DEVELOPER:
WISE Trust
LANDOWNER:
WISE Trust
TENANT:
WISE Group
PROJECT
MANAGER:
Arrow International
DESIGN:
Sekta Architects
ENGINEERING:
Innerscape
SUSTAINABILITY
CONSULTANT:
Connell Wagner
CONSTRUCTION: Arrow International
COMMISSIONING
AGENT:
Encom
ACOUSTIC
ENGINEER:
TOTAL NLA:
Design Acoustics
2,910m2
The 4 Green Star rating for Kakariki House is the start of a longer green
journey
for WISE. Were really committed to this. Wed like to aim for an
even higher rating. Its not just about having a green building; its about
working and living sustainably.
- WISE Joint Chief Executive Julie Nelson.
OFFICE
POINTS ALLOCATION
CATEGORY
TOTAL POINTS: 46
5 10
0POINTS
15
20
25
30
Management
DESIGN V1
BUILT
IN USE
INTERIORS
Indoor
Environment
Quality
Energy
Transport
ENERGY
Reduction in operational energy and greenhouse gas emissions
Heat recovery ventilation, economiser free air cooling and automatic fresh air controls
Lighting power density lower than a conventional building
Control zones for lighting are no greater than 100m throughout the building
Tenancy sub-metering incorporated
Meeting room occupancy sensors to reduce energy use of lighting and HVAC systems
Water
Materials
TRANSPORT
At least 25% of car parking spaces are designed for small cars
The building is located within close proximity to public transport
Land Use
& Ecology
Emissions
Available
Achieved
WATER
Low ow water ttings used throughout (WELS 4 star)- consumes 40-50% less water
than a conventional building
Extensive hot and cold water metering via a building management system, including
leak detection
Use of drought tolerant plants, requiring no additional watering once established.
No cooling towers were used reducing water consumption
MATERIALS
Over 90% of the existing structure reused
Over 60% of the existing faade reused
Oce t out fully integrated with base building works ensuring ecient resource use
Over 60% less PVC used compared to a conventional building
All carpet and paints are Environmental Choice NZ certied
LAND USE & ECOLOGY
The site had been previously developed thus avoiding encroachment on green eld land
There was minimal ecological impact resulting from the project
EMISSIONS
All refrigerants have an ozone depletion potential (ODP) of zero
Outdoor lighting designed to reduce obtrusive eects
No cooling towers used in the air conditioning system, preventing process waste heat
being released into the atmosphere
Water ow to sewers reduced through low ow ttings
Going green was not a dicult decision to make. Nor was the decision to recycle as
much of the existing building as possible. It wasnt the easy option or the cheapest
one but it was the right thing to do
- WISE Joint Chief Executive Jacqui Graham.