Escolar Documentos
Profissional Documentos
Cultura Documentos
3 Cleaning columns
4 Painting columns
Supervisor
:
Superintendent
Sub area
1 Walkways
No
Id Number
80002407
Name
RIYANTO
Position
Store Assistant
Status
Time in
Time out
Mile Point
Area
Sub Area
Activity
DS
06.00
18.00
MP74
29
2 Laydown
9
10
11
12
3
3 Main line
4
5
1 Install scaffold
13
14
3 Identify defects
15
4 Repair defects
16
17
4 All area
18
19
20
21
22
23
10
24
25
26
11
27
28
12
29
30
13
31
32
14
33
15
34
35
16
36
37
17
38
18
39
19
40
20
41
42
Prepared by,
Approved by,
43
44
45
46
47
Foreman
Dept. SPV/SUPT
Dept. Head/MGR
HR MGR/SUPT
48
Name
Name
Name
Name
49
Activity
Fabricate steel structure
50 QA Field
51 QA Office
52 Handover Document
Erect scaffolding
Demolish scaffolding
54 Document Control
55 Drafting
Cleaning tank
56 Electrical demolish
Cleaning pipe
Painting tank
Painting pipe
60 Install conduit
Excavation
61 Install cable
63 Install panel / DB
64 Cable termination
Pouring concrete
65 Pre-commissioning
66 Commissioning
skirting, vinyl
72 Equipment control
73 Machinary maintenance
Install furniture
75 Accounting
Delivery material
Lifting material
Issue material
Issued and return tools
stock control
Survey Topografhy
Survey Traverse
Calculation of Survey Data
Staking out coordinate position of
Site Plan ,Grid Line
Setting Bow Plank
Marking for position of Foundation
Monitoring for excavation
Setting and Levelling Ancor Bolt
Levelling Top Concrete ( checking
before pouring concrete)
Survey Plumbnes
Marking elevation of top Floor
and centre of grid line
Marking position of room, window,
door,celling ,ect
marking monitoring
Surveying for as built Drawing data
Safety induction and training
Supervising and monitoring
Input data for safety
Site inspection and testing
Field and documentation audit
3 Cleaning columns
4 Painting columns
Supervisor
:
Superintendent
Sub area
1 Walkways
No
Id Number
80004404
Name
SUTISNA BIN MARNA
Position
Steel Erection FM
Status
Time in
Time out
Mile Point
Area
Sub Area
Activity
DS
06.00
18.00
MP74
2 Laydown
V99179
TARSIM
80002350
V85586
BUSRIYONO
Welder
SADAM
Welder
9
10
11
12
3 Main line
1 Install scaffold
13
14
3 Identify defects
15
4 Repair defects
16
80003338
SLAMET RIYADI
Welder
80002355
ASEP SUNARYA
Steel Erection
80003102
USMADI
Steel Erection
20
V120461
ASEP SAEPUDIN
Steel Erection
21
V120802
Steel Erection
17
4 All area
18
19
22
23
24
10
25
26
11
27
28
12
29
30
13
31
32
14
33
15
34
35
16
36
37
17
38
18
39
19
40
20
41
42
Prepared by,
Approved by,
43
44
45
46
47
Foreman
Dept. SPV/SUPT
Dept. Head/MGR
HR MGR/SUPT
48
Name
Name
Name
Name
49
Activity
Fabricate steel structure
50 QA Field
51 QA Office
52 Handover Document
Erect scaffolding
Demolish scaffolding
54 Document Control
55 Drafting
Cleaning tank
56 Electrical demolish
Cleaning pipe
Painting tank
Painting pipe
60 Install conduit
Excavation
61 Install cable
63 Install panel / DB
64 Cable termination
Pouring concrete
65 Pre-commissioning
66 Commissioning
skirting, vinyl
72 Equipment control
73 Machinary maintenance
Install furniture
75 Accounting
Delivery material
Lifting material
Issue material
Issued and return tools
stock control
Survey Topografhy
Survey Traverse
Calculation of Survey Data
Staking out coordinate position of
Site Plan ,Grid Line
Setting Bow Plank
Marking for position of Foundation
Monitoring for excavation
Setting and Levelling Ancor Bolt
Levelling Top Concrete ( checking
before pouring concrete)
Survey Plumbnes
Marking elevation of top Floor
and centre of grid line
Marking position of room, window,
door,celling ,ect
marking monitoring
Surveying for as built Drawing data
Safety induction and training
Supervising and monitoring
Input data for safety
Site inspection and testing
Field and documentation audit
3 Cleaning columns
4 Painting columns
Supervisor
:
Superintendent
Sub area
1 Walkways
No
Id Number
Name
80002440
HERU GUNAWAN
Position
Status
Time in
Time out
Mile Point
Area
Sub Area
Activity
2 Laydown
HSE Assistant
80002445
SAMINO
HSE Assistant
9
10
11
12
3
3 Main line
4
5
1 Install scaffold
13
14
3 Identify defects
15
4 Repair defects
16
17
4 All area
18
19
20
21
22
23
10
24
25
26
11
27
28
12
29
30
13
31
32
14
33
15
34
35
16
36
37
17
38
18
39
19
40
20
41
42
Prepared by,
Approved by,
43
44
45
46
47
Foreman
Dept. SPV/SUPT
Dept. Head/MGR
HR MGR/SUPT
48
Name
Name
Name
Name
49
Activity
Fabricate steel structure
50 QA Field
51 QA Office
52 Handover Document
Erect scaffolding
Demolish scaffolding
54 Document Control
55 Drafting
Cleaning tank
56 Electrical demolish
Cleaning pipe
Painting tank
Painting pipe
60 Install conduit
Excavation
61 Install cable
63 Install panel / DB
64 Cable termination
Pouring concrete
65 Pre-commissioning
66 Commissioning
skirting, vinyl
72 Equipment control
73 Machinary maintenance
Install furniture
75 Accounting
Delivery material
Lifting material
Issue material
Issued and return tools
stock control
Survey Topografhy
Survey Traverse
Calculation of Survey Data
Staking out coordinate position of
Site Plan ,Grid Line
Setting Bow Plank
Marking for position of Foundation
Monitoring for excavation
Setting and Levelling Ancor Bolt
Levelling Top Concrete ( checking
before pouring concrete)
Survey Plumbnes
Marking elevation of top Floor
and centre of grid line
Marking position of room, window,
door,celling ,ect
marking monitoring
Surveying for as built Drawing data
Safety induction and training
Supervising and monitoring
Input data for safety
Site inspection and testing
Field and documentation audit
3 Cleaning columns
4 Painting columns
Supervisor
:
Superintendent
Sub area
1 Walkways
No
Id Number
80002831
Name
FITRA KUSUMA
Position
Status
Time in
Time out
Mile Point
Area
Sub Area
Activity
2 Laydown
Scaffolder L/H
80002522
Scaffolder
80005263
HENDRIK PAJAN
Scaffolder
80004463
HARIYONO
Scaffolder
9
10
11
12
3 Main line
1 Install scaffold
13
14
3 Identify defects
15
4 Repair defects
16
17
4 All area
18
19
20
21
22
23
10
24
25
26
11
27
28
12
29
30
13
31
32
14
33
15
34
35
16
36
37
17
38
18
39
19
40
20
41
42
Prepared by,
Approved by,
43
44
45
46
47
Foreman
Dept. SPV/SUPT
Dept. Head/MGR
HR MGR/SUPT
48
Name
Name
Name
Name
49
Activity
Fabricate steel structure
50 QA Field
51 QA Office
52 Handover Document
Erect scaffolding
Demolish scaffolding
54 Document Control
55 Drafting
Cleaning tank
56 Electrical demolish
Cleaning pipe
Painting tank
Painting pipe
60 Install conduit
Excavation
61 Install cable
63 Install panel / DB
64 Cable termination
Pouring concrete
65 Pre-commissioning
66 Commissioning
skirting, vinyl
72 Equipment control
73 Machinary maintenance
Install furniture
75 Accounting
Delivery material
Lifting material
Issue material
Issued and return tools
stock control
Survey Topografhy
Survey Traverse
Calculation of Survey Data
Staking out coordinate position of
Site Plan ,Grid Line
Setting Bow Plank
Marking for position of Foundation
Monitoring for excavation
Setting and Levelling Ancor Bolt
Levelling Top Concrete ( checking
before pouring concrete)
Survey Plumbnes
Marking elevation of top Floor
and centre of grid line
Marking position of room, window,
door,celling ,ect
marking monitoring
Surveying for as built Drawing data
Safety induction and training
Supervising and monitoring
Input data for safety
Site inspection and testing
Field and documentation audit
3 Cleaning columns
4 Painting columns
Supervisor
:
Superintendent
Sub area
1 Walkways
No
Id Number
80002886
Name
NANA TARYANA
Position
Status
Time in
Time out
Mile Point
Area
Sub Area
Activity
2 Laydown
Mason L/H
80002614
AHMAD JEJEN
Mason
80003086
WAWAN ERNAWAN
9
10
11
12
Mason
3 Main line
4
5
1 Install scaffold
13
14
3 Identify defects
15
4 Repair defects
16
17
4 All area
18
19
20
21
22
23
10
24
25
26
11
27
28
12
29
30
13
31
32
14
33
15
34
35
16
36
37
17
38
18
39
19
40
20
41
42
Prepared by,
Approved by,
43
44
45
46
47
Foreman
Dept. SPV/SUPT
Dept. Head/MGR
HR MGR/SUPT
48
Name
Name
Name
Name
49
Activity
Fabricate steel structure
50 QA Field
51 QA Office
52 Handover Document
Erect scaffolding
Demolish scaffolding
54 Document Control
55 Drafting
Cleaning tank
56 Electrical demolish
Cleaning pipe
Painting tank
Painting pipe
60 Install conduit
Excavation
61 Install cable
63 Install panel / DB
64 Cable termination
Pouring concrete
65 Pre-commissioning
66 Commissioning
skirting, vinyl
72 Equipment control
73 Machinary maintenance
Install furniture
75 Accounting
Delivery material
Lifting material
Issue material
Issued and return tools
stock control
Survey Topografhy
Survey Traverse
Calculation of Survey Data
Staking out coordinate position of
Site Plan ,Grid Line
Setting Bow Plank
Marking for position of Foundation
Monitoring for excavation
Setting and Levelling Ancor Bolt
Levelling Top Concrete ( checking
before pouring concrete)
Survey Plumbnes
Marking elevation of top Floor
and centre of grid line
Marking position of room, window,
door,celling ,ect
marking monitoring
Surveying for as built Drawing data
Safety induction and training
Supervising and monitoring
Input data for safety
Site inspection and testing
Field and documentation audit
3 Cleaning columns
4 Painting columns
Supervisor
:
Superintendent
Sub area
1 Walkways
No
Id Number
80002446
Name
SAMAN B KARMAN
Position
Status
Time in
Time out
Mile Point
Area
Sub Area
Activity
2 Laydown
Mason
80002453
TABRONI
Mason
9
10
11
12
3
3 Main line
4
5
1 Install scaffold
13
14
3 Identify defects
15
4 Repair defects
16
17
4 All area
18
19
20
21
22
23
10
24
25
26
11
27
28
12
29
30
13
31
32
14
33
15
34
35
16
36
37
17
38
18
39
19
40
20
41
42
Prepared by,
Approved by,
43
44
45
46
47
Foreman
Dept. SPV/SUPT
Dept. Head/MGR
HR MGR/SUPT
48
Name
Name
Name
Name
49
Activity
Fabricate steel structure
50 QA Field
51 QA Office
52 Handover Document
Erect scaffolding
Demolish scaffolding
54 Document Control
55 Drafting
Cleaning tank
56 Electrical demolish
Cleaning pipe
Painting tank
Painting pipe
60 Install conduit
Excavation
61 Install cable
63 Install panel / DB
64 Cable termination
Pouring concrete
65 Pre-commissioning
66 Commissioning
skirting, vinyl
72 Equipment control
73 Machinary maintenance
Install furniture
75 Accounting
Delivery material
Lifting material
Issue material
Issued and return tools
stock control
Survey Topografhy
Survey Traverse
Calculation of Survey Data
Staking out coordinate position of
Site Plan ,Grid Line
Setting Bow Plank
Marking for position of Foundation
Monitoring for excavation
Setting and Levelling Ancor Bolt
Levelling Top Concrete ( checking
before pouring concrete)
Survey Plumbnes
Marking elevation of top Floor
and centre of grid line
Marking position of room, window,
door,celling ,ect
marking monitoring
Surveying for as built Drawing data
Safety induction and training
Supervising and monitoring
Input data for safety
Site inspection and testing
Field and documentation audit
3 Cleaning columns
4 Painting columns
Supervisor
:
Superintendent
Sub area
1 Walkways
No
Id Number
80002537
Name
BUKHORI MEP
Position
Electrician L/H
Status
Time in
Time out
Mile Point
Area
Sub Area
Activity
DS
06.00
18.00
MP74
76
2 Laydown
80002990
DADAN KUSWARA
Electrician L/H
80002905
SAHRONI LCI
9
10
11
12
Electrician
3 Main line
4
5
1 Install scaffold
13
14
3 Identify defects
15
4 Repair defects
16
17
4 All area
18
19
20
21
22
23
10
24
25
26
11
27
28
12
29
30
13
31
32
14
33
15
34
35
16
36
37
17
38
18
39
19
40
20
41
42
Prepared by,
Approved by,
43
44
45
46
47
Foreman
Dept. SPV/SUPT
Dept. Head/MGR
HR MGR/SUPT
48
Name
Name
Name
Name
49
Activity
Fabricate steel structure
50 QA Field
51 QA Office
52 Handover Document
Erect scaffolding
Demolish scaffolding
54 Document Control
55 Drafting
Cleaning tank
56 Electrical demolish
Cleaning pipe
Painting tank
Painting pipe
60 Install conduit
Excavation
61 Install cable
63 Install panel / DB
64 Cable termination
Pouring concrete
65 Pre-commissioning
66 Commissioning
skirting, vinyl
72 Equipment control
73 Machinary maintenance
Install furniture
75 Accounting
Delivery material
Lifting material
Issue material
Issued and return tools
stock control
Survey Topografhy
Survey Traverse
Calculation of Survey Data
Staking out coordinate position of
Site Plan ,Grid Line
Setting Bow Plank
Marking for position of Foundation
Monitoring for excavation
Setting and Levelling Ancor Bolt
Levelling Top Concrete ( checking
before pouring concrete)
Survey Plumbnes
Marking elevation of top Floor
and centre of grid line
Marking position of room, window,
door,celling ,ect
marking monitoring
Surveying for as built Drawing data
Safety induction and training
Supervising and monitoring
Input data for safety
Site inspection and testing
Field and documentation audit