Escolar Documentos
Profissional Documentos
Cultura Documentos
CIVIL ENGINEERING
STANDARD SPECIFICATION
ISSUE: Initial
DATE:
PAGE:
21.07.93
1 of 6
DATE
DESCRIPTION/REASON
21.07.93
AUTHORISED BY:
DATE:
CIVIL CONTRACTS MANAGER
QR
This document is copyright and may not be copied or reproduced in any way without the approval
of the Manager Civil Engineering.
The information contained in this document is the property of QR and may not be used by any
party without the express approval of the Manager Civil Engineering.
ISSUE:
DATE:
Initial
21.07.1993
TABLE OF CONTENTS
Page
14.1
SCOPE.............................................................................................................................................. 3
14.2
PREPARATION OF FOUNDATIONS................................................................................................ 3
14.3
14.4
14.5
14.6
CONCRETING OF INVERT.............................................................................................................. 4
14.6.1
14.6.2
14.6.3
14.6.4
14.6.5
14.6.6
Extent of Concreting..................................................................................................... 4
Surface Preparation...................................................................................................... 4
Reinforcement............................................................................................................... 4
Concrete........................................................................................................................ 4
Concrete Pipe Joint.................................................................................................... 4
Protection of Finished Concrete....................................................................................4
14.7
14.8
QR - Civil Engineering
ISSUE:
DATE:
14.1
Initial
21.07.1993
SCOPE
PREPARATION OF FOUNDATIONS
ISSUE:
DATE:
14.5
Initial
21.07.1993
CONCRETING OF INVERT
14.6.1
Extent of Concreting
Surface Preparation
Reinforcement
Concrete
QR - Civil Engineering
in
ISSUE:
DATE:
Initial
21.07.1993
QR - Civil Engineering
ISSUE:
DATE:
Initial
21.07.1993
CONSTRUCTION PROCEDURE
LOT IDENTIFICATION
TRACEABILITY
Installation
Material source to
bedding/backfill
End Structures
ACTIVITY
INSPECTION POINT
REFERENCE
LEVEL OF
RESPONSIBILITY FOR
CLAUSE
INSPECTION
INSPECTION
Supply &
Deliver
Installation
End Structures
Bedding
14.2
Hold Point
Superintending Officer
Backfill Material
14.3
Hold Point
Laying
14.4
Witness
Superintending Officer
Repairs
14.3
Hold Point
Superintending Officer
Concrete Invert
14.6 (ii)
Hold Point
Superintending Officer
14.6 (vi)
Witness
Superintending Officer
Concrete
Slope
Protection
ACTIVITY
REFERENCE
CLAUSE
MINIMUM TEST
FREQUENCY
MINIMUM
REQUIREMENT
DESCRIPTION
TEST REQUIRED
Source Assessment
One 50 kg sample
14.3
1 per M.S.
1 per M.S.
Grading
AS 1289.C6.1
14.3
1 per 200 m
1 per M.S.
Acidity (pH)
QDOT Q121
Resistivity
QDOT122A
Compaction
AS 1289.E2.1
14.3
As required
1 per M.T.
1 per 100 m
1 per lot
Backfill
Material
Backfilling
AS 1289.E3.1
End Structures
Concrete
Slope
Protection
M.D.R. = Moisture/Density Relation, F.D.D. = Field Dry Density, M.T. = Material Type, M.S. = Material Source
QR - Civil Engineering