Escolar Documentos
Profissional Documentos
Cultura Documentos
August 1999
Prepared by Allegheny Power's Operations Planning Section of the System Planning and
Operations Business Unit
Project Description
The concept is shown on the sketch on the following page. As indicated, the two
57 MVA GT sets would be located about 1000 ft from the Springdale 138 kV bus. Each
generator would consist of 48 MW winter or 44 MW summer, gas combustion turbines
operating at 0.85 power factor. The units are designated as peaking units and will
probably operate during peak usage hours, approximately 2,000 hours per year per
unit. Service to the units will be provided by a single 138 kV line terminating on a
single 138 kV circuit breaker, and will include a 138 kV metering package. The
destination of output from the generators has not been designated and, therefore,
many assumptions were required in order to complete the study. They are listed in the
next section.
RIVER-
WPPCO
CUSTOMER
FIGURE NO. 1
CROSSING
STRUCTURES
RIVER-
NUG
1000 ft
CROSSING
HILL
STRUCTURE
STRUCTURE
KIT
TAN
NIN
G
KIS
KI V
ALL
EY
GOBAIN
SPRINGDALE
N.O.
T.
LS
RA
E
D
FE
EY
LL
VA
138 kV
HU
NT
IN
GD
YU
ON
KO
N
RIVER
TE
HI
W
NO.1A
HARWICK
YARD
TOWER
YARD
TOWER
WPPCO
DLCO
CHESWICK
138 kV
10/15/99
SOURCE
SPRINGDALENUG.PPT
REVIEWED
DATE
SPRINGDALE SUBSTATION
INSTALL 138 kV BREAKER AND METER TO
INTERCONNECT WITH NON UTILITY GENERATION
ARNOLD SERVICE CENTER
8-25-99
P. L. ZAWELENSKY
CHKD
SCALE
NS
AUTHORIZATION
REV
APPROVED
PL A N
DRAWN
PLAN NUMBER
CAD FILE
Allegheny Power
99-x-W
T. V. SPENCER
Results
The Feasibility Study (FS) results indicate that AP can accommodate the
Allegheny Energy Unit 1 and Unit 2, LLC\ESD request for interconnection of two 57 MVA
LM6000 GT sets.
Both power flow and short circuit studies indicate that the installation has no
detrimental effect on the AP transmission system. However, Allegheny Energy Unit 1
and Unit 2, LLC and ESD need to be aware that in the event that there is congestion on
the Eastern Interconnection, generation dispatch out of Springdale at times might be
restricted. In that case, AP will follow the North American Electric Reliability Council's
(NERC) Transmission Line Loading Relief Procedure (TLR) and the guidelines set forth
within that procedure. A copy of this procedure can be downloaded via the Internet
from the NERC website at http://www.nerc.com. Additionally, Allegheny Energy Unit 1 and
Unit 2, LLC or ESD may choose to implement the NERC Market Re-dispatch or the AP
Security Coordinator might implement the Lake Erie Emergency Re-dispatch (LEER)
procedures that may require the units at Springdale to operate. Allegheny Energy (AE)
has incorporated these procedures in its Open Access Transmission Tariff (OATT).
More information on the NERC market re-dispatch procedure can be obtained from the
NERC website at http://www.nerc.com. Information on the LEER can be obtained from
your companys representative to the Lake Erie Security Process committee, or from the
FERC-filed LEER proposal.
Assumptions
All future studies require assumptions concerning the control area load, facility
additions and transmission sales. This analysis is no exception. The most recent
System models, the 1998 series, from the base case database for the 1999 summer,
2003 summer and 2008 summer seasons were selected as those to be tested. AP
control area loads in those models ranged from 7,200 MW in the 1999 summer model
to more than 8,000 MW in the 2008 summer model. Facility additions were assumed to
be those as planned in the 1998 series of cases that followed the 1998-planning guide.
Note that during the period studied there is no expectation that the existing Springdale
Units 7 & 8 will be reenergized; so they were not modeled in this analysis. A quick
review of data indicates that AP, PJM, FE and DQE plan no major facility additions.
However, AEP and VP are planning to install major system additions in the Appalachian
Power Company Area of AEP and the northern area of Virginia Power Company. Those
planned facilities are modeled in the 2008 summer model but not in the 1999 summer
or the 2003 model. Transmission sales modeled for those years are those included in
the summer base case models and include only confirmed firm service reservations.
The destination of the power output from the proposed GT sets at Springdale is
unknown. Therefore, several transfer scenarios were assumed. Output from the GT
sets was assumed to stay within the AP control area, or alternatively to be sold offsystem to the west or to the east. Those additional tests modeling the output from the
Springdale site to the east assumed the power was being sold to PJM, while those that
took the power west modeled a transfer into DQE.
Springdale 138 kV
Three Phase Fault
Phase to Ground
Fault
Springdale (G1)
13.8 kV
0 Amps 0
0 Amps 0
* Note: It was assumed that a grounding resistor of 100 ohms is installed on generator
neutral.
**Note: The value used for the short circuit study (71.2 MVA) differs from the value
used for the steady state power flow analysis (57 MVA). This is necessary
because of differently sized equipment in the generation facilities.
Stability Considerations
The transmission system is designed so that generating units remain in
synchronism and that cascading outages do not occur for credible contingencies such as
electrical faults or sudden network changes caused by fault clearing and line reclosings.
Transient stability simulations are made to assess expected performance of
generating units when the transmission network is subjected to severe disturbances.
Test results are used to determine critical fault clearing times and the ability of the
system to prevent cascading outages. They are also used to study the effectiveness of
alternative transmission plans to optimize the system's transient performance. Since it
is impossible to anticipate and test for all combinations of contingencies that could
occur on an interconnected network, those cases judged to be less severe, using APS
transient stability criteria as a guide, are not routinely tested.
There are also many areas of the system, which are considered strong enough to
support the proposed amounts of generation without the need for stability analysis. It
may, therefore, be deemed unnecessary to perform any stability simulations and will be
evaluated on a case by case assessment.
Transient stability testing was not done as part of this study because the Project
generators are relatively small and, therefore, should not cause stability concerns for
any APS units.
When the proposed generating station is designed and dynamics data for turbine
generators are available, the Developer should perform a transient stability study to
determine critical fault clearing times and effects of line reclosings on the transient
stability of the Project units. In addition, any updated dynamic machine data should be
forwarded to Allegheny Power.
10
11
2.
3.
4.
5.
Transfer Capability
Fault Currents
Switching Surges
Power Quality
12
1.
INTRODUCTION
Bulk power planning and operating procedures consistently include reliability as one of the essential measures
of system performance. AP meets the need to expand and upgrade its transmission system by developing plans
using criteria that provide for continued reliable operation consistent with economic and regulatory constraints.
This document presents the reliability criteria used by AP to expand and upgrade the bulk power system of
lines and substations above 100 kV.
Transmission system expansion plans are developed with the goal of minimizing revenue requirements, which
include both capital and operating costs while meeting planning criteria that deal with maintaining acceptable
system performance. The proper application of transmission planning criteria requires substantial engineering
judgment based upon numerous and extensive studies of the system by the planning engineer. Prudently
managed utilities rely on their planning engineers' knowledge, experience, and judgment in applying the
criteria to specific circumstances on the transmission system. For this reason, it is simply not possible to
document all the criteria that may be used to decide the way in which a system is developed and expanded.
To understand reliability in system performance requires an understanding of how reliability affects a system.
The primary reliability objectives are adequacy and security. They can be defined as follows:
Adequacy - which is the capacity to meet system demand within major component ratings in
the presence of scheduled and unscheduled outage of generation and transmission
components or facilities, and
Security - which is a system's capability to withstand system disturbances arising from faults
and unscheduled removal of bulk power supply elements without further loss of facilities or
cascading outages.
In order to evaluate the reliability of a system, it is necessary to have benchmarks or criteria to determine the
levels of adequacy and security in a system.
13
1.
INTRODUCTION (continued)
The criteria in this document are based on AP and industrywide experience with equipment performance and
acknowledges the need to provide operating flexibility for maintenance outages while limiting customer
interruptions and the time required to restore service. Thus, various segments of the supply system will have
increasingly stringent reliability criteria as one moves from lower to higher system voltages involving greater
numbers of customers. Determination of the level of reliability that is acceptable depends upon what our
customers are willing to pay for and ultimately upon the regulatory commissions and their decisions granting
construction licenses and rate increases.
The following general planning objectives evolved and have been refined through years of experience to
achieve the objectives of maintaining acceptable system performance through an adequate and secure system
for the least cost. These objectives define the conditions under which a facility reinforcement would be added
to the transmission system.
The facility must represent an economical method to provide dependable service to our customers within
the constraints of regulatory, environmental, and political guidelines.
The facility should be sized to meet growth needs according to the AP load forecast while providing an
optimum level of reserve capability.
The facility installation should be timed to maintain reliability and minimize cost.
All feasible alternatives should be considered in planning a new facility. This includes, but is not
limited to, new technology, innovative applications of existing technology, controlling load growth, and
automation of controls.
14
1.
INTRODUCTION (continued)
Interconnected transmission facilities, in addition to meeting AP criteria, must meet or exceed reliability
criteria as established by the East Central Area Reliability Coordination Agreement (ECAR) Document No. 1
and the North American Electric Reliability Council (NERC) Planning Standards. These documents provide
reliability criteria that are designed to test the ability of ECAR member systems to withstand certain
contingencies without triggering a breakup and collapse of any major part of their bulk power supply network.
ECAR Document No. 1 is included in these criteria as Appendix A and the NERC Reliability Principles and
Guides as Appendix B.
Existing regulatory and environmental constraints such as the inability to obtain right-of-way can lead to
conditions that do not meet our planning criteria. The degradation of reliability levels caused by these
conditions must be recognized as such and not used as examples to justify subversion of reliability levels in
other areas of the system.
The testing done on the transmission system is by mathematically modeling the system and solving the various
simulated conditions on a computer using the power flow and transient stability programs.
The following represent the AP transmission planning criteria and are more fully discussed in Sections 2
through 5.
15
2.
2.2
Generation
All available generators are fully dispatchable to their normal seasonal operating capacity and
can regulate to the scheduled voltage.
16
2.
2.2.3
2.3
2.3.2
17
2.
2.3.4
Customer Loads
No customer should be interrupted by the contingency unless directly connected to the outaged
facility.
2.4
2.5
18
2.
2.6
Outage of transmission line, including double circuit tower line, when various generators are
unavailable.
2.7
NERC TLR
The FERC Transmission Line Loading Relief (TLR) procedure provides the means by
which transfers can be controlled and or removed to maintain transmission system
security. Substantial amounts of power continue to flow through the transmission
system and are considered inadvertent flows caused by power transfers that are not
contracted through the AP transmission system. With the implementation of the
NERC TLR, AP has been able to seek relief during periods of heavy transfers but may
19
System reactive compensation with adequate controls will be planned to supply the reactive
load and loss requirements of the system and to maintain acceptable voltage profiles as defined
in Sections 2 and 3 of this chapter for:
2.8.1.1
Normal conditions.
2.8.1.2
2.8.2
Currently shunt capacitors are used in conjunction with generators and line
charging reactance to supply transmission system var requirements. Static var
compensators and synchronous condensers may be used if instantaneous
reactive response is required for widely varying var load and where their very
high costs can be justified.
2.8.3
Each area or system should provide its own reactive load and reactive loss
under normal operating conditions.
2.8.4
Switched capacitors should not cause more than a 3% voltage rise under normal conditions
with all facilities in service.
20
requirements
3.
3.2
3.1.1
3.1.2
3.1.3
3.1.4
Primary protective relaying scheme inoperative: a permanent three-phase or single-phase-toground fault on any line or transformer cleared by primary protective relaying at one end of the
line, and backup or slower relaying at the other end.
21
4.
Transfer Capability
Transfer capability is used to assess and test the ability of the interconnected transmission network to
move power between entities, companies, regions, subregions, pools, etc. Sufficient transfer capability
is typically based on the ability to receive support from nonaffiliates during a generation capacity
emergency.
The criteria used by AP were adopted from the NERC transfer capability definition as recommended in
the NERC publication, "North American Electric Reliability Council Transmission Transfer Capability
(Appendix D). These criteria also are commonly used by interregional study groups such as the
VACAR-ECAR-MAAC (VEM) and MAAC-ECAR-NPCC (MEN) study committees. The First
Contingency Incremental Transfer Capability (FCITC) is defined by NERC as the power, incremental
above base transfers, that can be transferred in a reliable manner under the following conditions:
4.2
4.1.1
With all transmission facilities in service, all facility loadings are within normal ratings, and all
voltages are within normal limits.
4.1.2
The bulk power system is capable of absorbing the dynamic power swings and remaining
stable following a disturbance resulting in the loss of any single generation unit, transmission
circuit, or transformer.
4.1.3
After the dynamic power swings following a disturbance resulting in the loss of any single
generating unit, transmission circuit, or transformer, but before operator-directed system
adjustments are made, all transmission facility loadings are within emergency ratings and all
voltages are within emergency limits.
Fault Currents
Three-phase and single-line-to-ground short circuit currents and sequence voltages during faults are
calculated for each bus on the transmission system. Fault current values are used to check the short
circuit adequacy of equipment for system protection and protective coordination, and to determine
electrical system strength at various locations on the system.
4.3
Switching Surges
Switching surge studies are performed to determine transient and dynamic overvoltages and circuit
breaker recovery voltages during switching. These studies provide recommendations for switching
devices and allowable switching sequences which limit overvoltages on transmission system
components to levels within the equipment manufacturer's specified operating range. The studies also
facilitate selection of surge protection devices that provide proper protection and have adequate power
dissipation capacity.
Existing equipment capabilities and insulation coordination requirements determine acceptable transient
and dynamic overvoltage limits.
22
4.
Power Quality
The transmission system is designed to provide acceptable power quality. In addition
to optimal adequacy and security of the power supply, the system is designed so that voltage fluctuations
or total harmonic distortions of voltages are limited to the following levels:
4.4.1
Voltage Fluctuations
Voltage fluctuations or voltage flicker due to rapidly changing load is limited to a level, which
will not exceed the company guidelines shown in Appendix E.
4.4.2
Harmonic Limits
The harmonic currents that an individual customer injects into the AP transmission system, as
measured at the point of common coupling, shall not exceed the limits established by the
company as shown in Appendix E.
4.4.3
4.4.4
4.4.5
Facility Outages
Lower levels of power quality can be tolerated when significant elements of the supporting
transmission system are out of service.
23
5.
EHV
5.1.1
5.1.2
5.2
Lines
5.1.1.1
For reliability reasons, AP prefers to use only single circuit tower construction for
500 kV lines and will use single or double circuit construction on 345 kV as the
need arises.
5.1.1.2
EHV lines should be routed on exclusive right-of-way in which any parallel lines
are of a lower voltage class, the exception being the approach to a substation.
5.1.1.3
Line crossings should be avoided and EHV lines should always occupy the highest
position when crossing lower voltage lines.
Substations
5.1.2.1
The preferred bus configuration for EHV substations is "breaker and a half" when
more than four lines terminate on the bus. Most stations start out as ring buses and
evolve to "breaker and a half" as terminal positions are added.
5.1.2.2
Transformer positions can be located on the buses, in the "string," or split between
the two.
5.1.2.3
Source lines and load lines should occupy alternate positions around a ring bus or
be paired together on a "breaker and a half string."
5.1.2.4
5.1.2.4.2
Third and fourth transformers are added when the loss of one
transformer causes the remaining ones to load above their continuous
rating.
Area
5.2.1
Line Configuration
5.2.1.1.
24
5.
Area (continued)
5.2.1
5.2.1.3
Radial Lines
Radial or a single transmission line supply to substations may be justified for an
interim period when existing lower voltage lines can supply the substation load for
the outage of the radial line.
When the substation load exceeds the capability of the lower voltage supply to
provide backup for loss of the transmission supply, a second transmission supply is
planned. Justification of a second line is based on reliability versus economic
constraints with consideration given to the probability and timing of future area
loads.
5.2.1.4
5.2.2
Substation Configuration
Substations are an integral part of the area transmission network and interface the transmission
system with the subtransmission and distribution systems. Substations are developed in
coordination with the area transmission system to meet thermal, voltage, and other reliability
criteria.
5.2.2.1
Optimum Design
An area transmission substation is designed for two or more transmission line
terminals, multiple bus sections, and at least four transformers to serve a minimum
of 100 MVA load. The load may be served from local distribution circuits, the area
subtransmission system, or a combination of both.
25
5.
Area (continued)
5.2.2
Line Terminals
Terminal switching facilities for the transmission lines are either automatic
switches, circuit switchers, or circuit breakers as determined by system
configuration and the ability of the protective relaying scheme to isolate a faulted
line, bus section, or transformer.
5.2.2.3
Bus Sections
Bus sections are connected by automatic bus tie switches or circuit breakers as
determined by system configuration and the ability of the protective relaying
system to isolate a faulted line, bus section, or transformer. An effort is made to
minimize the number of lines and transformers connected to each bus section.
5.2.2.4
26
APPENDIX A
ECAR DOCUMENT NO. 1
Copies of this reference document can be viewed, printed or printed from the ECAR home page on the internet @
http:\\www.ecar.org.
September 1997
(Included by reference.)
Copies of this reference document can be viewed, printed or printed from the NERC home page
on the internet @ http:\\www.nerc.com. Or can be obtained from the North American Electric
Reliability Council (NERC) by request from the following address:
NERC
116-390 Village Boulevard
Princeton, New Jersey 08540-5731
Telephone: (609) 452-8060
Fax: (609) 452-9550
APPENDIX C
RELIABILITY COORDINATION PLAN
APS/PJM/VAPWR
RELIABILITY COORDINATION PLAN
(RCP)
REVISION 4
From
APV Operations Analysis Group
On
December 11, 1992
As Approved By
The APS/PJM/VAPWR SYSTEM PERFORMANCE
STEERING COMMITTEE
On
January 26, 1993
6/01/88
8/17/88
6/01/90
11/01/90
A:\RCP\COVER.293
cdm:02/93
APS/PJM/VaPwr
RELIABILITY COORDINATION PLAN (RCP)
Rev. 0
Rev. 1
Rev. 2
Rev. 3
Rev. 4
6/88
8/88
5/90
11/90
12/92
1.0 PURPOSE
The RCP outlines steps to be taken to avoid or remedy unreliable operation on the interregional bulk power
transmission system.
2.0 GENERAL
2.1 THERMAL OPERATION - The APS/PJM/VaPwr bulk power transmission system shall be operated so
that no bulk power transmission facilities exceed their normal rating on an actual basis and so that no facility will
exceed its emergency rating (as determined by the "control area" owning the facility) following the sudden loss of
any single generation or transmission facility.
2.2 VOLTAGE/REACTIVE OPERATION - The APS/PJM/VaPwr bulk power transmission system shall be
operated so that the actual and post-contingency voltage/reactive requirements of the control area owning the facility
are not violated.
2.3 NOTIFICATION - It is the intent of this plan that the initiating control area will notify all other
participants of implementation or cancellation of any level of this plan. The participants are defined as AEP, APS,
CEI, DL, OE, PJM, and VaPwr. In addition, the ORNS teletype should be used to notify ORNS members of the
implementation or cancellation of Levels II and IV. It is the responsibility of each control area to notify their
appropriate operating company personnel.
2.4 APS, PJM, and VaPwr Operation Planning groups shall regularly examine system conditions and provide
the system operators with procedures and methods to assure that the system will be operated reliably.
2.5 APS, PJM, and VaPwr System Operations shall communicate the current and expected reliability status
of their system to all neighboring systems.
2.6 APS, PJM, and VaPwr System Operators shall react as requested when a reliability violation is declared
by another system. However, a control area may notify the requesting control area that it is unable to comply if the
requested action will cause a reliability violation on its own system. The requesting control area should supply as
much information as is readily available about the system conditions. Disputes and any in-depth analysis questions
should be resolved after actions have been taken and the system has returned to a reliable state.
3.0 APS/PJM/VaPwr TRANSMISSION LIMITS
The operation of APS, PJM, and VaPwr can be affected by internal or external transmission limits. These
limits can be of a thermal nature (actual or post-contingency overloads), of a reactive nature (actual or
post-contingency voltage criteria violations), or of a steady-state stability nature (large system angular differences).
The system owning the limiting facility is responsible for detecting the problem, determining the indicator of
the limit and initiating the levels of this plan required to assure reliable operation. When possible, limiting
conditions should be anticipated in advance of each operating season and reviewed for appropriateness by all
participants of this agreement. Identification of anticipated limits and preliminary corrective strategies should be
included as a part of this document.
to maintain reliable and, to the extent consistent therewith, economical operations. Until superseded by revision of
this RCP, the agreed Curtailment Reference Value for each participant is:
PJM
Rev. 4
12/11/92
= 2245 MW
APS-VAPWR
VAPWR
= 300 MW
= 1300 MW
Prior to implementation of any step of this plan, the control area initiating the plan shall verify that all
actions or coordination that do not involve an economic penalty have been utilized to mitigate this condition. This
includes the use of "Heavy" Reactive Support under the Voltage Coordination Plan (VCP).
As conditions permit, purchase restorations shall be permitted in Level I. All cuts from
Level II and III actions are restored in Level I. If curtailments took imports below CRV
for one or both control areas, one control can restore up to the same percent of CRV as
the other control area before sharing the restoration in the ratio of the curtailments. After
all cuts are restored, notify ORNS that we are no longer requesting a restriction of
transfers.
Increases -
After all cuts have been restored and as conditions permit, purchases that are to be
increased are in the ratio as defined for the current contingency limit and transfer level.
Purchases to increase a participant's imports up to its CRV will be permitted prior to the
increase of purchases that would exceed a participant's CRV. If both control areas are
held below their CRV, the one with the lowest percent of CRV loaded may first increase
its purchases up to the same percent of CRV as the other. The two control areas would
then be allowed to increase purchases in the curtailment ratio as defined for the current
contingency limit.
NOTE: The initiating control area is responsible for contacting each importing area each time an increment of
transfers can be safely added to the schedules. No controlled transfers may be restored or added without
the consent of the declaring area. Level I is ended after all desired schedules have been loaded and
critical facility loading are stabilized below the current Level I trigger point.
Continue to review conditions. If conditions initially prevented a control area from full
compliance of Level II curtailments, move toward redistribution of curtailments to the
intended ratios as conditions permit.
Restoration -
Level II is ended whenever critical facility loading have dropped and stabilized below
the current Level II trigger point. All participants should be notified when Level II is
canceled. ORNS is not notified until all cuts have been restored in Level I.
Restoration of any curtailments or adding of any previously frozen transfers will take
place in Level I.
NOTE: If Level I was not implemented prior to Level II, then the initiating control area shall execute Level I actions
in conjunction with Level II.
If Levels I and II were not implemented prior to Level III, it is permissible to allow
control areas to readjust curtailments to reflect their curtailment ratio and/or their
preferred operating configuration. This is to be done after situation has stabilized and
could involve generation shifts and changes in purchases.
Restoration -
Level III is ended whenever critical facility loading have dropped and stabilized below
the current Level III trigger point. Restoration of any curtailments or adding any
previously frozen transfers will take place in Level I.
After system conditions have stabilized at Level III or better, adjustments to purchases
can be made so long as the total import from ECAR does not increase. These
adjustments should result in purchase levels that would have resulted if curtailments
had been made recognizing each control area's CRV and applicable curtailment ratio.
Restoration -
As soon as conditions permit, system loads shall be restored in the same proportion as
the load shed. Purchases necessary to restore load and end emergency procedures may
be restored while in Level III.
Additional purchases beyond those needed to restore load and end emergency
procedures should not be restored until Level I or better conditions are achieved.
Purchases should then be restored as specified under restoration in Level I.
Notify all plan participants and ORNS when Level IV is canceled.
LEVEL IV-B (EMERGENCY LOAD SHED) - a critical contingency has occurred and conditions in the
initiating control area have reached the minimum survivable operating point.
The initiating control area shall request APS, PJM, and VaPwr to shed load immediately and in an equal
amount specified on the limit sheet.
Coincident with load shedding, all remaining transactions that are judged to adversely affect the problem
should be brought to zero. Emergency purchases that could be beneficial in alleviating the condition or could be
used to restore load without adverse effect should be made coincident with other actions in Level IV. All
participants and ORNS should be notified of these actions as soon as possible. The goal of Level IV-B is to restore
the system to Level III conditions.
OPERATION AT THIS LEVEL IS UNACCEPTABLE
All actions are judged necessary to avert a system collapse.
Readjustment -
After system conditions have stabilized at Level III or better, adjustments to purchases
can be made so long as the total import from ECAR does not increase. These
adjustments should result in purchase levels that would have resulted if curtailments
had been made recognizing each control area's CRV and applicable curtailment ratio.
Restoration -
As soon as conditions permit, system loads shall be restored in the same proportion as
the load shed. Purchases necessary to restore load and end emergency procedures may
be restored while in Level III.
Additional purchases beyond those needed to restore load and end emergency
procedures should not be restored until Level I or better conditions are achieved.
Purchases should then be restored as specified under restoration in Level I.
Notify all plan participants and ORNS when Level IV is canceled.
(Included by reference.)
Copies of this reference document can be viewed, printed or printed from the NERC home page on the internet @
http:\\www.nerc.com. Or can be obtained from the North American Electric Reliability Council (NERC) by request
from the following address:
NERC
116-390 Village Boulevard
Princeton, New Jersey 08540-5731
Telephone: (609) 452-8060
Fax: (609) 452-9550
APPENDIX E
VOLTAGE FLICKER AND HARMONIC DISTORTION LIMITS
VOLTAGE FLICKER
The voltage fluctuations (flicker) a customer's load causes at the point of common coupling shall remain
below the Voltage Flicker Limits of Figure #1. APS uses UHP International, Inc. Network
Flicker/Harmonic Analyzer, using the RMS unweighted scale, to determine compliance with this limit.
FIGURE #1
TABLE 1
Maximum Harmonic Current Distortion Levels (in % IL)
For Each Individual Odd Harmonic (NOTE 1)
Where Service Voltage is Less Than 69 kV
ISC/IL
DC Note 3
<11
11#H<17
17#H<23
23#H<35
35#H
THD
#20
(NOTE 2)
4.0
2.0
1.5
0.6
0.3
5.0
7.0
3.5
2.5
1.0
0.5
8.0
10.0
4.5
4.0
1.5
0.7
12.0
>100Ϩ
12.0
5.5
5.0
2.0
1.0
15.0
>1000
15.0
7.0
6.0
2.5
1.4
20.0
TABLE 2
Maximum Harmonic Current Distortion (in %IL)
For Each Individual Odd Harmonic (NOTE 1)
Where Service Voltage is 69 kV But #138 kV
ISC/IL
DC Note 3
<11
11#H<17
17#H<23
23#H<35
35#H
THD
#20
(NOTE 2)
2.0
1.0
0.75
0.3
0.15
2.5
3.5
1.75
1.25
0.5
0.25
4.0
5.0
2.25
2.0
0.75
0.35
6.0
>100Ϩ
6.0
2.75
2.5
1.0
0.50
7.5
>1000
7.5
3.5
3.0
1.25
0.7
10.0
TABLE 3
(NOTE 4)
Maximum Harmonic Current Distortion Levels (In % IL)
For Each Individual Odd Harmonic (NOTE 1)
Where Service Voltage is Greater Than 138 kV
ISC/IL
DC Note 3
<11
11#H<17
17#H<23
23#H<35
35#H
THD
#50
2.0
1.0
0.75
0.3
0.15
2.5
>50
3.0
1.5
1.15
0.45
0.22
3.75
Where:
H
THD
( 2 + 2 + 2 + ...+ I h 2 )
THD = I dc I 2 I 3
* 100
IL
ISC
IL
60 Hz (Fundamental Frequency) RMS load current at the meter location during the time
of harmonic analysis. For new connections, IL is calculated from the size of the
transformer to be installed.
IH
And:
% I H = I H x100
IL
The values of THD and %IH as calculated above should be less than or equal to those listed in
Tables 1-3.
NOTES:
1.
2.
3.
Voltage Distortion
For limitations on the amount of voltage distortion, which may result at the customer's meter location, the
following table will apply:
TABLE 4
Maximum Harmonic Voltage Distortion (in % V1)
at the Customer's Meter Location
< 69 kV
69 to #138 kV
>138 kV
3.0
1.5
1.0
THD
5.0
2.5
1.5
Where:
THD
1/2
THD =
( V dc 2 +V 2 2 + V 32 + ...+ V h 2 )
V1
* 100
VH
V1
60 Hz RMS Voltage
And:
V
% V H = H x100
V1
Both V1 and VH have to be checked phase-to-phase and phase-to-ground.
The values of THD and %VH as calculated above should be less than or equal to those listed in
Table 4.
Commutation Notches
Commutation action, which is a transient short circuit resulting from thyristor's switching from one phase
to the next is a source of harmonic current and voltage distortion. The voltage distortion is more important,
because many thyristor packages use the voltage (assumed sinusoidal) zero crossing for control, and will
thus be limited at the user's meter location as follows:
1.
Depth of the commutation notch should not exceed 20% of the peak voltage magnitude.
2.
The area of the commutation notch, which is equal to the width of the notch in microseconds times the
average depth of the notch in volts, should not exceed 22,800 for a 480 volt service. For other service
voltages, this limit will be multiplied by VLL/480.
3.
As in Table 4, the total harmonic distortion of the voltage at the service panel shall not exceed 5%.