Você está na página 1de 8

AT WELDING DEFECT

ISSUED BY : GANZORY

FURTHER DEVELOPMENTS IN ULTRASONIC INSPECTION OF


PIPELINE GIRTH WELDS
Authors E.Ginzel and M.Hoff

Abstract
Ultrasonic Inspection has been widely used in Canada since the early 1980's for inspecting Mechanized Girth
Welds. In 1993 TransCanada PipeLines Limited (TCPL) became the first North American company to use
ultrasonics as the primary nondestructive testing (NDT) method on a pipeline construction project. Further
enhancements to the ultrasonic systems have increased the reliability, speed and evaluation capabilities of the
systems presently approved by TCPL. A review of the systems and the enhancements is presented in this paper.
Table of contents
Background
Recent Developments
o Mapping Enhancements
o Video Evaluation
o Mass Storage
Extremes in Test Conditions
Future Developments
Conclusions
Acknowledgments
List of Figures
References

Background
UT inspection techniques are now in place to detect all commonly found weld defects in pipeline girth welds
fabricated using mechanized welding methods. With the advantage of allowing longer flaws because of zone
discrimination as well as its advantage of speed and accuracy, UT now makes radiography redundant as the
primary inspection method on mainline construction where mechanized gas metal arc welding (GMAW) is
used. In 1993 TCPL introduced an inspection specification for mechanised girth welds. TWE-1 details the NDT
requirements for total weld evaluation and acceptance criteria applied to all mechainzed girth welds. Evaluation
is based on results of mechanised ultrasonic testing and visual inspection. Radiography is not a requirement of
the specification but can be used as a Quality Assurance check on the system. The specification outlines all
aspects of the UT inspection including qualification tests for new systems and new operators.
The inspection principles have been previously described by the authors (1) and are summarized as
follows;

AT WELDING DEFECT
ISSUED BY : GANZORY
The weld is divided into several zones (see Figure 1). Each zone covers approximately 2-3 mm of thickness of
the weld. Ultrasonic transducers are designed and positioned to investigate each zone from both sides of the
weld centreline (See Figure 2). The array of probes is moved around the girth weld by a motorized carrier which
moves along the same track the welding apparatus uses. Ultrasonic signals received by the instruments are
monitored by electronic gates. Both amplitude of signal and time of flight of the signal in the gated region are
monitored. The region gated is from just before the weld preparation line to just after the weld centreline. Gated
output, either time or amplitude or both, is digitized and displayed in a chart format. An operator evaluates the
chart results and makes a decision as to weld acceptability based on the length of signals exceeding a threshold
as set out in specifications and regulating codes.
Figure 1 Weld Zones - Schematic Representation of GMAW Discontinuities

Figure 2 Centre of Beam Ray Trace to Target Areas in the Zones (courtesy RTD Quality Services)

Inspection systems using these principles have proved to be very effective and statistics have shown good
correlation with most radiographic calls made. The advantages of the system are speed and accuracy; e.g. a 48"
diameter weld can be scanned AND ACCURATELY EVALUATED in about 2 minutes. Inspection is carried out
as soon as the metal temperature has cooled sufficiently to permit the probes to be placed on the metal (typically

AT WELDING DEFECT
ISSUED BY : GANZORY
four to five welds behind the last welding crew). With inspection results available so readily the UT system
provide a process control for the welding.
Not only does the system locate the defective areas along the length of the weld but by means of discrete zone
discrimination it can also establish the vertical position and vertical extent of the defect. This latter advantage
over radiography permits more precise engineering evaluation as to the seriousness of the defects located.(2)
This is the principle of the applied Engineering Critical Assessment (ECA).
Maintaining zone discrimination is a critical aspect of the technique. Problems encountered in the early stages
of development led to the discovery that velocity variations were causing significant zone changes of the beams.
These variations in velocity were from two sources; steel type and temperature. Acoustic velocity variations
from 3100m/s to 3400m/s were found to exist in the steels from various pipe mills. As well, the effect of
temperature on the acoustic velocity of the perspex refracting wedges became significant. For example; in
winter projects the ambient air temperature can drop to -50(C while the steel temperature after welding is
around 40(C. Winter projects require use of heated calibration blocks and 60% methyl alcohol in water is used
as a recyclable couplant.

Recent Developments
The earliest forms of data acquisition were described for the RTD Rotoscan system in the early 1980s (3,4).
These systems used only amplitude output to a chart recorder. This effectively provided a go/no-go criteria for
the operator to base evaluation on. Since signals from geometric reflectors such as root bead surface and weld
cap can occasionally enter the gated region the early go/no-go system was subject to numerous false alarms. To
provide another tool for the operator to eliminate these false alarm calls, chart display of signal transit-time in
the gate was an added feature of the inspection system in the late 1980's. With these tools it was then possible to
identify defects other than non-fusion including centreline cracking and porosity.
Development of ultrasonic girth weld inspection systems has continued in an effort to improve reliability of
evaluation, as well as detection of flaws and sizing of defects. This development has taken the form of increased
data acquisition. Increasing the amount of information provides the operator with a better opportunity to make
accurate evaluations. However, the speed of inspection cannot be compromised by slower acquisition speeds
nor can the inspection time be increased by the operator spending more time sorting through more data. Only
with the developments in computer technology have these two problems been overcome.
Aspects of recent developments can be grouped into three areas;
Mapping enhancements
Video evaluation
Mass storage
Mapping Enhancements
Normal manual inspection, using angulated shear wave ultrasonics, characterizes defects by the form of the
echo signal on the screen (A-scan) and its behavior as the probe is moved relative to the defect; lateral, forward
and back, pivoting and orbiting motions being used. The changes in time and in form that the signal goes

AT WELDING DEFECT
ISSUED BY : GANZORY
through during these probe movements is sometimes called "echo dynamics". Based on the echo dynamics of
the signal a good operator can reliably characterize a defect as to its type, size and orientation.
Unlike manual scanning, in the mechanised UT systems only lateral motion is possible as the probes are moved
around the weld. The echo envelope that is provided as the hard copy of the output for the gated peak amplitude
and transit time is used by the operator to evaluate the weld. If the operator had the ability to follow the subtle
changes seen on the A-scan presentation used by manual ultrasonic inspectors it would afford some of the
advantage of echo dynamics seen by the manual scanner. The use of echo dynamics incorporates how a signal
of interest moves with respect to not only probe movement but also to any other signals that may be present on
the screen. The operator of a mechanised system would be given a further advantage if the whole A-scan could
be collected instead of just the maximum amplitude and time in a gate. This can be done and the result of
stacking collected A-scans is usually termed a B-scan. Some (5) differentiate between a B-scan which is
generated when the probe motion is at right angles to the weld axis and a D-scan where probe motion is parallel
to the weld axis, but generally B-scans are considered stacked A-scans irrespective of the direction of probe
movement.
Only with the recent availability of high speed computer hardware and increased storage capacity has the
possibility of B-scan presentations on multiple channels been practical. This B-scan mapping, when used in
conjunction with the amplitude and transit time information, allows the operator to see trends associated with
geometries and to differentiate geometric reflectors from defect reflectors.
Figure 3 illustrates root bead misalignment and the improved ability to discern that from a root defect.

36KByte
Note: Mapping and amplitude/transit-time channels are arranged symmetrically on either side of the root bead
map channels in the middle of the image. Amplitude of signals in the gate is represented by dark solid lines in
the Root, LCP, Hot pass and Fill channels. Transit time of signals in these gates is represented by bands of greyshading.
An example of porosity found in the root bead is shown in Figure 4.

25KByte
Symmetry of the porosity indication in Figure 4 would be the same sort of evidence used to evaluate porosity
when seen in the porosity maps for the Fill regions of the weld.
Video Evaluation

AT WELDING DEFECT
ISSUED BY : GANZORY
Video monitoring of parameters is now commonplace in a wide variety of industrial applications including
electric power plants, chemical process lines and pollution control operations. The term given to this display is
generically called "mass data display". Each graphical element of the display represents a value from the
process. Each element is constant in its overall shape but is dynamic in behaviour. For example; lines can vary
in thickness with deviation from a reference value, or blocks of colour can change colour as a parameter
changes. The advantage of mass data display is that the human eye and brain can process thousands of graphical
elements in parallel and pick out abnormal regions. Arranging the data in an aesthetic logical fashion allows the
operator to identify areas of concern by deviations in pattern or colour.
An operator inspecting a heavy wall linepipe girth weld (about 17mm thick) may have 18 amplitude and time
channels to monitor as well as four B-scan channels plus coupling monitor channels. Fitting these all onto the
hardcopy and evaluating the results would suffer two main problems. First the delay of waiting for the hardcopy
increases time spent on the weld. Secondly, fitting over twenty channels of information on an 8 inch (20cm)
wide piece of paper provides the operator with very small traces to examine.
To overcome these problems operators now use large screen monitors to display the information. Twenty inch
(50cm) monitors or larger allow nearly double the size of image to look at compared to paper hardcopies. Also,
the images on the screen are in colour. This feature can be used to bring the operator's attention to potential
problem locations. As the scan progresses information is buffered and the data scrolls off the screen. When the
scan is completed the operator can scroll the data up and down and use tools such as magnification windows
and individual A-scan viewing. With the colour enhancements and larger image, an operator now makes all
evaluations based on the video image. The paper hardcopy is merely printed as a permanent record and stored as
per the regulatory requirements of the governing body.
Mass Storage
When amplitude and transit time are the only data collected at each data point only 1 byte of memory is needed
per data point. With a data point every 2mm and 16 probes collecting data a typical 42" diameter pipe would use
on the order of 30 kilobytes of memory. However, when four or more B-scans are added to the data acquired the
memory requirements increase greatly.
Calculating memory requirements for B-scans requires a knowledge of several items.
Digitizing an A-scan is the first step in constructing a B-scan. But each sample must be saved to computer
memory, therefore larger scan lengths and larger time of the gated period, require more memory than small
scans and short gated times.
For a simple B-scan using a 4 MHz contact 70 angle beam probe on a 16mm thick plate we would like to gate
the entire half skip distance for display. We would use the recommended minimum ADC rate of 16 MHz. We
must also consider that nearly 100mm time equivalent is traversed by the transverse wave (two way trip in
pulse-echo); hence (50 x 2) ( 5.9 = 31.3 microsecond (s).
At 16 MHz ADC 16 samples are made each s, so for the gated time of 16.9s, 500 samples will be recorded
for each A-scan. At each point 8 bits of amplitude information are collected (8 bits = 1 byte). If our B-scan is to
be collected along a 42" diameter weld, a 3400mm travel is needed. If an A-scan is collected at 1mm intervals,
the data generated would be:

AT WELDING DEFECT
ISSUED BY : GANZORY
500 x 1 x 1 x 3400 = 1 700 000bytes (1.7MB) the first parameter is 500 points per A-scan
the second is 1 byte per sample point on each A-scan the third is the number of A-scans
per mm (1) 3400 is the length of the scan in mm
A single 42" weld with both the traditional amplitude & time strip-chart style information plus four Bscans could result in a data file of over 7MBytes.
RTD files require setup parameter information as well as data file information but typically on the order of
1Megabyte per weld is stored in a 42" diameter weld. This significant reduction of file size is possible by a
clever technique that stores only a bit mapped image of the amplitude along the gated region collected by the
flash digitizer for each B-scan map plus the traditional amplitude and transit time stripchart information.
Although the entire waveform is not stored there is sufficient information for the operator to see trends
associated with geometries such as weld root bead and weld cap and it would be rare for the operator to need to
review the waveform. This B-scan map would be similar to the B-scan described by McMaster back in 1959.
Shaw Pipeline Services saves the entire A-scan but also achieves much smaller file sizes by employing
data compression for saving the files.
Even with the reduced file size technique used by the two companies, production rates of 150 to 200 welds per
day could result in a large stack of floppy disks for data storage. Hard disk drives of 1000MB are now common
but the rugged terrain that the system is subjected to presents a risk of damage to the hard drive. To avoid
potential data losses the mechanised systems now ensure backup files are made. The backup systems used are
either Bernoulli drives or Optical disks. The operator transfers files from the system hard drive to the removable
mass storage system one or more time each day thereby minimizing the number of files that could be lost. This
storage to other locations also speeds up the process as it requires more time to save a file as the hard drive gets
filled.

Extremes in Test Conditions

105 Kbyte
55 Kbyte
Figure 6: UT inspection truck ready
Figure 5: Positioning scanning
head on 48" diameter pipe on the to test within five welds of last weld
Canadian prairies. Daytime summer completed. Winter work in rock cuts
in the Canadian Shield near the
temperatures often reach 35to
Manitoba-Ontario border (Shaw
40C. (Shaw Pipeline Services)
Pipeline Services).

65 Kbyte
Figure 7: Loading the scanning head
on a 42" diameter pipe in the winter
northern Ontario. Equipment must
also be able to perform under
conditions of daytime highs of -40C.
(RTD Quality Services Ltd.)

Future Developments
In their earlier discussion (1) the authors speculated on the application of Time of Flight Diffraction (TOFD)
techniques being used on pipeline girth weld inspections. Many of the computer advancements that have made
the above developments possible have also been prerequisites for TOFD being applied to pipeline girth welds.

AT WELDING DEFECT
ISSUED BY : GANZORY
In a recent study by one of the authors (Ginzel), a 20" diameter girth weld was tested using a modified
immersion technique. All significant defects identified by radiography were detected and sized using the TOFD
technique (See Figure 8). When used independently the TOFD technique does not identify the side of the weld
where a defect is located. This drawback can be addressed by using two or three pulse-echo probes on either
side of the weld and collect the amplitude and time response as in the present systems. The requirement for
pulse-echo probes is also practical for areas where high-low conditions could mask flaws from the TOFD setup.
Figure 8 TOFD B-scan of a 20" Girth Weld (8.6mm wall)

28KByte
TCPL's TWE-1 specification is a very comprehensive specification and only minor modifications would have to
be made to address inclusion of TOFD technique.
The single greatest advantage of TOFD is its ability to precisely provide accurate vertical extent of a defect.
Accuracies of 0.1 to 0.2 mm are possible using TOFD. This could greatly extend allowable defect lengths in
Engineering Critical Assessment calculations when applying the code CSA-Z184 (6 or the newer ISO/CSAZ662 which combines both gas and oil pipeline construction.
Application of mechanized UT systems will, in future, need to adapt to other welding technologies. Until 1995
only one company provided a mechanized welding process used in Canada. This American company has
provided mechanized welding on projects all over the world but ironically it is not used on pipeline construction
in the USA. More recently two other systems have been developed, one from Italy and another from France.
These have slightly different configurations but inital studies on pilot projects indicate mechanized UT will be
as effective for these new systems as it has been for the older system.

Conclusions
Despite the fact that an effective specification (TWE-1) and apparatus (mechanized UT for mechanized GMAW
girth welds) have been adopted and proven reliable, efforts continue to improve the system. More information is
now collected making evaluations even more reliable. Although there is more information collected, collection
speed and analysis of the results have not been compromised.
Mapping enhancements, video evaluation techniques and mass storage of data have been features added to the
systems. These have all been based on computer technology developments which will probably be the
foundation for future development. Future improvements may require that even more information be acquired.
If this presents the operator with a longer required evaluation time it may be necessary to increase data
collection speeds. This would mean the probe arrays would be moved faster. Not only will there be mechanical
concerns to consider such as maintaining coupling and inspection apparatus integrity, there may also be a need
to use faster digitizing boards, faster CPU's and higher pulse-repetition frequencies in the ultrasonic pulserreceiver.

AT WELDING DEFECT
ISSUED BY : GANZORY
Although these potential developments may change the appearance of the apparatus seen on the pipeline rightof-way, the existing specification will be able to address nearly all future development without significant
modification.

Acknowledgments
The authors would like to thank RTD Quality Services Ltd. of Edmonton, Alberta, and Shaw Pipeline Services
Ltd. of Calgary, Albetrta, for their continued cooperation in developing pipeline girth weld inspection. The
authors would also like to thank TransCanada PipeLines Limited for their ongonig efforts to promote ultrasonic
inspection in the pipeline industry.

Você também pode gostar