ID

Task
Mode
1

Task Name

Duration

Start

Finish

1 PRE-CONSTRUCTION REQUIREMENTS

53 days

Wed 3/25/15

Fri 6/5/15

1.1 Civil design & permit

16 days

Wed 3/25/15

Wed 4/15/15

1.2 Electrical design & permit

11 days

Wed 4/1/15

Wed 4/15/15

1.3 Structural design & approval

14 days

Fri 4/3/15

Wed 4/22/15

1.4 Insulation design & final approval

15 days

Mon 5/18/15

Fri 6/5/15

1.5 Refrigeration design approval & downpayment

1 day

Wed 3/25/15

Wed 3/25/15

2 BUILDING CONSTRUCTION

206 days?

Wed 4/8/15

Wed 1/20/16

2.1 BUILDING CIVIL WORKS

206 days?

Wed 4/8/15

Wed 1/20/16

2.1.1 Site preparation

11 days?

Wed 4/8/15

Wed 4/22/15

10

2.1.2 Fabrication of rebars

120 days

Wed 4/8/15

Tue 9/22/15

11

2.1.3 Footing & Column @ GL A,B,D,H & J/1-15

71 days

Tue 4/21/15

Tue 7/28/15

12

2.1.4 Installation of anchor bolts

1 day

Tue 8/4/15

Tue 8/4/15

13

2.1.5 Tie Beam, Ret. Wall & Slab-on-Grade@ GL A-C/1-15

43 days

Tue 6/30/15

Thu 8/27/15

14

2.1.6 Tie Beam, Ret. Wall & Slab-on-Grade @ GL D-H/1-15

65 days

Tue 6/30/15

Mon 9/28/15

15

2.1.7 Tie Beam, Ret. Wall & Slab-on-Grade @ GL I-J/1-15

43 days

Tue 6/30/15

Thu 8/27/15

16

2.1.8 Finish building foundation

0 days

Mon 9/28/15

Mon 9/28/15

17

2.1.9 Machine Room & EE Room

38 days

Tue 6/30/15

Thu 8/20/15

18

2.1.10 Finish machine room foundation

0 days

Thu 8/20/15

Thu 8/20/15

19

2.1.11 Slab-on-Grade @ C-D & G-I/1-15

34 days

Tue 9/29/15

Fri 11/13/15

20

2.1.12 Top Slab

14 days

Sat 1/2/16

Wed 1/20/16

114 days

Thu 4/23/15

Tue 9/29/15

21

2.2 BUILDING STEEL STRUCTURE

22

2.2.1 Fabrication up to shipment

10 wks

Thu 4/23/15

Wed 7/1/15

23

2.2.2 Erection & installation

8 wks

Wed 8/5/15

Tue 9/29/15

24

2.2.3 Roofing

7 wks

Wed 8/12/15

Tue 9/29/15

25

163 days?

Mon 6/8/15

Wed 1/20/16

26

2.3.1 Fabrication

56 days

Mon 6/8/15

Mon 8/24/15

27

2.3.2 Shipment

78 days?

Mon 7/6/15

Wed 10/21/15

28

2.3.3 Installation of PU panels

100 days

Thu 9/3/15

Wed 1/20/16

237 days?

Thu 3/26/15

Fri 2/19/16

155 days

Thu 3/26/15

Wed 10/28/15

29
30

2.3 PU PANEL INSULATION

3 MECHANICAL & ELECTRICAL SYSTEM


3.1 REFRIGERATION SYSTEM

31

3.1.1 Fabrication of equipment

14 wks

Thu 3/26/15

Wed 7/1/15

32

3.1.2 Packing & shipment

7 wks

Mon 6/22/15

Fri 8/7/15

33

3.1.3 Equipment installation

5 wks

Thu 8/20/15

Wed 9/23/15

34

3.1.4 Piping works

10 wks

Thu 8/20/15

Wed 10/28/15

35

3.2 ELECTRICAL SYSTEM

168 days?

Wed 7/1/15

Fri 2/19/16

36

3.2.1 Electrical substation

86 days?

Wed 7/1/15

Wed 10/28/15

37

3.2.2 MTS/power panel/MDP/LP

14 wks

Wed 7/1/15

Tue 10/6/15

38

3.2.3 Cable trays

10 wks

Thu 8/20/15

Wed 10/28/15

39

3.2.4 Wiring (power, lighting, refrigeration intruments & controls)

12 wks

Thu 9/3/15

Wed 11/25/15

40

3.2.5 Miscellaneous (Genset & reefer outlet)

22 wks

Wed 7/1/15

Fri 2/19/16

90 days

Wed 7/22/15

Tue 11/24/15

41

3.3 WATER & WATER TREATMENT SYSTEM

42

3.3.1 Water divining & deepwell construction

6 wks

Wed 7/22/15

Tue 9/1/15

43

3.3.2 Pumping & piping works

10 wks

Wed 9/2/15

Tue 11/10/15

44

3.3.3 Water treatment (water softener for condenser water)

11 wks

Wed 8/5/15

Tue 10/20/15

45

3.3.4 Testing of water softener

2 wks

Wed 11/11/15

Tue 11/24/15

46

50 days

Mon 11/30/15

Fri 2/5/16

47

3.4.1 Testing & Commissioning

5 wks

Mon 11/30/15

Fri 1/1/16

48

3.4.2 Temperature pull-down

4 wks

Mon 1/11/16

Fri 2/5/16

49

3.4.3 Ready for final commissioning

0 days

Fri 2/5/16

Fri 2/5/16

185 days

Wed 6/17/15

Tue 3/1/16

35 days

Wed 11/4/15

Tue 12/22/15

7 wks

Wed 11/4/15

Tue 12/22/15

160 days

Wed 7/22/15

Tue 3/1/16

50
51
52
53

3.4 PRE-STARTUP

4 MISCELLANEOUS FACILITIES
4.1 FIRE FIGHTING
4.1.1 Sprinklers, hydrants & fire hose cabinets (incl. piping)

4.2 WASTE WATER TREATMENT FACILITY

54

4.2.1 Design & awarding to contractor

8 wks

Wed 7/22/15

Tue 9/15/15

55

4.2.2 Delivery & construction

16 wks

Wed 9/16/15

Tue 1/5/16

56

4.2.3 Testing & commissioning

8 wks

Wed 1/6/16

Tue 3/1/16

57

155 days

Wed 6/17/15

Tue 1/19/16

58

4.3.1 Design & awarding to contractor

8 wks

Wed 6/17/15

Tue 8/11/15

59

4.3.2 Fabrication of shoots & conveyors

23 wks

Wed 8/12/15

Tue 1/19/16

60

4.3.3 Bidding & purchase of weighing scales

3 wks

Wed 6/17/15

Tue 7/7/15

Project: Project1
Date: Mon 10/26/15

4.3 FISH RECEIVING AREA

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 1

Predecessors

9SS
2FS+3 days
11FS+4 days
11SS+45 days
11SS+45 days
11SS+45 days
11SS+45 days

4
12,22,16FF
16FF
5
26FS-38 days
16FS-25 days

6
31FS-20 days
18,32
33SS

38SS+2 wks

42
43,44

47FS+5 days

54
55

58
58SS

Resource1st
Names
Quarter
Feb

2nd Quarter
Apr

Mar

May

Jun

3rd Quarter
Jul

Aug

Sep

4th Quarter
Oct

Nov

Dec

1st Quarter
Jan

Feb

9/28
8/20

2/5

Project: Project1
Date: Mon 10/26/15

Task

Inactive Summary

External Tasks

Split

Manual Task

External Milestone

Milestone

Duration-only

Deadline

Summary

Manual Summary Rollup

Progress

Project Summary

Manual Summary

Manual Progress

Inactive Task

Start-only

Inactive Milestone

Finish-only

Page 2