Microsoft Project 2013

Lesson 02
Creating a Project Plan

Copyright 2012-2014, Simplilearn, All rights reserved.

Objectives
By the end of this lesson, you will be able to:

List the information required while setting up a new project

Create a new project in Microsoft Project 2013

Describe calendar and its types

Create a template from a completed project

Copyright 2012-2014, Simplilearn, All rights reserved.

Basic Information for a New Project


The Project Manager needs to define basic project details at the commencement of a new project.

Start date of a project


Finish date of a project

Project Schedule

Project Calendar

Copyright 2012-2014, Simplilearn, All rights reserved.

Microsoft Project 2013 Interface


There are different methods to create a project in Microsoft Project 2013.
As a blank
project

Copyright 2012-2014, Simplilearn, All rights reserved.

From an
existing
project

From a
Microsoft
Excel
workbook

From a
Microsoft
SharePoint
task list

From an
existing
project
template

Create Project from a Blank Project Template


A new project can be initiated in Microsoft Project 2013 by creating a blank project and then adding project details
into it.

Copyright 2012-2014, Simplilearn, All rights reserved.

Components of a Blank Project Template


The important components of a Blank Project template are shown here.
Quick Access
Toolbar
Ribbon

View
Task Name and
Description
Gantt Chart

Zoom
Status Bar

Copyright 2012-2014, Simplilearn, All rights reserved.

Create Project from an Existing Template


Microsoft Project 2013 has many pre-installed templates that can be used to create a new project.

New Product launch

Market Research
Schedule

Residential
Construction

Commercial
Construction
Copyright 2012-2014, Simplilearn, All rights reserved.

Merger or Acquisition
Evaluation
7

Create Project from an Existing Project


A new project can be created from an existing project.

A similar project can be used from the previous history to enter the new project details to it.

When a project is created this way, the existing project acts as the foundation for the new project.

2014 Simplilearn Solutions. All Rights Reserved.

Create Project from Microsoft Excel Workbook


New project can be created from an Excel workbook.

2014 Simplilearn Solutions. All Rights Reserved.

Create Project from Microsoft Excel Workbook (contd.)


If the project information is in Microsoft Excel Workbook format, it can be imported into Microsoft Project, without
losing the data or format.

2014 Simplilearn Solutions. All Rights Reserved.

10

Create Project from Microsoft SharePoint Task List


If the development team is using SharePoint for a project, the Project Manager can synchronize the task list from
SharePoint without using the Project Web App.

This will allow the team members to view the project schedule on SharePoint.

Any updates on SharePoint will be reflected in the Microsoft Project plan.

2014 Simplilearn Solutions. All Rights Reserved.

11

Sample SharePoint Task List


Sample task list from SharePoint Project tasks is shown here.

2014 Simplilearn Solutions. All Rights Reserved.

12

Introduction to Base Calendar


When planning a schedule, knowledge about working days and hours, down time, vacations, holidays, etc., are critical for a
project manager.

These details allow the project manager to plan the project resourcefully.

Hence, the project manager can set up a base calendar to plan his project in a better way.

2014 Simplilearn Solutions. All Rights Reserved.

13

Base Calendar
The key elements of a base calendar are as follows:

Resource Allocation

This helps in assigning the right resources for the project.

Project Scheduling

This helps in scheduling the project.

Resource Availability

This helps in identifying the working time to determine when the resources are available to work in the project.

2014 Simplilearn Solutions. All Rights Reserved.

14

Types of Base Calendar


There are three types of base calendar.

Standard Calendar

This calendar is from Monday to Friday.

This calendar is based on the standard work timings, between 8.00


a.m. to 5.00 p.m.

Base Calendar

Night Shift Calendar

This calendar is from Monday to Friday.

This calendar is based on the general night shift work timings,

between 11.00 p.m. to 8.00 a.m.

24-Hour Calendar

2014 Simplilearn Solutions. All Rights Reserved.

This calendar is used throughout the week.

This calendar is based on round-the-clock-work concept.

15

Create New Base Calendar


When the project team is spread across geographies, with each region having its own set of working and non-working
days, the Project Manager can create a new calendar for each geographical region.

He can apply these calendars to the resources and tasks.

Click Change Working


Time.

1
Create New Base
Calendar window is
displayed.
Click Create New
Calendar

Copyright 2012-2014, Simplilearn, All rights reserved.

16

Set Baseline
The Set Baseline command can be used to compare the status of the project with the original plan.
Baseline records the project plan and the resource allocation.
Microsoft Project 2013 permits eleven benchmarks.

Copyright 2012-2014, Simplilearn, All rights reserved.

17

Create a Template from a Completed Project


Microsoft Project 2013 allows you to save the completed project plans as project templates.

Strategies from past projects can be shared and can be applied to future projects.

2
3
1

Copyright 2012-2014, Simplilearn, All rights reserved.

18

Copyright 2012-2014, Simplilearn, All rights reserved.

19

Quiz 1

Which of the following provides the overall information of the project?


Select the answer.

a.
b.
c.
d.

Project Schedule
Base Calendar
Pre-Installed Templates
Project Information

Copyright 2012-2014, Simplilearn, All rights reserved.

20

Quiz 1

Which of the following provides the overall information of the project?


Select the answer.

a.
b.
c.
d.

Project Schedule
Base Calendar
Pre-Installed Templates
Project Information

Answer: d. Project Information


Explanation: Project Information option in Microsoft Project 2013 provides the overall information of the
project to the user.

Copyright 2012-2014, Simplilearn, All rights reserved.

21

Quiz 2

Which of the following provides option to create benchmarks to compare project performance?
Select the answer.

a.
b.
c.
d.

Gantt Charts
Project Schedule
Set Baseline
Standard Calendar

Copyright 2012-2014, Simplilearn, All rights reserved.

22

Quiz 2

Which of the following provides option to create benchmarks to compare project performance?
Select the answer.

a.
b.
c.
d.

Gantt Charts
Project Schedule
Set Baseline
Standard Calendar

Answer: c. Set Baseline


Explanation: Set Baseline command is used to create a base point, which acts as a benchmark to compare
the project performance.

Copyright 2012-2014, Simplilearn, All rights reserved.

23

Quiz 3

Which of the following calendar is used from 8:00 a.m. to 5:00 p.m.?
Select the answer.

a.
b.
c.
d.

Base Calendar
Standard Calendar
Night Shift Calendar
24-Hour Calendar

Copyright 2012-2014, Simplilearn, All rights reserved.

24

Quiz 3

Which of the following calendar is used from 8:00 a.m. to 5:00 p.m.?
Select the answer.

a.
b.
c.
d.

Base Calendar
Standard Calendar
Night Shift Calendar
24-Hour Calendar

Answer: b. Standard Calendar


Explanation: Standard Calendar is the type of calendar which is used from 8.00 AM to 5.00 PM.

Copyright 2012-2014, Simplilearn, All rights reserved.

25

Quiz 4

How many benchmarks can be created with Set Baseline command?


Select the answer.

a.
b.
c.
d.

5
7
11
15

Copyright 2012-2014, Simplilearn, All rights reserved.

26

Quiz 4

How many benchmarks can be created with Set Baseline command?


Select the answer.

a.
b.
c.
d.

5
7
11
15

Answer: c. 11
Explanation: You can create up to 11 benchmarks using Set Baseline command.

Copyright 2012-2014, Simplilearn, All rights reserved.

27

Quiz 5

Which of the following can be used to synchronize the task list, without using the Project Web App?
Select the answer.

a.
b.
c.
d.

Existing Projects
Microsoft SharePoint
Existing Templates
Microsoft Excel Workbooks

Copyright 2012-2014, Simplilearn, All rights reserved.

28

Quiz 5

Which of the following can be used to synchronize the task list, without using the Project Web App?
Select the answer.

a.
b.
c.
d.

Existing Projects
Microsoft SharePoint
Existing Templates
Microsoft Excel Workbooks

Answer: b. Microsoft SharePoint


Explanation: You can synchronize the task list from the SharePoint without using the Project Web App.

Copyright 2012-2014, Simplilearn, All rights reserved.

29

Summary
Here is a quick recap of what was covered in this lesson:

Information such as, project information, project schedule, project calendar, start
date, and finish date of the project are important to create a new project.
In Microsoft Project 2013, a new project can be created using a blank template,

an existing project, an existing template, a Microsoft Excel workbook, and a


Microsoft SharePoint tasks list.
A base calendar is the main calendar used in a project. The types of base calendar

are standard, night-shift, and 24-hour calendar.


The Set baseline command can be used to create a base point that acts as a
benchmark to compare the project performance.

Microsoft Project 2013 provides option to save an existing project, as a template


for future use.

Copyright 2012-2014, Simplilearn, All rights reserved.

30

Thank You

Copyright 2012-2014, Simplilearn, All rights reserved.