................................................. 83
Figure E.1 Impeller shapes related to specific speed ............................................ 92

Universitas Indonesia

LIST OF TABLES
Table 1.1. Tabulation of degumming process ......................................................... 1
Table 1.2. Tabulation of bleaching process ............................................................ 2
Table 1.3. Tabulation of hydrotreating process ...................................................... 2
Table 1.4. Tabulation of steam methane reforming process ................................... 4
Table 1.7. Startup procedure ................................................................................. 12
Table 1.8. Emergency Shutdown .......................................................................... 14
Table 2.1 Specification Data of Storage Tank ...................................................... 15
Table 2.2. Specification Data of Storage Tank ..................................................... 16
Table 2.3 Specification Data of Storage Tank ...................................................... 17
Table. 2.4. Specification Data of Storage Tank .................................................... 18
Table. 2.5. Specification Data of Degumming Tank ............................................ 19
Table. 2.6. Specification Data of Shift Converter Reactor ................................... 20
Table. 2.7. Specification Data of Absorber Column ............................................. 21
Table. 2.8. Specification Data of Steam Methane Reformer ................................ 22
Table. 2.9. Specification Data of Hydrotreating Ractor Design ........................... 23
Table. 2.10. Specification Data of Heat Exchanger E-101 ................................... 24
Table. 2.11. Specification Data of Heat Exchanger E-102 ................................... 25
Table. 2.12. Specification Data of Heat Exchanger E-107 ................................... 26
Table. 2.13. Specification Data of Heat Exchanger E-105 ................................... 27
Table. 2.14. Specification Data of Heat Exchanger E-106 ................................... 28
Table. 2.15. Specification Data of Fired Heater E-103 ......................................... 29
Table. 2.16. Specification Data of Fired Heater E-104 ......................................... 30
Table 2.18. Specification Data of Compressor C-102 .......................................... 33
Table 2.19. Specification Data of Pump P-101..................................................... 34
Table 2.20. Specification Data of Pump P-102..................................................... 35
Table 2.21. Specification Data of Pump P-103..................................................... 36
Table 2.22. Specification Data of Pump P-104..................................................... 37
Table A.1. List of Materials that Selected for Each Storage Tank ....................... 40
Table B.1. Sizing Shift Converter Reformer ........................................................ 62
Table B.2. Composition of the Incoming Gas ....................................................... 63
Table B.2. Steam Methane Reformer ................................................................... 69
Table C.1. Composition Properties ....................................................................... 79

vi

Universitas Indonesia

CHAPTER 1
CONTROL AND INSTRUMENT DESIGN

1.1.

Plant Control Tabulation


Table 1.1. Tabulation of degumming process

No Device

Control

Manipulated

Variable

Variable

Location
of Control
Valve

Sequence of
Instrumentation

Degumming Process
1

T-101

Level of Oil

Flow of crude After pump If the level of tank is

Tank

oil

and before

low, valve before

heater

heater will be closed


and the other valve
will be opened. It
make the oil go back
until the level is
normal enough

E-101

Temperature Temperature

Inlet of the

Increase the flow of

outlet of

heater

heating fluid if the

heating fluid

Heat

temperature of oil

Exchanger

going to degumming
tank does not react
the set point

V-101

Level of

Flow of

After pump If the level of mixing

Degumming

degummed

tank is low, valve

Tank

oil

before heater will be


closed and the other
valve will be opened.
It make the oil go
back until the level is
normal enough
1

Universitas Indonesia

Table 1.2. Tabulation of bleaching process

Location
No Device

Control

Manipulated

of

Sequence of

Variable

Variable

Control

Instrumentation

Valve
Bleaching Coloumn
1

E-102

Temperature

Temperature

outlet of Heat heating fluid

Inlet of

Increase the flow of

the heater

heating fluid if the

Exchanger

temperature of oil
going to adsorber
coloumn does not
react the set point

V-102

Level of

Flow of

After

If the level of adsorber

Bleaching

bleached oil

pump

coloumn is low, valve

Tank

before heater will be


closed and the other
valve will be opened.
It make the oil go back
until the level is
normal enough

Table 1.3. Tabulation of hydrotreating process

No Device

Control

Manipulated

Location

Sequence of

Variable

Variable

of Control

Instrumentation

Valve

Hydrotreating Reactor
1

E-107

Temperature

Temperature

Inlet of

Increasing the flow of

outlet of

of heating

the heater

heating fluid if the

Heat

fluid

Exchanger

temperature of oil
going to hydrogenation
reactor does not reach
the set point
Universitas Indonesia

Table 1.3. Tabulation of hydrotreating process (Contd)

C-102

Flow of

Pressure

Before

If the pressure outlet of

Hydrogen

outlet of

entering

comprossor is

Compressor

compresso decreasing, the valve


r

will be closed slowly


in order to make the
flow of hydrogen
entering the
compressor decrease.

R-104

Flow

Flow of

Before the

Increasing or

Control

Bleached Oil

reactor

decreasing the flow of


degummed oil if the
flow of oil going to
reactor is not suitable

R-104

Pressure of

pressure

Pressure

If the pressure is to

hydrothreati

safety valve

Relieve

high, the pressure

ng reactor

safety valve will be


opened to release the
excess gas until the
normal pressure. If the
reactor does not
release the gas, the
reactor will be hold
the over pressure and
the equipment will be
broken soon.

R-104

Level of

Flow of

After

If the level is too low,

Hydrotreatin

Green Diesel

hydrotreat

the valve will be

g Reactor

outlet

ing reactor closed slowly until the


normal level.

Universitas Indonesia

Table 1.4. Tabulation of steam methane reforming process

No

Device

Control

Manipulate

Variable

d Variable

Location of
Control
Valve

Sequence of
Instrumentation

Steam Methane Reformer


1 C-101

Flow of Gas

Pressure

Before

If the pressure outlet

Inlet

outlet of

entering

of comprossor is

Separator

Compressor

compressor

decreasing, the valve


will be closed slowly
in order to make the
flow of hydrogen
entering the
compressor decrease.

2 E-103

Temperatur

Temperature

Inlet of the

Increasing the flow

e outlet of

of heating

heater

of heating fluid if the

Heat

fluid

temperature of oil

Exchanger

going to the next


process does not
reach the set point

3 E-104

Temperatur

Temperature

Inlet of the

Increasing the flow

e outlet of

of heating

heater

of heating fluid if the

Heat

fluid

temperature of oil

Exchanger

going to the next


process does not
reach the set point

4 E-105

Temperatur

Temperature

Inlet of the

Increasing the flow

e outlet of

of heating

heater

of heating fluid if the

Heat

fluid

Exchanger

temperature of oil
going to the next
process does not
reach the set point

Universitas Indonesia

Table 1.6 Tabulation of steam methane reforming process (Contd)

5 E-106

Temperatur

Temperature

Inlet of the

Increasing the flow

e outlet of

of heating

heater

of heating fluid if the

Heat

fluid

temperature of oil

Exchanger

going to the next


process does not
reach the set point

6 R-101

Pressure

Flow of gas

After

If the pressure is too

outlet

reactor

low, the valve will


be closed slowly
until the normal
coloumn level.

7 R-101

Pressure

Pressure

Pressure

If the pressure is too

safety valve

Relieve

high, the pressure


safety valve will be
opened to release the
excess gas until the
normal pressure. If
the coloumn does not
not release the gas,
the coloumn will be
hold the over
pressure and the
equipment will be
broken soon.

8 R-102

Pressure

Flow of gas

After

If the pressure is too

outlet

reactor

low, the valve will


be closed slowly
until the normal
coloumn level.

Universitas Indonesia

Table 1.6 Tabulation of steam methane reforming process (Contd)

9 R-102

Pressure

Pressure

Pressure

If the pressure is too

safety valve

Relieve

high, the pressure


safety valve will be
opened to release the
excess gas until the
normal pressure. If
the coloumn does not
not release the gas,
the coloumn will be
hold the over
pressure and the
equipment will be
broken soon.

10 R-103

Pressure

Flow of gas

After

If the pressure is too

outlet

reactor

low, the valve will


be closed slowly
until the normal
coloumn level.

11 R-103

Pressure

Pressure

Pressure

If the pressure is too

safety valve

Relieve

high, the pressure


safety valve will be
opened to release the
excess gas until the
normal pressure. If
the coloumn does not
not release the gas,
the coloumn will be
hold the over
pressure and the
equipment will be
broken soon.
Universitas Indonesia

Table 1.6 Tabulation of steam methane reforming process (Contd)

12 V-103

Pressure

Flow of gas

After

If the pressure is too

outlet

reactor

low, the valve will


be closed slowly
until the normal
coloumn level.

13 V-103

Pressure

Pressure

Pressure

If the pressure is too

safety valve

Relieve

high, the pressure


safety valve will be
opened to release the
excess gas until the
normal pressure. If
the coloumn does not
not release the gas,
the coloumn will be
hold the over
pressure and the
equipment will be
broken soon.

1.2.

Process & Instrumental Design

Universitas Indonesia

P-101
Feed Pump

T-101
Crude Oil Tank

E-101
Heat Exchanger

V-101
Degumming tank

P-102
Feed Pump

Fosforic Acid

Steam

T-101
CPO /
NYAMPLUNG /
JATHROPA

LT

V-101

LI C
101

LT
FIC
101

PI
101

LI C

LI C
101

FIC
102

TT
101

FT
101

PI
102

FT
102

V-96

9
E- 101

Degummed
Oil

7
P- 102

P-101

Gum

8
5

Condensate

NAME

DEPARTEMEN TEKNIK KIMIA


FAKULTAS TEKNIK
UNIVERSITAS INDONESIA

P&ID DEGUMMING UNIT

RENEWABLE BIODIESEL FROM CPO,


JATROPHA OIL & NYAMPLUNG S OIL

SIGNATURE

DATE

GROUP 21

NAME
CORRECTED BY

PICTURE NO.
NO REVISION

WITHOUT SCALE

Universitas Indonesia

E-102
Heat Exchanger

V-102
Bleaching Unit

P-103
Pump

V-102

Steam

TIC
102

TT
102

Degummed Oil

E- 102
LT
102

LIC
102

FIC
103

3
M

PI
103

FT
103

6
5

Bleached Oil

P-103

Condensate

NAME

DEPARTEMEN TEKNIK KIMIA

FAKULTAS TEKNIK
UNIVERSITAS INDONESIA

P&ID BLEACHING UNIT


RENEWABLE BIODIESEL FROM CPO,
JATROPHA OIL & NYAMPLUNG S OIL

SIGNATURE

DATE

GROUP 21

NAME
CORRECTED BY

PICTURE NO.

NO REVISION

WITHOUT SCALE

Universitas Indonesia

10

C-101
Compressor

E-103
Feed Heater

R-101
Steam Methane Reformer

E-104
Heater

R-102
Shift Converter

E-105
Cooler

V-103
Carbon Dioxide Absorber

R-13
Methanator

E-106
Heater

15
Steam

Hydrogen

PIC

103

TI C
PT

105

103
TT

105
102

Steam

12

14

E-106

PIC

103

R-103

TI C

105
PT

Steam

103
TT

105
102

11
PIC

102

E-105

Metanator Liquid
Product

16
V-103

TI C

104

S-2

PT

102

Natural Gas

Condensate

TT

104
102

PIC

PT

13

Carbon Dioxide

PIC

101
Steam

E-104

Condensate

PT

R-102

101

PIC

C-101

Shift Liquid
Product

10

E- 103

Condensate

R-101

Reformer Liquid
Product

NAME

DEPARTEMEN TEKNIK KIMIA


FAKULTAS TEKNIK
UNIVERSITAS INDONESIA

P&ID STEAM METHANA REFORMER


RENEWABLE BIODIESEL FROM CPO,
JATROPHA OIL & NYAMPLUNG S OIL

SIGNATURE

DATE

GROUP 21

NAME
CORRECTED BY

PICTURE NO.

1st Revision

WITHOUT SCALE

Universitas Indonesia

11

E-107
Heater

R-104
Hidrotreating Reactor

C-102
Compressor

V-108
Green Diesel Tank

PT
102

11

PIC
102

104

Hydrogen

Excess Reactant

PIC

PT

104

C-102

PIC
102

6
FC
104

LT
104

R-104

Steam

LIC
104

FIC
107
TT
107

Bleached Oil

1
E-107

V-108

Condensate

NAME

DEPARTEMEN TEKNIK KIMIA


FAKULTAS TEKNIK
UNIVERSITAS INDONESIA

P&ID HYDROTHREATING UNIT

RENEWABLE BIODIESEL FROM CPO,


JATROPHA OIL & NYAMPLUNG S OIL

SIGNATURE

DATE

GROUP 21

NAME
CORRECTED BY

PICTURE NO.
NO REVISION

WITHOUT SCALE

Universitas Indonesia

12

1.3.

Start up, Normal and Shutdown Procedure

1.3.1. Start Up Procedure


Start up actions occurs every day beside Saturday and Sunday, this
makes 330 days plant startup per year. Startup will be explained step by step in
Table 1.7 below.
Table 1.7. Startup procedure

No

Procedure

Safety

Description

Precautions

All piping and instrument


are completed as P&ID.
1

Electrical set start up. All


electrical cords are

Instrument set start up

connected and no faulty


cord.
Ensure functionality of
2

control valves,

All equipment and

controllers, emergency

instrument set start up

shutdown system, etc.


All electrical
3

Install and activate


electrical system

cords are

Electrical set start up

connected and no
faulty cord

Activate steam utilities

Desired

Heater start up for


heating water utilities

temperature has
been reached

Pre-treatment

Pre-treatment startup

equipment start up to

All pre treatment

produce CPO from

equipment is safe

palm fruit, nyamplung, to operate


jathropa
6

Activate plant process

Starting all controller


Universitas Indonesia

13

instrument and checking

on plant and checking

alarm panel

alarm function
Starting reactor and

Activate main process


equipment

other process

All equipment

equipment after CPO

connected and no

level is adequate for

leakage

process

1.3.1.1.Start Up Procedures for Each Section


Start-up procedures in this system are divided into four parts based on
the number of units in our plant. Below are the procedures:
a. Degumming Unit
1. Check all of the systems are installed correctly
2. Check the controller of the system
3. Check the temperature at 65C and the process lasts for 15 minutes
b. Bleaching Unit
1. Check all of the systems are installed correctly
2. Check the controller of the system
3. Check substances that give color to the oil
4. Check all the equipment safe to operate
c. Hydrotreating
1. Check all of the systems are installed correctly
2. Check the controller of the system
3. Processes implement reactions of hydrotreatment promoted by catalysts
Nickel Molybdenum with buffer Alumina
4. The hydrotreatment reactions are generally carried out in the presence of
hydrogen
5. Check temperature at 300C and pressure at 2 atm
d. Steam Methane Reforming
1. Check all of the systems are installed correctly
2. Check the controller of the system

Universitas Indonesia

14

3. Check the steam flow from its temperature whether it is suitable or not for
entering the steam methane reformer
4. Reduced localized temperature

1.3.2. Shut Down Procedure


Manual shutdown. Manual shut down occur every end of year. It
occurs according to procedure:
1. Decrease the flow rate of feed CPO, Nyamplung oil, and Jathropa oil
gradually until the flows stop
2. Let all the flue gas flow until there is no excess flue gas in the piping line
3. Turn off all the equipment, such as heat exchanger, steam methane
reformer, and pump.
4. Uninstall the catalyst from all unit.
Emergency shutdown. Emergency shutdown only happen if theres
special condition occurs. Emergency shutdown relies on plant process control
instrument and alarm. The condition and procedure are shown in Table 1.8.
Table 1.8. Emergency Shutdown

No
1

Condition
Reactor temperature condition
reach too high or too low
Reactor flow condition reach
too high
Hydrotreating temperature

condition reach too high or


too low

4
5

Procedure

Shut the ball valve that related to the flow,


and maintenance or change with reserve
equipment if available

Steam Methane Reforming


flow condition reach too high
Pump failures

Universitas Indonesia

CHAPTER 2
EQUIPMENT SIZING
2.1.

Main Equiment

2.1.1. Storage Tank


2.1.1.1.Crude Palm Oil Storage Tank T-101
Table 2.1 Specification Data of Storage Tank

Identification
Item :

Storage Tank

Item Number :

T-101

Name of Equipment :

Crude Palm Oil Storage Tank

Item Amount :

10

Function :

Storing of Crude Palm Oil


Composition

Crude Palm Oil:

100%
Operation Data

Capacity :

44.70 ton/hr

Pressure :

2.576 atm

Temperature :

25oC

Storage Time :

7 days
Specification Design

Type :

Cylindrical Tank with Ellipsoidal Top


and Flat Bottom

Joint :

Double Welded Butt Joint

Material :

SA-283, Grade C

Volume :

949 m3

Diameter Tank :

7.48 m

Height Tank :

16.21 m

Wall Thickness :

0.97 inch

Head Thickness :

1.40 inch

15

Universitas Indonesia

16

2.1.1.2.Jatropha Oil Storage Tank T-101


Table 2.2. Specification Data of Storage Tank

Identification
Item :

Storage Tank

Item Number :

T-101

Name of Equipment :

Jatropha Oil Storage Tank

Item Amount :

10

Function :

Storing of Jatropha Oil


Composition

Crude Palm Oil:

100%
Operation Data

Capacity :

44.70 ton/hr

Pressure :

2.5645 atm

Temperature :

25oC

Storage Time :

7 days
Specification Design

Type :

Cylindrical Tank with Ellipsoidal Top


and Flat Bottom

Joint :

Double Welded Butt Joint

Material :

SA-283, Grade C

Volume :

968 m3

Diameter Tank :

7.53 m

Height Tank :

16.32 m

Wall Thickness :

0.97 inch

Head Thickness :

1.40 inch

Universitas Indonesia

17

2.1.1.3.Nyamplung Oil Storage Tank T-101


Table 2.3 Specification Data of Storage Tank

Identification
Item :

Storage Tank

Item Number :

T-101

Name of Equipment :

Nyamplung Oil Storage Tank

Item Amount :

10

Function :

Storing of Nyamplung Oil


Composition

Crude Palm Oil:

100%
Operation Data

Capacity :

44.70 ton/hr

Pressure :

2.565 atm

Temperature :

25oC

Storage Time :

7 days
Specification Design

Type :

Cylindrical Tank with Ellipsoidal Top


and Flat Bottom

Joint :

Double Welded Butt Joint

Material :

SA-283, Grade C

Volume :

961 m3

Diameter Tank :

7.51 m

Height Tank :

16.27 m

Wall Thickness :

0.97 inch

Head Thickness :

1.40 inch

Universitas Indonesia

18

2.1.1.4.Renewable Biodiesel Storage Tank T-102


Table. 2.4. Specification Data of Storage Tank

Identification
Item :

Storage Tank

Item Number :

T-102

Name of Equipment :

Renewable Biodiesel Storage Tank

Item Amount :

Function :

Storing of Renewable Biodiesel


Product
Composition

Crude Palm Oil:

100%
Operation Data

Capacity :

37,88 ton/hr

Pressure :

1.863 atm

Temperature :

25oC

Storage Time :

7 days
Specification Design

Type :

Cylindrical Tank with Ellipsoidal Top


and Flat Bottom

Joint :

Double Welded Butt Joint

Material :

SA-283, Grade C

Volume :

640 m3

Diameter Tank :

3.83 m

Height Tank :

8.94 m

Wall Thickness :

0.64 inch

Head Thickness :

0.80 inch

Universitas Indonesia

19

2.1.1.5.Degumming Tank V-101


Table. 2.5. Specification Data of Degumming Tank

Identification
Item

Mixer Tank

Item number

V-101

Equipment name

Degumming Tank

Number of Unit

Function

Reacting phosporic acid with gum

Mode Operation

Continue
Composition (%)

Oil

11.39 kg/h

Phosporic Acid

27,005.35 kg/h

Operating condition

Capacity

45,560 kg/h

Pressure

168.2 kPa

Temperature

64.12 oC

Type

Ellipsoidal vertical tank

Material

Stainless Steel 316

Volume

59.33 m3

Diameter tank

3.19 m

Height tank

8.51 m

Height of cylinder

6.38 m

Height of ellipsoidal

1.06 m

Wall thickness

4.29 mm

Head thickness

4.29 mm

Spesification Design

Universitas Indonesia

20

Table. 2.5. Specification Data of Degumming Tank (Contd)

Stirrer Design

Utilities

Impeller type

Axial four blade

Number of impeller

Impeller diameter

1.06 m

Impeller level width

0.213 m

Impeller to bottom

1.06 m

Diameter stick

0.353 m

Diameter baffle

0.266 m

Impeller speed

2 rps

Power

0.114 kW/h

2.1.2. Reactor
2.1.2.1.Shift Converter Reactor R-102
Table. 2.6. Specification Data of Shift Converter Reactor

Identification
Item

Shift Converter

Item Number

R-102

Function:

To produce syngas from Natural Gas and Steam

Type of Reactor

Multitubular Packed Bed Reactor


Operating Condition

Pressure

bar

4,16

Temperature

427

Dimension
Reaction Rate

kgmol/kg cat.h

0,378978

Residence Time

min

10,73

Volume Reactor

m3

16,35581

Catalyst Weight

kg

0,57

No. of Tubes

Tube Diameter

cm

1,733461

Diameter

cm

173,3461

Height

6,933845

Thickness

cm

5,0225
Universitas Indonesia

21

2.1.2.2.Absorber Column V-103


Table. 2.7. Specification Data of Absorber Column

Identification
Name

Absorber Column

Item Number

V-103

Function

To separating H2 and CO2 from Shift


converter unit

Number of unit

Material

Carbon Steel SA-283 Grade C

Type

Packing
Packing Width and Height

Tower Diameter

12.60 m

Height of packing

20.51 m

Permissible tensile stress

950 kg/cm2
Mechanical Design

Working pressure

101300 N/m2

Design pressure,p

106365 N/m2
0.106365 N/mm2

Permissible stress

95 N/mm2

Joint Efficiency (j)

0.85

Corrosion allowance

3 mm

Outer diameter, Do

12.659 m

Input Amine. T

150 oC

Input CO2, T

75oC

Output Amine, T

80 oC

Output CO2, T

95oC

Universitas Indonesia

22

2.1.2.3.Steam Methane Reformer R-101


Table. 2.8. Specification Data of Steam Methane Reformer

Identification
Item

Steam Methane Reformer

Item Number

R-101

Function:

To produce syngas from Natural Gas and


Steam

Type of Reactor

Multitubular Packed Bed Reactor


Operating Condition

Pressure

bar

4,5

Temperature

760

Dimension
Reaction Rate

kgmol/kg cat.h

4,08045

Residence Time

min

10,73

Volume Reactor

m3

57,39

Catalyst Weight

kg

523.23

No. of Tubes

Tube Diameter

cm

2,63

Diameter

cm

263,41

Height

10,54

Thickness

cm

5,0225

Universitas Indonesia

23

2.1.2.4.Hydrotreating Reactor Design


Table. 2.9. Specification Data of Hydrotreating Ractor Design

Unit:

CRV-100 Hydrotreating Reactor

Function:

To Produce Green Diesel


Triglycerides and Hydrogen

via

Operating Condition
Type of Reactor

Packed Bed Reactor

Pressure

bar

34.378

Temperature

300

Catalyst Volume

m3

8.33
Dimension

Residence Time

8.62

Volume

m3

10.42

Number of Tubes

414

Tube Diameter

in

1.968

Diameter

1.744

Height

4.366

Thickness

mm

Shell Thickness

mm

4.9

Material

Stainless Steel 316 SS

Universitas Indonesia

24

2.2.

Supporting Equipment

2.2.1. Heat Exchanger


2.2.1.1.Heat Exchanger E-101
Table. 2.10. Specification Data of Heat Exchanger E-101

Equipment Specification
Equipment Name

Heat Exchanger

Equipment Code

E-101
Increase the temperature of CPO

Function

before entering degumming process

Amount

Material

Carbon Steel

Type

Shell and Tube


Operating Data
Shell

Tube

kg/h

10000.00

4594.85

Temperature Inlet

155.00

25.00

Temperature Outlet

134.00

65.00

Operating Pressure

kPa

300.00

200.00

Flow Rate

Construction Data
LMTD

99.1969

UA

W/m C

5.7046

Duty

kW

122.1208

Heat Transfer Area

4.1637

Number of Passes
Shell ID

1-2
m

0.49

Tube Arrangement

Triangular

Number of Tubes

220

Tube Length

4.00

Tube OD

0.0191

Tube BWG
Tube Pitch

14.0000
m

0.0254

Universitas Indonesia

25

2.2.1.2.Heat Exchanger E-102


Table. 2.11. Specification Data of Heat Exchanger E-102

Equipment Specification
Equipment Name

Heat Exchanger

Equipment Code

E-102
Increase the temperature of CPO

Function

before entering bleaching process

Amount

Material

Carbon Steel

Type

Shell and Tube


Operating Data
Shell

Tube

kg/h

10000.00

5138.21

Temperature Inlet

155.00

64.23

Temperature Outlet

134.00

100.00

Operating Pressure

kPa

300.00

200.00

Flow Rate

Construction Data
LMTD

62.0925

UA

W/m C

32.0492

Duty

kW

122.1208

Heat Transfer Area

6.7828

Number of Passes
Shell ID

1-2
m

0.30

Tube Arrangement

Triangular

Number of Tubes

32

Tube Length

8.00

Tube OD

0.0191

Tube BWG
Tube Pitch

14.0000
m

0.0238

Universitas Indonesia

26

2.2.1.3.Heat Exchanger E-103


Table. 2.12. Specification Data of Heat Exchanger E-107

Equipment Specification
Equipment Name

Heat Exchanger

Equipment Code

E-107
Increase the temperature of oil before

Function

entering the reactor

Amount

Material
Type

Shell and Tube


Operating Data
Shell

Tube

kg/h

90000.00

41928.91

Temperature Inlet

400.00

102.44

Temperature Outlet

294.84

300.00

Operating Pressure

kPa

800.00

700.00

Flow Rate

Construction Data
LMTD

141.1967

UA ()

W/m C

20.2749

Duty ()

kW

5504.0209

Heat Transfer Area

165.4549

Number of Passes
Shell ID

1-2
m

0.49

Tube Arrangement

Triangular

Number of Tubes

264

Tube Length

12.00

Tube OD

0.0191

Tube BWG
Tube Pitch

14
m

0.0238

Universitas Indonesia

27

2.2.1.4. Heat Exchanger


Table. 2.13. Specification Data of Heat Exchanger E-105

Equipment Specification
Equipment Name

Heat Exchanger

Equipment Code

E-105
Decrease the temperature of shift

Function

product before entering absorption


process

Amount

Material

Carbon Steel

Type

Shell and Tube


Operating Data
Shell

Tube

kg/h

2135.00

36787.10

Temperature Inlet

430.00

25.00

Temperature Outlet

38.00

41.50

Operating Pressure

kPa

340.00
Construction Data

100.00

Flow Rate

LMTD

110.5275

UA ()

W/m C

743.3854

Duty ()

kW

727.5363

Heat Transfer Area

27.5850

Number of Passes
Shell ID

1-2
m

0.39

Tube Arrangement

Triangular

Number of Tubes

154

Tube Length

4.00

Tube OD

0.0191

Tube BWG
Tube Pitch

14.0000
m

0.0238

Universitas Indonesia

28

2.2.1.5.Heat Exchanger
Table. 2.14. Specification Data of Heat Exchanger E-106

Equipment Specification
Equipment Name

Heat Exchanger

Equipment Code

E-106
Decrease the temperature of

Function

methanator feed before entering


reactor

Amount

Material

Carbon Steel

Type

Shell and Tube


Operating Data
Shell

Tube

kg/h

18000.00

1845.43

Temperature Inlet

280.00

138.00

Temperature Outlet

262.75

260.00

Operating Pressure

kPa

340.00
Construction Data

100.00

Flow Rate

LMTD

57.2235

UA ()

W/m C

743.3854

Duty ()

kW

269.8557

Heat Transfer Area

18.4039

Number of Passes
Shell ID

1-2
m

0.30

Tube Arrangement

Triangular

Number of Tubes

90

Tube Length

4.00

Tube OD

0.0191

Tube BWG
Tube Pitch

14.0000
m

0.0238

Universitas Indonesia

29

2.2.1.6.Fired Heater E-103


Table. 2.15. Specification Data of Fired Heater E-103

Equipment Specification
Equipment Name

Fired Heater

Equipment Code

E-103
Increase the temperature of mixed

Function

feed before entering reformer process

Amount

Material

Stainless Steel

Type

Shell and Tube


Operating Data
Shell

Flow Rate

kg/h

2135.00

Temperature Inlet

140

Temperature Outlet

760

Operating Pressure

kPa

500

Radiant Section
Tube OD

in

8.626

Tube Thickness

in

0.05118

Number

of

Tubes

(Radiant)

Number of Tubes (Shield)

Combustion

(Fraction

40
12
0.15

Excess Air)

Firebox Diameter

ft

19.98

Flue Gas Temperature

2077,1

0.5087

Btu/hr

3.37 x 107

Emmisivity
Radiation Heat Transfer

Universitas Indonesia

30

Table. 2.15. Specification Data of Fired Heater E-103 (Contd)

Convection Section
Tube BWG

14.0000

Tube Pitch

0.0238

Wall Temperature

959

Number of Rows

Number of Tubes per Row

Flue Gas Temperature

1472

LMTD

430.28

Btu/hr

3.37 x 107

Convection Heat Transfer

2.2.1.7.Fired Heater E-104


Table. 2.16. Specification Data of Fired Heater E-104

Equipment Specification
Equipment Name

Fired Heater

Equipment Code

E-104
Increase the temperature of shift feed

Function

before entering water-gas-shift


process

Amount

Material

Stainless Steel

Type

Shell and Tube


Operating Data
Shell

Flow Rate

kg/h

2135.00

Temperature Inlet

760

Temperature Outlet

1050

Operating Pressure

kPa

500

Universitas Indonesia

31

Table. 2.16. Specification Data of Fired Heater E-104 (Contd)

Radiant Section
Tube OD

in

8.626

Tube Thickness

in

0.05118

Number

of

Tubes

(Radiant)

Number of Tubes (Shield)

Combustion

40
12

(Fraction
0.15

Excess Air)

Firebox Diameter

ft

19.98

Flue Gas Temperature

2077,1

0.5087

Btu/hr

3.37 x 107

Emmisivity
Radiation Heat Transfer

Convection Section
Tube BWG

8.626

Tube Pitch

0.5

Wall Temperature

959

Number of Rows

Number of Tubes per Row

Flue Gas Temperature

1472

LMTD

430.28

Btu/hr

3.37 x 107

Convection Heat Transfer

Universitas Indonesia

32

2.2.2. Compressor
2.2.2.1.Compressor C-101
Table 2.17. Specification Data of Compressor C-101

Equipment Specification
Name

Feed Methane Compressor

Code

C-101

Function

To help methane flow to feed mixer

Total

Vendor

Ingersoll Rand

Model

UP5 22-7

Type

Rotary Screw Air Compressor

Material

Carbon Steel

Frequency (Hz)

50

Nominal Power (kW)

22

Flow (m3/min)

3.54

Length/Width/Height (cm)

128/92/105

Weight (kg)

540
Operation Data

Flow rate (m3/h)

2.672

Mass flow (kg/h)

800

Suction Pressure (kPa)

520

Discharge Pressure (kPa)

824

Temperature Inlet (oC)

20

Temperature Outlet (oC)

63.25

Power (kW)

21.6

Universitas Indonesia

33

2.2.2.2.Compressor C-102
Table 2.18. Specification Data of Compressor C-102

Equipment Specification
Name

Hydrogen Compressor

Code

C-102

Function

To help hydrogen flow from methanator


to hydrogenation reactor

Total

Vendor

Ingersoll Rand

Model

M300-2S

Type

Rotary Screw Air Compressor

Material

Carbon Steel

Frequency (Hz)

50

Nominal Power (kW)

300

Flow (m3/min)

60.2

Length/Width/Height (cm)

400/193/215

Weight (kg)

5540
Operation Data

Flow rate (m3/h)

5.391

Mass flow (kg/h)

1578

Suction Pressure (kPa)

241

Discharge Pressure (kPa)

544.9

Temperature Inlet (oC)

280

Temperature Outlet (oC)

440.7

Power (kW)

290.2

Universitas Indonesia

34

2.2.3. Pump
2.2.3.1.Pump P-101
Table 2.19. Specification Data of Pump P-101

Equipment Specification
Name

Oil Feed Pump

Code

P-101

Function

To help oil to flow to heat exchanger then


mixer

Number of unit

Type

Centrifugal Pump
Operation Data

Liquid Volume Flow (m3/h)

49.96

Temperature (oC)

25

Suction Pressure (kPa)

101.3

Discharge Pressure (kPa)

202.6

Head (ft)

54.714

NPSHA (ft)

0.111

Efficiency

0.75

Hydraulic Power (kW)

2.35

BHP (kW)

3.14

Spesific Speed (rpm)

1327.109

Jenis Impeller

Radial Vane

Universitas Indonesia

35

2.2.3.2.Pump P-102
Table 2.20. Specification Data of Pump P-102

Equipment Specification
Name

Refined Oil Pump

Code

P-102

Function

To help refined oil to flow to heat exchanger


then adsorption column

Number of unit

Type

Centrifugal Pump
Operation Data

Liquid Volume Flow (m3/h)

50.76

Temperature (oC)

64.15

Suction Pressure (kPa)

66.85

Discharge Pressure (kPa)

168.2

Head (ft)

54.724

NPSHA (ft)

0.111

Efficiency

0.75

Hydraulic Power (kW)

2.39

BHP (kW)

3.19

Spesific Speed (rpm)

1336.109

Jenis Impeller

Radial Vane

Universitas Indonesia

36

2.2.3.3.Pump P-103
Table 2.21. Specification Data of Pump P-103

Equipment Specification
Name

Refined Bleached Oil Pump

Code

P-103

Function

To help oil to flow to heat exchanger then


hydrogenation column

Number of unit

Type

Centrifugal Pump
Operation Data

Liquid Volume Flow (m3/h)

49.96

Temperature (oC)

100

Suction Pressure (kPa)

101.3

Discharge Pressure (kPa)

2758

Head (ft)

960.21

NPSHA (ft)

0.111

Efficiency

0.75

Hydraulic Power (kW)

39.699

BHP (kW)

52.932

Spesific Speed (rpm)

151.618

Jenis Impeller

Radial Vane

Universitas Indonesia

37

2.2.3.4.Pump P-104
Table 2.22. Specification Data of Pump P-104

Equipment Specification
Name

Green Diesel Pump

Code

P-104

Function

To help green diesel to flow

Number of unit

Type

Centrifugal Pump
Operation Data

Liquid Volume Flow (m3/h)

34.01

Temperature (oC)

349.4

Suction Pressure (kPa)

101.3

Discharge Pressure (kPa)

202.6

Head (ft)

54.714

NPSHA (ft)

0.111

Efficiency

0.75

Hydraulic Power (kW)

1.6

BHP (kW)

2.138

Spesific Speed (rpm)

1094.523

Jenis Impeller

Radial Vane

Universitas Indonesia

CONCLUSION

Each equipment is sized to suit the need of the process. The main aspects
considered are volume, height, diameter, and energy.

The main equipment that uses multiple units to accommodate the process are
storage tank, hydrotreating reactor and unit separator.

The supporting equipment that used are pump, compressor, heat exchanger
and cooler.

The complete main equipment and its intrumentation is depicted in P&ID

The controller needed to be arranged based on the risk of the variable that
being controlled.

38

Universitas Indonesia

REFERENCES
Branan. 2012. Rules of Thumb for Chemical Engineer. 5th edition. USA: Stephen
Hall.
Brownell, L.E & Edwin H.Y. 1959. Process Equipment Design: Vessel Design.
John Wiley & Sons.
Walas, S.M. 1990. Chemical Process Equipment. Selection and Design.
Massachusetts Institute of Technology: Butterworth-Heineman Series in Chemical
Engineering.

39

Universitas Indonesia

APPENDIX A

A.1. Storage Tank


In the process of producing renewable biodiesel, because of not continues
supplies, storage tank are needed to store the raw materials and product. We have
to determine the size and dimension based on the flow rate of each material that
goes in and out the storage tanks.
We use three different types of storage tank to store three different type
crude oil for process that is crude palm oil, jatropha oil and nyamplung oil.
Moreover, we need storage tank for renewable diesel produced.
Material Selection
The raw material storage tanks form are cylindrical tanks because a
cylinder shape has a great structural strength and easier to fabricate. The top end
of storage tanks use ellipsoidal shape, while the bottom end is flat and stand
directly upon the ground. We use carbon steel as the material for storage tanks.
Table A.1. List of Materials that Selected for Each Storage Tank

No.

Storage Tank

Material Specification

1.

Crude Palm Oil Storage Tank

SA-283, Grade C

2.

Jatropha Oil Storage Tank

SA-283, Grade C

3.

Nyamplung Oil Storage Tank

SA-283, Grade C

4.

Renewable Biodiesel Storage Tank SA-283, Grade C

A.1.1. Volume of Storage Tank


For sizing the storage tanks, we estimate that the capacity of crude oil
storage tanks are able to fulfill the needs of material for a week depending on the
supply attendants. So, we determine one week as a batch.

40

Universitas Indonesia

41

Crude Palm Oil Storage Tank


Crude Palm Oil mass flow rate is 44700 kg/hour. So the storage tanks have

to store 7,509,600 kg/batch crude palm oil. The calculation of storage tanks
volume needed to store :
kg
7,509,600 week
m3
= =
= 8540.43
kg

week
879.3 3
m
To store the crude palm oil, we will use 10 storage tank. so, the crude palm oil
volume per tank is :
=

m3
3
week = 854.04 m
10
week

8,540.43

To calculate the total volume of storage tanks, safety factor has to be


considered. Safety factor of the tank is 10% of the total volume. This is based
on literature saying that for tanks which volume is above 3,8 m3, only 90%
volume is filled.
=

m3
3
week = 948.94 m
0.9
week

854.04

Jatropha Oil Storage Tank


Jatropha Oil mass flow rate is 44700 kg/hour. So the storage tanks have to

store 7,509,600 kg/batch jatropha oil. The calculation of storage tanks volume
needed to store :
kg
7,509,600 week
m3
= =
= 8711.83
kg

week
862 3
m
To store the jatropha oil, we will use 10 storage tank. so, the jatropha oil
volume per tank is :
=

m3
3
week = 871.18 m
10
week

8,711.83

To calculate the total volume of storage tanks, safety factor has to be


considered. Safety factor of the tank is 10% of the total volume. This is based

Universitas Indonesia

42

on literature saying that for tanks which volume is above 3,8 m3, only 90%
volume is filled.
=

m3
3
week = 967.98 m
0.9
week

871.18

Nyamplung Oil Storage Tank


Nyamplung Oil mass flow rate is 44700 kg/hour. So the storage tanks have

to store 7,509,600 kg/batch nyamplung oil. The calculation of storage tanks


volume needed to store :
kg
7,509,600 week
m3
= =
= 8641.66
kg

week
869 3
m
To store the nyamplung oil, we will use 10 storage tank. so, the nyamplung oil
volume per tank is :
=

m3
3
week = 864.17 m
10
week

8,641.66

To calculate the total volume of storage tanks, safety factor has to be


considered. Safety factor of the tank is 10% of the total volume. This is based
on literature saying that for tanks which volume is above 3,8 m3, only 90%
volume is filled.
=

m3
3
week = 960.18 m
0.9
week

864.17

Renewable Biodiesel Storage Tank


Renewable biodiesel produced have mass flow rate is 37880 kg/hour. For,

renewable biodiesel we determine 1 day for a batch. So the storage tanks have
to store 909,120 kg/batch renewable biodiesel. The calculation of storage tanks
volume needed to store :
kg
909,120 week
m3
= =
= 1150.78
kg

week
790 3
m

Universitas Indonesia

43

To store the renewable biodiesel product, we will use 2 storage tank. so, the
renewable biodiesel volume per tank is :
=

m3
3
week = 575.39 m
2
week

1150.78

To calculate the total volume of storage tanks, safety factor has to be


considered. Safety factor of the tank is 10% of the total volume. This is based
on literature saying that for tanks which volume is above 3,8 m3, only 90%
volume is filled.
=

m3
3
week = 639.32 m
0.9
week

575.39

A.1.2. Diameter and Height of Storage Tank


Based on rule of thumb, the ratio of height and diameter of tank for
cylindrical tanks is 2:1. Therefore, H = 2D. The volume of cylinder can be
calculated as :
1
1
= 2 = 3
4
2
The shape of tanks top cover is ellipsoidal and the bottom cover is flat, with
major axis ratio of 2:1. The volume of heads (cover and pedestal) is

3
24

. The tank

volume is:
3 3 133
=
+
=
2
24
24

Universitas Indonesia

44

Figure A.1. Types of head of storage tank


(Source: Perrys Chemical Engineering Handbook, 1999)

We use the equation of cylinder tank volume to determine the diameter of


cylinder.
3

24
13

The height of tank is an addition of cylinder and head of tank height. The cylinder
height is 2D as stated before. The head height is D/6.

Crude Palm Oil Storage Tank


Using the equation, the diameter of tank is :
3

3 2 8540.43
24
=
= 7.48
13
13

=
The cyclinder height is:

= 2 = 2 7.48 = 14.96
The head height is:
=

7.48
=
= 1.247
6
6

The total height is:


= + = 16.207

Universitas Indonesia

45

Jatropha Oil Storage Tank


Using the equation, the diameter of tank is :
3 2 8711.83
24
=
= 7.53
13
13

=
The cyclinder height is:

= 2 = 2 7.53 = 15.06
The head height is:
=

7.53
=
= 1.255
6
6

The total height is:


= + = 16.315

Nyamplung Oil Storage Tank


Using the equation, the diameter of tank is :
3 2 8641.66
24
=
= 7.51
13
13

=
The cyclinder height is:

= 2 = 2 7.51 = 15.02
The head height is:
=

7.51
=
= 1.252
6
6

The total height is:


= + = 16.27

Renewable Biodiesel Storage Tank


Using the equation, the diameter of tank is :
3

3 2 1150.78
24
=
= 3.83
13
13

=
The cyclinder height is:

= 2 = 2 3.83 = 7.66
The head height is:
=

7.66
=
= 1.27
6
6

The total height is:


Universitas Indonesia

46

= + = 8.937

A.1.3. Design Pressure


Pressure design of storage tank determines the type of storage tank used.
Height of fluid in the tank is calculated as follows:
=

The pressure of the tank is:


=
In calculating the design pressure, we assuming that the pressure safety factor is
15%.
= 115% (1 + )

Crude Palm Oil


=

854.04 16.207
= 14.59
948.94

= 879.3 9,81 14.59 = 1.24


= 115% (1 + 1.24) = 2.576

Jatropha Oil
=

871.18 16.315
= 14.68
967.98

= 862 9,81 14.68 = 1.23


= 115% (1 + 1.23) = 2.5645

Nyamplung Oil
=

864.17 16.27
= 14.64
960.18

= 869 9,81 14.64 = 1.23


= 115% (1 + 1.23) = 2.5645

Renewable Biodiesel
=

575.39 8.937
= 8.04
639.32

= 790 9,81 8.04 = 0.62


= 115% (1 + 0.62) = 1.863

Universitas Indonesia

47

A.1.4. Wall and Head Thickness


To calculate the wall and head thickness, there are several data we needs
to be determined such as corrosion factor, maximum allowable stress, joint
efficiency, and equipment age. These data determined based on the material
selected for each storage tank. Carbon steel has a bigger corrosion factor than
stainless steel, since carbon steel is more prone to corrosion. Corrosion factors of
stainless steel are also different depending on the grade of stainless steel.
Calculation of storage tanks wall thickness is based on circumferential
stress (longitudinal joint). We can use the following formula (Towler, 1990):
=

+
0.6

While head thickness of storage tank could be calculated with the following
formula:
=


+
2 0.2

where,
t = material thickness
P = pressure gauge
R= shell radius
Di= shell inner diameter
K = ellipsoidal formula factor
S = maximum allowable stress
E = joint efficiency = 0.85
C = corrosion factor = 0.015
A = planned equipment age = 30 year

Crude Palm Oil


=

37.86 147.24
+ 0.015 30 = 0.969
12,650 0.85 0.6 37.86

37.86 294.48 1.833


+ 0.015 30 = 1.40
2 12.650 0.85 0.2 37.86

Universitas Indonesia

48

Jatropha Oil
=

37.69 148.23
+ 0.015 30 = 0.971
12,650 0.85 0.6 37.69
=

37.69 296.46 1.833


+ 0.015 30
2 12.650 0.85 0.2 37.69
= 1.40

Nyamplung Oil
=

37.69 147.83
+ 0.015 30 = 0.969
12,650 0.85 0.6 37.69
=

37.69 295.66 1.833


+ 0.015 30
2 12,650 0.85 0.2 37.69
= 1.40

Renewable Biodiesel
=

27.38 75.39
+ 0.015 30 = 0.642
12,650 0.85 0.6 27.38
=

27.38 150.78 1.833


+ 0.015 30
2 12,650 0.85 0.2 27.38
= 0.802

A.2. Degumming Tank

Volume

Flow rate into the tank 46560 kg/h, to gain the volume we could divide the mass
rate with total density.
kg
46560 h
= =
= 53.39 3

872 3

So, the volume tank is 53.39 m3. Base on literature if volume above 3,8
3volume of each tank only filled 90%. The headspace is 10% thus the working
volume which calculated before is 90%. The use of headspace is a safety unit for
sudden increment volume.
=

53.39
= 59.33 3
0.9

Diameter and height of mixing tank


Universitas Indonesia

49

Comparison of high tank with tank diameter (Hs: D) = 2:1. The volume will be
represented by using ellipsoidal shape, the diameter and height of tank could be
calculated.
1
1
= 2 = 23
4
4
Cover and pedestal tank of ellipsoidal shape with major to minor axis ratio of 2:1,
so high head is h=16 (Walas, 1990). Volume of 2 cover is:
1
1
1
1
= 2 2 = 2 2 =
3
4
4
6
12
Tank volume is:
1
1
7
= + = 23 + 3 =
3
4
12
12
Tank diameter is:
3 12 59.33
3 12
=
=
= 3.19
7
7

Height of cylinder is Hs= 2D = 6,38 m


1

Height of cover ellipsoidal is Hh = = 1.06


6

Height tank is Ht = Hs + (2xHh) = 6.38 + (2x1.06) = 8.51

Pressure Design

Height of fluid in the tank


=



53.39 8.51
=
= 7.66
59.33

Pressure
= = 872 9.8 7.66 = 0.646 = 9.494

Thick of Wall and Head

Material choosen is stainless steel because condition of solution must be at pH


4,5. Avoiding corrosion, stainless steel used for this case
Thick of wall
Assumption of corrosion factor is (C) = 0,0042 in/year
Allowable working stress is (S) = 16.250 lb/in2 (Walas, 1990)
Assumptions connection efficiency is (E) = 0,85
Universitas Indonesia

50

Planned of tool age (A) = 30 years


Thick of cylinder is
=
=

+
0.6

9.494 62.99
+ 0.0042 30 = 0.169 = 4.29
16.250 0.85 (0.6 9.494)

Thick wall head (cap)


Assumption of corrosion factor is (C) = 0,0042 in/year
Allowable working stress is (S) = 16.250 lb/in2 (Walas, 1990)
Assumptions connection efficiency is (E) = 0,85
Planned of tool age (A) = 30 years
Thick of wall head is
=
=

+
0.2

9.494 62.99
+ 0.0042 30 = 0.169 = 4.29
16.250 0.85 (0.2 9.494)
Impeller

Type: axial four blade, this kind of impeller is chosen based on literature, if
viscosity < 5000 cp propeller is common used. This solution has 79 cp
Assumption of rotation speed (N): 120 rpm = 2 rps
Assumption of 80% efficiency motors
Mixer is designed with the following standards: (Walas, 1988)
Da : Dt = 1 : 3

Dt : J = 12

W : Da = 1 : 5

where:

Da : Db = 6 : 1

Da = stirrer diameter

C : Dt = 1 : 3

Dt = the diameter of the tank

Db = stick diameter
W = width of leaf stirrer
C = the distance from bottom of the tank
Reynold number is
=
1

Stirrer diameter is = = 3.19 = 1.06


Universitas Indonesia

51

Stirrer leaf widhth is = = 1.06 = 0.213


5

Strirrer height from the bottom = = 3.19 = 1.06


1

Diameter of stick = = = 1.06 = 0.353


Diameter baffle =

1
12

1
12

3.19 = 0.266

Where
Da = diameter impeller (ft)
N = rotation speed (rps)
= density (lb/ft3)
= viscosity (lb/(ft.s))
=

0.353 2 4.49
= 63.40
0.05

Figure A.1. Power Number


(Source: Walas, 1990)

Then, the power is


= 103 ( 3 5 )
= 103 (3 4.49 23 1.06) = 0.114 /

Universitas Indonesia

52

APPENDIX B
B.1. Hydrotreating Reactor
Fixed-Bed Reactors (FBRs) are the most commonly used reactor systems
in commercial hydrotreating operations. They are easy and simple to operate.
However, the simplicity of operation limits their use to the HDS of light feeds.
For example, in case of naphtha hydrodesulfurization, the reaction is carried out in
two-phases (gas-solid) fixed-bed reactors since at the reaction conditions the
naphtha is completely vaporized. On the contrary, for heavier feeds three phases
are commonly found: hydrogen, a liquid-gas mixture of the partially vaporized
feed, and the solid catalyst. The latter system is called a trickle-bed reactor (TBR),
which is a reactor in which a liquid phase and a gas phase flow co-currently
downward through a fixed bed of catalyst particles while reactions take place.The
gas is the continuous phase, and the liquid is the disperse phase (Quann et al.,
1988). A schematic representation of the phenomena occurring in a TBR based on
three-film theory is presented in Figure 3.3 (Korsten and Hoffmann, 1996;
Bhaskar et al., 2004). It is common to assume that mass transfer resistance in the
gas film can be neglected and that no reaction occurs in the gas phase, so that for
the reactions to occur, the hydrogen has to be transferred from the gas phase to the
liquid phase, whose concentration is in equilibrium with the bulk partial pressure
and then adsorbed onto the catalyst surface to react with other reactants. The gas
reaction products are then transported to the gas phase, while the main liquid
hydrotreated reaction product is transported to the liquid phase.
In Hydrotreating Reactor there will be two main reaction which are
reaction of tryglycerides and H2 also reaction between tryglicerides and H2, those
reaction can be combine into one that will produce the green diesel itself. The
volume of reactor is equal to the amount of catalyst used. It is because common
reactor for hydrotreating reactor is fixed bed reactor. In this process, catalyst used
is Nickel-Molybdenum alumina supported.
The material for the hydrotreating reactor was chosen to be Stainless Steel
316 SS. Due to the temperature conditions at about 250C, metal dusting not
comes into consideration. This leads to a construction material of carbon steel,
which is the least expensive material (Peters, 2003). However, since the process
Universitas Indonesia

53

streams at this stage produce some amount of CO2, sweet corrosion is believed to
be a problem. That is why we chose Stainless Steel as a material for hydrotreating
reactor.

Figure B.1. Fixed Bed Reactor


Source: Handbook of Petroleum Processing

1.

Hydrotreating Reactor (CRV-100)

Catalyst Weight
1

2 57 104 6 + 21 2 317 36 + 3 2 + 62 + 23 8 , 1 = 1
1

+
k1 = 0.008554 m3 kmol-1 s-1
Assumption:
Rate law of these reaction follow one order rate reaction in Packed Bed
Reactor. Equation for rate law in Packed Bed Reactor is

=

0
Where: = /
Universitas Indonesia

54

Equation for one order rate reaction:


=
So
/
=

0
The derivation of equation
/
=

= (1 )
= ( )

= (1 + )

(1 )
=

(1 + )

( )
=

(1 + )

So,

(1 )
( )
=
.
.
(1 + ) (1 + )

(1 )( )
=

2
[ (1 + )
]

Universitas Indonesia

55

This equation will be used to determine how much catalyst needed for each
reaction.
Molar flow Tryglycerides :

= 144 /

Molar flow Hidrogen :

= 570 /

144
=
= 0.2017 /
+ 144 + 570

= yA0 . = (0.2017)(3 + 1 1 1) = 0.4034


Feed volume flow :
= 4,351 3
Bulk density, = 3200 /3
Then we use polymath to determine conversion vs catalyst weight:

Figure B.2. Polymath Programming

Universitas Indonesia

56

Figure B.3. Polymath Programming Result

Figure B.4. Polymath Programming Graph

Universitas Indonesia

57

As the result of the polymath, the higher catalyst weight, the higher of
conversion. Therefore, we choose the conversion is 18% because the high
conversion needs a lot of catalyst. As we know that catalyst is expensive and the
lifetime is just about one year. For example, for 85% conversion needs 500,000 kg
catalyst, that is too much. So we just need 18% conversion plus we will recycle
the methane that is not converted into the syngas. At 18% conversion, we need
catalyst 37,000 kg.
Dimension of Reactor
Volume of catalyst that fills the reactor can be calculated as follow:
=

30,000 kg
=
= 8.33 3
3600 kg/m3

Then we assume that the catalyst fills 80% of reactor volume. So we can estimate
the reactor volume needed as follow:
=

100
8.33 3 = 10.42 3
80

Assume that L:D = 2.5:1 (Rule of Thumbs)


1 2
= 10.42 3
4
1
2 (2.5) = 10.42 3
4
3 = 16.672 3
= 1.744
The length is
= 2 = 4.36
Retention Time

10.42 3
3600
=
=

= 8.62
0 4,351 m3 /h
1
Wall thickness can be obtained by using method in Wallas.
Universitas Indonesia

58

Thickness (t) =

(P + ) x R
+ CA (Corrosion Allowance)
SxE 0,6P

Head Thickness (t) =

PxD
+ CA
2SxE 0.2(P)

With : P = operation pressure (Psig)


Pc = pressure because of catalyst weight
R = reactor radius (inch)
E = Joint efficiency, it assumed that the joint effieciency is 0.8
S = allowable stress
Due to the high pressures and temperatures in the primary reformer tubes,
a 25% chromium-20% nickel alloy is the preferred tube material. The
allowable stress is very dependent on the material that used for the vessel.
From the Perrys Chemical engineer handbook the allowable stress for the
conrete is 9.8 Mpa or 145,054 psi.
The pressure because of catalyst is :
=
Thickness (t) =

(30,000)(9.8)
=
=
= 123,287 = 17.87

0.25(1.744)2

(145 + 17.87) 34.33


+ 0.15 = 0.198
(145,054)(0.8) (0.6)(145 + 17.87)

= 5
Head Thickness (t) =

(145 + 4.1) x 68.66


+ 0.15 = 0.193
2x145,054x0.8 + 1.8x145

= 4.9
Tubes calculation
The maximum conventional heat flux through primary reformer tube walls
is approximately 5,921.176 kcal/ ft2hr with industry averages. Using this value
and the heat duty through the reformer calculated by Aspen, the primary reformer
tube size was calculated as follows:
=
=

8.895 107
= 15,174.35 2
5,921.176 2

Then, number of tubes needed is

Universitas Indonesia

59

= 413.4 414
Height of tube
Based on rule of thumbs, height of reactor is 1.25 times of tubes, so
=

1
1
=
4.36 = 3.488
1.25
1.25

Pinch tube selection and diameter of tubes


We choose square pinch of tubes because it is more easy to be cleaned.
The arrangement is at the picture below

Where :
= = 1.5
As we know, diameter of reactor is 1.744 m2, then the length of square is allowing
at phytagoras rule :
2 + 2 = 2
2 2 = 1.7442
2 =
=

1.7442
2

1.7442
= 1.233
2

Assuming the cover of the shell size is 10 cm = 0.01 m


Then tube line is
= 1.233 2(0.01) = 1.213
Universitas Indonesia

60

As we know that the number of tubes are 414, so


=
414 = (

1.213
1.213
+ 1) (
+ 1)

1.213 2
414 = (
+ )

1.213 + 2
414 = (
)

414 =

1.213 +

20.347 = 1.213 +
19.347 = 1.213
= 0.0627
So, we can calculate diameter of tubes
=

0.0627
=
1.25
1.25

= 0.05 = 1.968

B.2. Shift Converter Reactor R-102


Water Gas Shift (WGS) is reversible reaction. So both the forward and
reverse reaction is with thermodynamic equilibrium. The true dimensionless
equilibrium constant can predict from Gibbs free energy as denoted by the
following reaction.
=
All fixed Bed catalytic reactor assumed to behave like ideal plug flow reactor.
Equation used for the design or sizing of fixed bed reactor is:

Universitas Indonesia

61

Figure B.5. Equation used for the design or sizing of fixed bed reactor

Here is process condition, mole fraction, and molar flow of feed of water gas shift
reactor from Aspen Hysys simulation.

187,5

Feed Flowrate :

kgmol/h

0,052083 kgmol/s

8,314

4,16

bar

1050

Species Fraksi mol P parsial K


CO2

0,055

0,2288

H2O

0,2237

0,930592 0,908513

H2

0,5735

2,38576

CO

0,1178

0,490048 0,252871

9,59E-05

= 1 + + 2 2 + 2 2 +

2 2
2

= 1 + (0,252871 0,490048) + (9,59E 05 2,38576) + (0 0,2288)


+

(0,908513 0,930592)
= 1,4785
2,38576

Constant rate law

kj = 34.21
Rate Law
Universitas Indonesia

62

R1= 0,3799 kgmol/kg cat. S


The Calculation for sizing shift converter reformer is using Microsoft Excel and
the result is shown in the sizing table
Table B.1. Sizing Shift Converter Reformer

weight of catalyst

0,57

Cat Vol

13,90244 m3

Vol Reactor

16,35581 m3

A Reaktor total

0,016889 ft2

Tube
D Reaktor

kg cat

100
1,733461 m
173,3461 cm

6,933845 m

D tube

1,733461 cm
1,06

Residence time

in

0,018924 h
69,14921 s
1,152487 min

thickness

1,977392 in
5,0225

thicknes head

cm

3,829613 in
9,6478

cm

TUBE THICKNESS 0,129954 in

B.3. Absorber Calculation


The calculation manually doing which it will be suited to the rule of thumb.
Firstly, should do design the absorber by know the composition of incoming
gas from model simulation we have done.
Basis: 1 hour of operation
Universitas Indonesia

63

Table B.2. Composition of the Incoming Gas

Component
Kmols
Fraction Molecular Weight
Methane
84.72
0.03
16
Hydrogen 1799.7352 0.6373
2
H2O
451.5576
0.1599
18
CO
152.496
0.054
28
CO2
335.4912
0.1188
44
TOTAL
2824
1

1. The average of molecular weight of the incoming gas


1 1 + 2 2 + 3 3 + 4 4
=

MW = 6422.906 kg/kmols

2. Density of gas mixture


Given that Tin= 38oC, so the density of gas mixture will be calculated
by following:

gas = 251.7014855 Kg/m3


3. Amine and gas Flowrate Calculation
CO2 absorbed = 335.4912 kmoles = 14761.6128 kgs
Total CO2 absorbed by amine = 1003.2 Kgs
Based on the calculation:
0.407667 W needs 13758.41 Kgs
Then The value of W = 9.37477 Kgs/s
Amine flowrate (A ) = 9.37477 Kgs/s
Densitas (A) = 1040 Kg/m3
Gas Flowrate (G) = 5038.413 Kgs/s
Densitas (G) = 251.7015 Kg/m3
4. Column Selection
In this case of absorber, there are two kind of column, tray column
and packing column. We have choosen packing column for the reason:
Universitas Indonesia

64

The gas material which enter to the absorber column is a


corrosive gas.

From economic side, packing column is cheaper than tray column.

The pressure drop result of packing column is lower than tray


column. The contact between gas and liquid in packing column is
more perfect due to the higher area contact.

5. Material Selection
Then choose the following packing as given in the Richardson and
Coulson as seen in the Figure below

Figure B.6. Design for Various Packing

Based the table, the material selected is Racing Rings Ceramic,


because if it compared to the other material, Rashing Rings ceramic is
the best on because of it has corrosif endurance, it will be good to the
corrosif liquid.
Material

= 3 Ceramic. Rasching Rings

Nominal Size

= 76 mm

Bulk Density

= 561 kg/m3

Surface area

= 68 m2/m3

Packing factor = 65 m-1


Voidage

= 75%
Universitas Indonesia

65

6. Diameter Calculation
The calculationof it is based on Richardson and Coulson, volume 6.
Firstly we have to calculate below

0.5
= ( ) {( )}

FLV = 0.0009154
Then we have to plot the result to the flooding line graph to get the value
K4. From the plot of K4 Vs FLV. We get K4 at the flooding line 3.2

Figure B.7. Flooding Line Graph

G*= 49.913 Kg/m2s


Designing for a pressure drop of 42 mm water per m of packing. We
Have
K4 = 2.1
% Loading = 81.00925873%
G* = 40.4342758 Kg/m2s

Cross Section Area required


Universitas Indonesia

66

A = 124.60 2
Diameter required

D = 12.6 m
Hence the diameter which is calculated from this approach is 12.6 meter
7. Diameter Calculation
The number stage of packing column absorbtion tower can be
calculated by using the graph below from Richard and Coulson. From the
graph, we get the number of stage is about two stages.
8. Height of Packing Calculation

Volumetric Flowrate entering gas

= 20.017 m3/s

Gas Velocity at the bottom of tower

= 0.16 m/s

Mass Flowrate at the top of tower = 4439.84 Kgs/s

Volumetric Flowrate at the top of tower

= 17.64 m3/s

Gas velocity at the top of tower

= 0.14 m s
Universitas Indonesia

67

Liquid Flow

= 0.075 Kgs/ m2/s

Then We have to calculate the co-relation by the formula below

KG = 0.136
Area of Packing/ft height
A = 8597.9151 m
Height of Packing require
H = 20.51 m
9. Height of Packing Calculation
Inner Diameter = 12.60 meter
Height of pack req = 20.51 meter
Skirt Height = 2 meter
Density of mat column = 7700 kg/m3
Wind pressure = 130 kg/m2

Material Selection
Carbon Steel
Permissible tensile stress (f) = 950 kg/cm2

Thickness of shell = 3.008 mm

Universitas Indonesia

68

B.4. Steam Methane Reformer R-101


Before calculating the volume of the reactor, we should calculate the rate of
reaction by the kinetic equation of Steam Methane Reforming below (Datta, et al.
2000)
3
2
4 2 (1
)
4 2
=

(2 2 ) (1 + 2 2 )
2

The rate equations that were obtained based on the rate determining steps for
CH4 + H2O = 3H2 + CO. The rate of reaction use a kgmol/kg cat. S unit ( Hoang,
2005).
Where
= 1 + + 2 2 + 2 2 +

2 2
2

Qr = 4,561
With parameter kinetic, equilibrium constant and adsorption constant below.
3
1
2

1
1 = 2.5 ( 4 2
) 2
1

Reaction rate is rate = 4,08045 kgmol/kgcat.h


With the molar flow of 2135 kgmol/h, we can calculate the total weight of the
catalyst below
Weight of catalyst = 2135/ 4,08045 = 523.23 kg
By using bulk density of Ni/Mo-Al2O4 catalyst at 0.041 g/ml, we can
calculate the catalyst volume. Then, the volume of the reactor is (with 80% of
catalyst volume). After that, we calculate the number of tubes needed. Then,
calculate number of tubes needed. After that, we calculate the diameter and length
of reactor by 1:4 ratio. Then, we calculate the diameter of each tube. From the
literature we read, the construction materials used is a 25% chromium-20% nickel
alloy is preferred tube material (Low-alloy steels SA-203 grade D). The thickness
of reactor can be calculated by using a thickness calculation for tall vertical
vessel. The corrosion allowance is 1/32.

Universitas Indonesia

69

The value of S can be found onTable 13.1, Process Equipment Design by


Brownell. A welded-joint efficiency (E) of 0.85 is specified by the ASME code.
The material we used for our reactor is Low-alloy steels SA 203 grade D. After
that, we can use a torispherical heads for our reactor design and calculate the head
thickness.
The Calculation for sizing steam methane reformer is using Microsoft Excel and
the result is shown in the sizing table
Table B.2. Steam Methane Reformer

weight of catalyst

kg cat

Cat Vol

48,780488

m3

Vol Reactor

57,388809

m3

A Reaktor total

0,03

ft2

Tube
D Reaktor

100
2,6341016

263,41016

cm

10,536406

D tube

2,6341016

cm

1,06

in

0,0287566

105,0765

1,751275

min

1,9773921

in

5,0225

cm

3,829613

in

9,6478

cm

Residence time

thickness

thicknes head

TUBE THICKNESS 0,1299539

in
Universitas Indonesia

70

APPENDIX C
Heat Exchanger Design Procedure
Step 1. Obtain the required thermos-physical properties of hot and cold
fluids at the caloric temperature or arithmetic mean temperature. Calculate
these properties at the caloric temperature if the variation of viscosity
with temperature is large. The detailed calculation procedure of caloric
temperature available is in reference.
r=

Tc Tho Tci
=
Th Thi Tco

Step 2. Perform energy balance and find out the heat duty (Q) of the
exchanger
Q c = Q h = mc Cc (t 2 t1 ) = mh Ch (T2 T1 )
Step 3. Assume a reasonable value of overall heat transfer coefficient
(Uo,assm). The value of Uo,assm with respect to the process hot and cold
fluids.

Universitas Indonesia

71

Figure C.1. Shell and Tube Overall Coefficient

Figure C.2. Air Cooled Exchangers and Immersed Oil Overall Coefficient

Step 4. Decide tentative number of shell and tube passes (np). Determine
the LMTD and the correction factor FT. FT normally should be greater
than 0.75 for the steady operation of the exchangers. Otherwise it is
required to increase the number of passes to obtain higher FT values.
TLMTD =

(Thi Tco ) (Tho Tci )


(T Tco )
ln hi
(Tho Tci )

Step 5. Calculate heat transfer area (A) required:


A=

Q
U0,assm LMTD FT

Step 6. Select tube material, decide the tube diameter (ID = di, OD =
d0), its wall thickness (in terms of BWG or SWG) and tube length (L).
Calculate the number of tubes (nt) required to provide the heat transfer area
(A).

nt =

A
do L

Calculate tube side fluid velocity


u=

4 m(np nt )
di 2
Universitas Indonesia

72

Re =

4 m(np nt )
104
di

Step 7. Decide type of shell and tube exchanger (fixed tubesheet, U-tube
etc.). Select the tube pitch (PT), determine inside shell diameter (Ds)
that

can

accommodate

the calculated number of tubes (nt). Use the

standard tube counts table for this purpose.

Figure C.3. Coomon Tube Layouts

Figure C.4. Heat exchangers tube-layouts

Step 8. Assign fluid to shell side or tube side. Select the type of baffle
(segmental, doughnut etc.), its size (i.e. percentage cut, 25% baffles are
widely used), spacing (B) and number. The baffle spacing is usually chosen
to be within 0.2 Ds to Ds.

Universitas Indonesia

73

Figure C.5. Type of Heat Exchanger Baffles

Step 9. Determine the tube side film heat transfer coefficient (hi) using the
suitable form of Sieder-Tate equation in laminar and turbulent flow regimes.
Estimate the shell-side film heat transfer coefficient (ho) from:
ho D c 13 0.14
( )
( )
jH =
k

And find the hio from:


hio = hi

ID
OD

Step 10. Calculate overall heat transfer coefficient (Uo,cal)


UC =

hio ho
hio + ho

With the design overall coefficient is


UD =

Q
A T

The dirt factor is calculated from:


Rd =

UC UD
UC UD

Universitas Indonesia

74

Step 11. Pressure drop calculation will be the tube side pressure drop (PT)
and the shell side pressure drop (PS). Pressure drop in the straight section
of the tube (frictional loss) (Pt) and return (Pn) due to change of
direction of fluid. So the total of each pressure drop: PT = Pt + Pn
P =

fG2 De (N + 1)
5,22 1010 De st

If the tube-side pressure drop exceeds the allowable pressure drop for the
process system,
we can decrease the number of tube passes or increase number of tubes per
pass.
P =

LfG2
5,22 1010 Ds st

If the shell-side pressure drop exceeds the allowable pressure drop


P =

LfG2
5,22 1010 Ds st

The procedure is the same for all heat exchanger, the calculation is using
Microsoft Excel and the result is shown in the sizing table. Below will be shown
the calculation for one heat exchanger.

Material Selection for Heat Exchanger


For heat exchanger using low pressure and medium pressure steam as
heating fluid , we used carbon steel as material because temperature of process is
not too high. Moreover, Fluid that we used is Oil that cant cause corrosion. We
choose Carbon Steel SA-283 with Grade C because this material is commonly
used. Carbon steel is used because highly durable, low cost and easy to
manufactured.
Due to the high temperature like fired heater used for heating feed to steam
methane reformer. Therefore, carbon steels cannot be used as pipe material
because this material cannot be used in high temperature conditions. Carbon steel
can be used as material for temperature conditions bellow 1400oF. Materials that
can be used as wall material which can also be used in high temperature
conditions are stainless steel. Therefore, the proper material for low pH and high
Universitas Indonesia

75

temperature is stainless steel (SS)316L. Grade 316 is the standard molybdenum


bearing grade, second importance to 304 amongst the austenitic stainless steel.
The molybdenum gives 316 better overall corrosion resistant properties than grade
304 particular resist to pitting and crevice corrosion in chlorine environment.

C.1. Heat Exchanger E-101

Heat Balance

CPO,

25+65
2

= 450 , c = 2200 J/kg-K


Q = m.c.T
= (44,700 kg/h) (2200 J/kg-K) (338-298) K
= 3,933,600,000 J/h

Steam,

W =

152 + 145
2

= 148.50 ,

c = 4180 J/kg-K

3,933,600,000 J/h
(4180 J/kgK)(428407) K

= 44812,03 kg/h

Determine the LMTD

T1 = 155oC
t2 = 65oC
T2 = 134oC
t1 = 25oC
LMTD =

R=

S=

(1 2 )(2 1 )

(1 2 )
(2 1 )
(2 1 )
(1 1 )


ln( 1 2 )
2 1

(155134)
=

(6525)
(6525)

(15525)

(15565)(13425)
(15565)
ln((13425))

= 99.2oC

= 0.525

= 0.308

Determine the temperature difference


Universitas Indonesia

76

It could be obtained from the graph that shows temperature correction factor. The
available existing graphs are for two shell passes, four, multiple of four tube
passes, etc.
The example graph that is used in this case could be seen below :

Figure C.6. Temperature Correction Factor : two shell passes ; four or multiple passes
(Source: Kern)

The temperature correction factor (FT) that is obtained from Figure C.6 is 1.

The properties of tube and pitch could be obtained from Table and Table

From the following table could be obtained the exact value of tube outer diameter,
square pitch length, shell inner diameter, amount of passes, and the last one in
amount of tubes. Actually there is no calculation done before choosing the value
of tube and pitch properties, but the chosen one should logically makes sense.
In this case, the selected tube OD is 0.75 in = 0.019m
Square pitch length = 1 in = 0.0254 m
Shell inner diameter = 19.25 in = 0.49 m
Amount of passes = 2
So that the amount of tubes is 220

Universitas Indonesia

77

Figure C.7. Tube Sheet Layouts (square pitch)


(Source: Kern)

Besides that, the other tubes properties could be obtained from the following

Universitas Indonesia

78

Figure C.8. HE Layouts


(Source: Kern)

The table above is used by using the previous selected tube OD. As the tube OD is
considered to be then the BWG value could be obtained. The BWG value is
chosen randomly, so that the following properties that are in the same row could
be obtained.

Universitas Indonesia

79

The BWG value = 14


The wall thickness = 0.083 in = 0.0021m
Tube inner diameter = 0.584 in= 0.015m
Flow area per tube = 0.268 in2 = 1.73 x 10-4 m2
Surface/lin (outside) = 0.1963 ft2 = 0.018 m2
Surface/lin (inside) = 0.1529 ft2 = 0.014 m2
Then back to hysys. Heat Exchanger E-106 is the one that is used to show the
general Heat Exchanger sizing calculation. All the datas below are obtained from
the composition and properties part in Hysys.
Table C.1. Composition Properties

Hot (shell)
W (flowrate)
T1
T2
T average
SG
c
Q

Steam
2.7 kg/s
155 oC
134 oC
144.5 oC
1
1.85 kJ/kg oC
1651

Cold (tube)
W
t1
t2
T average
SG
c
Q

CPO
13.16 kg/s
25 oC
65 oC
45 oC
0.88
2.2 kJ/kg oC
1048

(Source: Authors Documantation)

SG or specific gravity value is obtained by dividing the mass density of the stream
which is in kg/m3. So that obtaining the specific gravity is by dividing it with the
basis 1000 kg/m3 (water).
c is heat capacity. It is obtained from the properties parts in Hysys, which is heat
capacity (kJ/kgmol oC). Then the Q value could be obtained using the equation
below :
Q = W x c x (TShell in - TShell out) for shell
= 2.7 kg/s x 1.85 kJ/kgoC x (155 oC - 134 oC)
= 104.895 kJ/s
Q = W x c x (TTube out TTube in) for shell
= 13.16 kg/s x 2.2 kJ/kgmol oC x (65 oC 25 oC)
Universitas Indonesia

80

= 1158,08 kJ/s

Determine the flow area

Shell flow area = [ Shell ID x (tube pitch tube OD) x baffle space ] / (144 x
tube pitch )
In order to make the calculation easier, then all of the variables above are
converted so that the unit is on International Unit.
tube pitch tube OD = 1 in 0.75 in = 0.25 in = 0.25 in x 0.0254 m/in = 0.00635
m
baffle space = 5 in = 5in x 0.0254 m/in = 0.127 m
tube pitch = 1 in = 0.0254 m

So that the shell flow area = (0.49 m x 0.00635 m x 0.127 m) / (144 x 0.0254 m )
= 0.00011 m2

Tube flow area = ( Flow area per tube x amount of tubes ) / (144 x amount of
passes)

= (1.73 x 10-4 m2 x 220) / (144 x 2)


= 0.00013 m2

Calculate the other possible flow rate by using the following equation :

Hot stream (in shell) = Qcold / [chot x (T1-T2)]


= (1158.08 kJ/s) / [ 1.85 kJ/kgmol oC x (155 oC - 134 oC) ] = 2.9806 kg/s
Cold stream (in tube) = Qhot / [ccold x (t2-t1)]
= (104.895 kJ/s) / [ 2.2 kJ/kgmol oC x (65 oC 25 oC) ]
= 11.9 kg/s
In the next calculation, the higher flowrate will be used. So that comparing the
flowrate from the hysys and calculation should be done before continuing the
calculation.
Hot stream (in shell) W from hysys = 2.7 kg/s
W from calculation = 2.9806 kg/s
Cold stream (in tube) W from hysys = 13.16 kg/s
W from calculation = 11.9 kg/s
Universitas Indonesia

81

The tube length is selected as 8, 10, 12, 16, or 20 feet. Likewise, the outer
diameter is specified as , 3/8, , 5/8, , 1, 1, or 1 inch. Usually, the tubes
are typically specified to be 14 BWG. The most common tube lengths are 16 and
20 feet and the most common tube OD values are or 1 inch. So, selecting one of
the values in each set will get the calculation to estimate the approximate number
of tubes start.
To determine the shell size, once the number of tubes has to be known, then select
a pitch and the number of passes have to be done. Typical initial guesses are 1 or
2 tube passes. A square pitch is chosen for reasons of convenience in cleaning the
outside of the tubes; when the tubes are in-line, cleaning us relatively
straightforward. The standard choice is a pitch equal to 1.25 inches for 1-inch OD
tubes, and a pitch of 1 inch for inch OD tubes. Tubes on a triangular pitch
cannot be cleaned by tools, but rather by passing a chemical solution through on
the shell-side. It is due to triangular pitches allow for the packing or more tubes
into a given space, they are more common when cleaning the outside is not a
major issue. Rectangular pitches are uncommon. According to this explanation,
the square pitches type is chosen.

Find the G value

It could be obtained by calculating using this formula :


G = W / flow area
Both shell and tube calculation are same.
Shell G = (2.9806 kg/s) / 0.00011 m2 = 27096.36 kg/m2.s
Tube G = (13.16 kg/s) / 0.00013 m2 = 101230,77 kg/m2.s

Calculate the De

Shell
OD2

De = 4 x
=4x

(The pitch)2 ( x 4 )
x OD x 12
(0.0254 m)2 (3.14 x

0.019m2
)
4

3.14 x 0.019 m x 12

= 0.00202 m
Tube
Universitas Indonesia

82

De = tube inner diameter = 0.015 m

Check the viscosity from Hysys

Steam = 1
CPO = 0.88
Find the *
* steam = x 2.42 = 1 x 2.42 = 2.42
* CPO = x 2.42 = 0.88 x 2.42 = 2.1296

Calculate the Reynolds Number (Re)

It is done by using this equation :


Re = (De x G) / *
Stream in shell
Re = (0.00202 m x 27096.36 kg/m2.s) / 2.71 = 20.197

Stream in tube
Re = (0.015 m x 101230,77 kg/m2.s) / 2.42 = 627.463

Find jH

jH value could be obtained from the graph in Figure below

Universitas Indonesia

83

Figure C.9 jH Factor


(Source: Kern)

jH in shell and Jh in tube got the same value which is 1000

Check the thermal conductivity from hysys

Steam (hot stream in shell) k = 0.02963 W/m K


CPO (cold stream in tube) k = 0.1721 W/m K
Calculate ho/ and hi/

Shell

ho/ =

jH x k
c x
De x (

)1/3

1000 x 0.02963 W/mK


0.00202 m x (

1.85 kJ/kgmol oC x 2.42


0.02963 W/m K

)1/3

= 6371

Tube
Universitas Indonesia

84

hi/ =

jH x k
c x
De x (

)1/3

1000 x 0.1721 W/m K


0.015 m x (

2.2 kJ/kgmol oC x 2.1296


0.1721 W/m K

)1/3

= 13005

Calculate the hio/, which is


hio/ =

hi
x

tubeID

tube OD

= 13005 x (0.0015 m / 0.0019 m ) = 10267

Calculate Uc

Uc = (hi/ x hio/) / (hi/ + hio/)


= (13005 x 10267) / (13005+10267)
= 5730

Calculate Ud

Way to calculate Ud is started by choosing the higher value between Q shell and
Q tube, which in E-106, the Q shell is 1087 kJ/s and Q tube is 1048 kJ/s. So that
the Q shell is used to continue the Ud calculation.
Ud = Q / (LMTD x Ft x contact area)
= (1651 kJ/s) / (99,2oC x 0.99 x 192.5 m2)
= 0.39

Calculate the pressure drop


2
=
5.22 1010

Shell
P = 8.3 psi
Tube
P = 6.4 psi
The pressure drop of shell and tube meet the requirement as are below 10 psi

C.2. Fired Heater


A fired heater is a direct-fired heat exchanger that uses the hot gases of
combustion to raise the temperature of a feed flowing through coils of tubes
aligned throughout the heater. Depending on the use, these are also called
furnaces or process heaters. Some heaters simply deliver the feed at a
predetermined temperature to the next stage of the reaction process; others
Universitas Indonesia

85

perform reactions on the feed while it travels through the tubes. Fired heaters are
used throughout hydrocarbon and chemical processing industries such as
refineries, gas plants, petrochemicals, chemicals and synthetics, olefins, ammonia
and fertilizer plants. Most of the unit operations require one or more fired heaters
as start-up heater, fired reboiler, cracking furnace, process heater, process heater
vaporizer, crude oil heater or reformer furnace.
A typical fired heater will have following four sections: (1) Radiant section, (2)
Shield section, (3) Convection section, and (4) Breeching and stack. A fired heater
may be a box (rectangular c/s) or vertical (cylindrical c/s) in shape. Same way, a
fired heater may be classified depending on location of the burners and type of the
draft.
I. Radiant Section Design
A. Radiant Heat Transfer in Radiant Section:
Applying basic radiation concepts to process-type heater design, Lobo & Evans
developed a generally applicable rating method that is followed with various
modifications, by many heater designers. Direct radiation in the radiant section of
a direct fired heater can be described by the equation shown below.

B. Heat Balance In The Radiant Section:


There are four primary sources of heat input as well as four sources of heat output
to the radiant section. We can now set up the heat balance equation as follows:
Qfuel + Qair + QSteam + QRFG = QR + QS + QLoss + Qout
Universitas Indonesia

86

Where,

C. Total Heat Transfer in Radiant Section (if Shield Section is present)

Where,

II. Convection Section Design


A. Overall Heat Transfer Coefficient, Uo

Where,

And,

Universitas Indonesia

87

Where,

And the resistances are computed as,

Where,

B. Inside film heat transfer coefficient, hi :


The inside film coefficient needed for the thermal calculations may be estimated
by several different methods. The API RP530, Appendix C provides the following
methods, For liquid flow with Re 10,000,

And for vapor flow with Re 15,000.

Universitas Indonesia

88

C. Effective outside heat transfer coefficient (he) for Fin tubes

Where,

III. Excel Programming


Design of different sections of fired heater has beenperformed using Microsoft
Excel Programming. For the calculation purpose, different calculation methods an
equations are used in the programming.

Universitas Indonesia

89

APPENDIX D
D.1. Compressor C-101
With used Hysys for sizing compressor, we got

(), (1 ),

(2 ), (), R, , MW and mass flow ().


a. Pressure Ratio
=

2 6.132
=
= 1.195
1 5.132

b. Discharge Temperature
= 1 [1 +
= 293 [1 +

(2 1 )1 1
]

(1.195)1.31911,319 1
]
0,75

= 320.2
c. Power
= + [(1 2 ) + (

12 22
)]
2

= 21.60

D.2. Compressor C-102


With used Hysys for sizing compressor, we got

(), (1 ),

(2 ), (), R, , MW and mass flow ().


a. Pressure Ratio
=

2 3.378
=
= 1.42
1 2.378

b. Discharge Temperature
= 1 [1 +

(2 1 )1 1
]

(1.42)1,33411,334 1
= 553 [1 +
]
0,75
= 620.66
Universitas Indonesia

90

c. Power
= + [(1 2 ) + (

12 22
)]
2

= 290.2

Universitas Indonesia

91

APPENDIX E
E.1. Pump P-101
Requirred differentual head is determined as follows:
Absolute Total pressure at pump suction
Bottom of stripper
14.7 psia
Elevation
0.75 psia
Friction piping
-0.5 psia
Friction valve
-0.2 psia
14.75 psia
Absolute Total pressure at pump discharge
Rich Amine to HE
29.39 psia
Elevation
2.754 psia
Friction piping
3 psia
Friction valve
2 psia
Friction filter
0 psia
37.144 psia

Differential pressure between suction and discharge is 22.394 psi


Head =

P
x 2.31 = 49.74 ft
SG

Required Head = Head + 10% Safety factor = 54.714 ft

NPSHA

Bottom of stripper
Elevation
Friction piping
Friction valve
Fluid vapor pressure

14.7
0.75
-0.5
-0.2
-14.7
0.05

psia
psia
psia
psia
psia
psia

So, NPSHA is 0.111


Hydraulic Power

220 USGPM
Universitas Indonesia

92

Head
SG
Hydraulic Power

54.71457 ft
1.04
3.161286 hp
2.357371 kW

Actual Horse Power


Hydraulic Power
3.161286 hp
Eff
0.75
BHP
4.215048 BHP
3.143162 kW

Spesific Speed
Nsd =

(rpm)Q(GPM)
3
[H(ft)]4

= 1327.109

Figure E.1 Impeller shapes related to specific speed

From Figure E.1 , it can be seen thay type of impeller for this pump is Radial
Vane.

Universitas Indonesia

93

E.2. Pump P-102


Requirred differentual head is determined as follows:
Absolute Total pressure at pump suction
Bottom of stripper
9.696 psia
Elevation
0.75 psia
Friction piping
-0.5 psia
Friction valve
-0.2 psia
14.75 psia
Absolute Total pressure at pump discharge
Rich Amine to HE
24.39 psia
Elevation
2.754 psia
Friction piping
3 psia
Friction valve
2 psia
Friction filter
0 psia
32.144 psia

Differential pressure between suction and discharge is 22.398 psia.


Head =

P
x 2.31 = 49.74 ft
SG

Required Head = Head + 10% Safety factor = 54.724 ft

NPSHA

Bottom of stripper
Elevation
Friction piping
Friction valve
Fluid vapor pressure

9.696
0.75
-0.5
-0.2
-9.696
0.05

psia
psia
psia
psia
psia
psia

So, NPSHA is 0.111

Universitas Indonesia

94

Hydraulic Power

Q
Head
SG
Hydraulic Power

223.344
54.71457
1.04
3.2091
2.3936

USGPM
ft
hp
kW

Actual Horse Power


Hydraulic Power
3.161286 hp
Eff
0.75
BHP
4.2798 BHP
3.1915 kW

Spesific Speed
Nsd =

(rpm)Q(GPM)
3
[H(ft)]4

= 1336.978

From Figure E.1 , it can be seen thay type of impeller for this pump is Radial
Vane.
E.3. Pump P-103
Requirred differentual head is determined as follows:
Absolute Total pressure at pump suction
Bottom of stripper
14.7 psia
Elevation
0.75 psia
Friction piping
-0.5 psia
Friction valve
-0.2 psia
14.75 psia
Absolute Total pressure at pump discharge
Rich Amine to HE
400 psia
Elevation
2.754 psia
Friction piping
3 psia
Friction valve
2 psia
Friction filter
0 psia
37.144 psia

Differential pressure between suction and discharge is 407.754 psia


Universitas Indonesia

95

Head =

P
x 2.31 = 872.92 ft
SG

Required Head = Head + 10% Safety factor = 960.21 ft

NPSHA

Bottom of stripper
Elevation
Friction piping
Friction valve
Fluid vapor pressure

14.7
0.75
-0.5
-0.2
-14.7
0.05

psia
psia
psia
psia
psia
psia

So, NPSHA is 0.111


Hydraulic Power

Q
Head
SG
Hydraulic Power

211.112
960.2146
1.04
53.23371
39.69936

USGPM
ft
hp
kW

Actual Horse Power


Hydraulic Power
53.23371 hp
Eff
0.75
BHP
70.98361 BHP
52.93248 kW

Spesific Speed
Nsd =

(rpm)Q(GPM)
3
[H(ft)]4

= 151.6187

From Figure E.1 , it can be seen thay type of impeller for this pump is Radial
Vane.
Universitas Indonesia

96

E.4. Pump P-104


Requirred differentual head is determined as follows:
Absolute Total pressure at pump suction
Bottom of stripper
14.7 psia
Elevation
0.75 psia
Friction piping
-0.5 psia
Friction valve
-0.2 psia
14.75 psia
Absolute Total pressure at pump discharge
Rich Amine to HE
29.39 psia
Elevation
2.754 psia
Friction piping
3 psia
Friction valve
2 psia
Friction filter
0 psia
37.144 psia

Differential pressure between suction and discharge is 22.444 psi


Head =

P
x 2.31 = 49.74 ft
SG

Required Head = Head + 10% Safety factor = 54.714 ft

NPSHA

Bottom of stripper
Elevation
Friction piping
Friction valve
Fluid vapor pressure

14.7
0.75
-0.5
-0.2
-14.7
0.05

psia
psia
psia
psia
psia
psia

So, NPSHA is 0.111


Hydraulic Power

Q
Head

149.644 USGPM
54.71457 ft
Universitas Indonesia

97

SG
Hydraulic Power

1.04
2.15 hp
1.6 kW

Actual Horse Power


Hydraulic Power
3.161286 hp
Eff
0.75
BHP
2.867 BHP
2.138 kW

Spesific Speed
Nsd =

(rpm)Q(GPM)
3
[H(ft)]4

= 1094.523

From Figure E.1 , it can be seen thay type of impeller for this pump is Radial
Vane.

Universitas Indonesia

Você também pode gostar